Chapter V Project Implementation
Chapter V Project Implementation
Project Implementation
Contents:
4.1Organization
4.1.1 Line and Staff Organization
4.1.2 Divisional Organization .
4.1.3 Matrix Organization
4.2 Project Planning
4.3 Project Control
4.4 Human Aspects of Project Management
4.5 Pre-requisites for successful Project Implementation.
Introduction:
A project implementation phase of a project provides wide scope for consultancy and
engineering work, first and frameset in the field of project management. This chapter,
concerned with various issues relating to project management is divided into five
sections.
4.1.Form of Project Organization
4.2 .Project Planning
4.3 .Project Control
4.4 .Human Aspects of Project Management
4.5 .Pre-requisites for successful Project Implementation.
The type of Project organization is determined by the authority that is given to the
persons responsible for the project, the project organization may take one of the
following three forms;
4.1.1. Line and staff organization
4.1.2. Divisional Organization
4.1.3. Matrix Organization
Page 1
coordinator, acts essentially in a staff position to facilitate the coordination of line
management in functional departments. The project coordinator does not have authority
and direct responsibility of the line management. He serves as a focal point for receiving
project related information and seeks to promote the cause of the project by rendering
advice, sharing information and providing assistance. He may gently coax line executives
to strive for the fulfillment of project goals. Deprived to exert leadership and feel unsure
of his role. His influence would depend on his professional competence, closeness to top
management, and persuasive abilities. Clearly this is a week form of organization, which
may be employed mostly for small projects it is certainly not suitable for large projects.
Advantages:
A very strong form of project organization.
It facilitate the process of planning and control
It brings better integration of effects and strengths the commitment of project
related personal to the objective of the project.
It considerably improves the perfect of fulfilling the time and budget targets.
Limitations:
It may entail on inefficient use of resources of the firm.
It may result in an unnecessary duplication of specialist in the company.
It may difficulty to achieve higher degree of specialization.
The authority and influence of the project manager are across the traditional vertical line
of command while the personnel maintain the departmental affiliation and are responsible
to their functional superiors; they are responsible to the project manager as well.
Limitations:
There is dual subordinations
Page 2
Responsibility and authority are not commensurate
The hierarchical principle is ignored.
4.2.1.Functions of planning:
Planning, a vital aspect of management serves several important functions.
i. It provides a basis for organizing work on the project and allocating
responsibilities to individuals.
ii. It is a means of communication and coordination between all those
involved in the project.
iii. It includes people t look ahead.
iv. It instills a sense of agency and time consciousness.
v. It establishes the basis for monitoring and control.
4.2.2.Areas of planning:
Comprehensive project planning covers the following;
a) Planning the Project work: the activities relating to the project must be spell out in
detail, they should be properly scheduled and sequenced.
b) Planning the manpower and organization: the manpower required for the project
must be estimated and the responsibility for carrying out the project work must be
allocated.
c) Planning the money: the expenditure of money in a time phased manner must be
budgeted.
d) Planning the information system: the information required for monitoring the
project must be performed.
Effective planning: by dividing the work into manageable elements, which can be
planned, budgets and controlled.
Assignment of responsibility for work element to project personnel and outside
agencies.
Development of control and information system.
Page 3
4.3. Project Control:
Project control involves a regular comparison of performance against targets, a search for
the causes of deviation, and a commitment to check adverse variances. It serves two
functions.
(i) Regular monitoring of performance and (ii) it motivates project personnel to achieve
project objectives.
Methods of Analysis:
Performance analysis seeks to remove this subjectivity be employing an analytical
framework based on the following terms.
BCWS: (Budgeted cost for work scheduled) It represents the total of three components (i)
budgets for all work packages, scheduled to be completed (ii) budgets for the portion in
process work, scheduled for the accomplished and (iii) budgets for the overheads for the
period.
BCWP: (Budgeted Cost for Work Performance) this is equal to the sum of three
components (i) Budgets for work packages actually completed (ii) budgets applicable to
the completed in process work and (iii) overhead budgets
ACWP: (Actual Cost of Work Performed) . This represents the actual cost incurred for a
accomplishing the work performed during a particular time period.
BCTW: (Budgeted Cost for Total Work). This is simply the total budgeted unto for the
entire project work.
Page 4
ACC: (Additional Cost for Completion) This represents the estimate for the additional
cost required for completing project.
Given the above terms, the project may be monitoring along the following lines;
The achieve satisfactory human relations in the project setting, the project manager must
successfully handle problems and challenges relating to;
Authority
Orientation
Motivation
Group functioning
What can be done to minimize time and cost overruns and thereby improve the prospects
of the successful completion of projects? While a lot of things can be done to achieve this
goal, the most important ones appear to be as follows.
Costs may be taken to avoid the above deficiencies so that the appraisal and formulation
of the project is through, adequate and meaningful.
Page 5
(a) It is led by a competent leader
(b) The authority of the project leads and his team is commensurate with their
responsibility
(c) Adequate attention is paid to the human being in the project
(d) System and method are clearly defined
(e) Rewards and penalties to individuals are related to performance.
4.5.5 Timely availability of fund: Once a project is approved adequate funds must be
made available to meet its requirements as per the plan of implementation it would be
high desirable if funds are provided even before the final approval to initiate advance
action.
Page 6
Proper discipline must be inculcated among contractors and suppliers by insisting
that they should develop realistic and detailed resource and time plans, which are
congruent with the project plan.
Penalties-which may be graduated-must be imposed for failure to meet contractual
obligations. Likewise, incentives may be offered for good performance.
Help should be extended to contractors and suppliers when they have genuine
problems-they should be regarded as partners in a common pursuit.
Project authorities must retain latitude to off-load contracts (partially or wholly) to
other parties well in time where delays are anticipated.
Page 7
Monitoring system creation
Start with the project action plan
Define measurements for cost, performance, and time
Important to remember that you must include all levels of activities
Furthermore, mechanisms for collecting the data must also be in place
Avoid tendency to focus on easily collected data
Page 8
Project Status Reports
Time/Cost Reports
Variance Reports
Not all stakeholders need to receive same information
Avoid periodic reports
All involved need to know their status
Report types
Routine
Exception
Special Analysis
Page 9
5.3. Project termination
Project termination (or close-out) is the last stage of managing the project, and occurs
after the implementation phase has ended. ... A review is then undertaken with the client
and other project stakeholders, during which the project outcomes are evaluated against
the project's stated aims and objectives.
Why Terminate?
Projects usually are terminated for two basic reasons: project success or project failure.
Senior managers, who “own” the project and who see the project as a building block in
the design and execution of organizational strategy, must create a cultural ambience that
encourages projects to be successful, but also allows a project to fail if it has lost its
strategic fit in the organization’s plans for the future.
However, all project terminations don't necessarily mean the project ended successfully.
Either way though, there are some steps that should be taken.
Page 10