EOT Claim and Prolongation Cost Claim - The Basic Concepts - Khuong Do Blog
EOT Claim and Prolongation Cost Claim - The Basic Concepts - Khuong Do Blog
Purpose of EOT
The structure of the delay analysis should be organized in two sections/steps: calculating
EOT and calculating compensable delay for prolongation cost.
To calculate correctly the EOT, acceptable delay analysis methods could be Time Impact
Analysis, Time Slice Windows Analysis, or As-Planned versus As-Built Windows
Analysis.
To calculate correctly the compensable delay for prolongation cost, an acceptable delay
analysis method could be Collapsed As-Built.
The results of the steps above are illustrated in the following example.
The planned duration of the project was 502 days and the actual duration was 677 days.
The actual delay was 175 days.
The first step of the delay analysis was performed and came up with an EOT of 74 days.
Therefore, the liquidated damage duration is 101 days.
The second step of the delay analysis was performed and came up with a compensable
delay of 26 days.
In conclusion, the Contractor is entitled to an EOT of 74 days and a prolongation cost of
26 days.
Advertisements
REPORT THIS AD