0% found this document useful (0 votes)
29 views

EOT Claim and Prolongation Cost Claim - The Basic Concepts - Khuong Do Blog

Uploaded by

Khuong Do
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views

EOT Claim and Prolongation Cost Claim - The Basic Concepts - Khuong Do Blog

Uploaded by

Khuong Do
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Khuong Do Blog

Primavera P6, Microsoft Project, Delay Analysis Tips & Tricks

EOT Claim and Prolongation Cost Claim –


The Basic Concepts

Purpose of EOT

It is often incorrectly thought that entitlement to an EOT automatically carries with it an


entitlement to compensation for prolongation costs during the period of the EOT. The main
effect of an EOT is that the Contractor is relieved of its liability for liquidated damages
during the period of the extension and is able to reprogramme its works to completion. Its
entitlement to compensation is usually to be found in other provisions of the contract or at
law. The benefit of an EOT for the Employer is that it establishes a new contract completion
date, prevents time for completion of the works becoming ‘at large’, and allows for
coordination/planning of its own activities, such as training operational staff. (SCL D&D
Protocol 2nd Edition, page 22)

Result of delay analysis

The structure of the delay analysis should be organized in two sections/steps: calculating
EOT and calculating compensable delay for prolongation cost.
To calculate correctly the EOT, acceptable delay analysis methods could be Time Impact
Analysis, Time Slice Windows Analysis, or As-Planned versus As-Built Windows
Analysis.
To calculate correctly the compensable delay for prolongation cost, an acceptable delay
analysis method could be Collapsed As-Built.

The results of the steps above are illustrated in the following example.

An example of calculating EOT and compensable delay for prolongation cost

The planned duration of the project was 502 days and the actual duration was 677 days.
The actual delay was 175 days.
The first step of the delay analysis was performed and came up with an EOT of 74 days.
Therefore, the liquidated damage duration is 101 days.
The second step of the delay analysis was performed and came up with a compensable
delay of 26 days.
In conclusion, the Contractor is entitled to an EOT of 74 days and a prolongation cost of
26 days.

Advertisements

REPORT THIS AD

You might also like