2 Substructure Waterproofing MS
2 Substructure Waterproofing MS
Revision No. 0 A
Date 12-07-11 14-08-11
Revision History First Submission O/E comments incorporated
Prepared by Reviewed by Approved by Approval By
(Section Head) (QA/QC In charge) (Project Manager)
Name CYN NKV NR
Revision No. 0 A
Date 12-07-11 14-08-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Substructure Waterproofing
MS/N-8033/C05 Page 2 of 6
Method Statement
CONTENT
1. Purpose
2. Scope
3. Reference Documents
5. Responsibilities
6. Procedure
7. Records
8. Attachments
Revision No. 0 A
Date 12-07-11 14-08-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Substructure Waterproofing
MS/N-8033/C05 Page 3 of 6
Method Statement
1. Purpose:
The purpose of this method statement is to describe the logical sequence of activities
involved in substructure waterproofing and the documents to be recorded for
substructure waterproofing.
2. Scope:
3. Reference Documents:
3.4 Drawing DWG TR CIV 04 01 Ground beam and slab water proofing.
4.8 Polyprime SB, 2 mm thick Bitustick R 3000 and 3.5 mm thick BituBoard
Bitumastic Sealant
5. Responsibilities:
Revision No. 0 A
Date 12-07-11 14-08-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Substructure Waterproofing
MS/N-8033/C05 Page 4 of 6
Method Statement
5.2 QA/QC In charge shall be responsible for the QA/QC activities at site.
5.3 Safety In charge shall be responsible for the EHS activities at site.
6. Method / Procedure:
6.1 General
6.1.2 All materials identified / used for the permanent works shall be complied
with the approved documents by Owner / Engineer, prior to the
procurement.
6.1.3 All EHS activities related to this activity shall be based on the Owner /
Engineer / Contractor EHS Management System Guidelines.
6.1.4 All quality assurance and quality control activities shall be in line with
contractor Civil Quality Management System and the specified
requirements of the contract, Project Quality Plan.
6.1.5.1 Polyprime SB
6.1.6 All materials whether loose or on pallets/tins shall be stored in dry and
shaded area to keep away form direct sunlight and to protect from
extreme temperature.
6.1.7 Water proofing shall be done to all sub structural concrete elements in
contact with soil which includes pile caps, tie beams, ground beams,
ground slabs, and columns below ground, etc.
6.1.8 The waterproofing works shall not be allowed when there is a risk of rain
or dust storm.
Revision No. 0 A
Date 12-07-11 14-08-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Substructure Waterproofing
MS/N-8033/C05 Page 5 of 6
Method Statement
6.2.4 The surface shall be made dry before priming with polyprime SB.
6.3.1 Once the surface is ready for water proofing, inspection shall be raised
and approval shall be made available prior to start of application of primer.
6.3.2 The contents of the drum shall be mixed for a few minute to remove any
sediment.
6.3.3 The primer shall be applied to clean smooth and dry surface by brush or
roller.
6.4.1 The prime coat shall be touch dry before the application of the membrane.
6.4.2 Two layers of 2mm thick approved elastomeric sheet membranes from
approved make shall be used.
6.4.3 300mm reinforcing strips shall be applied at both internal and external
corners prior to start the application of main water proofing membranes.
6.4.4 Main water proofing membrane shall be applied strictly in accordance with
the manufacturer instruction / technical data sheet.
6.4.6 Once the single layer application is completed, second layer of membrane
shall be applied at right angles to the first layer.
6.4.7 The vertical membranes shall be tucked into a groove cut in the concrete
and sealed with a suitable mastic sealant as shown on the approved
drawings. Groove also shall be primed with approved primer.
Revision No. 0 A
Date 12-07-11 14-08-11
Approved by NR NR
Larsen and Toubro Limited – ECC Division
New 132/33 kV Substation at Kalba
Contract No.: N-8033
Substructure Waterproofing
MS/N-8033/C05 Page 6 of 6
Method Statement
6.5.1.1 Approved 50mm thick protection screed (grade 20/10) for horizontal
water proofing membranes which shall be laid over the membrane
immediately after installation.
6.5.3 While laying the screed, damages to the membrane shall be avoided and
the surface of the membrane shall be cleaned and cleared of any debris
and foreign objects.
7. Records
7.2 Checklist
8. Attachments
8.2 Checklist
*******
Revision No. 0 A
Date 12-07-11 14-08-11
Approved by NR NR