Renovation Procedures and Requirements
Renovation Procedures and Requirements
D. Upon submission of requirements and approval of plans, a Notice to Proceed will be given
to signify that renovation may already commence.
E. Once the renovation is completed, requirements will be submitted to the Engineering
Office for Final Inspection. The following are the requirements:
• Accomplished request letter for Final Inspection
• Two sets of signed and sealed as-built plans in A3 size
• Megger testing results
• Certificate of building system (if relocation of a building system was completed, a
certification from the authorized contractor is required)
• Certification of waterproofing(if alterations at toilet & bath, laundry and balcony
was completed, a certification from waterproofing contractor is required)
F. If final work conforms to the specification plans originally submitted to the Engineering
Office a Certificate of Final Inspection will be issued to signify that the construction bond
may be refunded.
NOTE:
• Work permit should be filed three (3) days before the actual work.
• Each work permit shall be allowed to cover a maximum five (5) working days. Please
specify the works to be done on a daily basis. A separate sheet may be attached for this.
• Delivery permit should be submitted one (1) day before the delivery of item/s.
• Building property pass should be submitted one (1) day before the pull out of items/s.
• Delivery of renovation materials will only be allowed once the renovation application
has been approved.
• Daily inspection by the building administration office inside the unit may be done.