JSA For Foundation Concrete Repair
JSA For Foundation Concrete Repair
Page 1 of 7
Plant / Department Hadeed / Saudi Iron & Steel Company Baramil 3 Date : 13/03/2022 JSA Number : 01
Activity / Task Foundation Concrete repairs for Mechanical equipment New Revised
,1
1. Non- Compliance of SHEM Procedure
Job Steps (Sub-Task)
2. Equipment mobilization, 3. Removal of Existing concrete structure (Jack Hammering), 4. Demolition of Existing Grade Slab (Open Flame Activity, Cutting & Grinding), 5. Excavation, 6. Form work (Cutting of ply woods, 7.
Concrete pouring, 8. Grouting, 9. Housekeeping, 10. Covid-19
11. Covid-19
Underground lines and cables 2. Excavate only what mention in the drawing.
3. Prior to start excavation provide hard barricade
Improper access to excavation around the excavation area.
4. Provide sign board and blinking light to aware about
Fall of person in excavation
the hazard.
5
Cave-in 5. Provide a access route for the employee those who
need to access the area for work
Slip and trip 6. Hard barricade the excavated are to avoid person fall
in it.
7. Provide enough protection to the soil (shuttering) to
avoid Cave-in.
8. Maintain good housekeeping at the jobsite to avoid
slip and trip.
1. Provide a access route for the employee those who
Form work (Cutting of ply woods) L3 C3 2 need to access the area for work L5 C3 4 Supervisor/WPR & SO
Power tools 2. Use appropriate PPE’S for the job (leather gloves,
safety glass, helmet, safety shoes, coverall)
Sharp blades of s 3. Do not bend your back for long time instead has a
good body posture while performing job.
6
Personal injury with sharp edges of re-bars and 4. Do not lift materials by giving pressure on your back
wire bone, follow safe manual lifting procedure
Ergonomic hazards 5. Maintain good housekeeping at the jobsite to avoid
slip and trip.
Back pain during manual handling
Improper access to excavation 2. Use appropriate PPE’S for the job (leather gloves,
safety glass, helmet, safety shoes, coverall)
Personal injury with sharp edges of re-bars and 3. Do not bend your back for long time instead has a
7
wire good body posture while performing job.
4. Do not lift materials by giving pressure on your back
Ergonomic hazards bone, follow safe manual lifting procedure
Back pain during manual handling 5. Maintain good housekeeping at the jobsite to avoid
slip and trip.
Slip and trip
1. Assign flagman to guide the concrete vehicle to enter
Concrete pouring L3 C3 2 the job site. L5 C3 4 Supervisor/WPR & SO
Vehicle strike with plant equipment 2. Conduct gas test prior to start the work
3. Follow MSDS of the materials
8 Fire 4. Use rubber gloves and rubber boots
Chemical burn 5. Worker working on concrete pouring and vibrator
operators must use rubber gloves, rubber boots, eye
Concrete splashing protection and face shield
6. Maintain good housekeeping at the jobsite to avoid
slip and trip.
Poor Visibility
Health hazard
Grouting Spillage
1. Ensure frequent cleaning of work station from
Housekeeping L3 C3 2 obstructing, unwanted material / objects and slippery L5 C3 4 Supervisor/ WPR
floor.
Possible slipping and falling of personnel
10 2. Any spillage should be cleaned up immediately and
stored into approved container.
3. Keep the area clean and tidy all the time.
1. Maintain social distancing at least 1.6 meters: do not
COVID- 19 L3 C3 2 share food and PPE’S with anyone L5 C3 4 Everyone
Note: For risks cannot be reduced or mitigate after formal JSA study,
then approval shall be obtained as per SHEM-02 SAFER requirement.
Approved by Unit Owner/Operation Manager:
Approved By
SN Area Owner Sr.Manager (Minor Residual Risk) Department Signature Date
01
Note: If Residual Risk is, Significant and above SAFER Approval Required.
ENDORSEMENT SECTION (This section shall be filled incase this document use for same scope of work in future)
SFM-08.10-SHEM-009