Work Done #04 RAR 2
Work Done #04 RAR 2
Amounts (Rs.)
S/No Description % Age
Previous IPC This IPC Upto Date
1 2 3 4 5 (3+4)
LSM Proj
CA No :- /PD HQ/LSM/2018
RD :-
Date of Commencement :-
Date of Completion :-
Contract Price :-
Civil Works
Work Done
Ser. Quantity of Quantity of
Description Unit Rate (RS) Amount
No C.A Work Done
(RS)
Civil Works
8 Providing and laying of Grouted Rip Rap Class-B Cu.m 423.48 #REF! 6,838.00 #REF!
Work Done
Ser. Quantity of Quantity of
Description Unit Rate (RS) Amount
No C.A Work Done
(RS)
23 Presressing wire Strand 12.70mm dia grade 270 Ton 19.63 270,000.00 -
Prestressing Connes inlc local bursting spalling
reinforement other attachments as per the supplier
24 Each 192.00 5,800.00 -
recommendation including stressing & ancoring of
cables
25 Provison of stressing block Each 192.00 1,704.00 -
28 Drilling of RCC Piles 760mm dia Meter 1,100.00 #REF! 9,800.00 #REF!
Electrification
Work Done
Ser. Quantity of Quantity of
Description Unit Rate (RS) Amount
No C.A Work Done
(RS)
Civil Works
8 Providing and laying of Grouted Rip Rap Class-B Cu.m 415.00 6,838.00 -
23 Presressing wire Strand 12.70mm dia grade 270 Ton 17.84 270,000.00 -
Electrification
Amount (Rs)
Work Done
Clamied by Recomemended by Recommended by
H.Dte
Contractor DAD/ADH PDH
DEDUCTIONS
g) Project Advance -
SAY 9,000,000.00
AQS
SDO (B/R) Sign/ Date ________________
Sign/ Date ________________
RECOMMEMDED BY
ADH
DAD Sign/ Date ________________
Sign/ Date ________________
RAR No-05
Name of Contractor Lump Sum Cost Rs:- 606,632,714
2
Doors incl Painting
1 Aluminum Windows complete 6.02
Ventilation incl Glzing & Painting
Tiling incl Bath rooms,kitchen & Granite 9.77
2 /Marble
Water Supply
Saintary 5.82
3 Sui Gas
Int Electrification incl. conduits & 0.25%
cabling
8.23
Electric Fittings Fixtures 42.00%
4 Earthing & Lightening
Cupboards,Wardrobes, Kitchen Hood & 2.04
5 Rak Slab
Painting & Distmpering incl external 2.26
6 Finishes complete
7 Saintary Fitting Fixtures 2.53
Railing (Balconcy/stairs) Grills misc 4.56
8 finishes
9 Fire Fighting & Alaram System
0.67
10 Fasle celling incl 12th Floor
11 Site Clearance 0.21
100.00 100.00% 27.50%
RAR No-05
CONST Of 4 BED APARTMENT BLOCK NO.10 (B+G+12) Askari Heights 4 PHASE 2 DHA Phase -
V Islamabad
At Par Amount 606,632,714
CA DHAI-06/22 Name Of Contr:M/S Yukon Builders & Developers
Case History
Sta :Rawalpindi
Dtae: ______________2022 DG Housing
RAR No-05
CONST Of 4 BED APARTMENT BLOCK NO.10 (B+G+12) Askari Heights 4 PHASE 2 DHA Phase -V
Islamabad
CA DHAI-01/22
1 Planned Progress
2 Achieved Progress
3 Lead/Lag
4 Reason of Lag
AQS(W) DAD(W)
CONTERSIGNED
Sta :Rawalpindi
Date: ___________________ ADH(W)-IV DHAI-V
PAYMENT RECEIPT DETAIL CA DHAI-1/22
Construction of Block No. 10 of (B+G+ 12) (4 Bedrooms ) With Basement Parking at Askari Heights-IV DHA
Phase V Islamabad
MS Yukon Builders & Developers
A Cement
1 P.C.C (1:4:8) in PILES all as spd. 2.00 26.76 cum 3.51 100% 93.93 4.70
3 Dirty Concrete for Piles 4.00 38.50 cum 8.31 100% 319.94 16.00
5 P.C.C (1:4:8) in Bldg 2.10 199.45 cum 3.50 100% 698.08 34.90
6 Raft Footing using OPC 4000 PSI 2.2a 1,535.34 cum 8.31 100% 12,758.68 637.93
7 Beams & Stairs 3500 Psi 2.2b 292.28 cum 8.40 100% 2,455.15 122.76
8 Roof Slabs 3500 Psi 2.2d 819.95 cum 8.40 100% 6,887.54 344.38
9 Column 5000 Psi 2.3 a 239.90 cum 9.50 100% 2,279.00 113.95
10 Shear Walls & Lift Walls 5000 Psi 2.3 c 165.15 cum 9.50 100% 1,568.93 78.45
Say: 1,747
Rate : 12000/ton: 20,964,000.00
B STEEL FOR PILES
Pile Steel
417,162.50
S# Total
Description of Stores Total Received A/U Rate Total Rate Amount Remarks
Consumsed
CEMENT
OPL Cement (Bulk) 1,538.38 Ton 12,000.00 18,460,560.00 12,000.00 -
Total 1,538.38 18,460,560.00 -
STEEL
Deformed 3/8" (Gde-60) 161.81 Ton 117,000.00 18,931,770.00 117,000.00 -
Deformed 1/2" (Gde-60) 103.46 Ton 116,000.00 12,000,780.00 116,000.00 -
Deformed 3/4" (Gde-60) 168.22 Ton 116,000.00 19,512,940.00 116,000.00 -
Deformed 5/8" (Gde-60) 17.88 Ton 116,000.00 2,074,080.00 116,000.00 -
Deformed 1" (Gde-60) 164.17 Ton 116,000.00 19,043,720.00 116,000.00 -
Total 615.53 71,563,290.00 -