The document outlines the functions and processes of the Engineering and Operations Section of the Surigao del Sur Irrigation Management Office. The Engineering Unit is responsible for planning, designing, constructing and rehabilitating irrigation projects. The Operations and Maintenance Unit undertakes O&M activities and water distribution. The document describes the project planning process for existing systems which involves field validation and inclusion in the Ten-Year Development Plan. It also outlines the planning process for small projects which includes feasibility studies approved by the Chief Engineer over 30 working days.

Uploaded by

Aimee Gozon
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
253 views

Engineering Unit Desk Manual

The document outlines the functions and processes of the Engineering and Operations Section of the Surigao del Sur Irrigation Management Office. The Engineering Unit is responsible for planning, designing, constructing and rehabilitating irrigation projects. The Operations and Maintenance Unit undertakes O&M activities and water distribution. The document describes the project planning process for existing systems which involves field validation and inclusion in the Ten-Year Development Plan. It also outlines the planning process for small projects which includes feasibility studies approved by the Chief Engineer over 30 working days.

Uploaded by

Aimee Gozon
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 16

Document Code : NIA-SDS IMO-DM-001

National Irrigation Administration Revision : 001


Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 1 of 111

2. ENGINEERING AND OPERATION SECTION PROFILE


Engineering and Operation Section is one of the 2 sections in the ASDI Irrigation
Management Office, with 23 monthly positions under the approved Rat Plan.

2.1 Functional Description

Engineering Unit

 Development and formulation of short and long-range plans and programs for the
development of feasible irrigation and related water resources projects,
construction/rehabilitation of irrigation projects/systems, O&M of systems and utilization
and repair of available equipment.

 Undertake investigation and study all available and possible water resources in the
province primarily for irrigation purposes.

 To plan, design. Construct and/or improve all types of irrigation projects and appurtenant
structures.

 Undertake the construction and rehabilitation of irrigation projects/systems.

QUALITY OBJECTIVES

 Enhance project identification;


 Strengthening of planning unit in preparation and/or review of feasibility
studies and program of works in Caraga Region;
 Develop engineering section personnel capabilities through trainings and
seminars;
 Enhance the design and implementation of irrigation and multi-purpose
projects to be resilient to climate change
 Capacitate engineering personnel to adapt climate change application in all
phases of project implementation.
 Ensure compliance to the basic construction methods to attain good
workmanship and quality of work;
 Strengthen project monitoring in Caraga Region;
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 2 of 111

Operation & Maintenance Unit

 Undertake the O&M, repair and improvement of irrigation system.

 Implement plans and programs, guidelines and instructions on improved water


management and distribution in the system to increase production, irrigated areas and
cropping intensity in the service area.

 Prepare and implement the cropping pattern of the system in consultation with farmers
and other agencies.

 Implement plans and programs to close the gap between the irrigated and service areas
and increase crop production.

 Implement strategies in irrigation service fees (ISF) collection and other income of the
system.

 Undertake the organization, development and sustenance of farmers-irrigators group.

 Prepare reports on O&M, actual water requirements delivery, irrigated/planted/harvested


areas/collection and expenses.

 Establish tie-up and coordination with National Food Authority (NFA) and other agencies
engaged in food production.

 Prepare and submit periodic reports as required.


Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 3 of 111

2.2Engineering Unit Flow Processes


Fig. 2-1: Project Planning for Existing Irrigation Systems (with Request from
External)
Responsible
Office/
Timeline/
Key Activities Position
Duration
Title/
Designation
Start

1 Received request from farmers, IAs, LGU resolutions IMO


or communication from RO for the construction or
5 minutes
improvement of irrigation facilities

2 1 working
Direct planning unit to conduct Field Investigation/ IMO Manager day/ project
Validation and submit validated report

1-3 working
Passed 3 Planning Unit days/ project
Major requirements
w/ source of water? No For future
Area to be irrigated? consideration
Farmer/beneficiaries?

Yes
3 Planning Unit 1-2 working
days/ project
Submit report with recommendation to I.M.O.
Manager

4 IMO Manager 1 working


Submit report with recommendation to R.O. day

5
IMO include in the list of proposed projects IMO/Planning 1 working
under Ten-Year Irrigation Development Master Unit day
Plan
6 IMO/ 1 working
Furnish R.O. copy of Ten-Year Irrigation Planning Unit day
Development Plan

End
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 4 of 111

Fig. 2-2: Project Planning/Investigation Process for Small Irrigation


Project/Extension Projects

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation
Start
Division Manager, Chief
Eng’g., Planning Unit, 5 days
N
Design Unit, Survey Team,
Projects Identification
1 o IDU
Not Recommended

Conduct coordination meeting with Division Manager, Chief


Eng’g, Planning Unit, Design 1 working
LGU
2 Unit, Survey Team Leader, day
IDU

Prepare Program of Work for


3 Feasibility Study Planning Unit 1 Day

Check, Approve Program of Work for


4 Feasibility Study
Chief Eng’g. Operation 2 Days
Section, Division Manager

Submit Approved Program of Work


for Feasibility Study to Regional Receiving Personnel/ Division 1 Day
5 Office Manager

END
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 5 of 111

Fig. 2-3: Conduct Feasibility Study

Key Activities Responsible


Office/ Timeline/
Position/ Duration
Designation
Start
Feasibility Study Team, 30 working
Survey Team days
1 Gather Data for Hydrologic Survey, Agro-Economic Survey,
Soil Survey and analysis. Conduct Topographic Survey of
Service area.

2
Draftsman, Survey 30 working
Drafting & Plotting of Topographic
Survey Data Team Leader days

Planning Unit, IDU 15 working


days
3 Prepare Feasibility Study Report

Check / Submit Final Feasibility Study Chief Engineering 2 working days


4 (Form 1-3a) to Regional Office for Review Section, Division
and Approval. Manager

END

Fig. 2-4: Project Detailed Engineering Process:


Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 6 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation
1 Start Design Unit, 30 Working
Planning Unit days
Survey Team
Conduct Detailed Engineering Survey & Data Gathering

2
Drafting & Plotting of Detailed Engineering Data Draftsman, 30 working
Survey Team days
Leader

Chief 2 working
Submit complete Engineering & days
Is the YES design data to
3 Operation
project regional office for
design Section,
under SRIP
Division
NO Manager

4 Chief 1 working day


Engineering
Submit complete design data for DAM
Assign & direct design engineer Section,
to regional office for design to facilitate draft detail design
and plan preparation. Design Unit

30 working
Design days
5 Prepare Detailed Engineer
Design and Plan
B1

Chief 5 working
6 Check Designed Plans Engineering days
Section,
A
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 7 of 111

YES
B1

NO

7
Submit designed plans to the regional office for approval
Division 1 working day
Manager,
DM’s Staff

Fig. 2-5: POW Preparation Process:


Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 8 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation
1
Start
Planning Unit, 10 working
Project In- days
Prepare Quantity estimates, Master list of
Charge,
work items

2 Planning Unit 3 working


Prepare Program of Works days

3
Chief 1 working day
Check prepared Program of Works
Engineering
Section

YES
With
Corrections?

NO

4
Division
Approve POW if within IMO Manager
Authority.
1 working day

5 Furnish approved POW to Regional Office/ DM’s Staff, 1 working day


Submit POW to Regional Office for approval. Division Manager

END

Fig. 2-6: Project Construction Process


Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 9 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation

Start
DM’s Staff,
Division
Received Approved Program of Works Manager 5 minutes
1 Notice to Proceed

Division Manager,
Cons. Head, 1 working day
Conduct LEVEL off Meeting Regarding
Project In-charge,
2 Pre-Construction Conference.
Survey Team,
Chief Eng’g.
Section, IDS

IDO, PIC
Set LGU/ IA Coordination Meeting/
3 Courtesy Call 1 working day

4 PIC, IDO, Survey


Team Leader, 1 working day
Conduct Pre – Construction Conference- Const. Head, Chief
Project Presentation Engineering, DM

5 Conduct Joint/ as stake survey PIC, IDO, 10 working


Survey Team, days

Plotting of Plan, Profile and cross- section


6 (as stake survey data)
Draftsman, 5 working
Survey team days
Leader,

A
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 10 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation
7
A
Chief 2 working
Engineering days
Section
Check Plan, Profile and cross- section

a. Construction and Supervision of Diversion works, PIC, Chief


Canals & Appurtenants Structures, Roads and other Engineering,
Irrigation Facilities Const. Head,
8 Chief O&M, 3-10 Months
b. Monitoring and evaluation Prepared, Checked, DM, IDO and
Monthly Const. Meeting/ Accounting
Unit
c. Presentations of project Status and Submit Monthly
Progress report RIO

Process on
Variation
Order
YES YES
B* With Variation
Order
A*
With Suspension/ *
Time Extension/
Resumption?

9
NO YES

10
Conduct Pre – Final Inspection SUBMIT TO RIO FOR
APPROVAL
PIC, MONITORING
ENGR., CONST.
HEAD, DESIGN 2 working
UNIT, SURVEY days
TEAM, PIT
B

* - Figure 2-7: Processing of Contract Time Extension/ Suspension & resumption Order
**- Figure 2-8: Processing of Variation /Change Orders
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 11 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation
B PIT
1 working day

Prepare
11
Punch List

Is there any NO
B
deficiency?
12

YES

Rectify Deficiencies Project In-Charge, 7 working days


C
13 Chief
Engineering,
Const. Head

Final Inspection PIT, PIC, 1 working day


14 Const. Head,
Survey Team

15 Test Run
PIC, Division 1 working day
Manager, Const.
Head, Eng’g.
Head, IDO
C
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 12 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation
C

16

YES
Is there
any C
deficiency

NO

17 PIC, Chief 1 Working Day


Recommended for final acceptance of Engineering,
project B Const. Head` and
Division Manager

END
18
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 13 of 111

Fig.2-6: Processing of Contract Time Extension / Suspension and Resumption


Order
Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation

1 START

Received Request for Work


2 Suspension HR / CPB 5 minutes

3
Project In-Charge, 2 working
Evaluate attachment of Work Const. Head, days
A
Suspension / Approval Contract Mgt.
Unit, Chief Eng’g.,
Division Manager,
EOD, Regional
Manager

4 Project In-Charge,
Checked Processed Time extension / Const. Head,
Resume Order 1 working day
Contract Mgt.
Unit, Chief Eng’g.,
Division Manager,
EOD, Regional
Manager
5
YES
With
Comments /
Corrections A

NO

6 Project In-Charge,
Const. Head,
Submit Processed / Suspension/ Resume order/
Contract Mgt. Unit, 1 working day
Time Extension to Regional Office
Chief Eng’g.,
Division Manager,
EOD, Regional
Manager
7 END
Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 14 of 111

Fig.2-7: Processing of Variation Orders/Change Orders

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation

Received request for Variation HR / CPB 5 minutes


2 Order/Change Order

3 Project In-Charge,
Const. Head,
Evaluate Master list vs. Actual Constructed
Contract Mgt. Unit,
15-20 working
Facilities Verify and Prepare requested
A Chief Eng’g., days
Variation Work/Change Order
Division Manager

4
Checked Processed Chief Engineer, 1 working day
Variation/Change Order PIC, Division
Manager

With YES
Comments /
Corrections A

NO

6
Submit Processed Variation
HR / Division 1 working day
Work/Change Order to Regional office
Manager A

7 END

Fig.2-8: Processing of Project Completion Report


Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 15 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation

START Engineering 20 working


Unit, days
1 Institutional
Unit,
Accounting
Preparation of Project Completion Unit
Documents

Collection of Project Completion Engineering 1 working day


2 Documents Unit

3
Engineering Unit 1 working day
Preparation/ Book Binding of
Project Completion Report

4
Chief Engineering 3 working
Check & Sign Project Completion Section, IDU
Report Head, Division
days
Manager

5
DM’s Staff, 1 working day
Submit Project Completion Report Division Manager
to Regional Office for approval

END

Fig.2-9: Processing of Parcellary Map


Document Code : NIA-SDS IMO-DM-001
National Irrigation Administration Revision : 001
Surigao del Sur Irrigation Management Office Issue Date : AUGUST 15, 2022
DESK MANUAL Page(s) : 16 of 111

Responsible
Office/ Timeline/
Key Activities
Position/ Duration
Designation

START

Received Approved Program of DM’s Staff, 5 minutes


1 Works Division
Manager

2 PIC, IDU, O&M


Unit, Design Unit,
Chief Engineering
1 working day
Level Off Meeting for the Conduct of
Section, Survey
Parcellary Survey Team Leader,
Division Manager,

3
Gathering of documents/Conduct PIC, IDU , Design 20 working
Parcellary Survey Unit, Survey Team days

4
Plotting and Drafting of Parcellary Draftsman, 20 working
Map Survey Team days
Leader

5
Check and Sign Chief Engineering 2 working day
Parcellary Map Section, Division
Manager

6
Submit Parcellary Map to Regional DM’s Staff,
Office for approval
1 working day
Division Manager

END