PM2 Tools
PM2 Tools
Current Edition:
Project Management Tools & Techniques, v.2. September 2015.
© European Union, 2015
No parts of this work may be transmitted outside of the European Commission without prior
written permission.
PM Tools & Techniques
Ref. Ares(2020)5350662 - 08/10/2020
Current Edition:
Project Management Tools & Techniques, v.2.5 September 2015.
© European Union, 2015
http://intracomm.ec.testa.eu/PM2
https://webgate.ec.europa.eu/fpfis/wikis/display/pm2techniques/Welcome
This version is in line with the PM² Project Management Methodology Guide v.2.5
ISBN: 978-92-79-50854-7
No parts of this work may be transmitted outside of the European Commission without prior written
permission.
Email: [email protected]
PM Tools & Techniques
Table of Contents
1. The GROW Model ..................................................................................................................... 3
2. CIPP Model ................................................................................................................................ 5
3. PESTEL Analysis ......................................................................................................................... 7
4. Organising a To-Do List ............................................................................................................. 9
5. FSNPA Model of Team Performance (Tuckman's Model) ....................................................... 11
6. Effective Communication ........................................................................................................ 13
7. Project Stakeholder Matrix (PSM)........................................................................................... 15
8. Stakeholder Importance-Influence Matrix (SIIM) ................................................................... 17
9. Running Effective Meetings .................................................................................................... 19
10.Work Breakdown Structure .................................................................................................... 21
11.Product Breakdown Structure (PBS) ....................................................................................... 23
12.Efforts and Costs estimates..................................................................................................... 25
13.Three-Point Estimates using PERT .......................................................................................... 27
14.Project Scheduling................................................................................................................... 29
15.Critical Path Method ............................................................................................................... 31
16.Gantt Charts ............................................................................................................................ 33
17.Resource Levelling................................................................................................................... 35
18.Critical Chain Method ............................................................................................................. 37
19.Earned Value Management .................................................................................................... 39
20.Ishikawa/Fishbone Diagram .................................................................................................... 43
21.Delphi Technique .................................................................................................................... 45
22.Plan-Do-Check-Act Method .................................................................................................... 47
23.Make or Buy Analysis .............................................................................................................. 49
24.10 Cs of Supplier Evaluation .................................................................................................... 51
25.Proposal Evaluation Techniques ............................................................................................. 53
26.Pareto Chart ............................................................................................................................ 55
27.Project Assessment and Effectiveness Measurement ............................................................ 57
28.SECI Model - The Knowledge Spiral ........................................................................................ 59
29.Lessons Learned ...................................................................................................................... 61
PM Tools & Techniques
Introduction
The purpose of the PM2 Project Management Methodology is to enable European Commission Project
Managers (PMs) to deliver solutions and benefits to the European Commission through the effective
management of project work.
This document presents a set of Tools & Techniques addressing different areas related to project
management and project portfolio management.
Each Tool & Technique is summarised in 2 or 3 pages. It provides a high-level overview and summary
guidelines on how to use it as well as relevant references and sources for further reading.
The set of tools presented is by no means the complete set of tool used in project management - new
tools will be added as their description becomes available.
We hope that you find the first version of this publication useful and complementary to all our other
publications, that you have fun exploring further the Tools & Techniques and that you increase your
productivity by using them!
The CoEPM2 Team.
1
PM Tools & Techniques
2
PM Tools & Techniques
The GROW Model was introduced by John Whitmore to facilitate the setting of goals and the
designing of plans on how to achieve them. GROW is an acronym for Goal, Reality, Obstacles/Options
and Will/Way Forward. When applied within the context of a project, the GROW model enables the
project teams to set goals and review the action plans in order to achieve them. These goals can be
related to both the outcomes of the project (project goals) as well as to the individual performance of
team members (individual goals).
The four key elements of the GROW Model are described below:
Goal: An objective that the project team aims to achieve.
Reality: An assessment of the current situation, issues and challenges faced.
Obstacles/Options: Roadblocks in achieving the goals and options on how to overcome them.
Will/Way Forward: Action plans to overcome the obstacles to move ahead in a project.
The goals set by the project team should be specific and monitored from time to time. The goal setting
can be done through the use of frameworks like SMART, PURE and CLEAR. At any stage of the project
a review could be done of the current environment to understand the problems or issues faced by the
project team. The project team lists the current and expected future obstacles to achieving the stated
goal, and brainstorms on the different options that can be taken to overcome them. Action plans are
designed and executed based on the options identified. The goals are reviewed again at a later stage
in the project and the cycle is repeated.
Goal
Will / Way
Reality
Forward
Obstacles
/ Options
3
PM Tools & Techniques
SMART Goals:
Specific: The goals should be clear and unambiguous.
Measurable: There should be a well-defined criterion for measuring progress of goals.
Attainable: The objective should be realistic and not extreme so that it can be achieved.
Relevant: The goals should be aligned to the effort and time being invested.
Time Bound: Target date should be set for all the goals so that there is a constant focus.
PURE Goals:
Positively Stated: The goals should be stated in a positive rather than a negative way.
Understood: The goals need to be interpreted by everyone in the same manner.
Relevant: The goals should focus on the wider vision and be aligned to other goals.
Ethical: Goals should be aligned to the best practices of the larger organisation.
CLEAR Goals:
Challenging: The goals should stretch and push the team so that there is constant focus.
Legal: Goals should abide the law of the land and be in line with the larger organisation.
Environmentally sound: Goals should keep the environmental aspects in consideration.
Appropriate: Goals should be appropriate and relevant to the larger organisation.
Recorded: Goals should be written down and visible so that the focus is not lost.
4
PM Tools & Techniques
allocating resources, scheduling work and assigning human resources. Project Managers (PMs)
set up and confirm the plans and budgets before taking any action.
Measuring the outcomes of the project and comparing them with the project objectives provides
Project Managers (PMs) inputs whether to continue, modify or drop an existing project. However the
CIPP model is complete and robust, there are a few limitations in the process involved. The process of
getting the requirement details from several stakeholders can be slow, costly and complex. It can also
be difficult to measure the process efficiency due to the complexity of the processes or due to internal
political issues.
Overall the CIPP Model is a systematic and standardised process for any project evaluation.
6
PM Tools & Techniques
3. PESTEL Analysis
The PESTEL Analysis is a used tool to understand how an objective/goal is impacted by the
environment one is operating in. It provides information about five factors: Political, Economic, Social,
Technological, Environmental, and Legal that could have an impact on the project. This analysis helps
to brainstorm about the influence of each factor, as well as drawing a conclusion from it. This tool can
be used in any type of project where external factors could have an impact on the objective or
execution of the project.
The PESTEL analysis helps the project team to take into account changes in environment positively, so
that there is a higher probability of success. Understanding the environment factors, which are
beyond one’s control, helps to make a plan to tackle difficult potential scenarios. This analysis should
be free of assumptions and based on realities of the current environment.
The project team first identifies which of the factors are relevant for the current project objective. The
team then starts to brainstorm on the identified factors and assembles information on each factor.
Afterwards, this information is used in order to establish conclusions on the impact of each of the five
factors. In addition, these conclusions will feed the process of designing a plan on how to tackle
potential risk scenarios.
Political
Legal Economic
Project
Objective
Environmental Social
Technological
7
PM Tools & Techniques
Political
These are factors which could have an impact on the project through a related tax or labour
policy, market regulations or other political governance issues.
Economic
These are factors which could have an impact on the execution of the project. These include
factors related to economic growth, interest rates, budget cycles and other economical
governance issues.
Social
These are socio-cultural factors that could have an impact on the project objective. These
factors could consist of the population growth rate, age distribution, social attitudes and
preferences, lifestyle choices, cultural changes, etc.
Technological
These factors relate to the technological aspects, for example: research and development
activity, automation changes, emerging technology, outsourcing decisions, etc.
Environmental
These factors include ecological and environmental aspects, which might have an impact on
some industries like tourism, farming, insurance, which may be related to the project. The
factors include changes in weather, climate, landscape, etc.
Legal
These factors relate to which legal bindings operate the execution of the project. This could
include discrimination law, consumer law, antitrust law, employment law, health and safety
law or other legal governance issues.
The PESTEL model covers almost all the factors that could have an impact on the project objective. In
some cases of use, the PESTEL model has been extended to STEEPLED model, adding Ethics and
Demographics factors as well. However, the project team only needs to consider the factors which are
relevant to the current project objective or execution and to list down the factors impacting it. This
results in planning the right actions for countering any factors adversely impacting the project.
8
PM Tools & Techniques
Projects are not run in a vacuum; they are run in an organisational context. As a result, during the life
of the project, the Project Manager (PM) and team will get lost in the day-to-day activities and get
sucked into spending time on activities that do not directly contribute to the project goals. It is
important to manage available time well during projects by understanding the priority of activities. It
helps to organise a To-Do list by focussing on which activities need urgent attention and are important
for achieving project goals.
Important
Do not do Delegate
A To-Do list can be organised using an Eisenhower Matrix as shown in Figure 4.1 above. The matrix
categorises tasks into different quadrants based on importance and urgency. It is important to
understand these two types of categories in order to organise activities during projects:
Important: These activities have a direct effect on the outcome and achievement of the
project goals.
Urgent: These are activities that demand immediate attention before their consequences
affect project goals.
Based on the urgency and importance of activities, the Eisenhower Matrix categorises activities in the
following four quadrants:
Do Now: Urgent, Important activities that are Critical Activities of the project.
Schedule for later: Not Urgent, Important activities that are Important Goals of the project.
Delegate: Urgent, Not Important activities that are Interruptions of the project.
Do not do: Not Urgent, Not Important activities that are Distractions of the project.
Once the activities or tasks of a project are categorised, the Project Manager (PM) can easily organise
a To-Do list and optimise his or her time.
9
PM Tools & Techniques
Steps
List all the day-to-day activities that need to be completed for the project.
Rate the importance of each activity on a scale of 1 (Low) to 5 (High).
Rate the urgency of each activity on a scale of 1 (Low) to 5 (High).
Plot the activities on the Eisenhower Matrix (Urgency Rating, Importance Rating).
Organise a To-Do list according to the categorisation of activities in the four quadrants.
Different strategies should be employed for the activities categorised in the four quadrants.
It is easy to get lost in the day-to-day and a linear list of to-do’s that grows on a daily basis. It is
important to prioritise activities and understand what contributes to the project and what does not.
Using a standard prioritising method like the Eisenhower Matrix helps to keep the focus on important
activities that lead to the achievement of project goals and objectives.
10
PM Tools & Techniques
Project Manager:
Project Managers (PMs) need to be directive in this phase as team members work individually.
Stage 2: Storming
Team members:
In this phase ideas and solutions from team members may compete against each other.
The team addresses project issues (leadership model, communication channel etc.).
Differences, issues and conflicts stimulate the development of project team members.
Project Manager:
Project Managers (PMs) should provide guidance on professional behaviour during this time.
Stage 3: Norming
Team members:
Team members start respecting other views or opinions and come to an agreement.
Trust begins to develop through the valuable contribution of team members.
Individual team members play a greater role in handling project responsibilities.
Team members start supporting each other in the establishment of project deliverables.
Stage 4: Performing
Team members:
The team is highly motivated and knowledgeable resulting in a peak performance.
Members are now competent, autonomous and able to make decisions on their own.
High degree of comfort in the group is stimulating the completion of project tasks.
Project Manager:
Project Managers (PMs) contribute as team members rather than as supervisors.
Stage 5: Adjourning
Team members:
This stage is about completion and disengagement from project activities and members.
Individuals recognise their effort as part of the group and move on to other projects.
Also described as the Deforming and Mourning stage as team members get separated.
This phase can be difficult for team members who developed close work-relations.
In order to improve the project team performance, the main focus of the project Manager should be
to understand the stage of group development the project team is currently in. The model also states
that due to changes in the project environment, the group may tend to return to the previous stage of
the Tuckman Model. These changes in the project environment could be a new project Manager, a
change in project team members or changes in the project goals or objectives. Whenever this occurs it
is important to go through the different stages of the Tuckman model again.
12
PM Tools & Techniques
6. Effective Communication
Also bear in mind that the more persons or groups are at the receiver's side the harder it becomes to
have your message transferred in a clear and concise manner. So try to limit the audience for your
message and send maybe several messages to smaller groups.
Effective communication helps in problem solving and conflict management.
13
PM Tools & Techniques
14
PM Tools & Techniques
A project stakeholder matrix (PSM) is a specific artefact in the PM² methodology. This chapter starts
with the PSM as defined in the guide and adds another dimension to it.
This dimension is more a personal view of the project manager on the stakeholders. This overview can
also be useful in case the project manager is changed during the project as a handover document.
Keep in mind that this part of the Project Stakeholders Matrix is confidential and should not appear in
a public part of the project repository.
Step 3: Fill in the fields (for each identified stakeholder) following the guidelines given hereafter
The fields are grouped into several logical units. Every unit /field is explained hereafter.
Personal information: contains additional fields (e.g. email, mobile, etc.).
Active: to indicate for each phase the expected involvement of the stakeholder. The value is
translated in a colour line to give a clear picture of the involvement over time.
Communication profile: used to detail the ways of communication and the frequency of it for
this stakeholder. Information is taken from the communication plan and specific information
can be added (e.g. a face-to-face (FTF) in case of a crisis).
15
PM Tools & Techniques
Influence: this topic has 3 sub-topics. The first one being the power the stakeholder has on the
project to Make/force decisions. The second one is about the interest he/she has in the
project (e.g. the outcome can help in having a promotion). The last one is the influence to
guide/direct the project.
Risk appetite: for the 3 main areas (budget, timing, and scope) the risk appetite of the
stakeholder can be given. This can be useful when a change/issue is encountered to predict
the possible reaction of the stakeholder.
Concerns and needs: here you can add specific concerns needs that the stakeholder expressed
to you (e.g. GO LIVE date cannot change due to legal constraints).
Details: any interesting fact you learn about your stakeholder can be put under this topic. It
can go from the names of the children up to hobbies.
16
PM Tools & Techniques
This technique is used to facilitate and document the analysis of the influence and the importance of
each stakeholder in the project. As Project Manager (PM) it is out most important to know your
stakeholders and what they can mean/do for your project. This can be in a positive and in a negative
way.
The importance of a stakeholder indicates the extent to which his needs and interests will be
prioritised by planned activities. This means that a stakeholder is considered important when his
needs and interests will get a higher priority when creating/revising the planning. As a consequence he
will be faster contacted when a revision of the planning is possibly needed to get his/her feedback.
The influence of a stakeholder for the project is the power he has over the planning and
implementation of activities. A stakeholder that can demand a change in the planning has a big
influence on the project. Most of the time the person(s) that can allocate money and/or resources to
the project is (are) considered to have a high influence.
Step 3: For each stakeholder access the influence he has on the project
Do the same as in step 2 but now for the influence the person has over the schedule of the
project. Again 5 means that she/he has large influence over the schedule and 1 means nearly
no influence over the schedule.
17
PM Tools & Techniques
The four major parts in the table and the way to handle them are briefly described hereafter.
Part A: PROTECT: consists of stakeholders that have a great importance in the project but,
unfortunately, have low influence. Special attention is needed to protect their interests as they don't
possess the required influence to protect their own needs.
Part B: GOOD RELATION: these stakeholders have a huge interest and also a big influence in the
project. You need to set-up a close working relationship with them. Also agree the ways of
communicating with them besides the standard communication agreements. This can be a face-to-
face update on a daily/weekly basis.
Part C: LOW PRIORITY: this group has a low priority for the project and practically no influence so your
involvement in them should be a minimum. However be aware that they keep a positive attitude to
your project so don't neglect them.
Part D: MONITOR: this group may be a source of risk as their influence is high but the importance of
the project is low for them. So they need to be carefully monitored and managed to make sure that
they don't lose their interest in the project or, even worse, become a blocking factor.
18
PM Tools & Techniques
Figure 9.1 provides a set of general steps that should be taken to ensure that meetings are run
efficiently and effectively. This model focuses on thoroughly preparing the meeting to ensure
attainment of the objectives, and to improve communication and follow-up past meeting. The overall
concept is to be more focused and concise, and to ensure that meetings result in a set of key actions.
For larger or longer meetings, and particularly for brainstorming meetings, it is helpful to have
supporting staff performing all the record keeping and assisting in the facilitation of the meeting.
These roles include:
Timekeeper: Reminds the facilitator about the time allotted for key agenda items.
Notes Taker: Records and summarises the meeting minutes and distributes meetings notes.
Whiteboard Notes Taker: Writes ideas on the whiteboard during brainstorming sessions and
records the final points from the board to send to all invitees.
The organiser should take charge of the meeting and ensure that the discussion runs smoothly. Do not
hesitate to table, or put aside, topics that do not contribute to the meeting objectives, or are not part
of the agenda. The focus of the meeting should be to collect constructive inputs from everyone
present, and at the end of the meeting everyone should be aware of the key decisions and actions
that must be taken care-of.
A Work Breakdown Structure (WBS) consists of logically decomposing a project into smaller work
components. It is the first step to organise work, taking into account extensive details, in a structured
format. A Project Manager (PM) may use a WBS to decompose a project in stages, deliverables, activities,
tasks, business units, etc. However a WBS is a good way to define a decomposition of the project work, it
does not provide information on time, sequence or dependency of the work. The role of the project team
members is to support the Project Manager (PM) in identifying the lower level activities and tasks of the
project.
Different WBS techniques can be used to decompose a large project into smaller and identifiable activities.
Below are some of the commonly used techniques used by Project Managers (PMs) to create a
comprehensive and specific WBS.
WBS is a formal project deliverable and any changes to it should go through a change control process. It is
important for the Project Manager (PM) to review the WBS with the project team and the other
stakeholders before executing the project.
Project
1.0
Task Task
1.1.1.1 1.3.1.1
Task Task
1.1.1.2 1.3.1.2
Task
1.1.1.3
Figure 10.1 above is an example of a WBS which breaks down the work into work packages and respective
activities and tasks.
21
PM Tools & Techniques
22
PM Tools & Techniques
Product Based Planning is a technique that is, amongst other institutions, recommended by Prince2©. A
Product Breakdown Structure (PBS) is an essential part for this technique. Its purpose is to define the
products (deliverables) of a project and how they relate to each other. The PBS provides an exhaustive,
hierarchical tree structure of deliverables (physical, functional or conceptual) that make up the entire
project.
Prince2© describes a PBS as “a hierarchical structure that breaks down a final product into its constituent
sub-products. It helps the planner to think of what other products are needed to build the final product and
to clarify all necessary work for the creation of that final product".
The Product Breakdown Structure has a similar structure as the Work Breakdown Structure but it is used at
a different step in the planning process. The PBS precedes the WBS and puts the focus on representing the
desired outputs (products) needed for the project. This feeds the creation of the WBS which identifies the
tasks and activities required to deliver these outputs.
Quote: the PBS defines where you want to go and the WBS tells you how to get there.
23
PM Tools & Techniques
After these steps the PBS can be used to derive the tasks/activities needed for the WBS or for a product
based planning.
Note: There are several tools available on the market to perform this kind of representation (e.g. Visio,
PowerPoint, mindmapper, etc.).
24
PM Tools & Techniques
This technique has as predecessor the work breakdown structure (see chapter 10). The outcome of the
Work Breakdown structure is used as the input for the Cost and Estimates technique.
All the work items are estimated for the required effort to perform this work and the associated cost. The
required effort is then matched to the availability and the capability of the resources.
The Project Manager (PM) coordinates the estimation of the effort and cost for each task. This is done in close
collaboration with the task owners or other experts for each impact area (who are usually members of the
Project Core Team (PCT)).
There are different approaches when estimating time and cost for the finest detail level of tasks of a Work
Breakdown:
Based on expert advice.
Based on historical information.
Based on similarity to other tasks.
Based on the Function Point Analysis (FPA) method (IT projects).
Based on other tool or commonly acceptable methods.
Based on resource cost information (pricelists, outsourcing contracts…)
Note: the accuracy of the WBS is of the highest importance to get adequate estimates. When creating the
WBS with the stakeholders bear in mind to mention to them that the better the WBS the better the
estimates.
25
PM Tools & Techniques
Step 5: Estimate the likely cost to be incurred on the activity (if it must be traced).
If the Project Owner(PO) does not want detailed traceability for the cost per activity then you can
go to Step 6
For each activity add the cost of one workday (WD) times the number of needed workdays
Create the total cost for all activities
Step 6: Add non people cost
Finally add the related cost for any non-people related activity if necessary (hardware, software,
buying/renting of material, assets…)
If some items are regularly used you can consider to create a WBS dictionary containing fixed prices
for specific items (e.g. one test cycle)
Step 7: Finalise the estimate
The last step is to sum all different parts together and the total amount of effort and cost for your
project is available
Hereafter a table is presented that shows the relationship between the level of accuracy and the size of
projects.
26
PM Tools & Techniques
The minimum cost or effort that can be achieved in case that only good performance is
realised throughout the process. The probability of achieving this estimate should not be more
than 1% (i.e. there is 99% probability that the cost/effort or duration of this activity will be
larger than this estimate).
The most probable cost or effort that the person, that is best qualified to judge, would expect.
This estimate would also occur most often in case that the activity could be repeated
numerous times under the same conditions.
The maximum cost or effort needed in case that unusually bad performance is realised. The
probability of realising this estimate should not be more than 1% (i.e. there is 99% probability
that the cost/effort or duration of this activity will not exceed this estimate).
It is important to note that a basic assumption in the estimating process is that the three estimates are
based on the same level of effort, for example the same number of persons working or the same
number of shifts and days per week (i.e. 1 man day = 7,5 hours).
In addition, the three-point estimate is designed to capture and mitigate the uncertainty of providing a
single estimate, and is not designed to provide forecasts of buffers to mitigate changes to the
fundamental conditions of the project. For example, the technique can be used because the project
team is unsure of the difficulty of implementing some aspect of the project and is not used to capture
the effects of a change in the scope of the implementation.
Lastly, it is also important to note that the three-point estimate technique does not mean that expert
advice is no longer necessary to build project cost and duration estimates. While the technique
provides a weighted average of three estimates, a large standard deviation will mean that the
likelihood of achieving this expected cost or duration is very low. Involving experts to provide the
three-estimates will increase the accuracy of the three-point estimate and reduce the risk or
uncertainty of the project.
28
PM Tools & Techniques
The objective is to identify dependencies between tasks, assign resources for each task, identify task
start and end dates and work out the overall project duration.
Scheduling can be done for the entire project upfront or for portions thereof, such as individual stages
or iterations. Most of the time a high level schedule is established for the entire project and a detailed
schedule is created for the upcoming months.
Different scheduling methods and representations can be used. For instance, a list of dates/deadlines,
milestone plans, bar charts, network diagrams and linked bar charts can be used, and very often can
be seen as complementary to each other. The information requirements and effort for the application
of the various scheduling methods differ from one project to another. Similarly the effectiveness of
each scheduling method (or combination) depends on the type, size, complexity and dynamics, and
documentation and control requirements of each project.
Regarding scheduling there is thus not one technique that works for all projects. It is up to the project
manager to decide which tool(s) and/or technique(s) to use for his specific project.
29
PM Tools & Techniques
30
PM Tools & Techniques
The Critical Path Method (CPM) is a modelling technique that uses a mathematically based algorithm
to calculate the total duration of a project. CPM calculates the longest necessary path (longest
unavoidable duration) of planned activities from beginning to end of the project, otherwise known as
the critical path of the project.
CPM is used widely in projects where enough detail can be derived and estimates can be relatively
accurate. CPM is particularly useful in projects with many concurrent activities, or in organisations
running many concurrent projects. In these cases, resources are often shared across multiple activities
or projects, and understanding where there is a critically for timeliness is crucial to preparing the
resource management plan.
Since the critical path represent the longest necessary path of activities, it also represent the shortest
possible duration of the project to completion. When this duration is beyond what is required,
activities can be prioritised in order to shorten the duration of the critical path. This is done by pruning
the critical path activities, performing more activities in parallel (Fast tracking) or shortening the
duration of the critical path activities by adding more resources (Crashing the Critical Path).
Figure 15.1 shows an example network diagram with a set of activities A through H, along with the
respective duration and inter-dependencies and the basic CPM analysis performed to find the critical
path. The activities A, B, C, D and H form the longest path or the Critical Path (CP), whereas the other
activities (E, F and G) are off the critical path and can be delayed or extended until a certain point
without delaying the completion of the overall project.
31
PM Tools & Techniques
Overall, a Gantt chart is a useful technique which can also be used for planning and communication
purposes. However, Gantt charts for a larger project with many tasks can become crowded and lose
the positive aspect of simplicity. In these large Gantt charts, choosing the right level of granularity is
crucial to ensure that the visual remains useful and easy to communicate.
Note, however, that projects are often much more complex than what can be represented even in a
detailed Gantt chart. In such cases, a Gantt chart cannot be used on its own as it cannot include all the
critical information and project dynamics required for managing a project, particularly larger or more
complex projects.
Step 1:
Define the project's Work Breakdown (WB)
Step 2:
Identify the duration of each task
Step 3:
Identify the dependencies between tasks and activities in the WBS
Step 4:
Define the sequence of tasks in the project
Step 5:
Map the summary and terminal elements of the WBS on the Y-axis of a graph, and the
duration on the x-axis of the graph
Step 6:
Create horizontal bars to depict the length of each WB element, and connect the
dependencies identified in step 3
Currently, the most simplistic method to create a Gantt chart for a small project, as it does not involve
many parallel tasks, is by the use of a spread sheet software tool. In the case of large organisations or
projects, the use of dedicated tools that include Gantt chart capabilities is more advisable. In addition,
dedicated tools provide many other views of a project than simply a Gantt chart, which is a very useful
feature for those with knowledge of using the tool.
34
PM Tools & Techniques
External:
Constraints could arise based on the desires and needs of a third party involved. For example:
equipment has to be purchased from a third party before you are able to start the
configuration of the equipment.
Taking into account the identified constraints, resources levelling can be performed. Resource levelling
can for example require the delay of tasks until resources are available. Within a larger organisation,
resources could also be allocated across multiple, simultaneous projects. Therefore, resource levelling
could result in a delay of the project finish date if the tasks affected would be within the critical path.
The Critical Path Method is commonly used as a basis for levelling. Project Managers (PMs) use the
following techniques in order to resolve resource constraints:
Increasing the timeline or schedule of the project so that both cost and scope of the project
are respected
Reducing the scope of the project so that both time and cost of the project are respected
Increasing the cost so that both the time and scope of the project are respected. Techniques
to this are:
o Fast Tracking: The critical path tasks are performed in parallel (instead of sequential).
This increases the risk and the possibility of rework.
o Crashing: More resources are added to the critical path tasks to maintain the project
timeline. This results often in higher costs.
Certain IT tools, such as Microsoft Project, provide functionality to automatically level resources by
making one of the three project constraints (cost, scope and time) variable.
36
PM Tools & Techniques
When applying CCM it is important to always keep in mind that resources allocated to an activity are
encouraged to complete work at the fastest speed possible, and are not allowed to work on multiple
tasks at the same time. In addition, it is important to openly communicate with resources and to
provide them with clear and aligned priorities about the status of the critical chain, so that they are
only focussed towards the project deadline.
38
PM Tools & Techniques
Even though EVM metrics are largely objective, they are still subject to not only interpretation, but
also estimation error or bias on behalf of the Project Manager. Namely, EV is derived based on the %
complete of a work package, and is an estimate provided by the Project Manager and the project
team. In addition, the accuracy of PV is subject to the experience and information available to the
Project Manager during the planning phase of the project. PV and EV are then most accurate when the
Work Breakdown Structure (WBS) is very detailed and work packages are small in cost and duration.
Overall, EVM is a useful tool to manage project financials and performance. However, it only takes into
account quantitative aspects and ignores qualitative KPIs reflective of domains such as quality. EVM is
demanding in terms of project set-up because it requires a good reliable project plan, and in terms of
project monitoring and controlling because it requires measuring, gathering and tracking all necessary
indicators.
41
PM Tools & Techniques
42
PM Tools & Techniques
Following are the steps to analyse and identify root causes by the use of a Fishbone diagram:
Step 1:
Identify the problem in the project and the different cause categories, such as the nature of
issue, frequency, and people involved in the process, etc.
Step 2:
Analyse the cause categories involved in the problem
These cause categories could differ for each and every problem or project
Step 3:
Start analysing the primary and secondary causes for each cause identified
The problem statement, the primary and secondary causes are illustrated on the Fishbone
diagram
Step 4:
The Fishbone diagram is analysed by the project team focussing on one factor at a time
For detailed investigations, action items are noted for each factor in terms of additional
information required (ex.: surveys to be conducted, questionnaires to be sent, etc.)
Solutions on how to tackle the identified cause and effects within the project are developed
While analysing a problem using a Fishbone diagram, the scope should be manageable. The factors
should not be too broad so that it does not make the analysis difficult using the diagram. The team
should not spend too much time debating on where to place a primary or secondary cause. However,
it is important to build the right diagram for a thoughtful discussion. It is also important to find
solutions for each of the identified cause and effects of the problem statement.
44
PM Tools & Techniques
Step 1:
Choose a facilitator who can moderate a panel discussion based on research, data collection
and feedback from experts
Step 2:
Identify the experts for the panel discussion
The panel may include the project team, client, industry experts, subject matter experts
Step 3:
The facilitator presents the problem to the panel, so that the panel understands the issue at
hand and that the experts can express their views clearly
Step 4:
The facilitator issues questions for Round N (1, 2, 3…) to the panel through questionnaires or
surveys
The panel provides the feedback anonymously
Step 5:
Based on the feedback from the previous round, the facilitator moderates the discussion
The facilitator collects and summarises the discussion in order to build a consensus
Step 6:
If consensus is not reached, the process is repeated as of Step 4
If consensus is reached, the facilitator concludes the discussion and issues a summary report
containing future events, as well as a plan to tackle each impact to the project
Although the Delphi technique cannot predict the exact future events with certainty, it can however,
based on the opinion of an expert panel, help the project team to understand and take into account
the impact of potential future events, resulting in a more effective and efficient completion of the
project.
46
PM Tools & Techniques
Plan:
This step identifies problems related to the achievement of a project objective or execution.
This can be found out by several methods like the 5 Whys, Root Cause Analysis, and Fishbone
Diagrams, which are also described in this document. The problem statement outlines the
expected output from the solution.
Do:
In this step, several possible solutions are identified. The best alternative is chosen and
applied within the project. This small scale pilot could be involving few resources, limited
geographic area, new business processes, etc.
Check:
This step measures the effectiveness of the solution applied and analyses the outcome. It
identifies the areas of improvement in the solution and refines the processes. The “Do-Check”
steps are repeated until a feasible solution is reached which is in line with the expected output
defined in the Plan phase.
Act:
The solution, with corrective actions identified in the previous phase, is now implemented to
the problem as a whole. The process may not end at this step. In case of continuous process
improvement, the complete PDCA cycle is repeated to keep improving the project
management processes.
The Project Manager (PM) will define any process improvement objectives and run through the PDCA
cycles to achieve each of the improvement objectives. The PDCA cycle can be run or cycled multiple
times to ensure that the team achieves the improvement objectives. This iterative exercise is a
structured way to find and evaluate solutions before any of these solutions are implemented without
proper analysis, foresight and control.
Though the PDCA cycle is a well-structured and methodological process, it has a few limitations. This
method cannot be applied in emergency situations where a quick fix needs to be applied. The process
is time consuming and hence needs to be applied in projects where there is time available for
brainstorming and the implementation of pilot runs. The PDCA cycle is also not effective in adaptive
scenarios where finding a solution is difficult due to high complexity or uncertainty in the system.
48
PM Tools & Techniques
A Make or Buy Analysis helps the organisation to take an informed decision about what to outsource
and what not to outsource. In organisations, portfolio managers and project sponsors are often faced
with the dilemma to make or buy, considering the availability and skills of resources at hand. Project
teams can also use this tool to justify the reasons for the project in a business case, whereby the "buy"
option is an alternative to the preferred choice to "make".
The following lists the potential reasons for which organisations may go ahead with either a Make or a
Buy decision:
Cost effectiveness
Intellectual property concerns
Quality control issues
Supplier unreliability
Cost considerations
Lack of technical expertise
Supplier technical experience
Insufficient resources in house
The changes in the external environment trigger the question of Make or Buy. The various factors that
should be considered for this analysis are: cost comparison, technology and business processes,
supplier related information, and support systems. A final decision on Make or Buy is made after a
detailed analysis of the previous mentioned factors and the effect on the overall performance
measures related to the project. Figure 23.1 below illustrates the Make or Buy Analysis framework to
make a decision.
Technology and
Cost Factors Supply Factors Support Systems
Business Processes
Performance Measures
49
PM Tools & Techniques
Step 1: Preparation
A team is created for the analysis to be done, with an assigned team leader and a defined
objective. The team leader assigns roles and responsibilities for each team member to carry
out during the analysis
Step 4: Feedback
Feedback concerning the final Make or Buy decision is provided to relevant stakeholders. The
decision is supported with the analysis of all the factors involved
The large availability of specialised suppliers delivering high quality solutions, as well as the
proliferation of easily configurable out of the box solutions, often makes the buy option lower in cost.
As a result, it is often difficult to justify taking the make option as the preferred way forward.
Conducting the make or buy analysis generates more informed decisions, and adds to the
transparency of the process of selecting new products or services.
50
PM Tools & Techniques
Competency
This evaluates whether the supplier has the capabilities to deliver the products/services to be
procured. For example, views from other customers regarding the supplier can be considered.
Capacity
This factor indicates whether the supplier has enough capacity to fulfil the requirements. For
example, the supplier should be flexible so that it can handle fluctuations in demand.
Commitment
The supplier should ensure that it has proper standards and quality systems in place to ensure
a continuous supply of qualitative products or services.
Control
This factor evaluates the control capability of the supplier regarding its policies, procedures
and processes in order to ensure a consistent performance.
Cash
The supplier should be financially strong in order to survive through a rough economy,
without jeopardizing the requested qualitative products or services.
Cost
This is the total cost of all products or services to be supplied. The cost, along with all the
other factors, should be considered while evaluating a supplier.
Consistency
The supplier should demonstrate that it has proper procedures and processes in place to
ensure a timely supply of qualitative products or services.
Culture
To ensure a good relationship, the supplier should have similar cultural values as the
organisation. This ensures that both value the same principles for a lasting relationship.
Clean
The supplier should ensure that is has sustainability policies in place related to environment
laws and best industry practices.
Communication
This factor relates to the communication channels to be used by the supplier for notifications,
handling crisis situations and who would be the point of contact within the organisation.
The 10 Cs of supplier evaluation technique tends to change the focus compared to traditional ways of
evaluation, which mainly look at the cost. All factors are important with regards to supplier evaluation,
which would result not only in lower costs but also in consistency and reliability of the supply of the
requested qualitative products or services.
52
PM Tools & Techniques
Step 1: Plan and design the Request for Proposal and the Evaluation
Identify the project or contract objectives and the purpose it will serve in the long term
Determine the evaluation criteria covering all project objectives
Criteria could include several factors like cost, capability, duration and resource skills
Prepare evaluation matrix with weights for each criterion and each supplier
The criteria are reviewed with the central procurement team or other stakeholder
Design the RFP and send it to all the identified vendors or suppliers
Step 2: Form the Evaluation Team
As per the criteria identified include subject matter experts in the evaluation team
Determine team approach in deciding on number of panels and members in the panel
Assign roles and responsibilities to each team member with decision-making authority
Step 3: Conduct the Evaluation
Collate data from RFPs and calculate Total Score for each proposal using the matrix
Analyse the Total Scores of each proposal and any trade off scenarios for each supplier
Document results and different business scenarios with advantages and disadvantages
Step 4: Finalisation
Publish the final results
Hold negotiations with prospective suppliers for any clarifications required based on the
inputs provided in the RFP
Assign a contract or project to the best identified vendor or supplier based on the negotiations
and feedback
Some key points should be kept in mind during the process of the proposal evaluation:
A well-defined evaluation criteria should be outlined in the RFP for supplier selection
It is important to document shortfalls, assumptions and areas of risk for each proposal
The RFP specifications must be clear and avoid ambiguity
Evaluation ratings and weights of criteria should be applied consistently for all suppliers
It is important to define a minimum acceptable score per criteria and in total, particularly if
only one supplier is answering to the RFP
While using the trade-off method for proposal evaluation, there may not always be a clear
recommendation. There may be risks and uncertainties attached to costs, benefits or both. Some of
quantify certain areas of the proposal in order to fit the criteria and evaluation matrix. Qualitative
notes should be prepared taking assistance of subject matter experts for these factors.
Updates to the evaluation criteria or the proposal evaluation process should be documented, so that it
can be used in the next cycle of proposal evaluation.
54
PM Tools & Techniques
Step 3:
Determine the frequency of occurrence for each cause category identified in Step 2
Step 4:
Arrange the cause categories on a histogram with the highest to the lowest frequency of
occurrence
Add a cumulative contribution in percentage terms on the right vertical axis to complete the
Pareto Chart
Step 5:
Identify the top problem categories contributing to 80% of the causes from the Pareto chart
Use root cause analysis methods to drill down on these top causes to find solutions
Sometimes the top problem category identified may be too broad to address. In this case a second
level Pareto analysis may be conducted on the large problem category. This enables to break down the
analysis so as to apply the right solution to the right problem category.
One of the limitations of the Pareto analysis is that it might overlook smaller project issues, which
actually grow bigger with time. Due to low probability or existence of such an issue, it might not get
addressed. However, a small issue might be the root cause of a large problem in the future. In such
cases the Pareto Analysis can be performed at different time intervals in order to understand the top
issues in different phases of the project.
56
PM Tools & Techniques
A checklist can be used to quickly identify whether all activities of the measurement process have
been completed. The checklist should have several questions to assess the way the process of
measurement was conducted.
With the changing project environment the measurement process and criteria also need to keep
changing and evolving. Ensuring that the Project Assessment and Effectiveness measurement process
in in place and adopted can greatly increase the likelihood that the organisation benefits from the
project.
58
PM Tools & Techniques
The SECI (Socialisation, Externalisation, Combination, and Internalisation) model is a framework within
the practise of knowledge creation. New knowledge is created by moving from tacit to explicit
knowledge and back as a continuous process. Understanding the knowledge creation process in a
project is very important so that the project team is able to generate and share knowledge.
Understanding how knowledge and skills evolve and are transferred in and between project team
members is key to ensuring consistent and continuous levels of project performance and quality.
The continuous process of knowledge creation in a project involves two types of knowledge:
The SECI Model postulates that knowledge creation takes place when tacit and explicit knowledge
interact. There are four ways in which knowledge can be created:
Tacit Tacit
Explicit Explicit
59
PM Tools & Techniques
Step 1: Socialisation
During the first stage of the process the knowledge is in the tacit form. The key to acquire such
knowledge from an expert is through socialising by face-to-face interactions, meetings,
brainstorming workshops and sharing knowledge experiences
Step 2: Externalisation
The next step of converting tacit to explicit knowledge can be done through capturing the
acquired tacit knowledge in written or graphical formats. The project team captures the
knowledge gathered in the first stage by documenting concepts, models, hypothesis, graphics,
analogies, metaphors, etc.
Step 3: Combination
This stage combines explicit knowledge, captured from several sources, into one area.
Knowledge documented from various sources is synthesised as to compare different models,
concepts or hypothesis. This generalises several theories and compares the advantages and
disadvantages of different elements
Step 4: Internalisation
By putting this model into practice, the concepts and processes combined from different
sources in previous stages can be taken to the next level. Through action and reflection of
applying the knowledge, the information is internalised. This leads to the creation of new tacit
knowledge, after which the cycle is repeated by going back to Step 1
The knowledge created in a subsequent cycle of the SECI model will always be a higher level. The more
this cycle is repeated, the better the generated knowledge will be. Each stage, iteration and
implementation leads to new knowledge.
60
PM Tools & Techniques
Step 4: Prioritise
Once the opportunities and lessons learned are grouped, they are prioritised for greater focus
This also serves as a review session for all lessons learned and prioritised opportunities
Lessons learned can also be captured on a regular basis and archived. This archive could serve as a
starting documentation for project teams to execute similar projects.
62