HSE Operational Control Procedure For Electrical Work
HSE Operational Control Procedure For Electrical Work
Project : Location :
Project : Location
Sub-Contractor: : Nature of
work:
In portable power tools, the manufacturer molded plug should not be cut and no
22 joints shall be made. Use extension board for extra length, where required
Other than double insulated equipment, all the equipment should have 3 core
23
wires for single phase and five core wires for three phase
When a circuit is de-energized by circuit protective device (ELCB or MCB), the
24 circuit must not be manually re-energized until it has been determined that the
equipment and circuit can be safely energized
All electricians must use Electrical Resistant Rubber Gloves and Safety Shoes
25
or Boots
Prepared By : Approved By :
SE / SS : Project Manager :
Date : Date :