SCHEDULES

This document provides notes for a structural drawing of a building foundation including dimensions, materials, reinforcement details, and specifications. It specifies that the concrete grade will be M20, reinforcement bars will conform to IS:1786 Fe500, and lap splices will be staggered with minimum lap lengths. It also provides concrete cover requirements for columns, footings, beams and slabs. The document is to be read along with related architectural and structural drawings.

Uploaded by

pankaj kushwah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
113 views1 page

SCHEDULES

This document provides notes for a structural drawing of a building foundation including dimensions, materials, reinforcement details, and specifications. It specifies that the concrete grade will be M20, reinforcement bars will conform to IS:1786 Fe500, and lap splices will be staggered with minimum lap lengths. It also provides concrete cover requirements for columns, footings, beams and slabs. The document is to be read along with related architectural and structural drawings.

Uploaded by

pankaj kushwah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

NOTES:-

1. ALL DIMENSIONS ARE IN MM (U.N.O).


2. GRADE OF CONCRETE SHALL BE M20.
3. HYSD BARS CONFORMING TO IS:1786 (GRADE Fe500) / TMT BARS.
4. LAP LENGTH SHALL BE 50 TIMES BAR DIA AND LAPS SHALL BE
STAGGERED.
5. LAP SPLICES SHALL NOT BE PROVIDED.
a). WITHIN JOINT.
b). WITHIN A DISTANCE OF 2d FROM JOINT FACE.
c). CLOSE TO SUPPORT FOR TOP BARS AND CLOSE TO MID SECTION
FOR BOTTOM BARS.
6. CONCRETE CLEAR COVER TO MAIN RFT. SHALL BE AS FOLLOWS :-
COLUMNS = 40MM ALL SIDES.
FOOTING = 50MM AT BOTTOM & SIDES.
BEAMS = 25MM AT TOP, BOTTOM & SIDES.
SLAB = 20 MM AT TOP & BOTTOM.
7. THIS DRAWING SHALL BE READ ALONG WITH THE ARCHITECTURAL

FOOTING SCHEDULE
AND OTHER RELATED DRAWINGS.
8. THIS DRAWING SHALL NOT BE SCALED OFF.
9. CLEAR COVER TO REINFORCEMENT NEAREST TO THE FACE OF A
MEMBER SHOULD BE AS FOLLOWS :-
(a) LONGITUDINAL BAR IN BEAM : 25MM
(b) SLAB: NOT LESS THAN 15MM
FOOTING DIMENSION FOOTING REINFORCEMENT (c) FOR A LONGITUDINAL REINFORCING BAR IN A COLUMN:40MM

FOOTING COLUMN FOOTING (d) FOOTINGS : NOT LESS THAN 50MM

BOTTOM TOP 10. ALL BENT UP BARS SHALL BE BENT AT 45 AND AT L/4 FROM
CONTINUOUS EDGES AND T L/7 FROM CENTER OF SIMPLY SUPPORTED
NUMBERS NUMBERS TYPE L B D EDGES.
ALONG B ALONG L ALONG B ALONG L 11. ALL BENT UP BARS OVER CONTINUOUS SUPPORTS IN BEAMS SHALL
BE EXTENDED BY L/4 OR Ld ( WHICHEVER IS GREATER ) IN TO ADJOINING
SPAN. ( WHERE Ld IS DEVELOPMENT LENGTH OF THE PARTICULAR BAR.)
FC1 C1 Pad 1850 1700 375 T10@175 C/C T10@175 C/C 12. ALL BENT UP BARS OVER CONTINUOUS SUPPORTS IN SLABS SHALL
BE EXTENDED BY L/3 OR Ld ( WHICHEVER IS GREATER) INTO THE ADJOINING

FC2 C2 Pad 1850 1700 450 T10@175 C/C T10@175 C/C T10@175 C/C T10@175 C/C
SPAN.
13. TOP REINFORCEMENT OF ALL CANTILEVER BEAMS , SLABS AND
CROOKED BEAMS SHALL BE TAKEN BY Ld INTO THE COLUMNS OR INTO THE
THIS DOCUMENT IS THE PROPERTY OF KRIBAL ASSOCIATES. ANY IMITATION/REPRODUCTION OF THIS IS NOT PERMITTED WITHOUT PRIOR WRITTEN CONSENT FROM THE OWNER OF THE DOCUMENT.

CFC1 C3,C11,C12 Pad REF PLAN REF PLAN 500 T12@125 C/C T12@125 C/C T12@125 C/C T12@125 C/C
ADJOINING BEAMS OR SLABS. EXTRA TOP SHALL BE PROVIDED FOR
CANTILEVER PART.
14. NO CONCRETE WORK SHALL COMMENCE TILL ALL REINFORCEMENT

FC4 C4 Pad 2250 2100 450 T10@150 C/C T10@175 C/C DETAILS ARE APPROVED BY US AND CHECKED BY THE SITE ENGINEER-IN
CHARGE APPOINTED BY THE OWNER.
15. ONLY ORDINARY PORTLAND CEMENT ( O.P.C ) OF 43 GRADE /53
FC5 C5 Pad 1400 1250 400 T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C GRADE OF APPROVED MAKE SHALL BE USED FOR R.C.C WORK.
16. DISCREPANCIES, IF ANY SHALL BE BROUGHT TO THE NOTICE OF THE
STRUCTURAL CONSULTANT BEFORE COMMENCING THE WORK.
FC6 C6 Pad 2150 2000 425 T10@175 C/C T10@175 C/C 17. ALL MATERIALS USED FOR CONCRETING WORK, i.e., FINE AGGREGATE
( SAND )COARSE AGGREGATE AND WATER SHALL CONFORM WITH LATEST I.
S. CODE OF PRACTICE.
FC7 C7 Pad 2300 2100 450 T10@150 C/C T10@150 C/C 18.
(a)
DE-SHUTTERING :-
WALLS , COLUMNS AND VERTICAL FACES OF ALL STRUCTURAL
MEMBERS: 24 TO 28 HOURS AS MAY BE DECIDED BY THE ENGINEER - IN -
CFC3 C8,C14 Pad REF PLAN REF PLAN 500 T12@125 C/C T12@125 C/C T12@125 C/C T12@125 C/C CHARGE
(b) SLABS ( PROPS LEFT UNDER ) : 3 DAYS

FC9 C9 Pad 1600 1450 325 T10@175 C/C T10@175 C/C


(c) BEAMS SOFFITS ( PROPS LEFT UNDER ) : 7 DAYS
(d) REMOVAL OF PROPS UNDER SLABS;
1, SPANNING UP TO 4.5 M : 7 DAYS

FC10 C10 Pad 1600 1450 425 T10@175 C/C T10@175 C/C T10@175 C/C T10@175 C/C (e)
2, SPANNING OVER 4.5 M : 14 DAYS
REMOVAL OF PROPS UNDER BEAMS AND ARCHES;
1, SPANNING UP TO 6 M : 14 DAYS

CFC2 C13,C20,C28 Pad REF PLAN REF PLAN 550 T12@125 C/C T12@125 C/C T12@125 C/C T12@125 C/C 2, SPANNING OVER 6 M : 21 DAYS

FC15 C15 Pad 1950 1800 400 T10@150 C/C T10@150 C/C
FC16 C16 Pad 2200 2050 450 T10@150 C/C T10@150 C/C
FC17 C17 Pad 1800 1650 375 T10@175 C/C T10@175 C/C
FC18 C18 Pad 1700 1550 350 T10@175 C/C T10@175 C/C
FC19 C19 Pad 2400 2200 475 T10@150 C/C T10@150 C/C
FC21 C21 Pad 1150 1000 350 T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C
FC22 C22 Pad 1650 1500 425 T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C
01 03/08/2022 SECOND ISSUE AD
FC23 C23 Pad 1800 1650 350 T12@150 C/C T12@150 C/C 00 27/07/2022 FIRST ISSUE AD

FC24 C24 Pad 1700 1550 350 T12@150 C/C T12@150 C/C REV. DATE DESCRIPTION BY

FC25 C25 Pad 1600 1400 325 T10@175 C/C T10@175 C/C PROJECT:-

G+1 RESIDENTIAL AT SEONI. RAIPUR


FC26 C26 Pad 1750 1700 400 T10@175 C/C T10@175 C/C
FC29 C29 Pad 1650 1500 400 T10@150 C/C T10@150 C/C T10@150 C/C T10@150 C/C ARCHITECT:-

FC27 C27 Pad 1600 1400 400 T10@150 C/C T10@150 C/C YND STUDIO

FC30 C30 Pad 1600 1450 400 T10@150 C/C T10@150 C/C

KRIBAL ASSOCIATES
STRUCTURAL CONSULTANT
428, GOLDEN TRADE CENTRE
NEW RAJENDRA NAGAR
RAIPUR (C.G)
PH: 9713711228
N
DRAWING TITLE
FOOTING DETAILS W E

DWG NO. 04 S

DRAWN BY GANESH THORAT NTS DATE 27/07/2022


DESIGNED & ABHINAV DAGA REV. NO. 01 SHEET NO. 02
CHECKED BY