Gantt Chart (OFMS) - 1

The document outlines a project schedule spanning from July 2022 to November 2022. It includes 30 tasks related to brainstorming, requirements gathering, analysis, design, testing, maintenance, and documentation of a project. The tasks have defined durations, start and finish dates, and show dependencies between tasks.

Uploaded by

Sagun Shrestha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
25 views

Gantt Chart (OFMS) - 1

The document outlines a project schedule spanning from July 2022 to November 2022. It includes 30 tasks related to brainstorming, requirements gathering, analysis, design, testing, maintenance, and documentation of a project. The tasks have defined durations, start and finish dates, and show dependencies between tasks.

Uploaded by

Sagun Shrestha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

17 Jul 22 24 Jul 22

Name Duration Start Finish Predecessors


S M T W T F S S M T W T
1 Brainstorming 2 days 7/20/22 8:00 AM 7/21/22 5:00 PM
2 Topic selection 1 day 7/20/22 8:00 AM 7/20/22 5:00 PM
3 Problem Statement 1 day 7/21/22 8:00 AM 7/21/22 5:00 PM 2
4 Requirement Gathering 8 days 7/22/22 8:00 AM 8/2/22 5:00 PM 1
5 Functional Requirement 3 days 7/22/22 8:00 AM 7/26/22 5:00 PM
6 Non functional Requirement 2 days 7/27/22 8:00 AM 7/28/22 5:00 PM 5
7 Hardware and Software Requiremnt 3 days 7/29/22 8:00 AM 8/2/22 5:00 PM 6
8 Analysis 9 days 8/3/22 8:00 AM 8/15/22 5:00 PM 4
9 Discussion 1 day 8/3/22 8:00 AM 8/3/22 5:00 PM
10 Literature Survey 8 days 8/4/22 8:00 AM 8/15/22 5:00 PM 9
11 Design 20 days 8/16/22 8:00 AM 9/12/22 5:00 PM 8
12 Homepage 3 days 8/16/22 8:00 AM 8/18/22 5:00 PM
13 About page 2 days 8/16/22 8:00 AM 8/17/22 5:00 PM
14 Database Design 20 days 8/16/22 8:00 AM 9/12/22 5:00 PM
15 Registration Page 10 days 8/16/22 8:00 AM 8/29/22 5:00 PM
16 Login Page 5 days 8/30/22 8:00 AM 9/5/22 5:00 PM 15
17 HOD page 3 days 9/6/22 8:00 AM 9/8/22 5:00 PM 16
18 Faculty Page 2 days 9/9/22 8:00 AM 9/12/22 5:00 PM 17
19 Student Page 3 days 9/6/22 8:00 AM 9/8/22 5:00 PM 16
20 Contact page 2 days 9/9/22 8:00 AM 9/12/22 5:00 PM 17
21 Testing 18 days 9/13/22 8:00 AM 10/6/22 5:00 PM 11
22 Unit Testing 12 days 9/13/22 8:00 AM 9/28/22 5:00 PM
23 Integration Testing 9 days 9/13/22 8:00 AM 9/23/22 5:00 PM
24 Functional Testing 6 days 9/13/22 8:00 AM 9/20/22 5:00 PM
25 Manual Testing 6 days 9/29/22 8:00 AM 10/6/22 5:00 PM 22
26 Maintainance 12 days 10/7/22 8:00 AM 10/24/22 5:00 PM 21
27 Documentation 11 days 10/25/22 8:00 AM 11/8/22 5:00 PM 26
28 Site Installation 4 days 10/25/22 8:00 AM 10/28/22 5:00 PM
29 Prototype Feedback 4 days 10/31/22 8:00 AM 11/3/22 5:00 PM 28
30 Backtracking and Report 3 days 11/4/22 8:00 AM 11/8/22 5:00 PM 29

Gantt Chart(OFMS) - page1


24 Jul 22 31 Jul 22 7 Aug 22 14 Aug 22 21 Aug 22 28 Aug 22 4 Sep 22 11 Sep 22 18 Sep 22 25 Sep 22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Gantt Chart(OFMS) - page2


25 Sep 22 2 Oct 22 9 Oct 22 16 Oct 22 23 Oct 22 30 Oct 22 6 Nov 22 13 Nov 22 20 Nov 22 27 Nov 22
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

Gantt Chart(OFMS) - page3


Nov 22 4 Dec 22
M T W T F S S M T W T

Gantt Chart(OFMS) - p...

You might also like