Validation of Power Plant Transformers Re-Energization Schemes in Case of Black-Out by Comparison Between Studies and Field Tests Measurements
Validation of Power Plant Transformers Re-Energization Schemes in Case of Black-Out by Comparison Between Studies and Field Tests Measurements
Abstract-- The EHV network and power plant restoration Transmission over-
head lines
plan is a key process of a fast re-energization of customers.
Source Large power Target
The first step after a black-out consists in re-energizing lines Power transformer
and transformers, both on the network and in power plants, as plant
soon as possible, without taking too much risks. To validate the
strategy based on identified schemes, the following methodology
is detailed: first the critical point to deal with is the evaluation, by
using computation tools, of the temporary harmonic overvoltages Fig. 1. Network configuration studied in the case of transformer switching
generated by the transformer re-energization. If the conclusion is The source power plant is a large power plant generally
positive, field tests are performed. Finally, measurements are connected to the 400kV network and is used to re-energize an
compared with simulations results in order to validate the initial
auxiliary transformer. EHV lines are 50 kilometers long, and
feasibility study.
Keywords: black-out, transformer re-energization, field tests. in some cases can reach 250 kilometers. It must be necessary
sometimes to re-energize firstly an intermediate network
I. INTRODUCTION transformer.
In the case presented hereafter, a large network transformer
After a black-out, an initial energizing step is required
(3x357 MVA) has been switched on, located at 50 km of a
before completely restoring the electrical power to consumers.
900 MW power plant. EDF has experience on several schemes
Very weak networks can be used to re-energize, through
where 96 MVA auxiliary power plant transformers are
unloaded EHV lines, one or more other power generating
switched on, with both studies and field tests, but it was the
units. The first steps may consist in:
first time in France that such a large transformer was re-
- identifying the power plants islanded, that can be used
energized with such a network.
to restore power to those out of power in order to
secure them in priority,
II. EVALUATION OF THE TEMPORARY HARMONIC
- re-energizing the auxiliary transformers of the power
OVERVOLTAGES
plants out of power, and supplying the auxiliaries,
- re-connecting as soon as possible power plants together The energization of power transformers may create
through EHV lines, and supplying the load. saturation of the transformer magnetic core and can lead to
The main problems encountered during the first step of re- large harmonic temporary overvoltages due to high inrush
energizing transformers are steady state and transient currents. Key parameters for the analysis of such overvoltages
overvoltages that can damage electrical devices connected to are the following ones :
the network to restore. •• The resonance frequency of the network;
The following figure gives an example of topology of the •• The losses of the network, dependant on its resonance
studied network schemes. frequency, and the load connected to the network;
•• The saturation characteristic of the transformers
feeded by the network;
•• The voltage level at the end of the EHV lines.
In order to minimize both steady state and transient
overvoltages, the setting point of the source power plant
automatic voltage regulator is reduced to its minimum value,
François-Xavier Zgainski, Bruno Caillault, Vincent-Louis i.e. usually 0.9 p.u.
Renouard are working at EDF-DTG (General Technical Department), avenue
de l'Europe, 38000 Grenoble, France (email [email protected],
Furthermore, the levels of overvoltages and inrush currents
[email protected], [email protected]) depend also on the initial conditions of the switching :
•• closing times of the circuit breaker poles;
Presented at the International Conference on Power Systems •• remanent fluxes in the core of the transformer to
Transients (IPST’07) in Lyon, France on June 4-7, 2007
switch-on.
A. Description of the modeling of the network possible yet to reduce these uncertainty ranges, because of the
The electrical components of the network are modeled differences still remaining between simulations and field tests
using the EMTP tool. measurements ( see part III section C).
The generator is represented by a perfect voltage source In order to consider the uncertainty domain corresponding
with a resistance and an inductance that are obtained by a to these two parameters, which have an influence on the
computation based on the sub-transient values of the network resonance frequency value, 25 couples of values are
inductance and of the time constant. This simplified model is defined. Each couple has the same probability to fit with the
adapted for [100Hz-500Hz] frequency range resonances [7]. real value, and is thus associated with a network frequency
Its simplification is compensated for by taking into account value, which proximity with an harmonic of the 50Hz will lead
uncertainties on the value of the inductance (see section B). to particular resonances.
The line sections are modeled by using matrix PI section For each couple defined, 100 computations are done
model that deals with both electrical and magnetic coupling statistically to deal with the random switching initial
between each electrical conductor. One PI section is used for conditions: closing times of the circuit breaker poles, and
every 25 kilometers line section. In order to represent the remanent fluxes in the transformer core.
losses, parameters are calculated at the network resonance These initial conditions are considered as random
frequency. A good geometrical description of the over-head conditions because they can not generally be imposed and
line towers is provided. controlled. We use measurements in order to have an idea of
The transformers are described by three single phase their extreme values and apply random laws on these
transformers, described by a classical model shown on the conditions. The closing times rules are the following ones : the
following figure, that takes into account the iron losses, the first pole of the circuit breaker is closed anytime on one time
resistances of each conductors, and the short circuits values of period, and the second and third pole are closed with a
the transformer. standard deviation of 20 ms (i.e. one period of 50Hz). The
remanent flux values follow a uniform distribution, and are
RCu2 Ll2 Ll1 RCu1
supposed to reach 0,8p.u. [7]; due to the winding delta
connection always present in the power plant or network
MV side RFe L(λ) EHV side transformers considered, the sum of the three remanent flux
values is assumed to be equal to zero.
Fig. 2. Transformer model used in this study The saturation curve, and especially the Lsat i.e. the final
The non linearity of the transformer magnetic core is slope of this curve, is a key point for the computation of the
modeled by a non linear inductance - characterized by a curve inrush currents but is not very easy to obtain. The transformer
of the flux versus the current (flux(I)) – put in parallel with the manufacturer provides a Lsat slope value with a dispersion
iron loss resistance. For the target transformer, hysteresis is usually considered of +/-20 %. The lower value is taken in the
added, in order to take into account the remanent fluxes in the simulations.
iron core. Each pole of the circuit breaker is represented by an The results of the computations are the estimated
ideal switch in order to statistically modify the different probability to get overvoltages higher and longer than the
closing times of each pole. limits prescribed. The voltages and currents curves are also
analyzed to verify the realism of the computations, as
B. The methodology defined for the studies
illustrated below.
The simulations are made to check that the overvoltages
levels and durations stay under the admissible limits given by C. Results of simulations
the constructor, or, if not, within limits and proportion judged The following figure gives the simulation results obtained
acceptable, considering the strategic importance of the in one of the worse cases computed at the switching of the
transformer, situated in a power plant or on the network, and transformer.
considering the potential different solutions existing for re-
energizing it. 600000
In order to take into account the uncertainties on the key 400000
parameters of the network, a large number of computations V1 (V)
have to be performed. 200000 V2 (V)
V (V)
lines (Cϕ/t) is supposed to be known at +/- 5%. It hasn’t been Fig. 3. Three 400kV phase to earth voltages simulated in one case.
The currents and the voltages signals can be distorted
during several seconds. A natural frequency resonance is
superimposed on the fundamental frequency because of the
resonance between, on the one hand, the inductance of the
generator and the non linear inductance of the transformers,
and, on the other hand, the capacitance of the lines. If the
resonance frequency is close to an harmonic of the 50Hz, the
switching can lead to high resonances, during several seconds
(see fig. 4).
600000
EMTP-3.1 (300 curves)
400000
200000 V1 (V)
V (V)
V2 (V)
0
V3 (V)
-200000
-400000
t (s)
-600000
0,4 0,42 0,44 0,46 0,48 0,5
PHI1 [V]
quick phenomenon during a long time. The accuracy of the 900
measurements. -300
The voltages are measured via on site measuring voltage
PHI2 [V]
transformers. The error on the voltages are less than 0,5% for 600
the voltages between 0,8 and 1,2 Un. For the higher values, the
300
error can reach 3% for the phase–to-earth voltages, and 6% for
the phase-to-phase voltages. 0
1500
transformers for example, the specified precision has not been 1200
effects [3].
300
0
61,8 62,1 62,4 62,7 63 63,3
IV. COMPARISON BETWEEN SIMULATIONS AND [s]
MEASUREMENTS Fig. 7. Computation of the remanent fluxes on the three phases of the
transformer
The initial conditions of the tests are evaluated from the
The starting of the integration is determined in order to get
measurements. These data are put in our models, always
steady-state fluxes without any DC component before this
taking into account the dispersion on the network
disconnection. Nevertheless, we have a superimposed 50 Hz
characteristics. Then, a rather good comparison between
AC component in the measured signal probably due to the
measurements and simulations allows to validate the re-
capacitance of the circuit breaker. Because of the remanent
energization scheme. Furthermore, both models adopted and
induced voltages and therefore sinusoidal fluxes after the
their data are improved.
disconnection of the transformer, we consider that the
A. Initial conditions remanent flux values can’t be obtained with a precision better
The initial conditions are obtained via the analysis of the than +/- 10%.
measurements, i.e. the closing times of the three poles of the B. Comparison criterion in order to compare
circuit breaker that switch on the transformer, and the simulations to measurements and validate the models
remanent flux values in the transformer iron core.
The inrush currents give a lot of informations: the initial
conditions (instants of switching on), the peak current values
and their attenuation, and help to build the magnetization •• Influence of the initial conditions :
cycle of the transformer.
-700
The comparison criterion between measurements and
350 400 450 500 550 600 650 700 750 800
simulations data is firstly based on the maxima of inrush -750
currents. A mean square error computation allows to fit the -800
computed values within the uncertainty range adopted. Other -850
I2max(A)
type of comparison can also be used, like the comparison of
-900
the shapes of both the voltages and currents curves (peak
values, attenuation,… ) or the comparison of the harmonic -950
rates and attenuation. -1000
Simulations
C. Sensitivity analysis -1050 Measure
The analysis presented has been done on the peak values -1100
I1max (A)
of two of the three currents, reached at the re-energization of
the transformer. One simulation parameter is changed at a Fig. 10. Influence of the initial conditions on the peak currents computed and
compared to the measured currents
time in order to have an idea of the sensitivity on the results.
Initial conditions, that is to say the remanent fluxes
We have developed a software based on Matlab, that allows
multi parameters analysis and comparison between (supposed to be known in a range of +/-10%) and the closing
simulations and measurements. In the following figures, we times of the circuit breaker (supposed to be known in a range
plot the maximum current on phase 2 (I2max) as a function of of +/-1ms), seem to be in that case the most influent factors.
the maximum current on the phase 1 (I1max) : both
simulation results and measurements are plotted for It is therefore possible to adjust and optimize these
comparison. uncertainties in order to try to fit the current maxima
•• Influence of the uncertainties taken in the models: (measurements and simulations). As an illustration, the
following figures show, on the currents waves, the comparison
-750
between measurements and results of simulation.
I2max(A)
Simulations Lsat=0.16pu 0
-1050 Measure -200
Simulations Lsat=0.2 pu -400
-1100 Simulations Lsat=0.24 -600
-1150
-800
-1200 -1000
I1max (A)
0,08 0,1 0,12 0,14 0,16 0,18 0,2 0,22 0,24 t (s)
Fig. 8. Influence of the Lsat value on the peak currents computed and
compared to the measured currents Measurements
The previous figure shows that for a chosen set of initial 1000
J1computed (A)
conditions values, increasing the Lsat value within its 800
J2computed (A)
uncertainty range leads of course to decrease the values of the 600
J3computed (A)
400
peak currents. The influence is significant, and it shows that 200
I (A)
VI. REFERENCES
[1] Hermann Dommel, “EMTP Theory book”; Hermann Dommel, 1992
edited by Microtran Power System Analysis”, Vancouver, Canada.
[2] J. Mahseredjian, S. Dennetière, L. Dubé, B. Khodabakhchian, L. Gérin-
Lajoie, “On a new approach for the simulation of transients in power
systems”, IPST 2005, Montréal.
[3] Technical Notice of The EDF Transmission Network Division on the
measurement transformers. 1991.
[4] M. Rioual, C. Sicre, “Energization of a no-load transformers for power
restoration purposes. Impact of the sensitivity of the parameters”, in Proc.
2001 IPST International Conference on Power Systems Transients, pp 221-
227, Rio de Janeiro, Brasil, June 2001.
[5] Sébastien Dennetière, Jean Mahseredjian, Manuel Martinez, Michel
Rioual, Alain Xémard, “On the implementation of a hysteretic reactor model