JSA For Hydro Jetting, Removal and Cleaning of Sludge

Uploaded by

sk sajid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views18 pages

JSA For Hydro Jetting, Removal and Cleaning of Sludge

Uploaded by

sk sajid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 18

JOB SAFETY ANALYSIS (JSA)

TANK MODIFICATION AND REPAIR WORK

JSA Number: JSA Title:


Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
1. Site preparation  Poor communication M  DESCON employees shall have mandatory training. L
between work parties.  Work permit from the client, with all concurring parties signatures
approval must be obtained prior to start of work and display at
site
 Safety requirements stated on the work permit must be available on
 Inexperience persons / lack site and strictly followed
of safety awareness  Toolbox talk shall be conducted to all personnel on site &
documented before start of work.
 Appropriate PPE shall be worn by all personnel at site.
 Assigned trained dedicated Banks man for job with reflective jacket.
 No water no work policy shall be followed.
 Heat stress  Work Schedule according to heat Index
 Ear protection shall be worn where required.
 Noise  Noise meter will be made available at site.
 Maintenance of equipment on regular basis.
 Vehicles Movement  Use of Approved/Trained license drivers.
 Vehicle movements on site shall be controlled by banks man
 Appropriate signage to be provided.
JOB SAFETY ANALYSIS (JSA)
TANK MODIFICATION AND REPAIR WORK

JSA Number: JSA Title:


Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
2. Transportation of  Failure of equipment M  Conduct toolbox talk and LMRA prior to start of work at L
material to Work /crane /Trailer/ Pickup/ the specific location.
location including Truck etc  Ensure the condition of equipment, inspected, sticker Placed
removal of sludge  Road traffic accident during and for appropriate color code.
drums etc transportation of Tanks  All rigging gear shall be certified.
By Using Crane shell plates, pipe spools/  Synthetic belt or nylon sling shall be used instead of
,Trailer, Boom Truck supports and other steel wire rope for holding of material.
Pickup etc material.
 Ensure crane operators and riggers fully understand all work
tasks and hazards.
 Load shall be secured on the trailer bed to
 Body part injury during prevent accidental fall.
loading and unloading  Crane operator shall have the third party, certified
operation and applicable license.
 Use proper tag line during loading /off loading material.
 Access route shall be surveyed before transporting the Shell
Plates ,pipes & support material etc.
 Barricade with appropriate sign board on the effective area.
Riggers shall be experienced and third party certified.

2
JOB SAFETY ANALYSIS (JSA)
TANK MODIFICATION AND REPAIR WORK

JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK


Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 Use leather gloves for hand protection.
 Pinch point.  Keep away body parts (hand, feet, head, e.t.c) from the line
of fire (LOF).
 Suitable length of trailer shall be arranged according to
length of Shell Plates, pipe spools, supports etc.
 Vehicle hit to existing  Red flag at the back end of long pipe spool shall
facility be provided.
.  Site specific traffic rules shall be followed.
 All vehicle movements will be controlled by a certified banks
man.
 Banks man shall be provided for reversing vehicle.

3
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
3. Confined space  Lake of Communication H  All personnel working in confined space must have L
entry. confined space training.
 PRL confined space procedure shall be followed.
 Hole watcher is attentive all the time during confined
 Ventilation. space activity. Lighting provided in CSE to be 24V.
 Easy communication between hole watcher and supervisor
 Damage material is established all the time.
 Ensure that passage and transport rout is clear during
 Oxygen deficiency confined space activities. Proper access/agrees should be
accumulation of toxic maintained.
gases  Gas test to be done by AGT prior to entering into
the confined space.
 A trained and qualified individual should outside the tank
with the responsibility of ensuring the safety of authorized
entrants (Fabricator, Fitter, Welder e.tc) through the
performance pre‐entry briefing, checking and inspecting
 Physical hazards PPE, equipment and tools and performing regular
monitoring in ensuring person working inside pipe remains
safe for entry and occupation.

4
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 A written rescue plan that has provision for conducting a
timely rescue of individuals working inside the pipe
(Confined Space) should be kept on site. Raising the alarm
in the event of an emergency using the radio/mobile
phones provided to them.
 Ensure effective communication systems for the entry are
tested.
 Improper stacking of  Proper light should be provided less than 25v.
material  All material stack proper and category wise.
 Rescue arrangement shall be made while working more
than five meter inside large bore size.
 Unauthorized entrant  PRL SHE&S Procedure shall be followed.
 Close supervision required while working inside.
 Lack of oxygen  Execute the work under close supervision and presence of
/oxygen/ air hole watcher.
deficiency  Proper air supply to be provided or air mover will
be provided.
 Proper ventilation shall be there.
 Working crew shell be trained for confined space working.

5
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
4 Preparation of  Damage of original flange M  Proper and valid PTW to be obtained where applicable
water jetting of pipeline  Supervisor to conduct Tool box Talks and fill SAP
Tightening(manual  Property damage Sheet before start of activity.
and by machine)  Machinery, equipment or  Engineer/Supervisor to plan the job before starting activity.
portable tools in poor  Supervisor to ensure the availability of Method Statement,
condition/substandard Safe Work Method Statement & Risk Assessment at job
 Damage of stud threads location
 Supervisor having good communication skills
 Communication to manpower in the language they
understand
 Proper communication means (e.g. radio) to be provided
 Deployment of skilled manpower
 Follow safety precautions for rigging job.
 Use tools as per job requirement
 Use of uncertified /  Physical inspection of tools before each use for wear & tear
un‐ calibrated  Supervisor to ensure availability of proper and sufficient
equipments quantity of PPE’S

 Personal injury

6
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 Use all PPE’S as per job requirement
 Damage of threads of studs  Keep away hands and body parts away from the trap point.
 Pre/post inspection of equipment/ machinery will be
conducted.
 Tightening of studs will be in sequence to make leak
 Leaking during hydro proof joints.
testing  Gaskets will be placed between flanges.
 Adequate supervision will be at all work places.
 Calibrated equipment with certificates will be used
 Defective equipment  Use of proper and defect free tools / equipment
 Safety device of equipment in functioning condition (e.g.
 Uncelebrated gauges relief valve)
 Pressure relief safety valve (PRSV) Gauges tested and
 Unauthorized entry calibrated. Manifest tested and certified.
 At appropriate distance & proper hard barricade for above
and underground job points.
 Use appropriate safety signboards for air flushing / cleaning
job

7
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 Slipping/tripping  Barricade the affected areas with sign board.
 Full time supervision of the job.
 Inspect affected areas to ensure it does not conflict
 Personal injury with other activities.
 All connection to be checked for tightness and secured with
correct hose clamps safely and whip device.
Filling of water  Leaking M  Engineer/Supervisor to plan the job before starting activity.
in line / tanks  Information to working groups in surrounding area about
with this activity.
pump/manual  Property damage  Supervisor to recheck isolation and lock out / tag out
before starting job
 Use of proper tools for the job & no misuse of tools
 Personal injury  Crew will be available to tight the flanges during water
filling if needed.
 Environmental problem  Water filling will be done smoothly to ensure leak proofing.
 Securing from tripping hazard will be ensured by proper
house keeping
 Apply Lock out/Tag out procedure to each valve isolating

8
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
from connected system.
 Use appropriate blind valve.
 Team will be alert to attend any leakage.
Building up required  Working without PTW M  Engineer/Supervisor to make sure valid PTW made available
test pressure ready on site.
for water jetting  Improper planning  Engineer/Supervisor to plan the job before starting activity.
 Supervisor to conduct TSTI and step back 5x5 &
 Unauthorized personnel communicate hazards associated with the job to working
entry group
 Information to working groups in surrounding area about
this activity.
 Area will be properly barricaded
 Patrolling of the barricaded area will be done from
outside the barrier
 Supervisor to have sufficient communication means e.g.
 Uncelebrated gauges radio or cell phone
 Supervisor to recheck isolation and lock out / tag out
before starting job

9
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 Poor lighting during  Adequate lighting arrangement should be made available
evening / night (100~150 Lux Minimum).
 Use of Improper tools  Use of proper tools for the job & no misuse of tools
 Personal injury  Appropriate PPE’S will be worn as per job requirement and
job atmosphere / environment
 Property Damage  Workers attending equipment will not leave the equipment
 Damage of flange un‐attended and wear applicable PPE’S
 Supervisor to communicate & ensure that no tightening of
flanges will be done whilst the line is under pressure.
Place warning tag Do not Operate & Under Pressure.
 Only calibrated gauges to be used
 Environmental problems
 Periodic checks for leakage to be done
 Maintain working area clean and tidy.
 Pressure will be built smoothly.
 Pressure will be recorded during building up pressure.
 Team will be alert during the phase.
 Improper access and
egress.  Signboards of hydro testing will be placed.

10
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 Authorized entry will be ensured to avoid personal injury in
case of leaking.
 Proper access will be provided for emergency.
 Heat stress  Only suitably qualified and experienced personnel will be
deployed at all work faces.
 Adequate venting will take place at all high points to
release entrapped gas / air
 Ensure availability of cold water at job site in summer
 Drink water frequently to avoid dehydration in summer
 Ensure availability of heat stress shelter at job site
in summer
 Improper communication
 Act as per instructions against each flag color to
 Poor emergency response
prevent yourself from heat stress in summer
 Ensure availability of 1st aider, 1st aid kit and list of
1st aiders at job site
 List of emergency numbers to be made available Sup. To
have Descon Emergency Numbers Card
 Vehicle to be there at job site to be used in case of medical

11
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
emergency / personal injury
5 Water jetting  Damage equipment / H  Equipment should be inspected before used. L
/cleaning removal poor maintenance  Proper equipment maintenance should be done.
of sludge from tank
 In experience person H  Operator should be experience and qualified L
 Falling over /slip trip M  House keeping and job area to be reviewed and clean up L
and fall if necessary prior to commencing job.
 Extreme care to be taken inside confined space
 Non Protection of body H  Ensure standard PPE is worn as a minimum and wear L
part other item identified
 Hazardous Atmosphere M  Carefully read and follow the confined space entry permit L
requirements ie breathing apparatus LEL etc
 Cutting of limbs/ hit M  Hose restrainers to be installed on hoses before L
to body part. commencing work.
 Hand gun fitted with control trigger , cleaning to
be control be by hand gun.
 Safety watch should be provided,
 Area should be barricaded.

12
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 Gun barrel to be minimum of 1.2 meters
 Gun hose or lance operator to ensure his stance is
braced and firm.
 To avoid direct pressure of jet at limbs work facing away
from the body.
 Noise M  Ear muff / plug must be worn by all people in the L
immediate vicinity of the work being carried out and at the
jet.
 Whipping around M  All hose connections must be fitted with clips or some L
method of restraining device at all time.
 Injury to operators M  Pressure ratings to be checked , al hoses and fittings to L
be checked from damage prior to use.
 Overriding safety switch M  No live gunning will be permitted at any time. L
6  Manual handling /  Pinch points. M  Supervisor will be responsible to complete safe activity pre‐ L
Shifting of sludge  Hand injury  Use appropriate PPE’S as per job requirement.
 Maintain good housekeeping to avoid injuries.
 Plan before manual lifting
 Use manual handling / lifting Aids like trolley etc.

13
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
 Ensure no obstruction at job point, access/egress
 When long period of manual handling is required, give
 Drop of material. appropriate breaks.
 Keep the load as close to body as possible.
 Keeping load away from  Move feet rather than twisting back during manual
body handling.
 Avoid wearing tight clothing which may restrict body
 Muscular skeletal disease, movement
 Back pain  Ensure strong gripping during manual handling
 Bend your knees and not back during manual handling
 Lifting by bending back / lifting
 Use legs a the pivot point to raise or lower body with
the back straightened when lifting or lowering load
 Lifting unmanageable load  Shoulders should be kept level.
 Look ahead, not down at the load, once it has been
held securely.
 Material handling tools or equipment, such as barrows and
trolleys, should have handle heights that are between the

14
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
shoulder and waist.
 Such tools or equipment should be well maintained,
with wheels that run smoothly.
 Exhaustion  Assistance should be provided to handlers negotiating a
slope or ramp.
 Loads should travel over a smooth & even surface.
7 Extended  Inadequate lighting in and M  Adequate lighting at work area and Access/Egress area. L
hour/night Works around work areas, Emergency route to muster point to be clearly illuminated.
(Actual works will causing shadows or poorly  Proper cable management
be the same as lit work areas that could
 Use clear safety glass for night work for good visibility.
day work) result in unsafe acts and
 Warning Lights and sign boards.
injuries taking place
 Trained Flag man for equipment movement provided with
signal torch.
 Close supervision required while working in night shift.
8 Emergency  Poor Communication M  Educate the workforce about Emergency Procedure. L
Procedure /  All safety sign board shall be displayed properly at site.
Response  In case of any Emergency all work will be stopped, Shut

15
JSA Number: JSA Title: TANK MODIFICATION AND REPAIR WORK
Area: Activity: Hydro jetting , removal and cleaning of sludge etc Date

Task Description Hydro jetting , removal and cleaning of sludge etc

Uncontrolled Residual Risk


Risk
Step Activity Hazard H M L Control Measures H M L
down all running equipment & Machineries and reported to
Muster Point
 Improper Access/ Egress  Proper Access & Egress shall be available.
 All Workforces shall know the Muster Point location.
 PRL Emergency Procedure to be followed.
 Emergency # 00000000
 PRL Medical # 00000000
9 House keeping  Trips and fall M  All waste generated shall be contained and disposed off in L
designated waste skips.
 Sharp Objects  Do not store materials/equipments inside the plant area.
 Use Proper Personal protective equipment for handling of
 Equipment damage waste.
 All materials shall be removed from the site to a
safe storage location immediately after the work.

16
Approved
Signature Print Date

Performing Party
Signature Print Date

17