Estimation All
Estimation All
Estimate
to calculate the quantities required and then estimating the cost at suitable rates. This
can provide the expenditure likely to be incurred in the construction of the work or
information and knowledge about the work which is to be executed, hence financial
information. In doing so, the time required for completion, the investment required
and return of the investment can be obtained. In addition to a probable cost for the
work, it is also crucial to assign the specification of the construction for the work.
Purpose of Estimating
probable cost of the project can be determined. Thus, an estimate gives a close
approximation of the natural cost, the true value of which will not be known until the
project is completed and all costs are recorded. An estimator does not establish the
this simply establishes the amount which the contractor will receive for construction
the project.
project.
Know the cost of the project and finance required by the owner.
1
Ascertain the quantities of the materials required and sources of their
availability/ supply.
unskilled.
completion.
To make out estimate for a work or a project, the following data are needed:
1- Drawing: plans, sectional elevations and detailed drawings to scale and fully
2- Specifications:
work separately, in detail and are beneficial for the execution of the
3- Rates: the rates per unit of various items of work, the rates of various materials
2
skilled or unskilled as mason, carpenter, etc.., are available for preparing
estimates.
Types of Estimates
1- Approximate or Preliminary Estimates
agency will need to know the approximate cost before holding a bond election.
construction is desirable for tax purposes. For these purposes, the use of
volume then multiply the number of units by the estimated cost per unit; or
the estimated cost per cubic meter to determine the probable cost of the project.
It is also essential for an estimator to adjust the unit costs to allow for variations
construction difficulties.
For Example:
- Sewerage & water supply project: On the basis of per head of population
3
2- Detailed Estimates
submitting of bids or the entering into contracts for important projects. When
preparing a detailed estimate for a given project, the estimator should divide
1. Cleaning Site
This operation is also called site preparation which is one of the preliminary works to
be done for starting of construction works. The selected construction site needs to be
completed properly before the start of construction processes. In the site preparation,
all the scrubs, jungle or organic soil must be removed up to a certain depth, based on
2. Excavation
This work includes the excavation of cellars, piles, water tanks, trenches, septic tanks
and/or foundations. In this work, the surface soil is to be excavated with respect to
After having done the excavation, it might be necessary to place sand or crushed stone
and compact up to maximum 20cm depth. Samples may be taken for every 500m2 and
4
Example (1):
Estimate the amount of soil excavated for the construction of a raft foundation. It is
also known that 1.5m around the foundation should also be excavated with a depth
of 0.8m.
Solution:
D=0.8m
A 33 48 1584 1267.2
B 30 33 990 792
C 30 18 540 432
5
Detailed Estimate
There are two methods for calculating the quantities of materials of walls including
excavations:
The length of longer wall is measured in longitudinal direction end to end and the
short wall is measured inside to inside of long walls at every change of step or section.
These lengths are multiplied by breadth and depth or height to obtain the quantities.
Example (2):
Estimate excavated material quantity using long and short wall method for the
Solution:
Long walls = (10.8+0.8)*2= 23.2 m.l or Long walls = (10+ (2*0.8))*2= 23.2 m.l
6
Excavation= L*B*D
= 31.2*0.8*0.8 = 19.967 m3
Centre to centre distances of long and short walls having similar section are measured
𝟏
𝑸𝒖𝒂𝒏𝒕𝒊𝒕𝒚 = [(𝑳 – (𝒏 ∗ ∗ 𝑩)) ∗ 𝑩 ∗ 𝑫] (𝟑. 𝟏)
𝟐
Where:
L = total length
n= number of junctions
B= width or breadth
D= height or depth
This method is quick but requires special attention and consideration at junctions,
meeting points of partition or cross walls, etc. Therefore, for buildings having cross or
partition walls, for every junction or partition or cross walls with main walls, special
Example (3):
For the previous example estimate the quantity of the excavated material using centre
line method.
Solution:
7
Quantity = 31.2 * 0.8 * 0.8 = 19.968 m3
Example (4):
Estimate the quantity of the excavation material of a foundation shown below using
centre line method. If both the breadth and depth are 70cm.
Solution:
3) Crushed-Stone
spread over the base of the excavation with a certain thickness (8cm- 10cm). This is
8
advantageous to prevent water entering the soil beneath foundations during
Example:
Solution:
L= 39.4 m
Q=L*B
Concrete is a composite material consisted of water, gravel and sand (filler) embedded
in a hard matrix of material and the cement that fills the space among the aggregate
1 1.5 3
1 2 4
1 3 6
1 4 8
1 5 10
For low strength concrete works, (1 : 4 : 8) or (1 : 5 : 10) can be used e.g. plain
9
For normal foundation works and unreinforced floors, (1 : 3 : 6) can generally
be used.
For reinforced concrete works such as slabs, beams, stairs, joists and etc., (1 : 2
: 4) can be used.
For concrete structures, which are in contact with water, such as water tanks,
Now, to estimate the quantities of each Gravel, Sand and Cement, the following
𝐕𝐨𝐥. = 𝟎. 𝟔𝟕 ∗ (𝐂 + 𝐒 + 𝐆) (𝟑. 𝟐)
Where:
Therefore, multiplying the total volume by 0.67 can compensate the amount of the
-For 1m3 of concrete with (1 : 2 : 4), the quantities are estimated as:
1 = 0.67 * (C + 2C + 4C)
10
-The density of cement = 1400kg/m3
Example (1):
Estimate concrete materials (Gravel, Sand and Cement) for the following plan, if the
depth and width of the foundation are 40cm 60cm respectively and the used mix is (1
: 2 : 4).
Solution:
Vol. = 0.67 ∗ (C + S + G)
11
Example (2):
For a concrete arch dam illustrated in the figure below, estimate the concrete materials
(Plan)
Solution:
𝜋∗ 102
Area = (2 * 16) + (13 * 13) – ( ) = 122.46m2
4
To find the average radius, it is necessary to determine the centre of the area about
point (a):
𝐴 ∗ 𝑥̅ = ∑ 𝑎 ∗ 𝑥
13 𝜋 ∗ 102
122.46 ∗ 𝑥̅ = 16 ∗ 2 ∗ 8 + 13 ∗ 13 ∗ ( + 2) − ( ∗ (0.424 ∗ 10 + 2))
2 4
∴ 𝑥̅ = 9.818𝑚
𝜋 ∗ 60
𝑉𝑜𝑙. = 29.818 ∗ ∗ 122.46 = 3823.85𝑚3
180
12
3823.85 = 0.67 ∗ 7𝐶 → 𝐶 = 815.32𝑚3 (Volume of cement)
1141449.169
𝐶 = 1400 ∗ 815.32 = 1141449.169 𝑘𝑔 = = 1141.449 𝑡𝑜𝑛𝑠
1000
Example (3):
Estimate the required concrete materials for the following retaining wall, if the length
Solution:
1.2+2.6
A = (1.5 * 7) + (1.2 *1) + ( ∗ 5.5) = 22.15m2
2
13
C = 1400 * 132.238 = 185133.2kg = 185133.2/1000 = 185.13 tons
5) Stone Works
Stone works is usually estimated in cubic meters, but with the consideration of the
volume of mortar cement. Mortar cement occupies (25 – 30) % of the total volume of
the stone constructions. The diameter of stones may be (10 – 35) cm.
Cement Sand
1 2
1 3
1 4
14
-Mortar cement losses 25% when adding water; therefore, the volume is determined
as:-
Example:
Estimate the quantity of the stone required for constructing a wall, if the length is 10m
and the height and thickness are 3m and 0.35m respectively. It is also known that
Solution:
15
6) Brick Works
If the width of the wall is 36cm or more, Size of Brick will be (8 * 12 * 24) cm.
If the width of the wall is 24cm, Size of Brick will be (8 * 12 * 23) cm.
If the width of the wall is 11cm, Size of Brick will be (8 * 24) cm for 1m2.
If the width of the wall is 7cm, Size of Brick will be (12 * 24) cm for 1m2.
Note: Volume of mortar cement = total volume of bricks including mortar – (No. of
Example:
Estimate the quantity of bricks required for constructing a wall footing, if total length
is 28m and the height and thickness are 0.6m and 0.4m respectively. If the used mix of
mortar cement is (1: 3), estimate the required quantities of cement and sand.
Solution:
16
Volume of mortar cement = total volume of brick with mortar – (No. of brick * actual
brick size)
Example:
Estimate the quantity of blocks required for 1m3 if the width is 20cm.
Solution:
17
Vol. mortar = 1 – (51 * (0.2 * 0.2 * 0.4)) = 0.184 m3
8) Reinforced Steel
6 0.222
8 0.395 Stirrups
10 0.617
12 0.888
14 1.21
16 1.58
18 2
25 3.86 dams
Or the following formula can be used to estimate the weight of reinforced steel bars
𝑫𝟐
𝒘= (𝟑. 𝟒)
𝟏𝟔𝟐
Where:
18
This is derived from:
𝜋 𝐷 2 𝑙 ∗ 𝐷2
𝑤 = 𝑣𝑜𝑙 ∗ 𝛾𝑠 = ( ) ∗ 𝑙 ∗ 7850 =
4 1000 162
Where:
Main bars
Stirrup bars
Overlaps
Dowels
Hooks
19
A Reinforced Concrete Single Footing
General Information:
20
Hook Details (ACI 318M-08)
21
Example (1):
For the following foundation, estimate the quantity of reinforced steel. If the volume
is 40m3.
Solution:
100
∵ No. of Overlaps = = 8.33 ≈ 8
12
1- Main bars:
(16)2
w= ∗ 409.6 = 647.27kg
162
For ∅14:
(14)2
w= ∗ 307.2 = 371.67kg
162
22
2- Stirrups:
100
No. of Stirrups = + 1 = 501
0.2
(10)2
𝑤= ∗ 501 ∗ 2.5 = 773.15𝑘𝑔
162
Example (2):
For the following isolated square footing, find the quantity of the reinforced steel.
Solution:
1- Main Bars:
𝐿 2.35
𝑁𝑜. 𝑜𝑓 𝑏𝑎𝑟𝑠 = +1= + 1 = 8.83 ≈ 9 𝑏𝑎𝑟𝑠 For Hooks
𝑠𝑝𝑎𝑐𝑖𝑛𝑔 0.3
23
Total length of the bars = 2.862 ∗ 9 ∗ 2 = 51.516m
(16)2
w= ∗ 51.516 = 81.408kg
162
2- Dowels:
(25)2
w= ∗ 7.1 = 27.4kg
162
Example (3):
For a combined footing shown below, calculate the amount of reinforced steel. If the
Solution:
1- Main Bars:
-Long side:
24
29.85
No . of bars = + 1 = 100.5 ≈ 101 bars
0.3
10 − 2 ∗ 0.075
No. of overlaps = =0
12
(252 )
w= ∗ 2151.3 = 8299.768𝑘𝑔
162
-Short side:
9.85
No . of bars = + 1 = 33.8 ≈ 34 bars
0.3
30 − 2 ∗ 0.075
No. of overlaps = = 2.48 ≈ 2
12
(252 )
w= ∗ 2125 = 8198.3kg
162
2- Dowels:
(252 )
w= ∗ 14.2 = 54.78kg
162
25
Steel Reinforcement of Beams
1- Cut
2- Bend
Straight bars
Bent bars
Additional bars
Stirrups
26
A Reinforced Concrete Beam
Example:
For the following beam, estimate steel reinforcement. If stirrups (∅10@20cm c/c).
27
Solution:
Bottom Bars:-
1- Straight bar
2- Bent bar
(202 )
w = (10.65 + 10.04) ∗ = 51.09kg
162
Top Bars:-
1- Straight bars
2- Additional bars
Length = 1.75m
28
162
𝑤 = (7 + 10.04) ∗ = 26.92𝑘𝑔
162
Stirrups:
5.02
No. of Stirrups = + 1 = 26.1 ≈ 26
0.2
102
𝑤 = (35.88) ∗ = 22.148𝑘𝑔
162
The bars considered in beam are also taken into account in slab, except stirrups.
29
Example:
Solution:
Long Direction:
1- Straight bar
30
= 12 ∗ 10.944 = 131.328m
122
w= ∗ 131.328 = 116.736kg
162
2- Bent bars
For 5m span:
0.15−2∗0.02
Length of each bar = 5 + (2 ∗ ) − (2 ∗ 0.11) + (2 ∗ 0.2) + 0.5 + 1.33 −
cos45
0.02 = 7.30m
122
w= ∗ 87.84 = 77.86kg
162
For 4m span:
0.15 − 2 ∗ 0.02
Length of each bar = 4 + (2 ∗ ) − (2 ∗ 0.11) + (2 ∗ 0.2) + 0.5 + 1.66
cos45
= 6.63m
122
w= ∗ 79.57 = 70.73kg
162
3- Additional bars
For 5m span:
For 4m span:
122
w= ∗ 52.2 = 46.4kg
162
31
Short Direction:
1- Straight bar
10.56
No. of bars = + 1 = 27.4 ≈ 28 bars
0.4
= 28 ∗ 4.744 = 132.832m
122
w= ∗ 132.832 = 118.072kg
162
2- Bent bars
0.15−2∗0.02
Length of each bar = (4.4 − 2 ∗ 0.02) + (2 ∗ ) − (2 ∗ 0.11) = 4.45m
cos45
122
w= ∗ 124.63 = 110.78kg
162
3- Additional bars
122
w= ∗ 94.08 = 83.62kg
162
32
9) Gypsum Plastering
weight (Kg).
Where:
Thickness = 0.02 m
- The factor of (1.1) is used because gypsum losses 10% of its volume when
adding water.
Example:
Solution:
For this kind of plastering, mortar cement (1: 3) can be used. This may also be
measured by (m2); but to estimate the quantity of materials, the volume is required.
V = area ∗ 0.02
𝐕 = 𝟎. 𝟕𝟓 (𝐂 + 𝟑𝐂) (𝟑. 𝟔)
33
Example:
For 1m2, estimate the quantity of sand and cement required for plastering.
Solution:
C = 0.006667m3
Tile may have different dimensions (20* 20) cm, (25 * 25) cm, (30 * 30) cm and etc.
Example:
For 1m2 floor, determine the number of tile (30 cm * 30 cm). If joints distance is
3mm.
Solution:
1
No. of tiles = = 10.89 ≈ 11 tiles
0.303 ∗ 0.303
34
Main Items in Construction of Building Works
1- Cleaning site
2- Earthwork (m3)
- Excavation
- Filling
5- Masonry (m3)
- Manhole (No.)
35
Forms of Estimates
1 Cleaning site
2 Excavation m3
3 Concrete of foundation m3
1 Cleaning site
2 Excavation
3 Concrete of foundation
Total
Grand total
Example:
36
- Masonry work in foundation in 2 steps (1st step: 40cm breadth, 45cm depth and;
- Reinforced concrete of the roof (15cm thickness and 50cm projected out of the
37
38
The Section of the Foundation
39
40
Item Dimensions
Item description Unit No. Quantity Remark
No. L B H
1 Excavation
A m3 3 9.6 0.7 0.8 16.128 L= (4.45+4.45)+(2*0.7/2)=9.6m
B m3 4 3.7 0.7 0.8 8.288 L= 4.4- 0.7=3.7m
C m3 3 3.15 0.7 0.8 5.292 L=3.85-0.7=3.15m
D m3 1 1.9 0.7 0.8 1.064 L= 2.6-0.7=6.9m
E m3 1 0.7 0.7 0.8 0.392 L= 1.4-0.7= 0.7m
31.164
2 Filling (up to G.L.) Up to ground level
Total length
Crushed stone m3 55.65 0.7 0.07 -2.72
=(3*9.6)+(4*3.7)+(3*3.15)+1.9+0.7=55.65m
Lean Concrete of foundation m3 55.65 0.7 0.3 -11.68
Masonry work 1st step m3 55.65 0.4 0.45 -10.017
Filling m3 6.747 Filling= 31.164-(2.72+11.68+10.017)=6.747 m3
41
C m2 3 3.15 0.7 6.615
D m2 1 1.9 0.7 1.33
E m2 1 0.7 0.7 0.49
38.955
4 Lean Concrete
A m3 3 9.6 0.7 0.3 6.048
B m3 4 3.7 0.7 0.3 3.108
C m3 3 3.15 0.7 0.3 1.9845
D m3 1 1.9 0.7 0.3 0.399
E m3 1 0.7 0.7 0.3 0.147
11.6865
5 Masonry under DPC
1st Step
A m3 3 9.3 0.4 0.45 5.022 L=8.9+0.4=9.3m
B m3 4 4 0.4 0.45 2.88 L=4.4-0.4=4m
C m3 3 3.45 0.4 0.45 1.863 L= 3.85-0.4=3.45m
D m3 1 2.2 0.4 0.45 0.396 L=2.6-0.4=2.2m
E m3 1 1 0.4 0.45 0.18 L=1.4-0.4=1m
10.341
2nd Step
A m3 3 9.1 0.2 0.45 2.457 L=8.9+0.2=9.1m
B m3 4 4.2 0.2 0.45 1.512 L=4.4-0.2=4.2m
C m3 3 3.65 0.2 0.45 0.9855 L= 3.85-0.2=3.65m
D m3 1 2.4 0.2 0.45 0.216 L=2.6-0.2=2.4m
E m3 1 1.2 0.2 0.45 0.108 L=1.4-0.2=1.2m
5.2785
Total Quantity = 10.341 +5.2785 15.6195
6 Lean Concrete of DPC
A m3 3 9.1 0.2 0.1 0.546
42
B m3 4 4.2 0.2 0.1 0.336
C m3 3 3.65 0.2 0.1 0.219
D m3 1 2.4 0.2 0.1 0.048
E m3 1 1.2 0.2 0.1 0.024
1.173
7 Masonry work above DPC
A m3 3 9.1 0.2 3 16.38
B m3 3 4.2 0.2 3 7.56
C m3 3 3.65 0.2 3 6.57
D m3 1 2.4 0.2 3 1.44
E m3 1 1.2 0.1 3 0.36 Thickness of the wall of W.C & Bath =0.1m
32.31
Deductions:
Doors & Windows
D1 m3 5 1 0.2 2.2 2.2
D2 m3 2 0.8 0.2 2 0.64
W1 m3 5 1.5 0.2 2 3
W2 m3 2 0.3 0.2 0.3 0.036
-5.876
Lintels dimension (20 * 25cm)& extended (0.5cm)
Lintels over doors &windows
from each side of door and windows
D1 m3 5 2 0.2 0.25 0.5 L = 1 + 0.5 + 0.5 = 2m
D2 m3 2 1.8 0.2 0.25 0.18 L = 0.8 + 0.5 + 0.5 =1.8m
W1 m3 5 2.5 0.2 0.25 0.625 L= 1.5 + 0.5 + 0.5 =2.5m
W2 m3 2 1.3 0.2 0.25 0.13 L = 0.3 + 0.5 + 0.5 =1.3m
-1.435
Total Quantity = 32.31 – (5.876 + 1.435) 24.999
8 Reinforced Concrete
m3 1 10.1 9.45 0.15 14.3167 Long = 8.9 + 0.2 +(0.5*2) = 10.1m
43
Short= 3.85 + 4.4 + 0.2 +(2 * 0.5) = 9.45m
9 Finishing Works
9-1 Cement Plastering
Front and Back elevations m2 2 8.45 3.25 54.925
Side elevations m2 2 9.1 3.25 59.15
Verandah wall side m2 2 2.3 2.85 13.11
Verandah ceiling m2 1 4.2 2.85 11.97
Under Slab (projected) m2 2 10.1 0.5 10.1 Long
Under Slab (projected) m2 2 8.45 0.5 8.45 short
Faces of slab (front &back) m2 2 9.45 0.15 2.835
Faces of slab (Sides) m2 2 10.1 0.15 3.03
163.57
Around doors & windows
D1 sides m2 6 0.075 2.2 0.99 Only 3 doors plastered by cement
D1 top m2 3 1 0.075 0.225
W1 sides m2 10 0.075 2 1.5 2 sides for each (2*5)
W1 tops &bottoms m2 10 1.5 0.075 1.125
W2 m2 8 0.3 0.075 0.18 2 windows * 4 sides =8
4.02
167.59 =163.57+ 4.02 =167.59 m2
Deductions:
D1 m2 3 1 2.2 6.6
W1 m2 5 1.5 2 15
W2 m2 2 0.3 0.3 0.18
21.78
Total net Quantity = 167.59 + 21.78 145.81
44
9-2 Gypsum Plastering
Room 1 & 2
Walls m2 4 4.25 2.85 48.45 Long walls
Walls m2 4 3.65 2.85 41.61 Short walls
Ceiling m2 2 4.25 3.65 31.025
Room 3
Walls m2 2 4.2 2.85 23.94 Long walls
Walls m2 2 3.8 2.85 21.66 Short walls
Ceiling m2 1 4.2 3.8 15.96
Corridor
Walls m2 2 2.8 2.85 15.96
Walls m2 2 2.4 2.85 13.68
Ceiling m2 1 2.8 2.4 6.72
Around doors & windows
D1 sides m2 14 0.075 2 2.1 7 doors plastered * 2 sides = 14
D1 tops m2 7 1 0.075 0.525
D2 sides m2 4 0.075 1.8 0.54
D2 tops m2 2 0.8 0.075 0.12
W1 sides m2 10 0.075 2 1.5
W1 tops m2 10 1.5 0.075 1.125
224.915
Deduction:
D1 m2 7 1 2 14
W1 m2 5 1.5 2 15
D2 m2 2 0.8 1.8 2.88
-31.88
45
9-3 Glass Tile
Walls W.C & Bath m2 4 1.2 2.2 10.56
Walls W.C m2 2 1 2.2 4.4
Walls Bath m2 2 1.3 2.2 5.72
35.27
Deductions:
D1 m2 7 1 0.2 1.4
46
D2 m2 2 0.8 0.2 0.32 Outside bath & W.C
D2 m2 2 0.8 2 3.2 Inside Bath & W.C
W2 m2 2 0.3 0.3 0.18
-5.1
Total net Quantity = 35.27 – 5.1 30.17
47
B: Canal Earthworks
Based on the natural ground level, depth and the required design level of a
Fully in cutting
Fully in embankment
48
𝐒𝐞𝐜𝐭𝐢𝐨𝐧𝐚𝐥 𝐚𝐫𝐞𝐚 𝐢𝐧 𝐜𝐮𝐭𝐭𝐢𝐧𝐠 = 𝐛𝐝 + 𝐳𝐝𝟐
𝐒𝐞𝐜𝐭𝐢𝐨𝐧𝐚𝐥 𝐚𝐫𝐞𝐚 𝐢𝐧 𝐟𝐢𝐥𝐥𝐢𝐧𝐠 = (𝒃𝟏 + 𝒃𝟐 ) ∗ 𝐡 + 𝟐𝐒 ∗ 𝐡𝟐
b: width
Example:
Calculate the quantity of earthwork of a portion of channel with the following data:
Bed width = 6m
49
H = 1.7m
Distance 0 50 100 150 200 250 300 350 400 450 500
N.G.L 335.24 334.8 334.43 334.12 334.5 334.98 334.68 334.4 334.6 334.1 333.8
Proposed bed level 334 333.94 333.88 333.82 333.76 333.7 333.64 333.58 333.52 333.46 333.4
Solution:
Distance 0 50 100 150 200 250 300 350 400 450 500
N.G.L 335.24 334.8 334.43 334.12 334.5 334.98 334.68 334.4 334.6 334.1 333.8
Proposed bed level 334 333.94 333.88 333.82 333.76 333.7 333.64 333.58 333.52 333.46 333.4
Top of bank level 335.7 335.64 335.58 335.52 335.46 335.4 335.34 335.28 335.22 335.16 335.1
Height of filling 0.46 0.84 1.15 1.4 0.96 0.42 0.66 0.88 0.62 1.06 1.3
Mean height 0.65 0.995 1.275 1.18 0.69 0.54 0.77 0.75 0.84 1.18
50
b = 6m, z = 1, S = 1, b1 = 1.5m, b2 = 2.5m
di = N. G. L − bed level
A1 = (bd + z𝑑 2 ), Q1 = (bd + z𝑑 2 ) ∗ 𝐿
0 1.24 0.46
51
C: Road Earthwork Estimating
Cross-section of earthwork of road in filling or in cutting is usually in the form of
1
Sectional area = Bd + 2 ( ∗ Sd ∗ d) = Bd + Sd2
2
S:1 is the ratio of side slops (horizontal : vertical)
𝐐𝐮𝐚𝐧𝐭𝐢𝐭𝐲 = ( 𝐁𝐝 + 𝐒𝐝𝟐 ) ∗ 𝐋
Note: if it is required to turf or pitch the sides of the road, it will be significant to
52
Example:
Prepare an estimate for the road from a station of 420m to a station of 660m. Draw the
longitudinal section and cross-section both cutting and filling. Implement the rate of
earthwork in cutting and filling of 3000ID/m3 and 2000ID/m2 for turfing. Side slopes
are 1.5:1 for cutting and 2:1 for filling and the road width is 12m. The natural ground
Chainage 420 450 480 510 540 570 600 630 660
N.G.L 118.6 119.25 119.4 118.85 118.5 117.25 116.8 117.15 117.2
Solution:
N.G.L 118.6 119.25 119.4 118.85 118.5 117.25 116.8 117.15 117.2
D.L 118.6 118.45 118.3 118.15 118 117.85 117.7 117.55 117.4
53
1) Earthwork
420 0 0 0
-1169.775 736.98
420 0
450 -0.8
480 -1.1
510 -0.7
540 -0.5
54
660 0.2 0.3 0.67082 30 40.248
249.52
Abstract Cost
Total 6219305
55
Worked Example:
Prepare a detailed estimate for a reinforced concrete retaining wall of 30 m in length whose cross-section is given below.
Assume: hook length = 15cm, overlap = 40cm, cover = 7cm (earth) and 5cm (form).
Stem
56
57
Solution:
Item Dimensions
Details of Items Unit Nos. Quantity Remark
No. L (m) B (m) D (m)
1 RCC work 1 : 2 : 4
Stem m3 1 30 (0.6+0.2)/2 6 72
2 Steel Bars
Stem
Right Side
58
N = ((6.5 – 0.05 – 0.07)/0.25) + 1 = 26.52
Left Side
Base Slab
59
∅16mm @ 10 cm c/c N = ((30 – 2 * 0.05)/ 0.1) + 1 = 300
m 300 3 900
(Heel) L = 1.65 + 0.6 + 0.75 – 0.25 – 0.05 + (2 * 0.15) = 3
Abstract of Quantities
2. Steel Bars
222
2.1 ∅22mm = (1403.93) * = 4194.457kg
162
162
2.2 ∅16mm = (1280) * = 2022.716kg
162
142
2.3 ∅14mm = (1513.7) * = 1831.39kg
162
102
2.4 ∅10mm = (1348.5) * = 832.4kg
162
60
Worked Example:
Prepare a detailed estimate for a reinforced concrete water pool of interior dimensions (14m * 35m). the used mix is (1 : 2 : 4).
Assume: hook length = 16*db, overlap = 30cm, cover = 7.5cm (earth) and 4cm (form).
200 200
mm mm
14m
4.5 m
Ø16 @ 200
Ø16 @ 200 mm
mm Ø16 @ 300
Ø25 @ 350
mm
.3m mm 0.3 m
400 mm
400 mm
15 m
Ø16 @ 300 mm
61
Solution:
Item Dimensions
Details of Items Unit Nos. Quantity Remark
No. L (m) B (m) D (m)
1 RCC work 1 : 2 : 4
Walls
2 Steel Bars
Base Slab
N = 2 * (( 15 - 2 * 0.075)/0.3) + 1 = 101
N = 2 * (( 36 - 2 * 0.075)/0.35) + 1 = 206.85
∅25mm @ 350 mm m 207 15.95 3301.65
L = 15 – 2 * cover + 2 * hooks + 1 * overlap
62
L =(15 – 2*0.075) + 32*0.025 + 0.3 * 1 =15.95m
N = 2*(98.8/0.20) + 1 = 990
∅16mm @200mm m 990 1.221 1208.79 L = base thickness – cover + 40db +12db + 4db
Walls
N = 2*(98.8/0.20) + 1 = 990
N = 2*((4.5 – 2* 0.02)/0.25) + 1 = 38
(no. overlap = 8)
102.416m
63
Abstract of Quantities
2. Steel Bars
122
2.1 ∅12mm = (3891.808) * = 3459.384889kg
162
162
2.2 ∅16mm = (3763.462) + (1208.79) + (4668.84) * =15235.30588kg
162
252
2.3 ∅25mm = (3301.65) * = 12737.84722kg
162
64