007 - WMS of K2 Paste
007 - WMS of K2 Paste
Table of Contents
01 Scope of works 04
03 Construction procedures 05
04 Inspection 06
08 Environment requirement 07
09 References attachment 07
1. Scope of work
Project Manager:
Project Manager is responsible for developing and managing technology projects and
their cost, time and scope. Responsibilities include: project plan, communication plan,
allocating tasks and setting milestone.
Management of the safety control supervisors to check the site condition in the safety
concern
Report to the Site Manager in relation to the health, safety and environment protection
activities.
Workers: The Project Worker's main function is to manage the day-to-day activities of a
project or part of a service. The Project Worker will also assist the Service Manager to
develop and support a range of flexible, creative and responsive community-based
initiatives for people with dementia and their careers.
TBT/Job specific training will be given to all members before starting the activity.
Necessary work permit should be taken by TFPL from APG prior to the start-up of activity.
All equipment, tools & tackles should be having required documents like TPI, Calibration &
MTC etc.
WATER RINSING:- Wash pickling solution with fresh until the surface is free of acid
solution.
DRYING:- The water rinsed surface shall be dried in open air or with dry.
Protection:- Passivation and rinsed area for stainlesssteel shall be stored in such a way to
avoid further contamination.
4. INSPECTION
Visual inspection shall be carried out under a bright light, minimum 1,076 Lx. Items
cleaned in accordance with this procedure shall be free of paint, oil, grease, welding flux,
slag, heat-treating and hot-forming scale, dirt, trace, metal and abrasive particles and
chips, and other gross contamination. Visual inspection shall be conducted with mirrors,
and other aids, as necessary, to properly examine inaccessible or difficult-to-see
surfaces.
Assessment shall be done for the activity, access, illumination and work platform.
Ensure that all tools and tackles have the valid third-party certificates
Ensure that job specific PPE with Mandatory PPE are provided to all including full body
harness
Ensure to barricades the area with warning signs board & only authorized person allow to
working area.
8. Environmental requirements
Prevent noise pollution by using environment friendly machines and equipment’ s and oils.
9. References Attachment: