This document provides a method statement for performing passivation using K2 paste on a project for Perstorp Industries India Pvt. Ltd. It outlines the scope of work, roles and responsibilities of personnel including the project manager, site engineer, supervisor, and workers. It describes the construction procedures for degreasing, applying the K2 paste, rinsing, and drying. Inspection, required plant/equipment, storage/handling, health/safety requirements, and environmental considerations are also covered. An attachment includes the manufacturer's MSDS for K2 paste.

Uploaded by

alla malik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
273 views6 pages

007 - WMS of K2 Paste

This document provides a method statement for performing passivation using K2 paste on a project for Perstorp Industries India Pvt. Ltd. It outlines the scope of work, roles and responsibilities of personnel including the project manager, site engineer, supervisor, and workers. It describes the construction procedures for degreasing, applying the K2 paste, rinsing, and drying. Inspection, required plant/equipment, storage/handling, health/safety requirements, and environmental considerations are also covered. An attachment includes the manufacturer's MSDS for K2 paste.

Uploaded by

alla malik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS007 R0


Contract No.: SER/0153/21-22 Date Issued: 22.02.2022

Project: Perstorp Elephant Project

Method Statement for Passivation (K2 paste)

Contractor: TRIMURTI FABRICATORS PVT LTD

PMC: Aker Powergas Solutions


Client: Perstorp Industries India Pvt. Ltd.
TFPL Job No: 50611-2041

0 22.02.2022 Issued for Approval Rahmatullah S. JOSEPH


Ansari

Rev Date APG PEM Document Status Prepared By Checked by Approved By


Status

Doc Title: MS for Erection of structural Column Page 1 of 6


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS007 R0


Contract No.: SER/0153/21-22 Date Issued: 22.02.2022

Rev. Date Revision Details

1 22.02.2022 First Issue

Table of Contents

Section Title Page

01 Scope of works 04

02 Personnel rules and responsibilities 04

03 Construction procedures 05

04 Inspection 06

05 Plant and equipment 06

06 Storage and handling 06

07 Health and safety 07

08 Environment requirement 07

09 References attachment 07

Doc Title: MS for Erection of structural Column Page 2 of 6


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS007 R0


Contract No.: SER/0153/21-22 Date Issued: 22.02.2022

1. Scope of work

This procedure covers the minimum requirements for Passivation


(K2 Paste)

2. Personal Rules and responsibility

 Project Manager:
      Project Manager is responsible for developing and managing technology projects and
their cost, time and scope. Responsibilities include: project plan, communication plan,
allocating tasks and setting milestone.

 Preparation of the work procedure and review

 Calibration and maintenance of equipment

 Notification to Supervisor for inspection

 Training for Superintendents, Supervisors and Staffs

 Site Engineer: A site engineer offers advice in the planning, co-ordination and


supervision of technical aspects of construction projects. A site engineer's role is
vital to a construction project: they have a number of responsibilities including
solving technical issues, providing advice, management and preparing reports.

Doc Title: MS for Erection of structural Column Page 3 of 6


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS007 R0


Contract No.: SER/0153/21-22 Date Issued: 22.02.2022

 Apply to approved MSDS on site

 Provide for inspection/test

 Control of workers on site

 Preservation of material on site

 Training to be provide to the worker

 Supervisor: A Supervisor oversees the construction activities that take place on the


Work site. They are heavily involved in planning, organizing and controlling
Projects.
Construction Supervisors are responsible for supervising the contractors and staff
while maintaining a safe work environment.

 Supervision for apply k2 paste activities

 Distribute the job to workforce

 Cooperating with worker on workplace safety and health matters.


 Safety officer: The Safety Officer is responsible for monitoring and assessing
hazardous and unsafe situations and developing measures to assure
personnel safety. The Safety Officer ensures the Site Safety and Health Plan is
prepared and implemented. The Safety Officer ensures there
are safety messages in each Incident Action Plan.

 Management of the safety control supervisors to check the site condition in the safety
concern

 Report to the Site Manager in relation to the health, safety and environment protection
activities.
Workers: The Project Worker's main function is to manage the day-to-day activities of a
project or part of a service. The Project Worker will also assist the Service Manager to
develop and support a range of flexible, creative and responsive community-based
initiatives for people with dementia and their careers.

Doc Title: MS for Erection of structural Column Page 4 of 6


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS007 R0


Contract No.: SER/0153/21-22 Date Issued: 22.02.2022

3. Construction procedure to be followed

 TBT/Job specific training will be given to all members before starting the activity.

 Necessary work permit should be taken by TFPL from APG prior to the start-up of activity.

 All equipment, tools & tackles should be having required documents like TPI, Calibration &
MTC etc.

 Area should be barricaded or cordon off.

 DEGREASING:-Cleaning shall be done after fabrication and welding is completed.


Cleaning gel shall be used to remove discolouration, Oxide scale & heat marks.

 PASSIVATION TREATMENT: - K2 paste is carried out to remove residual contaminants


and oxide firms, and to obtain a clear and uniform surface by means of k2 paste. All
scales and contaminants shall be removed by the cleaning process.

 WATER RINSING:- Wash pickling solution with fresh until the surface is free of acid
solution.

 DRYING:- The water rinsed surface shall be dried in open air or with dry.

 Protection:- Passivation and rinsed area for stainlesssteel shall be stored in such a way to
avoid further contamination.

 K2 paste MSDS to be kept at storage area.

4. INSPECTION

Visual inspection shall be carried out under a bright light, minimum 1,076 Lx. Items
cleaned in accordance with this procedure shall be free of paint, oil, grease, welding flux,
slag, heat-treating and hot-forming scale, dirt, trace, metal and abrasive particles and
chips, and other gross contamination. Visual inspection shall be conducted with mirrors,
and other aids, as necessary, to properly examine inaccessible or difficult-to-see
surfaces.

5. Plant and equipment

Doc Title: MS for Erection of structural Column Page 5 of 6


Rev No: 00
PERSTORPP ELEPHANT PROJECT

Contractor: TRIMURTI FABRICATORS PVT LTD Doc. Ref. No: TFPL/APG/MS007 R0


Contract No.: SER/0153/21-22 Date Issued: 22.02.2022

Boom lift, Scaffolding.

6. Storage and handling

 All material will be maintained cleanly and in good condition.

 All tools and tackles must be free from dirt, grease.

7. Health and safety

 Assessment shall be done for the activity, access, illumination and work platform.

 Ensure that all tools and tackles have the valid third-party certificates

 Ensure that job specific PPE with Mandatory PPE are provided to all including full body
harness

 Ensure to barricades the area with warning signs board & only authorized person allow to
working area.

8. Environmental requirements

Prevent noise pollution by using environment friendly machines and equipment’ s and oils.

Minimize the dust generation as low as practicable.

Keep area clean and tidy.

9. References Attachment:

Manufacturer MSDS of k2 paste submitted separately.

Doc Title: MS for Erection of structural Column Page 6 of 6