The document is a bill of quantities for construction of a building at Islamia School. It provides details of 10 line items for work including excavation, filling, plain cement concrete, masonry work, and supply of M-20 design mix concrete for items like footings, columns, plinth beams, etc. It specifies the quantities, units, rates and amounts for each work item along with relevant specification numbers. The total estimated contract value for the construction is ₹2,255,373.

Uploaded by

Ramesh rammi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views

Building Estimate

The document is a bill of quantities for construction of a building at Islamia School. It provides details of 10 line items for work including excavation, filling, plain cement concrete, masonry work, and supply of M-20 design mix concrete for items like footings, columns, plinth beams, etc. It specifies the quantities, units, rates and amounts for each work item along with relevant specification numbers. The total estimated contract value for the construction is ₹2,255,373.

Uploaded by

Ramesh rammi
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

9/24/22, 8:34 AM

Bill of Quantity Items Print Preview


Current Tender Details  
Enquiry/IFB/Tender 19/EE/Circle-II/GWMC/CTN/24/e-
Tender ID 353739
Notice Number procurement/2022-23, Dated : 19-09-2022
Construction of Building at Islamia School in
Name of Work ward no.26. (General Funds)(4th Call) Tender Category Works

Tender Type OPEN Estimated Contract Value 2255373


Bid Submission Closing
30/09/2022 04:00 PM Tender Evaluation Type Percentage
Date

Back Print

BOQ Item Details  


S.No Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

1 Construction of Building As per SSR 87.64 Cum 394.83 34602.90


Dismantelling of brick massionary /Tiles including cost and conveyance of all materials and labour
charges etc complete.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

2 Construction of Building As per SSR 69.00 Cum 420.67 29026.23


BLD-CSTN-2-1 (9): Earth work excavation in Ordinary Soil by Manual Means-Upto 3 m depth for
foundations and depositing on bank for all lifts and with an initial lead of 10m including all
operational, incidental, labour charges such as shoring ,sheeting, planking, strutting, etc. complete for
finished item of work including excluding dewatering charges etc as per SS - 20 B (APSS 308). for
fOUNDATIONS
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

3 Construction of Building As per SSR 5.81 Cum 2107.82 12246.43


Filling with Sand in trenches, sides of foundations and basement with initial lead in layers not
exceeding 15 cm thick, consolidating each deposited layer by watering and ramming including cost
and conveyance of water to work site and all operational, incidental, labour charges, hire charges of T
& P etc., complete for finished item of work. (APSS NO. 309 & 310)
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

4 Construction of Building As per SSR 18.31 Cum 4518.70 82737.40


Providing Plain Cement Concrete (1:4:8) mix using 40mm nominal size HBG crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, conveyance of all
materials to site and labour charges, centering, machine mixing, laying etc., Complete.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

5 Construction of Building As per SSR 28.63 Cum 4316.93 123593.71

1/7
9/24/22, 8:34 AM

Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

Construction of RR Masonary in Cement Mortor ( 1:6 ) Prop using hard granite stone including cost &
Conveyance of all materials like Cement, Sand , Water, Granite Stones, including Charges on all
Materials, ,labour charges for cutting Stones to required size and shape, mixing of Cement Mortor
,Construction, Scaffolding Charges curing etc., complete for finished item of Work .
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

6 Construction of Building As per SSR 6.75 Cum 9841.93 66433.03


Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER
with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site . sales & other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing, laying concrete, vibrating, curing,
centering and suttering charges etc.,complete but excluding seignorage charges, cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum cement content as per IS
code for PLINTH, PEDESTALS and FOOTINGS.
Note : 1) The cement content is adopted as 350Kg/cum
for estimating purpose only.The exact quantities will be as per mix design. 2) As per mix design, if the
cement content is found to be less than 350 Kgs/ Cum the defference in cost shall be deducted
(Footings)
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

7 Construction of Building As per SSR 4.41 Cum 10466.80 46158.59


Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER
with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site . sales & other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing, laying concrete, vibrating, curing,
centering and suttering charges etc.,complete but excluding seignorage charges, cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum cement content as per IS
code for PLINTH, PEDESTALS and FOOTINGS.
Note : 1) The cement content is adopted as 350Kg/cum
for estimating purpose only.The exact quantities will be as per mix design. 2) As per mix design, if the
cement content is found to be less than 350 Kgs/ Cum the defference in cost shall be deducted
(Trepezodial Portion)
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

8 Construction of Building As per SSR 4.66 Cum 13083.19 60967.67

2/7
9/24/22, 8:34 AM

Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER
with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site . sales & other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing, laying concrete, vibrating, curing,
centering and suttering charges etc.,complete but excluding seignorage charges, cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum cement content as per IS
code for PLINTH, PEDESTALS and FOOTINGS.
Note : 1) The cement content is adopted as 350Kg/cum
for estimating purpose only.The exact quantities will be as per mix design. 2) As per mix design, if the
cement content is found to be less than 350 Kgs/ Cum the defference in cost shall be deducted
(Coloumns)
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

9 Construction of Building As per SSR 5.03 Cum 12480.86 62778.73


Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER
with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site . sales & other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing, laying concrete, vibrating, curing,
centering and suttering charges etc.,complete but excluding seignorage charges, cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum cement content as per IS
code for PLINTH, PEDESTALS and FOOTINGS.
Note : 1) The cement content is adopted as 350Kg/cum
for estimating purpose only.The exact quantities will be as per mix design. 2) As per mix design, if the
cement content is found to be less than 350 Kgs/ Cum the defference in cost shall be deducted
(Plinth BEam)
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

10 Construction of Building As per SSR 6.94 Cum 12075.67 83805.15


Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER
with 20mm size graded machine crushed hard granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site . sales & other taxes on all materials including all operational, incidental
and labour charges such as weigh batching, machine mixing, laying concrete, vibrating, curing,
centering and suttering charges etc.,complete but excluding seignorage charges, cost of steel and its
fabrication charges for finished item of work (APSS No. 402) with minimum cement content as per IS
code for PLINTH, PEDESTALS and FOOTINGS.
Note : 1) The cement content is adopted as 350Kg/cum
for estimating purpose only.The exact quantities will be as per mix design. 2) As per mix design, if the
cement content is found to be less than 350 Kgs/ Cum the defference in cost shall be deducted (Roof
BEam)
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

11 Construction of Building As per SSR 124.93 Sqm 1614.54 201704.48

3/7
9/24/22, 8:34 AM

Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

Supply and placing of the M-20 Design Mix Concrete corresponding to IS 456 using WEIGH BATCHER
/ MIXER with 20mm size graded machine crushed hard granite metal (coarse aggregate) from
approved quarry including cost and conveyance of all charges etc., Complete. ( 150 mm thick(
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

12 Construction of Building As per SSR 3538.00 Kgs 65.62 232163.56


Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and
technical specifications for Bars below 36 mm dia including over laps and wastage, where they are
not welded etc., Complete
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

13 Construction of Building As per SSR 37.48 Cum 330.66 12393.14


Supply and Filling with Gravel in trenches, sides of foundations and basement with initial lead in
layers not exceeding 15cm thick, consolidating each deposited layer by watering and ramming
including all operational, incidental, labour charges, seignorage charges, hire charges of T & P etc.,
complete for finished item of work.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

14 Construction of Building As per SSR 33.01 Cum 6581.18 217244.75


Brick Masonary 2nd Class Ground moulded or treditional size 23x11x7 Cm in Cement Mortor 1:6 Prop
including Cost & conveyance of all Materials like Cement, Sand, Bricks, Water, etc., to site cost of
charges on all materials, including all labour charges like mixing Cement Mortor, scaffoding charges
lift charges , curing charges etc., complete for finished item of work
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

15 Construction of Building As per SSR 124.93 Sqm 180.11 22501.14


Plastering with CM 2 coats, 12 mm thick, base coat in CM (1:4), 8mm thick and top coat in CM (1:3),
4mm thick with sponze finishing..
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

16 Construction of Building As per SSR 311.52 Sqm 493.33 153682.16


Plastering 20mm thick two coats with base coat of 16mm thick in C.M. (1:6) and top coat of 4mm
thick in C.M. (1:3) with dubara sponge finishing including cost & conveyance of all materials like
cement, Sand , Water, etc., to site, charges, all operational, including charges, labour charges for
mixing mortar, finishing, scaffolding, lift charges, curing , including cutting grooves where ever
necessary etc., complete
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

17 Construction of Building As per SSR 14.40 Sqm 8783.59 126483.70

4/7
9/24/22, 8:34 AM

Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) 2 Track?2 Panel Sliding windows with
mesh duly manufactured using UPVC `reinforced profiles of 91 mm x 49 mm x 2.20 mm for outer
frames, 62 mm x 41 mm x 2.20 mm for sliding shutter frames capable of mounting single glazing
system, structurally reinforced with 30 mm 15 mm x 1.5 mm with hot dip galvanized up to 50 microns
of minimum thickness of 1.0/1.2 mm and the shutter of fly screen with fibre mesh shall be made of
size 21mm x 58mm extruded uPVC window profile section of white colour having outer wall thickness
of 2.2mm (± 0.3mm) provided with reinforcement of minimum 1.5mm thick G/J/U/S/O type GI
section duly mitred cut and thermal welded at all corners and prefabricated & welded through fusion
welding. The window sash shall be fitted with 5 mm thick clear float glass of reputed make & Glazing
bead shall be co-extruded with Grey colour soft PVC. System shall have single point locking with
Touch Lock and the system is to be installed at the site using anchor fasteners, silicon rubber sealant,
easy glazing/ deglazing at site etc., including cost and conveyance of all materials, accessories, labour
charges for transportation, erection at site complete for finished item of work.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

18 Construction of Building As per SSR 4.80 Sqm 6931.65 33271.92


Providing, supplying & fixing of Fixed Louvered Ventilator made out of multi chambered uPVC
sections with Glazing bead shall be co-extruded with Grey colour soft PVC. having isolated drainage
and reinforced with Galvanized Iron profiles throughout the window. The outer frame having an
overall size of 60 mm x 55 mm x 2.40 with reinforcement of 1 mm thickness and Mullion with overall
size of 74 mm x 60 mm x 2.40 mm with reinforcement of 1 mm thickness. (Composition of profile
shall consists a minimum of 5.5 PHR of TiO2 and not more than 12 PHR of CaCo3 for every 100 parts
of PVC resin).Ventilator shall be provided with 4.5 mm Pin Head glass,standard hardware. Wall
thickness of frame & Mullion shall be 2.4 mm., including cost and conveyance of all materials,
accessories, labour charges for transportation, erection at site complete for finished item of work
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

19 Construction of Building As per SSR 73.96 Sqm 1002.86 74171.53


Flooring Supply of ordinary soluble salt porcelain vitrified tiles screen printed and polished of size
600 x 600 mm and thickness between 8-9 mm 1st quality conforming to IS:13711, IS:13712, IS:13630
(Parts 1 to 15) of any colour and finish in all shades and designswith vitrified tiles of 1st quality, set
over base coat of cement mortar (1:8), 12 mm thick over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like consistency spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste to full depth mixed with pigment of matching shade, including cost of all
materials like cement, sand water and tiles etc., complete, including, etc., complete for finished item
of work
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

20 Construction of Building As per SSR 4.00 Cum 91094.00 364376.00


Supply and Fixing Medium Teak Wood scantlings: 2.0 to 3.0 M MTBSC-D.I-02 including Labour
charges for wrought and put up including fixing in position for Teak wood for door frame and
panned shutters TBSC-T.I-27
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

21 Construction of Building As per SSR 480.00 Kgs 93.96 45100.80


5/7
9/24/22, 8:34 AM

Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

Supply and Fixing in position of MS steel works like Window Grills, Compound Wall Grills, Iron Doors,
Windows etc, including cost and conveyance of all material , labour charges for fabrication and fixing
in postion etc,. Complete
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

22 Construction of Building As per SSR 124.93 Sqm 648.60 81029.60


Flooring with Polished Shabad stones 1st class 15 to 18 mm thick (Tandur Stone slabs) set over base
coat of CM (1:8) over already laid CC bed / RCC Roof Slab, including neat cement slurry of honey like
consistency spread @ 3.3 kgs per sqm. & Jointed with neat cement to full depth including cost of all
materials like cement, sand, and water and flooring stones etc., complete, including charges, labour
charges for dressing of flooring stones etc., complete for finished item of work, including the cost
and conveyance of all materials.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

23 Construction of Building As per SSR 436.45 Sqm 45.47 19845.38


White washing one coat with whiting of approved quality to give an even shade after thoroughly
brushing the surface to remove all dirt and remains of loose powdered materials including cost of all
materials, labour charges and incidental such as scaffolding, lift charges etc., complete for finished
item of work, but excluding conveyance charges of materials
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

24 Construction of Building As per SSR 115.00 Rmt 85.00 9775.00


Supply and Laying of ISI 25mm outer dia heavy grade with IS:9537 part 3 regid PVC pipe concealed in
Roof Slabs with all required PVC / Metallic Deep Boxes including masonary work and labour charges
etc., complete. Makes : Sudhakar / GM / Modi / Million Plast.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

25 Construction of Building As per SSR 115.00 Rmt 96.00 11040.00


Supply and laying of ISI 25mm outer dia medium grade with IS:9537 part 3 regid PVC pipe concealed
in wall with all required PVC / Metallic Junction Boxes including masonary work and labour charges
etc., Makes : Sudhakar / GM / Modi / Million Plast.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

26 Construction of Building As per SSR 10.00 Each 68.00 680.00


Supply and erecting PVC / GI / MS Galvanished fan hook box with hook in RCC slab including all
Labour charges etc., complete.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

27 Construction of Building As per SSR 50.00 Each 745.00 37250.00

6/7
9/24/22, 8:34 AM

Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS / HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A Modular switch, Ceiling rose/BH/SBH Modular switches with cover
plate and GI switch box including all labour charges etc., complete. (for Non-Residential Building)
Makes of wires : Finolex / RR Kabel / Havells / KEI / L&T / Polycab / HPL / RPG / Power flex / GM /
Million / Gold Medal. Makes of switches: GM Four-Five / Legrand Arteor / Schneider Zen celo
/Honeywell Blenge Plus/ Cabtree Verona/ Million logus / Gold Medal Curve.
Subwork Name Specification Number Quantity UOM Rate(INR) Amount(INR)

28 Construction of Building As per SSR 86.57 Each 119.10 10310.49


Carting of the Exavated earth upto a lead upto 4-5 km beyond the initial lead of 1 Km from site
including loadingand unloading as per the engineer in charge
Total(INR): 2255373