Pex Specs
Pex Specs
Contents
PART 1 - GENERAL
1.1 Reference
1.2.1 Type of pipes and fittings specified in this section include the following:
a) Copper Tube
b) Plastic pipes
c) Plastic tubing
d) Grooved piping products
e) Miscellaneous piping materials/products
f) Pex Pipes
1.4 Submittals
Submit maintenance data and parts lists for each type of mechanical
fitting. Include this data, product data, and certifications in maintenance
manual.
1.6.1 Provide factory applied plastic end caps on each length of pipe and
tube. Maintain end caps through shipping, storage and handling as
required to prevent pipe-end damage and eliminate dirt and moisture
from inside of pipe and tube.
16.2 Where possible, store pipe and tube inside and protected from weather.
Where necessary to store outside, elevate above grade and enclose with
durable, or by packaging with durable, water proof wrapping.
1.6.3 Protect flanges and fittings from moisture and dirt by inside storage
and enclosure, or by packaging with durable, water proof wrapping.
PART 2 - PRODUCT
2.1 Materials
a) UPVC pipes and pipe fitting to BS 3505 ClassE with push fit joints
for below grade installation.
Fittings for PEX Tube: ASTM F 1807, EN ISO 15875 metal-insert type with
copper or stainless- steel crimp rings and matching PEX tube dimensions.
3.2 Arrange and install piping to obtain maximum head room, avoiding
structural interference. Where piping is to be furred in, or concealed, the
Contractor shall coordinate the work to maintain his lines and levels.
3.4 The inside of all pipe, fittings, traps, valves and other equipment shall be
smooth, clean and free from blisters, loose mill scale, sand and dirt when
erected. Protect the open ends by using temporary plugs or caps.
3.5 The slope of the line shall be uniform between established elevations
without pockets.
3.6 Where piping of dissimilar metals, including copper piping and ferrous
materials, are joined provide dielectric couplings.
3.7 Install piping serving all equipment in such a manner that only small sections
need be removed to permit removal, cleaning or inspection (as applicable)
of the unit itself, or coils, tube bundles or heat exchangers contained therein.
3.9 Where raised face flanges are to be mated with flat face equipment or valve
flanges, the raised face of line flanges shall be removed. Bolt holes shall
straddle centre lines. Steel flanges to be bolted to cast iron valves of
equipment nozzles shall be flat faced, with full gaskets. In piping material
classes permitting use of both welding neck and slip-on flanges, use of
welding neck flanges shall be restricted to locations adjacent to welding fittings
and butterfly valves.
3.11 Piping and pipe sizes not indicated on the drawings shall be of size as
3.13 Pipe all relief valves, backflow preventers and drain valves to nearest floor drain.
3.14 Steel piping installed in inaccessible locations shall have welded joints.
3.15 Apply two coats of asphalt paint to all pipe laid in concrete or passing
through concrete.
3.16 All pipes shall be concealed inside walls, and/or furred spaces unless
specifically indicated otherwise.
3.19 Carry out, without cost, all alternations necessary in the arrangement of work
which has been installed without proper study and approval in order to
make such work come with finished lines of walls, ceilings and floors or to
allow the installation of the work of others.
PART 4 - EXECUTION
4.1 Pipe passing under a driveway or parking lot with less than 1.5 m cover
shall be encased in 150 mm of 1.37 MPa concrete on the top, bottom and
sides.
4.2 Compaction for the full width of the pipe trench shall be to at least 95%
Modified Proctor Density.
4.3 Connections between piping of steel and copper or brass shall be made
using dielectric fittings.
4.4 Provide thrust blocks for buried water mains, at every change in direction
of the pipe, to resist the thrust due to the test pressure and unexpected
surge during operation. Thrust blocks shall be poured against undisturbed
soil.
4.5 Allow for the expansion and contraction of all pipes. Install expansion joints to
have sufficient flexibility to prevent end thrust and movements caused
by thermal expansion and contraction which can cause damage to piping
and joints. For all PVC, PPRC and HDPE piping, provide expansion joints as
required to absorb all movements in piping systems.
4.6 Provide expansion joints for all piping at building expansion joints. Expansion
joints for PVC, PPRC and HDPE piping shall be as recommended by the
manufacturer. Expansion joints for steel and copper piping shall be as
described in Section 15304.
4.8 Flush all fluid-carrying systems after completion with a stream of water or
appropriate fluid at the highest obtainable pressure and velocity. Discharge
the flushing fluid through all strainers and out through line sized valves with
hose ends. Clean all strainers. Repeat flushing operation to the approval of
the Client Eng./ Consultant until the water is running clear, colourless and
odourless.
4.9 If the water pressure normally available on site is, in the Client Eng./
Consultant opinion, inadequate to perform proper flushing, then the Contractor
shall provide at his own expense, pumps, tanks, etc., to give pressure and
volume flows to the satisfaction of the Client Eng./ Consultant.
4.10 For layer systems, the flushing and cleaning shall be carried out in sections of
every three floors.
4.11 All piped pressure systems shall be hydraulically tested to at least 1.5
times the operating pressure. Pressure shall be maintained for at least 24
hours.
END OF SECTION
22 11 16
Contents
1.2.3 Provide all electrical works related to this section, to comply with the
requirements of relevant electrical sections.
1.3.3 The Complete Pump set shall be Factory tested as per Project Design
Parameters as per International Standards / Regulations.
1.3.4. The Complete Pump set shall be installed on common base frame (Epoxy
Coated) with heavy duty spring mounts
1.3.5. The Pump set shall be provide with Factory fitted power & control wiring and
control panels IP-65 as per project requirments.
1.4 Submittals
1.4.3 Submit full hydraulic calculations to verify flow and head of pumps based on
shop drawings. Calculations shall be approved by CLIENT/CONSULTANT
prior to final selection of pump.
1.4.5 Maintenance Data: Submit maintenance data and parts lists for each type of
pump, control and accessory, including “trouble – shooting” maintenance
guide. Include this data, product data, shop drawings and wiring diagrams in
maintenance manual.
1.5.2 Store pumps and components in clean dry place. Protect from weather, dirt,
fumes, water, construction debris, and physical damage.
1.5.3 Warranty / Spare parts; The Contractor shall provide full warranty for a
period of two year for complete set in all respects including pumps, motor,
VFD etc from the date of provisional acceptance certificate. The warranty
shall include parts and labour costs for the repair and replacement of defects
in material or workmanship. Contractor shall provide spare parts (at the time
of delivery of equipment) for three year operational after warranty period at
the time of hand over.
PART 2 - PRODUCTS
2.1.1 General
Vertical multistage centrifugal pump sets - Transfer Pump sets for Domestic
Water: Packaged Pump sets. Packaged pump sets shall be self-contained fully
automatic package units. The units shall be complete with duty/standby pumps,
quantity (as shown on the equipment schedule) and an automatic control panel
consisting of the following:
b. TP&N isolating switch, fully enclosed, interlocked with panel door and
external operating handle.
c. Hour run meter for each pump
Where more than one duty pump is specified for a pump set, the duty pumps
shall start with a 15 seconds time delay (adjustable) between each pump.
The “hand” button shall be spring loaded and shall override all control circuits
(except overload) so that the selected pump can be checked for operation.
Due to limited height of tanks the water levels at which pumps are switched
have to be determined accurately. Therefore, level switches with stainless steel
drop rods (which act as guides for floats) shall be used. Float switches with
plastic floats and directly connected cables shall not be permitted.
The water transfer pump sets shall operate based on level switches located in
the tanks. A set of level switches shall be provided for each compartment of the
tank. One level switch each shall be provided for starting each of the duty
pumps, one level switch for switching off all pumps and one level switch for
water high level alarm indication. A three-position switch shall be provided to
enable isolation of any one of the tanks (or compartment of the tank) from the
ON-OFF control circuit for maintenance. The third position shall be for normal
operation, i.e. all tanks (or compartments) are included in the ON-OFF control
circuit.
The transfer pump set shall include a pressure switch. Pressure switch shall
function as a safety cut off for pumps in case the pump cut-off level switch
malfunctions and ball float valves in the tank close. In case the pumps are
switched off by the pressure switch, the pumps shall not restart for 5 minutes
(adjustable), alarm indication shall be provided (indication light on panel fascia
and volt free contacts for indication to BMS) and the alarm condition shall
persist until it is manually reset.
h. Dry run protection based on level switch in each compartment of the feed tank
including indication. A three-position switch will be provided to enable
isolation of any one of the tanks (from dry run protection circuit) for
maintenance. The third position shall be for normal operation, i.e. all tanks
(or compartments) are included in the dry run protectioncircuit.
i. Alarm indication when pumps cut off due to pressure switch as detailed above
Materials
a. Casing: Stainless steel casing with drain connection fitted with plug.
o. Impellar: Stainless steel, multistage
q. Seal: Mechanical
s. Temperature Range: Up to 50 Deg C for cold water, up to 120 Deg C for hot
water
t. Ambient Conditions: Pumps must be suitable to operate at an ambient
temperature range of 55 Deg. C.
u. Pressure : PN 16 minimum or 150% of maximum or as per the system
requirement.
y. Piping: For piping materials and installation inside pump room shall be ABS
piping system
z. Piping, including valves and other components, may have grooved ends for
grooved joints.
aa. Control Panel: Factory installed and connected as an integral part of unit
complying with IEC and UL 508; automatic for multiple-pump, with load
control and protection functions. Protected to IP 55 and wired to IEE wiring
regulations.
bb. Enclosure: IP55.
cc. Hydro pneumatic Tank: Pre-charged, bladder tank with replaceable
natural rubber, diaphragm or bladder.
dd. Flexible Connectors:
PART 3 - EXECUTION
3.1 Examination
3.1.1 Examine areas, equipment foundations, and conditions with installer present for
compliance with requirements for installation and other conditions affecting
pump performance. Do not proceed with installation until unsatisfactory
conditions have been corrected.
Examine the installed plumbing and drainage system, verify actual locations of
piping connections prior to installation.
3.3 Installation
3.3.1 Comply with pump manufacturers written installation and alignment instructions.
3.3.2 Install pumps in locations indicated and arrange to provide access for periodic
maintenance, including removal of motors impellers, couplings and
accessories.
3.3.3 Adjust metal supports or wedges until pump and driver shafts are level. Check
couplings faces and pump suctions and discharge flanges to verify that they are
level.
3.3.4 Install suction and discharge pipe sizes equal to or greater than the diameter of
water pump nozzles.
3.3.5 Install valves of types and at locations indicated that are same size as the
piping connecting water pump, bypasses, test headers and other piping
systems.
3.3.7 Support pumps and piping separately so that weight of piping system does not
rest on pumps.
3.3.8 Install piping accessories, hangers and supports, anchors, valves meters and
gages, and equipment support as indicated for complete installation.
3.3.9 Install flow meter and sensing elements where indicated, install flow-measuring
system components and make connections according to manufacturers written
installation instructions.
3.4 Alignment
After alignment is correct, tighten foundation bolts evenly but not too firmly. Fill
base plate completely with non shrink, non metallic grout, with metal blocks and
shims or wedges in place. After grout has hardened, fully tighten foundation
bolts. Check alignment and take corrective measures required.
3.5 Connections
Connect suction and discharge side of the piping system to the pumps.
3.6.3 Perform field-acceptance tests for the pump unit (pump, driver and controller)
and system piping when pump unit installation is complete. Where possible,
field-correct malfunctioning equipment, then retest to demonstrate compliance.
Replace equipment that cannot be satisfactorily corrected or that does not
perform as specified and as indicated, then retest to demonstrate compliance.
Verify that each pump unit performs as specified and as indicated.
3.7.1 General
After completion of the Work, Contractor shall run a test over a sufficient period
of time to prove the proper capacity and performance of all apparatus, etc., and
the system as a whole.
3.7.2 The Contractor shall carry out commissioning and testing of all equipment
installed.
Test and adjust controls and safeties. Replace damaged and malfunctioning
controls and components.
Check that the pump is free to rotate by hand. Do not operate the pump if it is
bound or if it drags even slightly until cause of trouble is determined and
corrected.
a. Prime pump by opening suction valve and closing drains, and prepare
pump for operation.
Final setting positions for all regulating and controlling devices shall be
recorded and such records shall form part of the manual of the operating and
maintenance instructions.
All systems shall be field tested and run on load, with all automatic controls in
operation and all circuits balanced to produce design conditions, in presence
and to the satisfaction of the CLIENT/CONSULTANT.
In case of unsuccessful test run, the Contractor shall take necessary step for
the rectification and retested to the satisfaction of the CLIENT/CONSULTANT.
The Contractor shall also provide services of skilled and unskilled staff during
the test run of all the systems as required by the CLIENT/CONSULTANT.
END OF SECTION
22 11 23
1.1 Reference
1.4 Submittals
1.4.3 Maintenance Data: Submit maintenance data and parts lists for each type of
equipment, control and accessory, including “trouble - shooting” maintenance
guide. Include this data, product data and shop drawings in maintenance
manual.
1.5.2 Store equipment and components in clean dry place. Protect from weather,
dirt, fumes, water, construction debris, and physical damage.
2.1.1 The manufacture and design of the hot press moulded GRP sectional water
storage tanks with 25 mm layer of rigid polyurethane foam of 40 kg/m³ and
covered with UV resistant GRP layer , shall be to the quality standard
requirements of BS EN ISO 9001 and shall comply with BS7491 : Part 3 : 1994
glassfibre reinforced plastic cisterns for cold water storage.
2.1.2 Cisterns shall be manufactured by the (hot press moulded method) glass
reinforced plastic, moulded at temperatures up to 150 deg.C using isophthalic
unsaturated polyester resins, UV stabilized and ‘E’ glassfibre reinforcement,
color shall be to the approval of the Client/Consultant Engineer.
2.1.3 The cistern design shall incorporate 1.00 x 1.00m pillow panels to walls of non-
insulated cisterns with provision for flat panels for connections and fittings.
Purpose made cover panels 1.00m x 1.00m and 1.00m x 0.50m flat panels
positioned to give free draining channels.
2.1.4 Base panels available as internally flanged IFB with 1.00m x 1.00m flat panels,
fasteners internal, or externally flanged EFB with 1.00m x 1.00m flat panels and
one pillow sump panel, fasteners external.
2.1.5 All Surfaces of the panels shall be smooth and crevice free to provide hygienic
finish and be dimensionally accurate with sharply defined profiles.
2.1.6 Float valve chambers to be provided with central hinged lockable ABS lid,
1.00m x1.00m in plan, with options of 180mm, 300mm, 500mm depth with
provision for type A air gap in compliance with BS6281 : Part1 : 1992.
2.1.8 All tanks deeper than 1.50m shall be fitted with internal GRP ladders, external
standard duty stainless steel access ladders.
2.1.9 Where partitions are required, they must be of full height using standard panels.
Each compartment to be capable of supporting water on either side with one
side empty.
2.1.10 Panels to be rigidly supported by a combination of stainless steel 316L tie rods
internally and galvanized box sections externally. Bolts and nuts used in
assembly of tanks shall be stainless steel 316/A4 grade.
2.1.11 Steelworks designed to BS5950, internally stainless steel 316/A4 grade and
externally mild steel galvanized to BS729. The cisterns to incorporate external
wall bracing on depths greater than 1.50m, and tie rods 2.00m.
2.1.12 Extruded synthetic rubber sealing strip to be used covering full width of panel
flange providing a watertight seal.
Panel strength shall be fully compliant with BS 7491 : Part 3 : 1994 , giving a
factor of safety of tanks in excess of 6 times working pressure against rupture.
2.1.17 Tank's water level and over flow alarm shall be monitored from Building
Management System.
PART 3 - EXECUTION
3.1.1 All tanks shall be installed strictly in compliance with the manufacturer’s
instructions.
3.1.2 All cisterns to be installed on either flat continuous foundation or close center
beams conforming to manufacturer’s specification of flatness and deflection.
3.1.5 The testing of panels and sealant shall be as listed by Water Research Center,
UK conforming to water fittings Bylaws Scheme.
END OF SECTION
22 12 00
Contents
1.1 Reference
Conform to general requirements for Mechanical Services of Division 21, 22, 23.
Firms regularly engaged in manufacture of floor drains, cleanouts and roof drains
of types and sizes required, whose products have been in satisfactory use in the
similar service for not less than five (5) years.
1.3 Submittals
PART 2 - PRODUCT
2.1 Materials
a) Floor traps: ABS / HDPE with rodding eye (110 dia top inlet, 82 dia outlet)
with minimum water seal of 7 cm.
b) Floor drain: ABS / HDPE body with 150 x 150mm heavy duty stainless
steel/cast bronze gratings and covers. The open area of strainer shall be
at least two third of the cross sectional area of the drain line to which it
connects. Note wherever floor drain is indicated it shall be connected to
floor trap unless other wise indicated.
c) Funnel floor drain where specified shall include a nickel bronze funnel
secured to the grating.
d) Flower bed drain where specified shall be heavy duty, dome type drain
coated cast iron body with bottom outlet complete with combination
membrane flashing clamp/gravel guard, low silhouette dome and stainless
steel mesh screen over dome, no floor trap is required.
e) Floor trap with trap primer shall be normal floor drain as described above
but with trap primer connection.
a) Floor type: ABS / HDPE body with square or round adjustable, secured,
heavy duty Stainless steel top with 3mm tile recess.
b) Wall type: ABS / HDPE body with square heavy duty stainless steel
smooth wall access cover and frame, 150 x 150mm.
c) Clean out at high level shall be HDPE screw cap and washer.
All covers, frames & gully gratings shall be manufactured from ductile iron and
be coated with an approved heavy duty, glossy, chemical and abrasion resistant,
corrosion resistant, non discoloring, UV resistant, epoxy paint system to a
minimum D.F.T. of 375 microns (such that when the cover is pulled over the
frame, the coating should not go).
With each consignment the supplier has to submit routine QC test reports that
shall also include the batch numbers that comprises the consignment.
Nevertheless the CLIENT/CONSULTANT shall do the quality auditing from time
to time.
The traceability system of the supplier shall be such that it should be able to
trace any failures, at least, up to the raw materials sources.
Any personnel from client, consultant, etc should be able to visit the
supplier’s yard, testing arena, storage area etc. shall immediately given
access. If any regular/random tests or QA/QC records are requested to
check the continued compliance, then it shall be obliged immediately.
Manhole covers, gratings and frames shall comply with EN 124. The
materials shall be ductile iron of grade 500/7 or 600/3 as per ISO 1083 or
grade 80-55-06 as per ASTM A536. All frames shall be bolted to cover slabs.
The batch numbers shall be legibly marked, comprehensive & visible and the
traceability from these numbers shall be at least up to the Raw Material,
Each batch and/or consignment shall be accompanied by Batch’s Tensile
testing bar.
ONE percent of all supplies shall be tested for Load, Microstructure (>66%
The Tops shall be delivered to UAE in fine cast. The surface shall be free of
any irregularities whatsoever like grooves, voids (more than 2mm in depth),
Color shades, Filling, Unevenness, Roughness, Depression, etc.
The coatings shall be Solvent Free Pure Epoxy. The thickness of the coating
shall not be less than 375 microns and when subjected to pull off Tests as
per ASTM D4541, the Adhesion shall be more that 6 MPa.
If any random test fails in load, tensile, permanent set then 3 more samples
will be tested an if any one of these 3 fails then the approval is suspended,
During the Suspension no more supplies will be allowed for any of the
projects, and for any size, supervised by CLIENT/CONSULTANT, from the
date of suspension, even if they have passed the required tests.
All covers, except those for storm water drains shall be water, gas and
airtight.
In general all covers and frames used in paved area are shall be of type
D400 and all covers and used in non-traffic green or side walk areas shall be
of type C250 and those used outside pavements or walkways shall be B125.
Paved area includes roads, tiled roads, parking areas and footpaths.
All covers shall be fitted to the frames and tested at the manufacturer’s
works, and covers and frames shall be similarly numbered in a legible and
permanent manner in a position which will not be visible when fitted in place.
The Contractor shall ensure that the covers are fitted to the appropriately
numbered frames after the frames have been fixed.
Covers to manholes shall have lids with an approved non-slip surface and
shall be of non rocking type with three point suspension.
All sewer manhole, sewer chamber and valve chambers shall have the
equivalent Arabic notation for the expression ‘Sewerage, (followed by the
year of completion)’ clearly cast into the upper side of the covers in letters
approximately 45 mm high. Storm water manholes and chamber covers shall
be similarly badged with “CLIENT/CONSULTANT, Storm Water” in both
English and Arabic.