07 Project PERT
07 Project PERT
ESTIMATE
Example: ABC Associates
ET = (a + 4m + b)/6 2 = ((b-a)/6)2
Activity Expected Time Variance
A 6 4/9
B 4 4/9
C 3 0
D 5 1/9
E 1 1/36
F 4 1/9
G 2 4/9
H 6 1/9
I 5 1
J 3 1/9
K 5 4/9
• Project Network
D J
5 3
H
A E 6
6 1
I
Start
C F 5 Finish
3 4
K
B G 5
4 2
• Earliest and Latest Times
D 6 11 J 19 22
5 15 20 3 20 23
H 13 19
A 0 6 E 6 7 6 14 20
6 0 6 1 12 13
I 13 18
Start
C 6 9 F 9 13 5 13 18 Finish
3 6 9 4 9 13
K 18 23
B 0 4 G 9 11 5 18 23
4 5 9 2 16 18
• Earliest/Latest Times and Slack
Activity ES EF LS LF Slack
A 0 6 0 6 0*
B 0 4 5 9 5
C 6 9 6 9 0*
D 6 11 15 20 9
E 6 7 12 13 6
F 9 13 9 13 0*
G 9 11 16 18 7
H 13 19 14 20 1
I 13 18 13 18 0*
J 19 22 20 23 1
K 18 23 18 23 0*
• Determining the Critical Path
D 6 11 J 19 22
5 15 20 3 20 23
H 13 19
A 0 6 E 6 7 6 14 20
6 0 6 1 12 13
I 13 18
Start
C 6 9 F 9 13 5 13 18 Finish
3 6 9 4 9 13
K 18 23
B 0 4 G 9 11 5 18 23
4 5 9 2 16 18
Question
Beta Distribution
Probability
a m b Time
Optimistic Mean Pessimistic
Probabilistic Activity Times - Another Example
Task 2 3 6 9
Task 3 1 3 5
Task 4 2 4 12 Task 1
Task 5 2 3 4 Task 2
Task 6 3 4 5 Task 3
Task 7 2 2 2 Task 3
Task 10 1 4 7 Task 4
= 25 weeks
2 = 62/9
= 6.9 weeks2
Probability Analysis of a Project Network