QLD Manual For Assessing Consequence Categories and Hydraulic Performance of Structures
QLD Manual For Assessing Consequence Categories and Hydraulic Performance of Structures
Table of Contents
1 Scope ...............................................................................................................................................................3
1.1 Related Guideline and laws ......................................................................................................................3
1.2 Background ...............................................................................................................................................3
1.3 Purpose .....................................................................................................................................................4
2 Assessment requirements ............................................................................................................................4
2.1 Initial consequence category assessment ................................................................................................4
2.1.1 Exemptions ........................................................................................................................................5
2.1.2 Consequence category—based on assessment of failure event scenarios ......................................6
2.2 Hydraulic performance criteria for dams that are regulated structures ...................................................10
2.2.1 Failure to contain – seepage............................................................................................................10
2.2.1.1 Managing seepage consequences for higher risk contaminant concentrations.......................11
2.2.2 Hydraulic performance criteria for regulated dams that are assessed as ‘significant’ or ‘high’
consequence for the overtopping scenario ....................................................................................................12
2.2.2.1 Hydraulic performance objectives for ‘failure to contain – overtopping’ ...................................12
2.2.2.2 Managing design storage allowance and extreme storm storage in integrated water
management systems .................................................................................................................................13
2.2.2.3 Estimating the design storage allowance .................................................................................14
2.2.3 Failure to contain – dam break ........................................................................................................14
2.2.3.1 Hydraulic performance objectives for ‘failure to contain – dam break’ .....................................14
2.3 Specific considerations for levees and associated hydraulic performance criteria. ................................15
2.3.1 Consequence assessment for levees ..............................................................................................15
2.3.2 Hydraulic performance criteria for levees that are regulated structures ..........................................16
3 Definitions .....................................................................................................................................................18
4 References ....................................................................................................................................................18
Appendix A—Example methods for estimating the design storage allowance ............................................19
A.1 Estimating the design storage allowance using the method of deciles for volumetric containment ........19
Background ....................................................................................................................................................19
Method of calculation .....................................................................................................................................21
A.2 Estimating the design storage allowance using the method of operational simulation for performance
based containment .........................................................................................................................................22
General ...........................................................................................................................................................22
Documentation ...............................................................................................................................................22
Model continuity and net balance check ........................................................................................................23
Climate data used in modelling ......................................................................................................................24
Hydrological processes and water management operations .........................................................................24
Conservative assumption of no seepage losses or transmission losses .......................................................24
Runoff processes............................................................................................................................................25
Model calibration and validation .....................................................................................................................25
Accounting for model inaccuracy and lack of calibration data .......................................................................25
Appendix B—Notes on consequence assessment based on failure event scenarios .................................27
Flooding considerations for consequence assessment .................................................................................27
Failure to contain consequence .....................................................................................................................27
Dam break flood consequence .......................................................................................................................28
Fundamental consequence evaluation data ..................................................................................................28
Inspection of site or desktop analysis.............................................................................................................28
Collation and assessment of data ..................................................................................................................29
Appendix C—Minimum requirements of certification/certification report ....................................................30
Version history
5.01 29 March 2016 The document template, header and footer have been updated to
reflect current Queensland Government corporate identity
requirements and comply with the Policy Register.
Page 2 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
1 Scope
This Manual for assessing hazard consequence and hydraulic performance of structures (the Manual) sets out
the requirements of the administering authority, for consequence category assessment and certification of the
design of ‘regulated structures’, constructed as part of environmentally relevant activities (ERAs) under the
Environmental Protection Act 1994 (EP Act).
The term regulated structures includes land-based containment structures, levees, bunds and voids, but not a
tank or container designed and constructed to an Australian Standard that deals with strength and structural
integrity. Structures may be assessed using this Manual as being in one of three consequence categories: low,
significant or high. Where categorised as a significant or high consequence, the structure is referred to as a
regulated structure.
This Manual does not provide a detailed methodology for the design of dams, spillways and levee structures.
The detailed design of a regulated structure is to be undertaken by a suitably qualified and experienced person 1
with relevant professional experience, and requires appropriate documentation and certification 2.
The Manual does not limit, amend or change in any way, any other requirements to be complied with under
environmental authority (EA) conditions and/or regulations for the design and operation of a dam 4. Further, this
Manual does not negate any lawful requirements of the EP Act, other Commonwealth, state or local
government laws or requirements under relevant standards or agreements.
1.2 Background
Good practice engineering for dams, spillways, and levee structures requires that they be assessed for the
consequences associated with ‘dam break’ and ‘failure to contain’ scenarios, and that the impacts of such
potential failures are identified and considered in their design and operation.
The early identification of the consequence potential of these structures is important in determining the standard
of reliability required for design, construction and operation of the structure. The default objective for any
structure containing substances (liquid and/or solid material) that could result in environmental harm is that the
substances be contained so as to prevent or otherwise minimise harm to the environment.
Whilst this Manual details the hydraulic performance criteria for regulated structures, it does not prescribe site
planning standards. Site planning should consider avoiding wherever possible and practicable locating
regulated structures in high risk or sensitive locations (e.g. flood plains, above shallow groundwater systems,
residential areas, environmentally sensitive areas).
1 The term ‘suitably qualified and experienced person’ is defined in the definitions.
2A copy of the certification required can be found at appendix B
3 This is the publication number, which can be used as a search term to find the latest version of the publication at
www.des.qld.gov.au.
4 An example of other legislative requirements that may be relevant are those relating to referrable dams under the Water
Page 3 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
The Manual does not detail operational standards for regulated structures. However, the water management
strategy for a site must entail active management (including if relevant, treatment) of contaminated waters in
regulated structures so that in the event of an incident, the impact is reduced to as great an extent as possible,
(if not avoided altogether). This should include use of pumps and transfer systems of appropriate capacity to
effectively manage contaminant water levels in the structure. Water management should also minimise
unnecessary generation of contaminated waters by segregating clean catchment flows from contaminated
catchment flows. In this context, regulated structures also include flood protection levees to reduce risk of
ingress of clean floodwaters into operational areas where they may become contaminated with possible adverse
impact on water management operations and containment performance.
Structures that could have significant or high impacts need to be carefully designed and operated.
1.3 Purpose
1. guide the assessment of the consequence category of all structures constructed as part of activities that
require an EA or development approval
2. guide the determination of the structures that require formal documentation; and
3. provide approved methods for specifying the design performance and monitoring requirements for those
structures.
• Part 2—outlines the hydraulic performance requirements for dams that are assessed as being regulated
structures
• Part 3—outlines specific considerations for assessing levees and hydraulic performance requirements for
levees that are assessed as regulated structures
2 Assessment requirements
2.1 Initial consequence category assessment
This part provides guidance for undertaking a consequence category assessment for a structure which is a dam
or levee.
All structures which are dams or levees associated with the operation of an ERA, must, unless otherwise stated
in this Manual, have their consequence category assessed based on the potential environmental harm that
would result from the failure event scenarios (Section 1.1) described in this Manual. Specific considerations for
levees are included in part 3 of this Manual and consequence category assessments for levees should be
conducted in consideration of the information contained in this section.
The consequence category will determine whether the structure is a regulated structure. A structure is only a
regulated structure where the consequence category for the structure is ‘significant’ or ‘high’.
The consequence category of a structure is the highest consequence category determined under any of the
assessment criteria set out in this part for each failure event scenarios.
Page 4 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
2.1.1 Exemptions
Structures are excluded from the requirements of this Manual if they comply with (a) or (bb):
v. allow the structure to be managed in a way that first prevents then minimises the potential of fluids
overtopping.
iv. meet a site-specific or pro-forma certification of a design plan to contain the wetting front; and
v. allow the structure to be managed in a way that first prevents then minimises the potential of fluids
overtopping.
(a) a description of all the documents which constitute the design plan;
i. the applicable standards including engineering criteria, industry guidelines, relevant legislation and
regulatory documents, relied upon in preparing the design plan; and
ii. all relevant facts and data used in preparing the design plan, including any efforts made to obtain
necessary facts and data, and any limitations or assumptions to facts and data used in preparing
the design plan;
iii. setting out the reasoning of the suitably qualified and experienced person who has certified the
design plan, as to how the design plan provides the necessary required performance to ensure the
stability and structural integrity of the proposed structure.
(c) detailed criteria for the design, operation, maintenance and decommissioning of the regulated structure,
including any assumptions.
To be clear, structures used to contain wastewater from stimulation activities (i.e. fracc flowback water) are also
exempt if they meet the above requirements AND the structure is certified by a suitably qualified and
experienced person as being able to contain the wetting front. As an alternative to the RPEQ certifying the
structure as being able to contain the wetting front, a suitably qualified and experienced person may certify a
Page 5 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
‘pro forma’ design that will contain the wetting front. The pro forma approach means that individual suitably
qualified and experienced person certification for each structure is not required when the design is used.
The consequence category of a structure must be assessed by a suitably qualified and experienced person and
include:
1. Documentation of the assessment, including the methodology used, of each of the following failure event
scenarios:
(a) ‘Failure to contain – seepage’ – spills or releases to ground and/or groundwater via seepage from
the floor and/or sides of the structure;
(b) ‘Failure to contain – overtopping’ – spills or releases from the structure that result from loss of
containment due to overtopping of the structure; and
(c) ‘Dam break’ – collapse of the structure due to any possible cause.
Assessment of the ‘Failure to contain – seepage’ scenario is only required for new structures and does not
apply to structures approved prior to development of this version of the Manual.
Assessment of the ‘Failure to contain – overtopping’ and ‘Dam break’ scenarios are required for both new and
pre-approved structures.
In assessing each scenario under item 1, the types of impacts that may occur under the scenario must be
identified and considered, and must include any local and regional flooding that may lead to:
2. Documentation of the assessment, in relation to each of the above scenarios, of the potential for each of
the following:
(a) the failure of a structure placing lives at risk due to dwellings or workplaces being in the failure impact
zone;
(b) downstream consequences, including but not limited to failure of other structures that may be affected
by any flooding;
(e) long term potential adverse effects due to release of contaminants to groundwater systems and soil
profiles;
5 This includes consideration of overtopping from inside and from outside due to flood ingress over the dam wall
6 Examples of other dam failure modes may include piping and pump failure
Page 6 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
(g) storage releases that may chemically interfere with waters used as sources of drinking water.
3. Despite any exemption that would otherwise have been applicable under the Water Supply (Safety and
Reliability) Act 2008, a failure impact assessment in accordance with the requirements that would
otherwise have applied under that Act if the structure is a dam that is either:
(a) more than ten metres in height with a storage capacity of more than 1500 Mega litres (ML); or
(b) more than ten metres in height with a storage capacity of more than 750ML and a catchment area that
is, more than three times its maximum surface area at full supply level;
If the dam exceeds these parameters, the additional assessment must be included in the
consequence category assessment, unless valid justification is documented in the consequence
category assessment for not doing so.
4. Documentation of any other matter that the suitably qualified and experienced person reasonably considers
to be relevant to the assessment, taking into account the guidance at the beginning of this Manual about
Scope, Related Guideline and Laws, Background and Purpose.
Upon completion of a consequence category assessment, a structure will have a consequence category
identified for each of the scenarios identified under item 2. These consequence categories will be determined by
applying Table 1 to the assessment of each failure event scenario.
Consequence categories for each failure scenario are subsequently used to determine the appropriate hydraulic
performance criteria in accordance with Part 2 of this Manual.
The consequence category for each failure event scenario may be changed by relocating the structure away
from where it could/will affect environmental values, including public amenity and safety. The consequence
category for a failure event scenario cannot be changed by adding a design element.
Page 7 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
required in all cases. Any consideration of potential impacts on groundwater systems should consider the water quality of
the potential receiving aquifer as well as the quality of fluid stored in the regulated dam. Existing groundwater drawdown in
areas surrounding resource operations (e.g. drawdown as a result of mine pit or underground mine dewatering) can also be
considered when assessing the consequence of dam seepage on groundwater systems.
10 'An adverse effect on human health means a physiological effect on human health and does not include an impact on the
quality of downstream water that merely negatively affects taste and which is unlikely to cause persons to become physically
ill.
11 Adverse effects includes chronic and acute effects where an acute effect is on living organism/s which results in severe
symptoms that develop rapidly, and a chronic effect is an adverse effect on a living organism/s which develops slowly. In
Page 8 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
some instances, it may be necessary to carry out or reference existing ecological/toxicological studies to assess the impacts
of contaminants on living organisms.
12 See Environmental Protection (Water and Wetland Biodiversity) Policy 2019for definitions
13 Wetland of general ecological significance’ means a wetland shown on a map of referable wetland as a ‘general
workers’ accommodation, agricultural facilities on the holder’s land such as a farm shed or farm dam or infrastructure solely
for servicing the holder.
Page 9 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
2.2 Hydraulic performance criteria for dams that are regulated structures
The requirements under Part 2 only apply where a dam is assessed to be a regulated structure. The hydraulic
performance objectives for dams that are regulated structures are directly related to the assessed consequence
category for each failure event scenario:
1. ‘Failure to contain – seepage’ – dams that are regulated structures must be designed to ensure
appropriate containment of contaminants in accordance with a specified design standard based on the
assessed consequence category for the ‘failure to contain – seepage’ scenario.
2. ‘Failure to contain – overtopping’– dams that are regulated structures must be designed to ensure
appropriate containment of contaminants up to a specified probability of exceedance criteria based on the
assessed consequence category for the ‘failure to contain – overtopping’ scenario.
3. ‘Dam break’ – spillways of dams that are regulated structures must be designed to ensure that the
structure will survive and can successfully pass a flood event up to a specified probability exceedance
criteria.
The hydraulic performance objectives for dams that are regulated structures in relation to the ‘failure to contain
– seepage’ scenario are to be achieved by:
2. determining appropriate materials, design parameters and construction requirements to achieve the relevant
design objective for containment
3. determining appropriate design parameters and construction requirements to meet the design objectives
relating to leak detection and rectification.
High consequence Designed with a floor and sides Have a system that will Either be capable of
of material that will contain the detect any passage of repair to rectify any
wetting front and any entrained the wetting front or passage of the wetting
contaminants within the entrained front through either the
bounds of the containment contaminants through floor or sides of the dam,
system during its operational either the floor or sides or else be
life. of the dam15.
15 Leakdetection and/or monitoring requirements will be required by conditions on the environmental authority. Consistent
with the requirements of this table, additional monitoring may also be required. For example, groundwater bores may be
required to be monitored in the vicinity of some dams (‘failure to contain – seepage’) if the groundwater systems are
Page 10 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
decommissioned and
rehabilitated.
Significant Designed with a floor and sides Have a system that is N/A16
consequence of material that will minimise appropriate to
(or reduce) seepage to avoid demonstrate that
the environmental harm in the significant harm as per
significant consequence table 1 will not occur.
category in Table 1 and ensure
that the environmental harm
likely to occur is only as in the
low consequence category of
that table.
For dams assessed as having a ‘high’ consequence category for the ‘failure to contain – seepage’ scenario, and
also assessed as exceeding, one or both of the thresholds in Table 3, the design criteria in Table 4 will apply to
the structure in addition to those controls which are required for a “high” consequence structure in Table 2.
Table 3. Specific contaminant trigger levels Consequences for higher risk dams associated with the
‘Failure to contain – seepage’ scenario
Contaminant Limit
pH pH <5
Table 4. Additional design criteria for dams determined to meet the requirements of Table 3
Dams that are both assessed as having a ‘high’ Constructed with a system for the collection and
consequence category for ‘failure to contain – proper disposal of any contaminants that move
seepage’ scenario, and that are assessed as beyond the bounds of the containment system
meeting the consequence thresholds identified in
Table 3 for the ‘failure to contain – seepage’ scenario
identified as potentially at risk, or if there is uncertainty about the impacts from seepage from the regulated dam.
Conditions, including conditions about monitoring are imposed under the provisions of the EP Act.
16 While rectification measures are not a design requirement, this does not remove any subsequent obligations imposed by
the administering authority to require rectification or decommissioning of a dam if dam failure is believed to have caused,
or about to cause, environmental harm.
Page 11 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
2.2.2 Hydraulic performance criteria for regulated dams that are assessed as ‘significant’ or ‘high’
consequence for the overtopping scenario
The DSA, ESS and MRL requirements in this section must be addressed for only those dams assessed as
having a ‘significant’ or ‘high’ consequence for the ‘failure to contain – overtopping’ scenario. If a dam was
assessed in the low consequence category for the ‘failure to contain – overtopping’ scenario, the determinations
for a DSA, ESS and MRL are not required even if the dam is otherwise a regulated structure, e.g. if assessed as
‘significant’ or ‘high’ consequence for the ‘failure to contain – seepage’ scenario only.
Definitions for DSA, ESS and MRL are set out in the Guideline. In summary:
(a) The DSA is an available volume provided in a dam as at 1 November each year in order to prevent a
discharge from that dam up to a specified annual exceedance probability (AEP).
(b) The ESS means a storm storage allowance determined in accordance with the criteria below.
(c) The MRL is a level at which the dam has a remaining available volume equivalent to the ESS
allowance and this must be marked in a clearly visible location [NB this would not be required for ‘all’
dams if using a linked MRL system].
The DSA, ESS and MRL can be distributed across multiple regulated dams as described in Section 2.2.2.
In determining the hydraulic performance requirements under this section, the consequence category to be
applied is the consequence category determined from the ‘failure to contain – overtopping’ scenario.
The hydraulic performance objectives for dams that are regulated structures in relation to the ‘failure to contain
– overtopping’ scenario are to be achieved by:
1. selecting an appropriate AEP for adequate wet season containment storage (DSA) from Table 5
2. selecting an appropriate methodology to determine minimum capacity requirements for wet season
containment storage (DSA). The suitability of the selected method for ensuring the appropriate mitigation of
risk of harm must be substantiated and certified by the suitably qualified and experienced person in the
design plan for the dam
(a) selecting the highest volume/lowest level required in a regulated dam to contain:
i. the runoff from the contributing catchment of the particular dam for a 72-hour duration storm at
the AEP specified in Table 5, using 100% runoff of rainfall and making documented
conservative assumptions regarding the operability of equipment during the event; and
Page 12 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
ii. a wave allowance at that AEP as estimated using a recognised engineering method.
(c) measuring ESS/MRL volume with respect to the dam spillway level.
The estimation of an operational DSA and ESS volume must, as a minimum, be undertaken in accordance with
this part and take into consideration reasonably foreseeable scenarios including, but not limited to, climatic
variability and pump or power failures during wet weather events.
A dam that is a regulated structure must be designed and operated such that:
(a) Sufficient available storage is maintained to accommodate expected inputs and outputs during the
year.
(b) The DSA is provided for at the 1 November for the coming wet season.
(c) All reasonable efforts are made to ensure the ESS is provided for at all times.
Consequence category for ‘failure to contain – Wet season Storm event containment
overtopping’ containment (DSA) (ESS)
72 hr duration
2.2.2.2 Managing design storage allowance and extreme storm storage in integrated water
management systems
1. For sites with interconnected regulated dams functioning as an integrated containment system, the DSA
and/or ESS volume calculated for the entire containment system catchment may be shared across a
number of regulated dams comprising the containment system.
2. Where this approach is taken, the design and operating rules for the system as a whole must be
documented in a system design plan that is certified by a suitably qualified and experienced person.
3. The system design plan must contain the design plans, the ‘as constructed’ plans, the operational rules for
each individual regulated dam that forms part of the system, the standards of serviceability and
accessibility of water transfer equipment or structures, and the operational rules for the system as a whole.
Note: An acceptable system design should have demonstrable resilience in the event of failure in any
component of the system and provision for redundancy. For example, fixed plant and equipment, and
automatic operation are features that would add resilience.
Page 13 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
4. The system design plan must state what DSA and/or ESS volume is to be located in each regulated dam
that forms part of the system on the 1 November prior to the next wet season.
5. Where DSA and/or ESS is to be distributed across a containment system, the design and operation must
consider and allow for the practical limitations of being able to redistribute stored volumes across the
containment system (including operability of equipment under extreme weather conditions).
6. A methodology for accurately identifying the MRL for the water management system (i.e. when the total
remaining available free volume in the water management system is equal to the ESS) must be specified in
the design plan and identified by a physical marker (or marker’s) in a clearly visible location wherever
possible. Where the ESS is to be shared across multiple storages in an integrated system, the
methodology for determining when MRL for the entire system is reached and how it is to be managed must
be documented in the design plan.
7. The transfer capacity of redistribution systems must consider the possible need to transfer large volumes of
water within short timeframes (i.e. not use average wet season accumulation to determine required transfer
capacity).
8. The overall objective of the system design must remain the minimisation of the potential for harm that could
occur from a failure to contain contaminants.
9. If there is complexity or diverse constraints in the way that transfer systems can be operated to effectively
redistribute accumulating waters during the wet season, this must be considered by the suitably qualified
and experienced person in selecting the methodology used as the basis for calculating the DSA and/or
ESS requirements.
The certification required as part of the regulated structures approval must specifically certify that the chosen
method for estimating DSA is considered suitable, by the suitably qualified and experience person, to be relied
upon for the mitigation of risk or harm associated with the ‘failure to contain – overtopping’ scenario. This must
be substantiated and certified in the design plan for the dam. This requirement for certification also applies to
any methodology that may be used to estimate the DSA in situations where a significant proportion of expected
inflows into the structure are likely to be as a result of pumping or other means of transfer.
Notwithstanding the above, Appendix A details two example methods for estimating the DSA that could
potentially be used. This appendix is provided as guidance only and is not intended to limit the ability of the
suitably qualified and experienced person to select a method that best suits the available data and individual
circumstances for the dam in question.
In determining the hydraulic performance requirements under this section, the consequence category to be
applied is the consequence category determined from the ‘dam break’ scenario.
The hydraulic performance objectives for dams that are regulated structures in relation to the ‘dam break’
scenario are to be achieved by selecting an appropriate design AEP for spillway capacity in accordance with
Page 14 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
Table 6. Table 6 provides a range of design events for spillways. A designer should select and document a
conservative capacity from the nominated range based on expected dam break consequences.
When determining the spillway capacity, it must be assumed that the dam commences full at the spillway crest
level; and that diversion works designed to restrict the contributing catchment are not effective, unless those
diversion works are included specifically in the certified design plan and designed to the same hydraulic
performance criterion as the spillway. Appropriate freeboard and wave allowance above the peak design flood
level in the dam should be provided and documented.
Containment dams 1:1 000 AEP To Spillway design flood peak level + wave run-up
allowance for 1:10 AEP wind
high consequence 1:100 000 AEP
Containment dams 1:100 AEP To Spillway design flood peak level + wave run-up
significant consequence allowance for 1:10 AEP wind
1:1000 AEP
2.3 Specific considerations for levees and associated hydraulic performance criteria.
2.3.1 Consequence assessment for levees
Levees may differ from most dams containing contaminants, where the consequence category can be readily
determined for ‘failure to contain’ and ‘dam break’ scenarios in accordance with Table 1 and appendix B.
For flood protection levees or diversion levees, the suitably qualified and experienced person conducting and
certifying the assessment needs to consider the function of the levee in relation to the broader operations and
management of contaminants at the site, including functions to protect the integrity of contaminant storages.
The following situations should be considered for consequence assessment of levees.
1. Levee designed for the diversion of contaminated waters or protection of the structural integrity of a dam
Where a levee is designed to divert contaminated waters into a containment dam (which also means designed
to prevent release of contaminants), or as part of the protection of the structural integrity of a containment dam,
the levee should be considered a key design element of the relevant dam.
The consequence assessment is then to be undertaken for ‘failure to contain - overtopping’ and ‘dam break
17 The design criteria identified in this table are relevant to a dam break scenario that is caused by failure of the spillway to
pass a flood of the identified probability or where flood ingress over the tops of the banks occurs. As such, they are not
relevant to dam break failure modes where no inflows exist to the dam, such as failure caused by piping. Consideration by
the suitably qualified and experienced person may need to be given to the appropriateness of the consequence category for
the ‘dam break’ scenario and the correct application of the design criteria in this table if there is a significant difference in
consequence between the different failure modes.
18 Spillway capacity selected by the certifier with rationale.
19 If spillway design flood is PMF, no wave run-up is required. Part of safety bunds of embankments may be used for waver
Page 15 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
scenarios’ (as outlined in Table 1 and appendix B) from the perspective that the levee is an integral part of the
dam performance and failure of the levee could result in either failure to contain contaminants, and/or result in
dam break failure of the dam.
Where a levee is designed to prevent ingress of non-mine affected flood water into an operational area, or
catchment of a containment system, the suitably qualified and experienced person conducting and certifying the
assessment and construction would declare that the levee is a regulated structure where the flood modelling
shows that the pit would be encroached by a flood event with a probability more likely than or equal to 1:1000
AEP. The design and construction of the levee is to meet the criteria in Table 7 scenarios.
Where the flood modelling shows that an operational area or catchment of a containment system would be
encroached by a flood event with a probability less likely than 1:1000 AEP, a cost benefit analysis should be
undertaken to decide if a levee is to be constructed to provide protection against such an event.
For levees determined to be regulated structures based on their function primarily to exclude flood water, design
criteria are defined in Table 7 of this Manual.
The consequence assessment for both situations must include sufficient documentation of the context of the
levee in relation to site containment systems and surrounding waterways and catchments (with maps and
quantified data on catchments within and outside the containment system) to substantiate the classification
determined to be appropriate by the suitably qualified and experienced person conducting and certifying the
assessment.
In the above situations, if the consequence of ‘failure to contain’ and ‘dam break’ of the levee has been
incorporated into the relevant dam assessment, there does not have to be an individual consequence
assessment of the levee separate to the dam assessment.
There is no requirement for a consequence assessment for the ‘failure to contain – seepage’ scenario to be
conducted for levees.
2.3.2 Hydraulic performance criteria for levees that are regulated structures
The requirements under this section only apply where a levee is assessed to be a regulated structure in
accordance with Part 1 and section 3.1 of this Manual.
In determining the hydraulic performance requirements under this section, the consequence category to be
applied is the consequence category determined from the ‘dam break’ scenario.
The hydraulic performance objectives for levees in relation to the ‘dam break’ scenario are to be achieved by
designing and maintaining each levee so that:
(a) it isolates and diverts the peak flow from a design storm of critical duration for the contributing
catchment relevant to the zone to be protected by the levee, at an AEP specified in Table 7; or
(b) it can adequately accommodate the estimated level and flow rate of a release of flowable materials
that may result from failure of other works or infrastructure; and
Page 16 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
(c) in at least one place in the levee crest, there is a restricted length of low crest, limiting the freeboard at
that point, such that a flood exceeding the design protection level of the levee will be directed to a
planned area or areas within the zone to be protected.
Consequence category for levee20 Design criteria - flood level for embankment crest levels*
20 The design criteria identified in this table are relevant to section 2.3.1 – Consequence assessment for levees. As such,
they are not relevant to dam break failure modes where no overtopping occurs, such as failure caused by piping.
Consideration by the suitably qualified and experienced person may need to be given to the appropriateness of the
consequence category for the ‘dam break’ scenario and the correct application of the design criteria in this table if there is a
significant difference in consequence between the different failure modes.
21Refer definition of a levee. Table 1 consequence assessments are not necessarily used to assign a consequence
category to a levee; refer to the Appendix for further guidance. All regulated levees are required to provide a minimum of
1:1000 AEP flood protection.
Page 17 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
3 Definitions
Note: Definitions of terms in this document are provided in the guideline Structures which are dams or levees
constructed as part of environmentally relevant activities (ESR/2016/193422).
4 References
1. Downstream Hazard Classification Guidelines, ACER Technical Memorandum No. 11, U.S. Department of
the Interior, Bureau of Reclamation 1988.
2. Guidelines on Dam Safety Management, Australian National Committee on Large Dams (ANCOLD) August
2003.
3. Guidelines on the Consequence Categories for Dams. Australian National Committee on Large Dams
(ANCOLD) October 2012.
4. Guidelines on Tailings Dams. Australian National Committee on Large Dams (ANCOLD) May 2012
5. Queensland Dam Safety Management Guidelines. Queensland Department of Natural Resources and Mines
February 2002
6. Guideline for Failure Impact Assessment of Water Dams. Queensland Department of Environment and
Science June 2010.
7. Guidelines on Acceptable Flood Capacity for Dams. Queensland Department of Natural Resources and Water
February 2007.
8. Technical Guidelines for the Environmental Management of Exploration and Mining in Queensland.
Queensland Department of Minerals and Energy January 1995.
9. Dam Safety Course Notes. Queensland Government Dam Safety Group DPI Water Resources March 1994.
10. Guidelines on Selection of Acceptable Flood Capacity for Dams, Australian National Committee on Large
Dams (ANCOLD) March 2000.
11. Guidelines on Prevention of Water Pollution from Cyanide Use in Gold Ore Processing, Queensland
Government Department of Environment and Heritage, January 1990.
22This is the publication number, which can be used as a search term to find the latest version of the publication at
www.des.qld.gov.au.
Page 18 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
Background
Rainfall data is available for most localities throughout Queensland from the Bureau of Meteorology. Studies of
this data indicate that:
1. Queensland is subject to tropical/sub-tropical wet seasons typically caused by monsoonal/tropical lows and
cyclones.
2. Consistently for locations in the river basins depicted in Figure 1, an average of up to 70% of total annual
rainfall occurs during the periods of months as indicated in that figure.
3. Cumulative wet season rainfall for a series of storms generally exceeds that of a rare event storm.
4. Extreme storms are most likely to occur during the wet season.
Queensland is subject to tropical/sub-tropical wet seasons typically caused by monsoonal/tropical lows and
cyclones.
Pre-wetting of land increases the proportion of rainfall that reports as runoff. When land is saturated a large
portion of rainfall becomes surface runoff. This situation can occur commonly during wet seasons experienced
in Queensland.
In consideration of the above, and for the purposes of this Manual, the Method of Deciles analysis should be
applied on the basis of the conservative assumptions including 100% runoff and no evaporation during seasonal
rainfall periods. It should also be assumed that all diversion drains and bunds remain operative.
Page 19 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
Figure 1. Critical wet periods for method of deciles analysis relative to river basins.
RIVER BASINS
Page 20 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
Method of calculation
This method of estimating DSA is based on rainfall deciles. It uses records from a Bureau of Meteorology daily
rainfall station with similar meteorology and sufficient length of record, at a location sufficiently close to the site
to enable conservative estimation of wet season rainfall runoff volume reporting to a dam.
2. for any particular year, the record in that year must include the wet season for that year; and
3. be located within the same basin as the site where the dam is/is proposed to be constructed or operated. In
large river basins the rainfall station should, as a minimum, be located in the catchment of tributary rivers.
4. If no suitable daily rainfall station records exist, then Silo Data Drill for a point within the site of the
proposed dam may be used.
5. The duration of a critical wet period should be determined from Figure 1, based on the physical location of
the site relative to river basins in Queensland.
6. The annual maxima wet season rainfall for the critical wet period is to be determined by sampling from the
station or silo rainfall data. Sampling to create the critical wet period should be based on contiguous
periods for the critical wet period.
7. The maximum rainfall for the critical wet period must then be sampled for each available wet season (within
the period from November in one year to May in the following year inclusive) in the station record. A plotting
position formula is to be applied to the resulting statistical series, and a ‘best fit’ trend made to the data.
8. Rainfall depths for relevant AEPs are interpolated or extrapolated as necessary, from the statistical
analysis.
(a) 100% of the rainfall on contributing catchments is assumed to report to the dam combined with
process inputs to the dam over the critical wet period
(b) the sum of net daily process inputs are to include process water, tailings, and other water disposed of
or stored in the regulated dam, and runoff and seepage waters captured outside the contributing
catchment of the regulated dam and pumped into the regulated dam or its catchment during the wet
season
(c) net daily process inputs cannot be a negative value for the purposes of estimating process inputs in
the DSA calculation
(a) individual regulated dams corresponding to the catchment of that dam and be made available within
each individual regulated dam at the start of each wet season; or
(b) an integrated containment system distributed across a number of regulated dams corresponding to the
catchment of all dams and be made available within the system at the start of each wet season.
Page 21 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
(a) rainfall data sources; statistical analyses; and determined AEP wet season rainfall depths
(b) catchments including maps, quantified areas, and assumptions of catchment diversion works
(c) basis of process inputs into the DSA calculation including necessary procedures or operations to
ensure that process inputs do not exceed the allowance in the DSA volume estimate
(d) where relevant, assumptions, constraints, operations, and procedures relied upon to distribute DSA
allowance for an integrated containment system across a number of regulated dams.
A.2 Estimating the design storage allowance using the method of operational simulation for
performance based containment
General
This method for estimating DSA can be used at the discretion of a suitably qualified and experienced person
where there is local historical monitoring data for a sufficient period to form a basis for robust validation of
modelling methods and assumptions.
It involves:
1. Establishing a time based operational simulation model of the site’s water management system.
2. Demonstrating satisfactory model performance through comparison between metered and simulated data.
3. Provision of documentation to meet with the requirements of independent technical review and
substantiation. The completeness of documentation should be sufficient to allow independent replication of
the modelling by a suitably qualified and experienced person.
4. Quantification of simulation accuracy and selection of an appropriate design simulation margin (DSM) for
the purposes of DSA estimation.
(a) the simulated maximum increase in the stored water inventory within the regulated dam (or entire
containment system comprising several regulated dams) over the wet season subsequent to 1
November each year, as determined from plotting position analysis of operational simulation outcomes
for the selected design AEP, plus
(b) an additional volume equal to the DSM times the volume calculated in 5 (a) above.
6. Items A through to, and including, H that follow define the minimum essential requirements and
considerations for any operational simulation modelling application and related methods, that are to be
used to assess system performance in mitigating environmental hazards, including the calculation of
design storage capacity of regulated dams.
Documentation
Comprehensive documentation of the whole modelling process and results is required sufficient to enable
independent replication of the model representation and assessed performance outcomes. This should include:
Page 22 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
(b) substantiation that the modelling application is suitable for the purpose
(d) catchment maps (with topography sufficient to demonstrate drainage patterns within the system,
upstream and downstream)
(e) system configuration plans (all key infrastructure comprising the containment system, including works
intended to exclude clean waters)
(g) all assumptions and relevant associated data (or reference to data sources) to support model
parameterisation
(j) relevant mine and waste facility plans and other matters that affect model processes (i.e. source and
loss rates of waters and/or contaminants)
(o) method of interpreting model results to characterise system performance outcomes; and statement of
limitations for the purpose and where relevant limitations in the model use for alternative purposes
(p) relevant recommendations for monitoring and/or model improvement to maintain or improve validity of
the assessed system performance outcomes.
Other matters may also need to be documented where they are deemed by the relevant suitably qualified and
experienced person, certifier, or other stakeholders involved in the review of the methods or outcomes, to be of
significance for the model representation, or purpose of the assessment. The requirements of the certifier are to
take precedence.
Modelling should be mass conservative for water volumes and, where relevant, mass of contaminants.
The checking of model results and documentation should demonstrate a net balance check of water (and mass
of contaminants where applied) for:
(a) every storage or significant conveyance element (e.g. upstream and downstream watercourse
reaches); and
(b) the system as a whole across the period of the model simulations.
Page 23 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
Climate inputs to the model (rainfall and evaporation) must be representative of the historical variability and
sequences for the specific site. The period of climate data should be as long as possible to adequately
represent the extremes of climate and climate sequences that can occur at a site.
Rainfall inputs to modelling must include a sequence of at least 100 years of real data (infilled as necessary
from nearby stations) to deliver output for performance analysis and benchmarking against other model inputs.
Such a rainfall sequence can be produced from, in order of preference:
(b) ‘datadrill’ (both from silo enhanced meteorological data, published on the web); or
(c) independently created using nearby Bureau of Meteorology rainfall stations in the region—where this
can be demonstrated to be robust and consistent with conditions on the site.
Stochastically derived rainfall data may only be used for modelling of containment systems where it is
demonstrated that application of the data to continuous time-series simulation of rainfall-runoff processes
satisfactorily replicates observed runoff characteristics. For modelling of containment systems where there is
reasonable possibility of substantial carry-over water volumes from a wet season well into the next year’s wet
season, care is required to ensure that the possibility of sequential wet seasons evident in historical climate
records is properly represented by the applied climate data.
Evaporation estimates used may need to be adjusted for any local limitations due to expected water quality (e.g.
salinity, low pH), and location (e.g. water surface below surrounding land and low surface air flow) where
relevant to ensure reasonably conservative outcomes of the assessment.
The suitably qualified and experienced person must document the basis upon which it is expected that the
climate data has been used conservatively for the purpose of the assessment.
Modelling methods/assumptions of hydrological processes and water management operations should be utilised
and substantiated to a sufficient degree to ensure that the water balance model adequately represents the
system performance response to climate variability.
The use of annual averages of rainfall and evaporation in modelling storage volume outcomes is not acceptable.
An assessment of system performance risks to the environment (particularly overflows from dams and
adequacy of storage capacity), must assume that there are no seepage losses from dams and no transmission
losses from open channel systems used to transfer water. This assumption is intended to be conservative from
the perspective of containment performance but may not be conservative for other outcomes of operational
simulation modelling (such as water supply reliability).
Page 24 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
Runoff processes
The processes represented to transform rainfall onto a catchment to runoff rates/volumes must replicate the
catchment responses to a full range of climatic conditions including, but not limited to, conditions during wet
seasons.
As a minimum requirement, an established and properly calibrated 'watershed' element of the water balance
model that accounts for antecedent catchment conditions must be used.
Where outcomes going into a wet season are being assessed using a water balance model, the watershed
calibration must be demonstrated to be appropriate for wet season conditions.
For existing operations where historical operations and/or monitoring data is available, that data must be used
to calibrate and validate the models based on comparison of simulated and historical water inventory (storage
volumes) over time sequences of wet and dry climate periods (seasonal fluctuations).
Professional care and judgement must be applied to ensure the accuracy of storage curves for dams in making
these comparisons. Discrepancies between simulated and historical observed data may be acceptable
providing that the differences can be adequately explained and justification made that the model representation
maintains conservative assumptions relative to the specific purpose of the assessment.
A best estimate approach shall be applied to those situations where there is insufficient historical data for
calibration, including:
• substantiating that runoff parameters are appropriate for catchment conditions including runoff estimates for
disturbed lands
For combined water and contaminant balance models, validation needs to extend to validating the water quality
results from the model against historical water quality data. Professional care and judgement must be exercised
in the validation methods used and adequate substantiation and explanation provided on the significance of the
validation results relative to the specific purpose of the assessment.
Estimates of potential contaminant concentrations on any release must be based on a validated water balance
model together with conservative estimates of contaminant concentrations likely to be in relevant dams at the
time of any release.
A properly constructed and calibrated operational simulation water balance model will provide a best estimate
time series site water balance, without undue imposed bias.
However, the application of simulation outcomes to containment system design and operation requires the
addition of appropriate margins to conservatively compensate for observed deficiencies in simulation accuracy
or lack of calibration data.
Page 25 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
For the purposes of this Manual, model accuracy may be defined with respect to the Seasonal Simulation
Margin (SSM), which is to be derived when adequate calibration data is available. SSM is calculated as the
numerical difference between recorded and simulated storage inventory maxima for each water year of
simulation, expressed as a percentage of the simulated storage inventory maxima, for the particular storage
under consideration. SSM is a positive value when recorded inventory volumes are greater than simulated
containment system inventory volumes and set to zero otherwise. SSM can never be a negative value. A
design simulation margin (DSM) is to be applied to simulation outcomes to provide conservative compensation
for model inaccuracy.
where: i ranges from 1 to number of annual SSM values, and V i is the associated simulation volume,
When there is inadequate data for model calibration a minimum DSM value of not less than 50% shall be
applied
The required conservative margin is then calculated by multiplying the volume of interest by the DSM.
Page 26 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
The degree of immunity to regional and local flooding, the upstream and downstream effects of the dam on such
flood events, and potential erosion of the dam or the general environment; must be addressed in the
consequence assessment, design, operation and decommissioning of dams.
‘Failure to contain’ consequences are those potential dam failures that are typically non-flood producing, but the
release of contaminants could endanger environmental values including human life. Examples of events
include:
• releases due to pipe bursts in tailings or process water circuits associated with the dam;
• inundation by floodwaters;
• erosion of containment structures around mining waste (decommissioned tailings dams, waste heaps etc);
and
Evaluation of the consequence potential on release requires information on the probable chemical nature of the
stored material, including rates, volume and concentrations at the time of a possible release. Acidity and metal
ions in solutions due to prolonged contact with ore bodies or stored material must be considered.
Contaminant concentrations at discharge must be estimated based on the contaminant concentration in the
dam, and design parameters such as available storage volume. Operational water balance models may also be
used to estimate likely instances of volumes and concentrations at discharge.
Conservative assumptions should be made to estimate outcomes of the worst case contaminant release or
collapse of the structure. Assessments must always consider the potential interaction of failure of one dam with
any other dams on site.
Assessment of progress of wetting fronts through dams with liners must be informed by proper materials testing
(note: in-situ testing is not required as part of this assessment), knowledge of the design sizing and likely driving
head during operation, the underlying hydrogeological conditions, and the potential impacts on underlying land
and groundwater.
Page 27 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
The prerequisites for a dam break consequence are the existence, either permanently or temporarily, of a large
body of water or other flowable substances (slimes, tailings, etc); and environmental values, including stock,
human life or property, that are susceptible to harm should a dam break occur.
While not required for the purposes of this Manual, good design and consequence assessment is likely to
require that employees and persons associated with the operations for which the holder of an authority is
responsible that are likely to be located in the failure path are considered. The requirement to appropriately
consider site personnel safety is not removed by adherence to the requirements of this Manual.
The estimated extent of the flood at a particular probability level is called the ‘failure impact zone’. The potential
for losses to humans and stock must be considered. A high consequence for humans on a flood plain or
elsewhere is associated with water depths occurring in excess of 300 millimetres (0.3 metre).
If the ‘failure impact zone’ is contaminated by the dam break flood, the environmental harm and potential for
consequent harm from contaminants including access by stock or humans to the contaminants, must also be
fully considered. Clean up in the general environment can involve substantial costs that would fall within the
meaning of ‘environmental harm’ in the Act.
Applications that involve the construction and operation of any containment structure, must include relevant
information on which an initial consequence assessment by the applicant has been undertaken.
Dam owners are likely to have much of the information already available. The minimum information is:
• maps showing the location of the proposed project in relation to surrounding land use and watercourses—
including the general topography and contours at a suitable scale
• details of environmentally sensitive areas, rare and endangered species and human habitation and
infrastructure developments in the near vicinity or general area and particularly downstream
• details of watercourses and groundwater aquifers that are or might be used as water resources
• engineering sketch drawings, in accordance with good professional practice and sufficient to fully define the
layout, structure, volume and proposed means of construction of all aspects of operations associated with
the proposal
• details of quantities and concentrations of all raw materials, products, by-products and waste products
produced in operations associated with the proposal; and
• details of all studies conducted to assess requirements for storage and strength of all structures associated
with the project—such as hydrological and geotechnical data.
Whether or not a site inspection is required for a particular dam as part of a consequence assessment is a
matter for consideration by the suitably qualified and experienced person concerned. However, that person
must be satisfied that all relevant aspects have been otherwise researched and documented to enable a reliable
consequence assessment in each case.
Page 28 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
Any assessment must include areas in the potential failure path or downstream of the dam that could be
impacted by collapse or failure of the dam. Relevant matters include (but are not limited to):
• infrastructure including human habitation, worker accommodation and site offices, road crossings
• recreation facilities (parks and known local camping spots, etc) along watercourses
• presence of stock, irrigation and domestic water supply pumps, and water holes
• mine adits (entrances to underground mining) and/or open cuts (voids)—current or proposed
A consequence category based on ‘dam break’ or ‘failure to contain’ scenarios, must be assessed based on the
most adverse environmental harm that can arise from the range of all possible scenarios. The consequence
category is based on the consequences of failure, not on the perceived probability of the failure occurring.
• A suitable range of rainfall scenarios will need to be considered in order to cover all potential harm and the
required performance contained in tables 5 and 6.
• Where potential harm is by release of a contaminant, account should be taken of the potential dilution by
clean runoff entering the dam prior to release and potential dilution in receiving waters.
• For an earth dam or bund wall, a ‘sunny day’ failure can also occur due to loss of structural integrity of the
wall, such as piping failure or weakness in zones of the wall (various causes).
Of course, the probability of piping and similar mechanisms occurring are reduced by good design and
construction practices, and regular inspections by informed operators and qualified professionals. The purpose
of a consequence assessment is to identify dams that require more care and attention in that regard.
Page 29 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
(a) the certification must be stated in the terms required by any condition that is referenced;
(b) for consequence assessment report: provides an assessment of the consequence category of the
dam/structure/facility in accordance with the Manual published by the administering authority;
i. the design has been prepared in accordance with good engineering practice and the design/dam is
also consistent with the standards required for structures of the assessed consequence category as
set out in the Manual published by the administering authority
ii. provided the structure is constructed or modified (in consultation with the designer) in the manner
specified and the facility is operated and maintained as recommended, the dam/structure/facility is
capable of delivering the performance stated in the attached report so as to be compliant with
relevant conditions of the environmental authority.
(d) for ‘as constructed’ drawings: the documentation has been prepared based upon appropriate
methodology and assumptions, inspections at specified hold points and the attached report addresses
relevant aspects;
(e) for construction report: the structure has been constructed in accordance with the design drawings
and specifications (or as modified in consultation with the designer); as constructed drawings;
construction control test results and other relevant data; or
(f) for annual inspection report: identify details of inspection of the current condition of the facility;
assessment of the hydraulic capacity of the facility; assessment of the physical condition and
performance with respect to design intent; whether operation has been undertaken in accordance with
the operational plan. The certification report should also reference the operational plan on which a
regulated structure performance relies, together with information about the extent to which the
regulated structure has been operated in accordance with the operation plan over the last year. The
certification report should include any potential implications of non conformance with the operation
plan.
Note: minor variation may be made to the wording of the form where it is necessary to ensure that the
information provided is accurate and complete, for example, where it is necessary for a suitably qualified and
experienced person to rely on subsidiary certifications from someone in the same area of specialisation.
Page 30 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
____________________________________________________________________________________
____________________________________________________________________________________
I hereby state that I am a Registered Professional Engineer of Queensland and meet the requirements of the
definition of ‘suitably qualified and experienced person’.
Statement of certification
All relevant material relied upon by me, including subsidiary certifications of specialist components, where
required by the environmental authority, is provided in the attached report(s) <report name/ref> dated <date>.
Refer to the Manual for guidance on the nature of the certification statements that should be included here.
Note: the following is a guide to the minimum information required. Further information may be necessary as
part of the certification to comply with all conditions of the environmental authority.
• <identify, where appropriate, what is not included in the certification—including information about any
limitations, restrictions or exclusions that apply to the certification>
Page 31 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
• <identify if the certification was under supervision, the extent of the supervision>.
I <full name of person making the declaration>, declare that the information provided as part of this certification
is true to the best of my knowledge. I acknowledge that it is an offence under section 480 of the Environmental
Protection Act 1994 to give the administering authority a document containing information that I know is false,
misleading or incomplete in a material particular.
Signed: ____________________________________
Date: _______________________________________
Page 32 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
_________________________________________________________________________________
_________________________________________________________________________________
I hereby state that I am a Registered Professional Engineer of Queensland and meet the requirements of the
definition of ‘suitably qualified and experienced person’.
Statement of certification
All relevant material relied upon by me, including subsidiary certifications of specialist components, where
required by the environmental authority, is provided in the attached report(s) <report name/ref>dated <date>.
I hereby certify that the <annual inspection report> entitled <report name/ref>and dated <date> for the <name of
dam/structure/facility>:
2. Identifies the relevant environmental authority condition which is the subject of the certification;
5. Provides an assessment of the physical condition and performance with respect to design intent;
6. Identifies whether operation has been undertaken in accordance with the operational plan;
23This certification for the annual inspection report sets out the minimum requirements. It has been provided as
a guide but its use is not mandated. Other forms of certification will be accepted for the annual inspection report
as long as they contain the minimum requirements outlined in manual and guideline.
Page 33 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science
Manual
Manual for assessing consequence categories and hydraulic performance of
structures
7. References the operational plan on which a regulated structure performance relies, together with
information about the extent to which the regulated structure has been operated in accordance with the
operational plan over the last year;
9. Identifies, where appropriate, what is not included in the certification—including information about any
limitations, restrictions or exclusions that apply to the certification;
11. Identifies if the certification was under supervision, the extent of the supervision;
12. <Include further statements as necessary to comply with all conditions of the environmental authority
and the Manual for Assessing Consequence Categories and Hydraulic Performance of Structures
ESR/2016/1933>.
I <full name of person making the declaration>, declare that the information provided as part of this certification
is true to the best of my knowledge. I acknowledge that it is an offence under section 480 of the Environmental
Protection Act 1994 to give the administering authority a document containing information that I know is false,
misleading or incomplete in a material particular.
Signed: ____________________________________
Date: _______________________________________
Page 34 of 34 • ESR/2016/1933 • Version 5.02 • Effective: 29 MAR 16 Department of Environment and Science