Thrust Boring 05 - Details

The document details 17 thrust boring projects including location, length, status, and notes. It provides key information on the thrust boring ID, approved plans, boring length, jack pipe details, work status, and remarks for each project.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
84 views1 page

Thrust Boring 05 - Details

The document details 17 thrust boring projects including location, length, status, and notes. It provides key information on the thrust boring ID, approved plans, boring length, jack pipe details, work status, and remarks for each project.

Uploaded by

Dilip Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Thrust Boring Detail DI 800 Dia (1200mm RC Jacking Pipe) B: APPROVED WITH COMMENT

Thrust Profile Drawing


WORK STATUS TB No.
S. Approved Plan & Profile Boring Chanaige Length RC Jacking RC Jacking DWG
Length for Ref. Remarks
NO Drg No. Approved (m) Pipe Start Pipe End Status Open
From To RC Pipe Grouting only
DWG No. cut

1 1 1 0+274.00 0+281.00 7.00 0+272.400 0+284.900 12.50 B TB-01 Balance

2 1 2 2+788.00 2+798.00 10.00 2+781.720 2+801.740 20.02 B done done TB-02 Near Omanoil

3 1 3 2+863.00 2+876.00 13.00 2+846.870 2+876.830 29.96 B done done TB-03


4 1 4 3+045.00 3+056.00 11.00 3+038.710 3+064.530 25.82 B done done TB-04
5 1 5 3+522.00 3+533.00 11.00 3+518.930 3+536.430 17.50 B done done TB-05
6 1 6 4+944.00 4+955.00 11.00 4+943.680 4+956.180 12.50 B done done TB-06
7 1 7 5+300.00 5+317.00 17.00 5+295.300 5+320.300 25.00 B TB-07 Balance
10m 10 m done & Cancelled
extra (Balance)
8 1 8 5+160.00 5+173.00 13.00 5+169.330 5+191.830 32.50 B TB-08
added
RCJ pipe
9 1 9 7+865.00 7+879.00 14.00 7+861.000 7+878.500 17.50 B TB-09 Balance
RC jacking completed
10 1 10 9+617.00 9+654.00 37.00 9+616.200 9+653.200 …........ B done TB-11 pipe laying balance

11 1 11 6+130.00 6+136.00 6.00 6+068.100 6+083.100 12.50 B TB-12 Balance

12 1 12 11+185.00 11+219.00 34.00 11+202.000 11+242.000 40.00 B TB-13 Balance

13 1 13 10+112.00 10+127.00 15.00 10+085.000 10+105.000 20.00 B TB-14 Balance

14 1 14 10+186.00 10+198.00 12.00 10+188.000 10+213.000 25.00 B TB-15 Balance

15 1 15 14+711.00 14+725.00 14.00 14+712.260 14+732.380 21.00 B done TB-18 Pipe laid
Approved drawing
16 1 16 19+172.00 19+188.00 16.00 21.00 Approx Length
not Received yet
Approved drawing
17 1 17 10+072.00 10+080.00 8.00 12.70 Approx Length
not Received yet
Approved drawing
18 1 18 10+625.00 10+673.00 48.00 48.00 Approx Length
not Received yet
19 Total 297.00 Total 393.50
Opencut 20
1 PAW-093 2018-JV-SD-PP-AL05-418 21 9+366.00 9+382.00 16.00 9+361.000 9+383.500 22.5 B TB-10 Opencut done