Daily Progress of Parnai HEP by PMC 07.10.2022

The daily progress report summarizes work at the Parnai HEP project site on 07.10.2022. Sixteen laborers worked on shuttering and reinforcement of the fish pass walls. Drilling, blasting, and mucking were completed at faces 4, 5, and 6 of HRT and Adit 1. Concreting was also done in various sections of the project. A total of approximately 150 laborers were deployed across activities like excavation, concreting, drilling and mucking.

Uploaded by

mohit sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views1 page

Daily Progress of Parnai HEP by PMC 07.10.2022

The daily progress report summarizes work at the Parnai HEP project site on 07.10.2022. Sixteen laborers worked on shuttering and reinforcement of the fish pass walls. Drilling, blasting, and mucking were completed at faces 4, 5, and 6 of HRT and Adit 1. Concreting was also done in various sections of the project. A total of approximately 150 laborers were deployed across activities like excavation, concreting, drilling and mucking.

Uploaded by

mohit sharma
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Daily Progress of Parnai HEP by PMC

S No. Detail description of activities at project site on 07.10.2022 No. of Labours deployed
1. Barrage:-
a) Shuttering of Breast wall and reinforcement placing in fish pass 16 (Day shift)
wall 1 & 2 in progress. No work in night.
b) Concreting of fish pass wall -02 shall be done today.

2. HRT & Adit 1.


a) HRT Face 1:-
a) No activity in face -01 other than dewatering. 04 (02 for Day shift + 02
for night shift)
b) Face 4:-
a) Face drilling, loading , blasting and mucking completed at 777.8 m 08
from C/L of Adit -02
b) Blast taken and mucking in progress.
c) Face RD 779.5 m from C/L of Adit -02 .
c) Face 5:-
a) Drilling, loading , blast and mucking completed at 797.5 m from (Day Shift 09 +
C/L of Adit -02 Night Shift 08) = 17

d) Face 6:- (Day Shift 08 +


a) 7.5 Cum Backfill concreting done between 1691.6 to 1698.1 Night Shift 08)= 16
from outer face.
b) Loosefall muck removal in progress between 1698.1 to 1704
m from outer face.
e) Adit 1:-
a) Backfill concrete 12 cum completed at RD 232.2 m. (Day Shift 09 +
b) Face drilling and loading completed and blast taken at 234.1 m Night Shift 09) = 18
3. Penstock:-
a) Earthwork excavation in progress between AB 13 to AB 14. 02
4. Power House :-
a) 02 cum stone filling and concreting 0.375 cum for two vertical 15
bands completed.

Note:- The Contractor has submitted the target for the month of Oct 2022.