0% found this document useful (0 votes)
347 views

Abstract of CPWD-Part 1 - Electrical Notes & Articles

This document provides guidelines for electrical wiring based on CPWD Part 1 standards. It outlines requirements for lighting circuits, power circuits, plug sockets, minimum wire sizes, outlet heights, distribution board clearances, conduit types and sizes, junction boxes, fish wires, earthing, conductor clearances for roads, buildings and railways, and cable trench specifications. Requirements include maximum points per lighting circuit, minimum conductor sizes, clearance distances, conduit thickness and accessories to be used.

Uploaded by

hemant kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
347 views

Abstract of CPWD-Part 1 - Electrical Notes & Articles

This document provides guidelines for electrical wiring based on CPWD Part 1 standards. It outlines requirements for lighting circuits, power circuits, plug sockets, minimum wire sizes, outlet heights, distribution board clearances, conduit types and sizes, junction boxes, fish wires, earthing, conductor clearances for roads, buildings and railways, and cable trench specifications. Requirements include maximum points per lighting circuit, minimum conductor sizes, clearance distances, conduit thickness and accessories to be used.

Uploaded by

hemant kumar
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 18

Electrical Notes & Articles

Sharing Abstracts,Notes on various Electrical Engineering Topics.

Abstract of CPWD-Part 1

Abstract of CPWD Internal Electrification Part-1

Lighting Circuit

Per Circuit Not more than 10 Points of Lighting or Total 800Wa which is less

Power Circuit

For Residential Per Circuit Less than 2 No of 5A/15A Plug Socket


For Non Residential Per Circuit Less than 1 No of 5A/15A Plug Socket

Plug Socket

In Residential wiring ,wiring of Socket outlet shall be done by copper Cable only

Min Size of Wire

For Lighting Circuit Smallest size of conductor shall be 1.5 Sq.mm


For Power Circuit Smallest size of conductor shall be 4 Sq.mm

Plug Socket
5A/6A or 15A/16A Socket shall be installed at following heights:
For Non Residential building 23cm above Floor,
For Kitchen 23cm above
Platform,
For Bathroom not Socket is provided in bathroom MCB/IC will be 2.1 meter from fixed appliance and
at least 1 meter away from Shower.

Operating Rod

Operating Rod/Handle of Distribution Board at the height of min 2meter

D.B Clearance

Clear Distance in front of Switch Board/D.B shall be min 1 meter.


If there may be bare connection at back of Switch Board than space behind S/W shall be either less
than 20cm or more than 75cm.
No fuse Body shall be mounted within 2.5 com edge of D.B or Panel
Clearance between 2.5 cm is maintained between opposite polarity.

Switch Box

Switch Box or Regular Box shall be mounted normally 1.25 meter from floor level.

Fan Hook

For Fan Hook in concrete roof 12mm diameter MS Rod in ‘U’ Shape, horizontally Leg at Top at least
19 cm on either side.
Connection between adjustment Building (Out House, Garages) (Safety Clearance)
If the distance with adjustment building is less than 3 meter and there is no any Road interval than
GI pipe of suitable size shall be installed. This pipe shall be exposed on wall at height of not less than
2.5 meter.
If the distance with adjustment building is more than 3 meter and there is any Road interval than GI
pipe of suitable size shall be installed. This pipe shall be exposed on wall at height of not less than 4
meter.
Metallic Conduit

Shall be used for Industrial wiring, Heavy mechanical Stress, shall be ISI marked, The Thickness shall
not be less than 1.6mm(16SWG) for conduits up to 32mm Diameter and not less than 2mm (14SWG)
for conduit above 32mm Dia.
No steel conduit less than 20 mm Diameter shall be used.
For rigid Conduit IS:2509 /IS:3419 and For Flexible Conduit IS:6946.
All Metallic conduit accessories shall be threaded type (Not pin grip, clamp grip)
Saddle for surface conduit work on wall shall not less than 0.55mm(24 gauge) for conduit up to
25mm Diameter not less than 0.9mm (20 gauge) for larger Diameter

Metallic Outlets

Fore Cast Boxes: Wall thickness shall be at least 3mm.


For Welded mild Steel Box: Wall thickness shall not be less than 1.2mm (18 gauge) for Boxes up to
size 20cmX30cm. Above This size 1.6mm (16guage)thick MS Boxes shall be used.
Clear depth of Out less Box shall not be less than 60mm.This will be increased as per mounting of
Fan regulator

Bends in Conduits

Bending radius not less than 7.5 cm

Fixating Conduits on Surface

Conduits shall be fixed by saddles not less than 1meter interval but in case of coupler/Bends in either
side of saddles, The saddle shall be fi ed 30 cm from fi ing.

Junction Box

Depth of Junction Box shall be min 65mm as per IS:2667.


Fish Wire

GI fish wire of 1.6mm/1.2mm(16SWG) shall be used

Non Metallic Conduit Accessories

Normally grip Type.


PVC Box IS:5133 (PartII) thickness not less than 2mm,Clear depth of PVC Boxes not less than 60mm.

Non Metallic Surface Conduit

Conduits shall be fixed by saddles not less than 60cm interval but in case of coupler/Bends in either
side of saddles, The saddle shall be fi ed 15 cm from fi ing.

Busbar

Bulbar shall be 100A,200A,300A,400A,500A,600A,800A


The Cross-section area of Bus bar shall be same as Phase Bus bar (Up to 200A) for higher Capacity
Neutral Bus bar must be not less than half cross section areas of Phase Bus bar.
Bus bar shall be suitably installed with PVC sleeve/Tap.
Bus bar Chamber shall be fabricated with MS angle for Frame work and sheet steel of thickness not
less than 1.5mm.
Minimum clearance between phases to earth shall be 26mm and phase to phase shall be 32mm.

Bus bar Trucking

Bus bar Trucking are generally used for interconnection between T/C over 500KVA/D.G set over
500KVA and their switch Board Panel.
Bus bar Trucking enclosure sheet steel of min 2mm thickness

Earthing
Type of earthling are Pipe earthling/Plate earthling/Strip earthling
Length of Buried strip shall not be less than 15meter.
Two copper strip, each size 50mmX5mm shall be provided as each bus bar in 11KV S/S or D.G
generally.
Each strip should be connected separately to earth.
Two no of Body earthling of T/C, Panel, D.G are connected to earth Bus.
Neutral Leads of T/C, D.G shall not be connected to earth Bus.
The minimum Cross-section are of protective conductor(Not contained within cable or wire) 2mm
Dia(14SWG) for Copper, 2.5mm Dia (12SWG) for G.I, 2.24mm Dia (13SWG).

Earthing Pit shall not be closer than 1.5meter from Building.

Top of Pipe earthling electrode shall not be less than 20cm below the ground level.
Plate electrode shall be buried in ground with face vertical and it’s Top not less than 3meter below
ground level.
The strip of earthling electrode shall be buried in trench not less than 0.5m deep.
If strip electrode cannot be laid in straight length. It may be Zigzag with deviation up to 45 Degree
from axis of strip.
In Plate Earthing Diagram of water pipe shall not be less than 20mm and in Pipe earthling reducer of
40mmX20mm shall be used.
Earthing Pit Size shall be not less than 30cmX30cmX30cm.
Thickness of MS cover of earthling pit shall be not less than 6mm and having locking arrangements.
Earthing resistance of each electrode shall be less than 5Ω and for Rocky Soil not less than 8Ω
Earthing conduit for earthling wire shall be Medium class 15mm Diagram GI pipe and for Earthing
Strip shall be medium class 40mm Diagram GI Pipe.

Conductor Clearance (min) (Different Voltage)

When two conductor of different Voltage are erected on same support min clearance between LV/MV
and 11KV shall be min 1meter.

Conductor Clearance (min) (Different Support)

A Clearance not less than height of tallest support may be maintained between parallel overhead line
on Different support.
When two overhead line cross each other vertical clearance between LV/MV and 11KV shall not be
less than 1.25meter and for LV/MV and 33KV line shall be not less than 2meter.
Conductor Clearance (min) (Across Road)

Min Conductor Clearance across Road: For LV/MV Line is 5.8 meter and for HV Line 6.1meter

Conductor Clearance (min) ( Along Road)

Min Conductor Clearance along Road: For LV/MV Line is 5.5meter and for HV Line 5.8meter

Conductor Clearance (min) (Along/Across)

Min Conductor Clearance along/across Road: For LV/MV/HV up to 11Kv (Bare Conductor) Line is
4.6meter.
Min Conductor Clearance along/across Road: For LV/MV/HV up to 11Kv (Insulated Conductor) Line
is 4.0meter.
Min Conductor Clearance along/across Road: For HV (11Kv to 33Kv) Line is
5.2meter.
Min Conductor Clearance along/across Road: For EHV (above 33Kv) is 5.2meter + 0.3 meter for every
33KV (Not less than 6.1).

Conductor Clearance (min) (From Building)

Min Conductor Vertical Clearance above Building: For LV/MV Line is 2.5meter from highest
Point.
Min Conductor Horizontal Clearance near Building: For LV/MV Line is 1.5meter from nearest
Point.
Min Conductor Vertical Clearance above Building: For MV/EHV (up to 33KV) Line is 3.7meter from
highest Point.
Min Conductor Vertical Clearance above Building: For MV/EHV (above 33KV) Line is 3.7meter +
0.3meter for every 33KV

Min Conductor Horizontal Clearance above Building: For MV/EHV (Up to 11KV) Line is
1.2meter.
Min Conductor Horizontal Clearance above Building: For EHV (Up to 33KV) Line is
02meter.
Min Conductor Horizontal Clearance above Building: For EHV(above 33KV) Line is 2meter +
0.3meter for every 33KV
Conductor Clearance (min) (Cable crossing):

The horizontal and vertical distance between Power and Communication cable shall not be less than
60cm.

Conductor Clearance (min) (Railway crossing):

After taking approval of railway authority, Cable under railway track shall be min 1meter from
bo om of sleeper under RCC or cast Iron Pipe.
Cable in parallel to Railway track shall be min 3meter far away from center of nearest Track.

Cable trench

For single cable: For below 11Kv.Min length of Trench shall be 35cm and depth shall be min 75cm (
with sand cushioning of 8cm at bo om +Cable+ protective covering/Sand cushioning of 17cm above
Cable) and without Cushioning Depth shall be 75cm+25cm.
For single cable: For above 11Kv.Min length of Trench shall be 35cm and depth shall be min 1.2meter
( with sand cushioning and protective covering).
For multi cable in horizontal level: Min distance between two cable shall be 20cm and min distance
between cable and edge of trench on both side shall be 15cm
For multi cable in Vertical level: Min distance between two cable shall be 30cm.(min Sand cushioning
at bo om of trench shall be 8cm +Cable+ min Sand cushioning of 30cm+Cable+protective
covering/Sand cushioning of 17cm above Cable)
For LV/MV cable cushioning is not required where there is no possibility of mechanical damages.
Extra loop of cable at end shall be 3meter for cable termination/Joints.

Cable Route Marker

Cable Route Marker shall be min 0.5meter away from cable trench at the interval not exceeding
100meter parallel.
Plate Type Cable Route Marker shall be made of 100mmX5mm GI/Aluminum Plate welded/Bolted
on 35mmX35mmX6mm Iron angle of 60cm Long.
Cement Concrete (C.C) type marker shall be made in formation of 1:2:4.

Cable Bending Radius


1 Core Unarmored(Multi Armored(Multi
Voltage core) core)
11KV 20D 15D 12D
22KV 20D 20D 15D
33KV 20D 25D 20D

Cable Lying in Pipe

For Single Conductor Shall be min 10cm Diameter and more than Two Cable shall be min 15cm Dia.

Cable in Road Crossing

In Road Crossing Cable shall be laid min 1 meter below Road in Pipe.

Cable Tray (Perforated)

Cable Tray may be fabricated by two angle irons of 50mmX50mmX6mm as two longitudinal
members with cross bracing between them 50mmX5mm welded/Bolted at angle and 1 meter spacing
of 2mm thick MS sheet.

Steel Tubular Pole

1/6 length of Steel Tubular Pole + 30 cm from base shall be coated with Black Bituminous paint on
both internally and externally. The remaining portion of the pole shall be painted with Red oxide.

Cross arm

LV/MV Line: MS angle iron of size not less than 50mmX50mmX6mm


(4.5kg/meter)
11KV Line: MS angle iron of size not less than 65mmX65mmX6mm (5kg/meter)
LV/MV Line: MS Chanel iron of size not less than
75mmX40mmX4.8mm(7.14kg/meter)
11KV Line: MS Chanel iron of size not less than 75mmX40mmX4.8mm(7.14kg/meter)
For LV/MV Line: Min distance shall be 5cm between center of insulation pin and end of cross
arm.
For 11KV Line: Min distance shall be 10cm between center of insulation pin and end of cross arm.

Cross arm Length

Voltage Nom of Length of Cross


Horizontal Con Arm

LV/MV 2 Conductors 55cm

LV/MV 4 Conductors 115cm

LV/MV 4 Conductors 175cm

11KV 3 Conductors 225cm

Insulators:

For LV/MV Overhead Line: Pin/Shackle Insulator and For 11KV Line Pin/Disc Insulator
For Pin Insulator for LV/MV line: Stalk Length 135mm Shank Length 125 mm, min Load
2KN.
For Pin Insulator for 11KV line: Stalk Length 165mm Shank Length 150 mm, min Load 2KN.

D Clamp

D clamp shall be made of MS Flat size of 50mmX6mm,height of 75mm Galvanized and only used for
vertical configuration for LV/MV Line only.

Pole Top Clamp

Pole Top clamp made from Flat iron 50mmX8mm.


Stay wire Rod

Stay wire Rod shall not be less than 1.8 m Long and 19mm Dia. Anchor Plate shall not be less than
45mmX45mmX7.5mm.

Overhead Conductor (min)

For LV/MV Line: AAC(All Alu. Conductor) 7/1/2.21mm, ACSR 6/1/1/2.11mm, AAAC (All Alu. Alloy
Conductor) 7/2.09mm(20Sqmm)
For 11KV/33KV Line : AAC(All Alu. Conductor) N/A, ACSR 6/1/1/2.11mm, AAAC (All Alu. Alloy
Conductor) 7/2.56mm(30Sqmm)

Binding Wire

Binding Wire with insulator shall be done with 2.6mm(12SWG) soft aluminum wire.

Earthing in Overhead Line

Earthing wire shall not be less than 4mm(8SWG) and min 3 earthling Pit per KM shall be required.
If there is no Continuous wire for earthling in overhead line than each pole should be earthed.

Same Support

For LV/MV Line on Same Support Vertical distance: Between Phase to Earth shall be min 30cm and
Between Phase to Phase min 20cm
For LV/MV Line on Same Support Horizontal distance: Between Live wire on either side of support
shall be 45cm.
For LV/MV Line on Same Support Horizontal distance: Between Live wire on same side of support
shall be 30cm.
For LV/MV Line on Same Support Horizontal distance: Between central of pin insulator to end of
cross Arm shall be 05cm.
For HV Line in Triangular Configuration for 11KV/33KV Line shall be min 1.5meter.
Overhead Line Struts

The Pit for Struts shall be located not less than 1.8meter from pole side. The depth of Pit shall be at
least 1.2meter

Danger board

All Support carrying HV Line shall be fi ed with Danger Board( IS:2551-1982) at height of 3meter.

Anti Climbing Device

For HV Line (IS:278-1978) having 4Point Barbs 75mm+12mm apart weight 128/125 gm/meter shall be
wrapped helically with pitch of 75mm around Limb of Pole height of 3.5meter to 5 to 6 meter.

Looping Box

Looping Bus shall be fabricated from MS Sheet of 1.6mm(16SWG) thickness, Min Size
250mmX200mmX100mm for single cable entry and for 250mmX300mmX100mm for more than two
cable entry

Feeder Pillar

Feeder Pillar shall be fabricated min 2mm thick MS sheet and hinged type double door at front side.
If width of Pillar shall be less than 60cm than single hinged type door shall be permi ed.
Min height of Pedestal of Feeder Pillar shall be not less than 45cm and 1 to 2 meter height from Road
Level.
Each Feeder Pillar shall be earthed with 2 no of Earthing electrode

Substation

Clear Height of S/S Building shall be min 3.6meter.


Area of Sub station

Sub Total Transformer Room Total S/S Area


Station Area (Transformer, HT/LT Panel
without D.G)
2X500KVA 36 Sq 130 Sq
meter meter
3X500KVA 54 Sq 172 Sq
meter meter
2X800KVA 39 Sq 135 Sq
meter meter
3X800KVA 58 Sq meter 181 Sq
meter
2X1000KVA 39 Sq 149 Sq
meter meter
2X1000KVA 58 Sq 197 Sq
meter meter

35 Responses to Abstract of CPWD-Part 1

Gabriel says:
September 6, 2011 at 3:10 pm
I so much enjoy your notes on clearance. Pls can you send more important notes on electrical that can
help me in this profection.

Reply
CHANDRASHEKHAR M says:
July 11, 2012 at 8:58 am
VERY USEFUL INFORMATION , GOOD EFFORTS

Reply
jaspal singh says:
December 2, 2011 at 2:47 pm
how many light/fan/caall bell etc. for type 4 residentlal flats & what will be santioned load

Reply
Nihar Raj says:
December 25, 2011 at 5:28 pm
Dear Jignesh
Keep up the good work. Best wishes

Reply
Arun Sahoo says:
May 26, 2012 at 6:18 pm
Excellant Work Mr Jignesh. I am a Sr Design Engr at ABB and my wife is in CSEB. We both liked ur
blog. It is very helpful

Reply
meraj says:
July 6, 2012 at 4:17 pm
excellent notes, can u provide some more information about lux level calc and electrical designing

Reply
Vishwa Murthy.Vagga says:
July 14, 2012 at 6:32 am
Sir, I am working for a pvt organisation in T&D division, will you please explain us regarding how to
calculate the current carrying capacity of AAAC and ACSR conductors.

Reply
Jignesh.Parmar says:
July 14, 2012 at 2:18 pm
R u Talking about Selection of Overhead conductor for Distribution Line ??? For that You have to
Calculate Voltage Regulation of Line. Excel Sheet for that is already given in This Blog.
If you talk about Current Capacity of Overhead line than It is normally given on Catalog of It’s
Manufacture.

Reply
Jitendra Mahida says:
August 10, 2012 at 6:29 am
very very good information for electrical engineer , I am salute to your effort for knowledge share &
ready material

Reply
THIRUGNANAM.P says:
August 28, 2012 at 6:05 pm
Dear Mr.JIGNESH.PARMAR,

I am veryuseful for your guide line in electrical clerence and all other guide line books,to much
thaks.this is useful for our new genarations.
warm regards,
P.Thirugnanam,
site manager,
siemens nairobi-kena,
mb.no.706099746

Reply
Syed mansoor says:
October 17, 2012 at 6:16 am
Dear Sir

Please upload General specification of electrical works (External)- part2, i m not able to find that book
any where, so please upload it, i will be very thankful to you.

Reply
Chandrashekhar Mandwekar says:
October 29, 2012 at 11:27 am
very important information

Reply
Abil says:
February 9, 2013 at 11:39 am
Sir am working as an electrical consultant so can you refer me some books that can increase my
design knowledge…..Thank you for this blog as this is really informative

Reply
M Suresh says:
March 7, 2013 at 11:47 am
how to improve the voltage (overcome voltage drop) over the long distamce laid (>1KM) LT power
XLPE cable?? Can we do it by providing capacitor bank or any other alternative method??

Reply
Jignesh.Parmar says:
March 7, 2013 at 2:11 pm
You can improve VD by installing Capacitor at trail end up to certain limit only.
For decreasing VD you have to upgrade your Cable size or decrease distance only.

Reply
Er. S K Pal says:
October 4, 2013 at 5:42 am
Please check the size of cable. For 2.85KM cable size required 240 Sqmm even for 10 Amp load
giving 8 volt drop
.

Reply
ANIL DESHAPANDE says:
March 26, 2013 at 11:12 am
The information is very useful. Congrats for the efforts.

Reply
Bhavinkumar chovatiya says:
June 4, 2013 at 4:54 am
superb .

Reply
Bhavinkumar chovatiya says:
June 4, 2013 at 4:58 am
sir, i wanting to know about substion desing so i need distance between equipment to equipment
distance of s/s like isolator to ct …plz givw me ans

Reply
Muruganantham says:
September 19, 2013 at 12:33 pm
Dear sir this is very useful for me .Please tell me the above details from Which standard please reply
me sir.

Reply
Jignesh.Parmar says:
September 19, 2013 at 5:30 pm
It is already standard “Central public works department”-CPWD,India

Reply
soumya k says:
September 28, 2013 at 3:51 pm
dear sir, i want to know about concreting details for erection of pcc pole 9m long,STP 11 MT,stay
purpose.

Reply
S.Kundu says:
November 14, 2013 at 10:19 am
Dear Mr Jignesh Parmer,
I have seen this site which is very helpful to me to ge ing more knowledge and information
regarding equipments, calculation and some standard. You are requested to please share some
testing knowledge about relay testing, transformer testing procedure, and electronics related issue
like drive , soft starter and there commissioning procedure.

Regards,
Suman Kundu,

Reply
B.Venkat Reddy says:
March 4, 2014 at 8:26 am
Dear Sir,

Many Thanks for your Efforts for shearing Engineering Knowledge, Its really very Important for
every Electrical Engineer.

Be Well,

B.Venkat Reddy.

Reply
Gunjan baghel says:
March 14, 2014 at 8:00 am
Very useful information good efforts all the best.

Reply
Anand says:
June 26, 2014 at 12:01 pm
can you pl. tell me if there is any rule to consider ELCB for industrial sockets in kitchen.

Reply
ASR REDDY says:
September 18, 2014 at 9:56 am
Electrical Articles & Notes

By JIGNESH.N.PARMAR ,this is available in book form in India.

We need about transmission line survey and calculations

Reply
fawad says:
January 26, 2015 at 10:53 am
respected sir, it is very useful information for electrical engrs, sir, i appreciate your work.
thanks.

Reply
Ashutosh Verma says:
February 17, 2015 at 10:00 am
Dear Jignesh,

do you or any one have the swithgear sizing calculation I.e. including selection of MCCB, fuses etc.

ill be very thankful

Reply
jangchu singye says:
August 26, 2015 at 5:05 pm
Sir,
I have seen this site which is very helpful to me to ge ing more knowledge and information
regarding equipment, calculation and some standard. And sir do you have any reference regarding
the calculation of jumper length in 400kV transmission line for tension type tower. I would be very
grateful if sir can upload some data.

Reply
Anand says:
December 11, 2015 at 6:38 am
Sir,
I have some question. For HT breaker sizing( While selecting VCB, SF6), it is always chosen 400A,
630A or above thought the current rating is below 150A( eg: for Demand load of 2000kVA 630A VCB
/ LBS is selected).
1. Why is it ?
2. Why don’t they manufacture lower rating HT Breakers ?

Reply
vamsielect says:
March 27, 2017 at 6:35 am
a small doubt sir, is there any specific code num for cpwd internal house wiring…? please mention
it…if there
Reply
sunil R tripathi says:
February 25, 2018 at 6:56 am
Dear Sir,

Thanks for these useful information.

Can you just guide me for the minimum distance between two trefoil cables installed in trenches &
same in the trays mounted in cable vault. Kindly share the reference for the same.

Regards,

Reply
Abdulwahab Solkar says:
November 23, 2018 at 11:03 am
Thank you sooooooooo much Sir.

Reply
Dr Mukesh Kumar says:
November 2, 2019 at 8:45 am
Dear Jignesh Ji,

Good Morning!

After taking volunteer retirement on completion of 11 years from Indian Naval Services I joined
Merchant Navy where i met with an accident in 2014 and got paralyzed complete left side of my
body. Now I am able to walk with stick limping but left hand is still not in use. I have two Engineer
children and one BMM daughter but none look after me. Even my wife is living with my children.
Now I am pulling on with irregular earnings with great difficulties. i am 56 but i am rejected for any
and all jobs.However I shall remain thankful to you for utilizing your notes.

Thanks & Regards,

Mukesh Kumar
Kalyan [Mumbai]

Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.

You might also like