Surveying Practical 2.0 (Setting Out) Report
Surveying Practical 2.0 (Setting Out) Report
Team number: 11
Date: 31/08/2022
1|Page
Table of contents
1. Introduction………………………………………….. 3
2. Aim…………………………………………………… 3
3. Orientation and direction calculation………………. 3-9
4. Fieldwork…………………………………………….. 9-10
5. Sketch of building……………………………………. 11
6. Summary and conclusion……………………………. 12
2|Page
1. Introduction
Setting out is either the process by which information is taken from construction design drawings
and then pegs, profiles, or other marks are set to control the construction work and to ensure that
each element is constructed, where the positions and levels of buildings, roads, drainages, sewers, and
all other engineering projects are already marked on a plan are transferred to the ground by a variety
of methods and by specifically manufactured instruments.
2. Aim
128°3’10’’ -0.729968
351°6’21’’ 0.729952
3|Page
Point A
S= 25.185 -0.245918
Point B
S= 43.185m -0.245918
Point C
4|Page
𝐵𝐶
Tan θ= (𝐽1−𝐵)
10
θ= 𝑡𝑎𝑛−1(43.185)
= 13°2’16’’
α= 255°45’50’’ - 13°2’16’’
= 242°43’34’’
= 44.328m
Point D
10
Tan θ= (37.185)
10
θ= 𝑡𝑎𝑛−1(37.185)
= 15°3’8’’
α= 255°45’50’’ - 15°3’8’’
= 240°42’42’’
5|Page
Horizontal direction J1-D= 240°42’42’’
= 38.506m
Point E
5
Tan θ= (37.185)
5
θ= 𝑡𝑎𝑛−1 (37.185)
= 7°39’30’’
α= 255°45’50’’ - 7°39’30’’
= 248°6’20’’
= 37.520m
6|Page
Polar J1-E J1 -85 962.061 +56 067.238
α= 248°6’20’’ -0.927872 -34.814 -13.991
S= 37.520m -0.372898
E -85 996.875 +56 053.247
Point F
5
Tan θ= ( )
31.185
5
θ= 𝑡𝑎𝑛−1(31.185)
= 9°6’32’’
α= 255°45’50’’ - 9°6’32’’
= 246°39’18’’
= 31.583m
7|Page
F -85 991.058 +56 054.723
Point G
10
Tan θ= (31.185)
10
θ= 𝑡𝑎𝑛−1( )
31.185
= 17°46’46’’
α= 255°45’50’’ - 17°46’46’’
= 237°59’4’’
= 32.749m
Point H
8|Page
10
Tan θ= (25.185)
10
θ= 𝑡𝑎𝑛−1(25.185)
= 21°39’22’’
α= 255°45’50’’ - 21°39’22’’
= 234°6’28’’
= 27.098m
4. Fieldwork
9|Page
10 | P a g e
5. Sketch of building
11 | P a g e
6. Summary and conclusion
In order for a building to be effectively constructed, it is crucial to precisely measure the structure's
measurements in accordance with the layout plan. Buildings with errors will have defaults, which
will cost more money and even put the safety of the facility at risk. Therefore, when starting out,
more caution must be used. The length of each wall shall be clearly defined, and the angles of each
wall shall be 90 degrees.
There are two types of mistakes that can be made when a structure is set up: systematic mistakes and
random mistakes. These errors ought to be avoided, and there are a few things that may be done to fix
them. To properly lay out the structure, office work must be carried out with extreme precision. It is
recommended that two separate people perform the computations because the person who checks the
first computation might follow procedures yet fail to catch problems. Nevertheless the project was
done successfully as a group and the calculation also augment the precision of the setting out done at
the field.
12 | P a g e