100% found this document useful (1 vote)
750 views

ITP For ASPHALT CONCRETE PAVING

The document is a site inspection and test plan for asphalt/concrete paving for the rehabilitation and expansion of the SWTP-Yanbu. It outlines acceptance criteria and inspection requirements for the base course and wearing course paving. Tests include mix designs, material testing, surveys, installation procedures, compaction testing, and density/thickness measurements to ensure the paving meets specifications. Inspectors from the subcontractor, contractor, and owner will monitor different elements to confirm quality standards are achieved.

Uploaded by

Mohammed Mujahid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
750 views

ITP For ASPHALT CONCRETE PAVING

The document is a site inspection and test plan for asphalt/concrete paving for the rehabilitation and expansion of the SWTP-Yanbu. It outlines acceptance criteria and inspection requirements for the base course and wearing course paving. Tests include mix designs, material testing, surveys, installation procedures, compaction testing, and density/thickness measurements to ensure the paving meets specifications. Inspectors from the subcontractor, contractor, and owner will monitor different elements to confirm quality standards are achieved.

Uploaded by

Mohammed Mujahid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

REHABILITATION AND EXPANSION OF

SWTP-YANBU
Doc. No.: 03-A20-CE-ITP-003 Site Inspection and Test Plan for Date of Issue: 25 Dec.2013
Rev. No.: 0 Asphalt/Concrete Paving Page: 1 of 4

SITE INSPECTION AND TEST PLAN FOR


ASPHALT/CONCRETE PAVING

0 Issued for Construction 25 Dec. 2013 Isrhael J.H. Jeong Keun Park
B Issued for Approval 22 Dec 2013 Isrhael J. H. Jeong Keun Park
A Issued for Approval 15 Dec 2013 Isrhael J. H. Jeong Keun Park
Rev. Description Date Prepared By Checked By Approved By
REHABILITATION AND EXPANSION OF
SWTP-YANBU
Doc. No.: 03-A20-CE-ITP-003 Site Inspection and Test Plan for Date of Issue: 25 Dec.2013
Rev. No.: 0 Asphalt/Concrete Paving Page: 2 of 4

Project Name: Rehabilitation & Expansion of SWTP - Yanbu I.T.


INSPECTION AND TEST PLAN FOR ASPHALT CONCRETE PAVING Pag
Contract No.:
Discipline: Civil Da
Acceptance Criteria Inspection for
No. Description of Inspection or Test Reference Verifying Doc.
Subcontractor Contractor QC Owner/PMC
(Code/Std/Spec/Proc)
ASPHALT CONCRETE PAVING Section 02513
1. Mix-design for Base Course Section 02513 1.2.C H H W/R
A. Material Test
a) Fine Aggregates/Gradation/Sp.Gr.
Third Party Lab. Report
b) Coarse Aggregate/Gradation/Sp.Gr. Section 02513 1.2.B
H
c) Asphalt Cement Material Test Cert. H W/R
B. Laboratory Design Mix(Marshall Method)
Section 02513.7.C Third Party Lab. Report
C. Trial Test/Plant Production Site Compaction

1.1 Survey(Level/Slope/Alignment) ITP-CE-F003 H H (W)


1.2 Installation ITP-CE-F014/ITP-CE-f013

1.2.1 Base Course W


H H
1.2.2 Surface Drop Section 02513 3.1 W
Inspection Report/ITP-CE-
1.2.3 Prime Coating Section 02513 3.1B H W (W)
F014
1.2.4 Placing Section 02513 3.4
1) Asphalt Mixture Test
 Asphalt Binder Content
 Mineral Aggregate Gradation
 Theoretical Maximum Sp.Gr. Section 02513.3.6 Third Party Lab. Report H W/R W/R
 Bulk Sp.Gr. of Compacted Mixture
 Marshall Stability and Flow
 Air Voids in Compacted Mixture

1.2.5 Compaction
1. Initial Compaction
2. Medium Compaction Section 02513 3.5 W W/R W/R
Third Party Lab. Report
3. Final Compaction
4.Finishing

1.2.6 Testing(Compacted Pavement)


1. Density (93-95%) Section 02513 3.6.B.1 Third Party Lab. Report H
ITP-CE-F014 I (W)
2. Thickness Section 02313 3.6C (W)
I : Inspection R : Review (W) : Random Witness W: Witness H: Hold

I.T.P
Project Name: Rehabilitation & Expansion of SWTP - Yanbu
INSPECTION AND TEST PLAN FOR ASPHALT CONCRETE PAVING Pag
Contract No.:
Discipline: Civil Dat
Acceptance Criteria Inspection for
No. Description of Inspection or Test Reference Verifying Doc.
Subcontractor Contractor QC Owner/PMC
(Code/Std/Spec/Proc)
ASPHALT CONCRETE PAVING Section 02513
2. Mix Design of Wearing Course Section 02513 3.5
A. Material Test
REHABILITATION AND EXPANSION OF
SWTP-YANBU
Doc. No.: 03-A20-CE-ITP-003 Site Inspection and Test Plan for Date of Issue: 25 Dec.2013
Rev. No.: 0 Asphalt/Concrete Paving Page: 3 of 4

a) Fine Aggregate/Gradation/Sp.Gr.
Third Party Lab. Report
b) Coarse Aggregate/Gradation/Sp.Gr.
c) Asphalt Cement Material Test Cert H (W) (W)
B. Laboratory Design Mix
Third Party Lab. Report
C. Trial Test/Plan Production/Site Compaction
2.1 Survey( Level/Slope/Alignment) ITP-CE-F003 H H (W)
2.2 Installation
2.2.1 Wearing Course Section 02513 2.1
ITP-CE-F014
2.2.2 Surface Preparation Section 02513 3.1 H W W
2.2.3 Tack Coating Section 02513 3.1.B Inspection Report/ ITP-CE-F014
2.2.4 Placing Section 02513 3.4
A. Asphalt Mixture Test
a) Asphalt Binder Content
b) Mineral Aggregate Gradation
Section 02513 3.6
c) Theoretical Maximum Sp.Gr. Third Party Lab. Report H (W) (W)
e) Marshall Stability & Flow
f) Air Voids in Compacted Mixture
2.2.5 Compaction
a) Initial Compaction
(W)
b) Medium Compaction Section 02513 3.5
ITP-CE-F014 H (W)
c) Final Compaction H
d) Finishing (W)
2.2.6 Testing (Compacted Pavement)
Third Party Lab. Report/ITP-CE-
a) Density (93-95%) Section 02513 3.6.B.1 H
F014 W
b) Thickness Section 02513 3.6.C Third Party Lab. Report W
H
3 Repair Activity ITP-CE-F014 H (W)
4 Pavement Markings Section 02513 3.7 Inspection Report/ITP-CE-F014 (W) (W)

I : Inspection R : Review (W) : Random Witness W: Witness H: Hold


REHABILITATION AND EXPANSION OF
SWTP-YANBU
Doc. No.: 03-A20-CE-ITP-003 Site Inspection and Test Plan for Date of Issue: 25 Dec 2013
Rev. No.: 0 Asphalt/Concrete Paving Page: 4 of 4

INSPECTION REPORT FOR PAGE 1 OF 1


ASPHALT/CONCRETE PAVING

Project Name: Rehabilitation & Expansion of SWTP-Yanbu Contract No.: 720018705


Ref. No.:
Work Area/Location: Date:

Sub-con Name:

Elevation : From To Ref. DWG. No.

Application :
Sub grade Sub-base Base
Asphalt Surface Concrete Surface

Inspection Result
No. Description Remarks
Accept Reject
Road Crossing Underground Utilities for Mechanical,
1
Electrical, C&I Etc. Verified & Checked
2 Surface Condition
3 Each Layer Thickness
4 Compaction Test (FDT and /or PBT)
5 Final Surface( Elevation, Slope, Alignment, Profile ; etc.
6 Test Requirement(as per ASTM D797/ Marshall Method)
7 Prime Coat (to be applied asphalt)
8 Tack Coat (to be applied asphalt)
9 Expansion and/or Construction Joint(for concrete)
10 Concrete Placing & Curing(for concrete)
11 Joint Filler
12 Final Surface Condition( asphalt or concrete)
13 Repair(patching)
14 Pavement Marking
15 Survey Report
Note:

Prepared By Witnessed By Witnessed By


Subcontractor Contractor Owner/PMC

NAME: NAME: NAME:

SIGNATURE: SIGNATURE: SIGNATURE:

DATE: DATE: DATE:


Form No.: ITP-CE-F014

You might also like