ITP For ASPHALT CONCRETE PAVING
ITP For ASPHALT CONCRETE PAVING
SWTP-YANBU
Doc. No.: 03-A20-CE-ITP-003 Site Inspection and Test Plan for Date of Issue: 25 Dec.2013
Rev. No.: 0 Asphalt/Concrete Paving Page: 1 of 4
0 Issued for Construction 25 Dec. 2013 Isrhael J.H. Jeong Keun Park
B Issued for Approval 22 Dec 2013 Isrhael J. H. Jeong Keun Park
A Issued for Approval 15 Dec 2013 Isrhael J. H. Jeong Keun Park
Rev. Description Date Prepared By Checked By Approved By
REHABILITATION AND EXPANSION OF
SWTP-YANBU
Doc. No.: 03-A20-CE-ITP-003 Site Inspection and Test Plan for Date of Issue: 25 Dec.2013
Rev. No.: 0 Asphalt/Concrete Paving Page: 2 of 4
1.2.5 Compaction
1. Initial Compaction
2. Medium Compaction Section 02513 3.5 W W/R W/R
Third Party Lab. Report
3. Final Compaction
4.Finishing
I.T.P
Project Name: Rehabilitation & Expansion of SWTP - Yanbu
INSPECTION AND TEST PLAN FOR ASPHALT CONCRETE PAVING Pag
Contract No.:
Discipline: Civil Dat
Acceptance Criteria Inspection for
No. Description of Inspection or Test Reference Verifying Doc.
Subcontractor Contractor QC Owner/PMC
(Code/Std/Spec/Proc)
ASPHALT CONCRETE PAVING Section 02513
2. Mix Design of Wearing Course Section 02513 3.5
A. Material Test
REHABILITATION AND EXPANSION OF
SWTP-YANBU
Doc. No.: 03-A20-CE-ITP-003 Site Inspection and Test Plan for Date of Issue: 25 Dec.2013
Rev. No.: 0 Asphalt/Concrete Paving Page: 3 of 4
a) Fine Aggregate/Gradation/Sp.Gr.
Third Party Lab. Report
b) Coarse Aggregate/Gradation/Sp.Gr.
c) Asphalt Cement Material Test Cert H (W) (W)
B. Laboratory Design Mix
Third Party Lab. Report
C. Trial Test/Plan Production/Site Compaction
2.1 Survey( Level/Slope/Alignment) ITP-CE-F003 H H (W)
2.2 Installation
2.2.1 Wearing Course Section 02513 2.1
ITP-CE-F014
2.2.2 Surface Preparation Section 02513 3.1 H W W
2.2.3 Tack Coating Section 02513 3.1.B Inspection Report/ ITP-CE-F014
2.2.4 Placing Section 02513 3.4
A. Asphalt Mixture Test
a) Asphalt Binder Content
b) Mineral Aggregate Gradation
Section 02513 3.6
c) Theoretical Maximum Sp.Gr. Third Party Lab. Report H (W) (W)
e) Marshall Stability & Flow
f) Air Voids in Compacted Mixture
2.2.5 Compaction
a) Initial Compaction
(W)
b) Medium Compaction Section 02513 3.5
ITP-CE-F014 H (W)
c) Final Compaction H
d) Finishing (W)
2.2.6 Testing (Compacted Pavement)
Third Party Lab. Report/ITP-CE-
a) Density (93-95%) Section 02513 3.6.B.1 H
F014 W
b) Thickness Section 02513 3.6.C Third Party Lab. Report W
H
3 Repair Activity ITP-CE-F014 H (W)
4 Pavement Markings Section 02513 3.7 Inspection Report/ITP-CE-F014 (W) (W)
Sub-con Name:
Application :
Sub grade Sub-base Base
Asphalt Surface Concrete Surface
Inspection Result
No. Description Remarks
Accept Reject
Road Crossing Underground Utilities for Mechanical,
1
Electrical, C&I Etc. Verified & Checked
2 Surface Condition
3 Each Layer Thickness
4 Compaction Test (FDT and /or PBT)
5 Final Surface( Elevation, Slope, Alignment, Profile ; etc.
6 Test Requirement(as per ASTM D797/ Marshall Method)
7 Prime Coat (to be applied asphalt)
8 Tack Coat (to be applied asphalt)
9 Expansion and/or Construction Joint(for concrete)
10 Concrete Placing & Curing(for concrete)
11 Joint Filler
12 Final Surface Condition( asphalt or concrete)
13 Repair(patching)
14 Pavement Marking
15 Survey Report
Note: