Principles For Temporary Traffic Management Plans
Principles For Temporary Traffic Management Plans
Introduction
All developers and contractors intending to use any part of a road or road related area such as a
footpath will need to apply to Roads ACT for the authorisation of a temporary traffic management
(TTM) plan.
TTM plans are used to manage the safety of the public and workers on site. They document the
authorisation to install, display or interfere with, change or remove traffic control devices (TCDs),
temporary TCDs and other features. All TTM plans must be prepared by a qualified person and must
include details on:
• any TCDs, including temporary devices, that are to be installed, removed or altered
In addition to a TTM plan, developers and contractors will need to apply for:
• work approval – for any occasion when work will occur on public unleased land including the
implementation of measures included within the TTM plan
If permanent signage, road markings or other TCDs need to be changed as a result of development
the developers and contractors will need to apply for an approval to amend the TCD inventory.
Guiding principles
The following guiding principles are considered as part of the decision process for the authorisation
of TTM plans and the approval of requests to close any part of a public road (including footpaths and
nature strips). In priority order the guiding principles are as follows:
• SAFETY – TTM plans must control the risks, for both workers and the general public,
associated with work on or adjacent to the public road. These plans need to be mindful that
any feature placed within the road environment has the potential to be a hazard for road
users. This is particularly so for the more vulnerable road users such as cyclists, pedestrians
and the mobility impaired. Attention to detail when locating signs and directive barriers is
essential.
• ACCESSIBILITY – TTM plans should ensure access to the public road and essential goods and
services is maintained for all road users. Consideration must be given to accommodating the
needs of bus users and the mobility and visually impaired including provision of parking.
• AMENITY – TTM plans should minimise delays to traffic (including pedestrians and cyclists)
and, where practical, maintain the most direct and convenient route between destinations.
There is an expectation that traffic lanes, footpaths, cycle paths, cycle lanes and shared
paths should remain open for use. Traffic lane and footpath/nature strip closures and their
associated detours will only be considered when there is a safe alternative or when
construction has to occur on or within the public road. There is also an expectation that
footpath and cycle routes will be maintained on the same side of the street and that
additional road crossings will be minimised. Where this is not possible the detour should be
as short as possible and as close to the level of difficulty of the original route. Designers
should consider adjoining or nearby developments when selecting detours as well as the
impact of increased traffic on existing paths.
• ASSET – TTM plans should minimise damage and the risk of damage to the road asset
including natural features such as landscaping and trees.
Note: Temporary Traffic Management must be designed to accord with AS1742 part 3 and the
Traffic Control at Worksites Manual (RMS 2012).
• Variety of user needs – Cyclists and pedestrians have a wide variety of ability and needs.
TTM plans needs to be designed to accommodate the needs of all likely pedestrians and
cyclists. If a facility is provided for a segment of cyclists or pedestrians this should be
outlined in the TTM plan. For example, an on road cycle lane which not all cyclists have the
confidence to use.
• Path quality – Cyclists and pedestrians require a high quality path. TTM plan designers need
to give consideration to providing:
o suitable grade
o adequate clearance from temporary fencing including protruding post footings, the
treatment of path connections including at grade path connections and treatment of
temporary kerb ramps.
If any of these requirements cannot be met in a particular case, designers must consult Roads ACT as
soon as possible.
• Legibility – Cyclists and pedestrians tend to have more time to assess their route and are
more easily able to make route choice decisions on the move. If cyclists and pedestrians
need to detour the reason needs to be obvious and clearly communicated at the earliest
opportunity.
Note: Designers must refer to the ACT Municipal Infrastructure Standards (in particular MIS 05 –
Design Standard – Active Travel Facilities Design) for acceptable dimensions for cycle paths and
footways.
Dictionary
• Public road is any street, road, lane thoroughfare, footpath or place that is territory land and
open to or used by the public.
• Traffic Control Devices (TCD) are the proscribed signs, road markings and other controls
used to warn, inform and guide traffic. It is an offence for anyone other than an authorised
person to install, remove or alter any TCD.
• Temporary Traffic Control Devices are the proscribed temporary road signs, road markings
and directive barriers used to manage and regulate all traffic (which includes vehicular,
pedestrian and cyclist traffic). It is an offence for anyone other than an authorised person to
install, remove or alter any temporary TCD.
• Temporary Traffic Management Plans are a plan prepared by a qualified person that detail
the use of temporary TCDs and changes to permanent TCDs for the management of traffic
at, through, past and on the approaches to work sites. An authorised TTM forms a legal
agreement authorising a person to install, remove or alter permanent TCDs in accord with
the authorised TTM plan. Any change from the authorised plan must be documented and
may require additional authorisations. The TTM is not a blanket approval for works and
separate approvals may be required for other specific activities (you should check with
Roads ACT).