Method Statement Electrical

This document outlines the method statement for temporary and permanent site electrical works. It details the operations including requesting permission and power details, deploying electricians, barricading the site, and using appropriate materials and earthing. It also covers checking safety measures like caution signs, protective equipment, and removing hazards. Installations will be inspected and documented using checklists. Monitoring and follow up actions include periodic reviews by safety personnel, with work halted if any issues are identified.

Uploaded by

muqtar4u
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
164 views2 pages

Method Statement Electrical

This document outlines the method statement for temporary and permanent site electrical works. It details the operations including requesting permission and power details, deploying electricians, barricading the site, and using appropriate materials and earthing. It also covers checking safety measures like caution signs, protective equipment, and removing hazards. Installations will be inspected and documented using checklists. Monitoring and follow up actions include periodic reviews by safety personnel, with work halted if any issues are identified.

Uploaded by

muqtar4u
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

METHOD STATEMENT FOR TEMPORARY & PERMANENT

SITE ELECTRICAL WORKS

1. OPERATIONS

1.1 Request to be made to the site in charge of Risinia with details as follows:

a) Purpose
b) Location with sketch of distribution
c) Power consumption details
d) Earthing details

1.2 Deployment of qualified electricians for carrying out the work.

1.3 Site should be properly levelled and barricaded before commencement of the
installation job.

1.4 Installations should be conforming to statutory requirement comprising of proper


earthing, required capacity ELCB and standard switchgears or approved make.

1.5 All the cable used shall be aluminum / copper armored PVC insulated of
appropriate rating.

1.6 Whenever cable joints are unavoidable, it shall be properly insulated or proper
junction box shall be used and as far as possible taken over ground with proper
supports giving adequate ground clearance.

1.7 All cable connections shall be through proper cable lugs, connectors and cable
glands.

1.8 All the spare holes of switchboard shall be plugged.

1.9 All the DB’s switchboards etc. shall be properly earthen subsequently
connecting to the main earth pit.

1.10 After the completion of the works, installation shall be checked by the authorized
person and report submitted through the required checklist format.

1.11 Protection from rain and sun for DB’s switch boards.

1.12 No smoking anywhere.

1.13 No storage of paints, diesel etc.

1.14 No provision to use as store for dress material, food etc.

1.15 Smooth accessibility.


2. CHECKLIST

2.1 Ensure proper cautioning with caution board regarding the danger due to
electricity.

2.2 Electrician working shall use proper safety shoes, rubber hand gloves, ear
defenders, electrician tool kit. Etc.

2.3 Proper rubber mats shall be used in front of switchgears.

2.4 All unwanted materials shall be removed from the premises.

2.5 Handling by only competent / approved electricians.

2.6 Firefighting facility.

2.7 Appropriate authority (in writing) from competent persons.

3. INSPECTION & DOCUMENTATION OF CHECK

3.1 Electrical site checklist of Risinia in place.

3.2 Availability of authorized DG operators / technicians in site spot.

3.3 Report of toolbox talks.

3.4 Availability of first-aid box at site.

3.5 Emergency arrangement taken care of.

4. MONITORING AND FOLLOW-UP ACTION

The above arrangements shall be checked and verified by the concerned execution
engineer / supervisor of RISINIA and the system shall be reviewed at a periodical
interval by safety personnel of RISINIA.

In case of identification of any of the lacunae / lapses, as described, the activities shall
be halted by safety / electrical personnel of RISINIA and no risk / short cut whatsoever
shall be taken at any point of time.