45 CAN TCH UG 0001 V01 Cost & Allowables User Guide
45 CAN TCH UG 0001 V01 Cost & Allowables User Guide
Candy V 2.01e12.8
While it is essential to understand where a project stands financially at any point of time, it is more
important to have the ability to forecast its financial status at completion. The Cost and Allowables module
provides all the tools necessary to achieve this, thereby assisting the Project Team to maximise the
profitability of a project.
There are a variety of documents and reports available that are customisable to the requirements of the
Project Team.
REQUIREMENTS
To extract the most benefit from Cost and Allowables, users should have a working knowledge of Candy
Estimating and Valuations as this manual refers to the Bill document, Valuations, Worksheets, Resources,
Project Codes and Subcontract Manager.
DEFINITIONS
Below is a list of definitions for the terminology used within this manual:
• Step 2: Select New Document > 1. Cost & Allowable > 1.1 Cost and Allowables by Period.
To ensure the correct comparison between Cost and Allowables, users should measure the Actual
Quantity on the same date as the Cost Close for accounts.
The Task Code column is included, by default, within this document. The BuildSmart® accounting system
contains both the Task Code (Activity Code) and Cost code (Ledger Code) for more comprehensive
financial reporting. If your accounting system does not make use of Task Codes, its column can be
removed from the document (see below).
• An Excel file.
• Step 1: In Cost & Allowables > Documents > Cost & Allowables documents.
• Step 2: Select the document 3.1 Cost Import, then click Select.
• Step 3: Select Tools > Import Costs To-Date > Import from File.
• Step 5: Select from the available column headings that match headings of the imported cost file.
• Step 6: Headings on the import document can be removed by inputting the number of lines that are
to be ignored (see below).
The Code Description does not require matching as Candy already associates the Cost Code
Description with the Cost Code.
If the imported file is incompatible with the information within Candy, a notification message will
display, it is most likely that the column headings within the imported document remain undefined as
Cost Codes in Candy. These can be deleted using a Control & Delete key combination.
Cost Adjustments
After every cost import, further adjustments can be made by the site personnel to reflect the ‘True’ Cost
To-Date. Those adjustments are performed using the imported costs on the same document, ‘3.1 Cost
Import’, and get made under the following headings:
These are costs that have been misallocated and must be corrected. The total of this column must always
equate to zero.
Accruals
S/C Liability
This is the difference between the Subcontract Pay Amount and the Due Amount.
• Step 1: Under Subcontract Manager tab > Subcontract Document Manager > 3.1 Subcontract
Summary or select the icon to access the Subcontract Document Manager.
These are materials that have been pre-purchased but may not be claimable within the current Valuation,
such as materials off-site.
Contras
Residual
This refers to the pre-purchase of equipment, such as formwork, which must be written off over a period
of time.
Other
Notes
Once adjustments have been entered, Costs are releasable for comparison against the Allowable.
To view this, from the document 3.1 Cost Import, take the following steps:
• Step 1: Select Tools > Release Costs for Cost and Allowables.
The Actual Cost column (above) is used within the Cost and Allowables documents and labelled as
To-Date Cost (below).
The To-Date financial position of the Job as the Actual Allowable. This gets compared to the To-Date
costs of the Job and is broken down into the project Task code and Cost Code.
The To-date section displays the current position between Allowable and Cost, whereas the Remaining
section displays the forecast position from current to completion, future costs are influenced by:
• The necessity to employ another subcontractor with rates different to Allowable rates.
• Cost Worksheets.
• Subcontract Manager.
It is inevitable that throughout a project, the prices of resources change. To analyse the effect of these
price changes, the Cost Rate must be entered in the following way:
• Step 1: Under Estimating > Document Manager > Resources > 2.3 Resource List with Cost
Rates.
In the following example, the Resource Stock Bricks has been updated to reflect the current rates.
Production outputs, waste allowances and other variables may require adjustment to reflect current onsite
conditions.
To make these adjustments, complete the following steps:
• Step 2: Select New Document > 6. Costs to complete > 6.1 Bill with cost rates for cost w/s
adjustment.
In this exercise, the production output of Excavate to stockpile is increased from 150m3/day to
175m3/day, and the production output of Backfill & Compact is increased 250m3/day to 300m3/day.
Take note how the worksheet title is now ‘Cost Worksheet’ after changing the production output, the Cost
Rate now differs from the original Cost rate.
Cost and Allowables reports against the Subcontract Accounts (Ledger) Code without any change to Cost
or Allowable worksheets, regardless of whether there are multiple subcontractors allocated to one or
more BOQ items. This is possible by identifying the Subcontract Cost Code and the Net Worksheet Cost
Code.
The Subcontract Cost Code is the code to which payments for a specific subcontract get allocated. This
code is typically the Ledger Code used by the accounts department to identify the cost against the
subcontractor.
• Step 1: Under the Cost & Allowables tab > Main > Definitions and Settings.
Once the Cost Codes are defined, complete the following steps;
• Step 1: Under the Subcontract Manager tab > Main > Subcontract Manager. Alternatively, you
may select the icon on the toolbar.
• Step 4: Select the Subcontract Cost Code from the dropdown list, this is the Cost Code that Cost
and Allowables gets reported against; in this example, the Subcontract Cost Code is 901.
• Step 7: Select the Subcontract Cost Code from the dropdown box, the Subcontract Cost Code is
902.
The Net worksheet Cost code is the Cost Code of the subcontract resource in the worksheet of the
current Subcontract Bill.
The example below shows that column 17.3 Resource Cost Code List is added to document
1.1 Subcontract Bill, indicating that the Net Worksheet Cost Code for the items in the Subcontract Bill
is 900.
• Step 1: Under the Cost and Allowables tab > Document Manager > select 1.1 Cost & Allowable
by Period.
• Step 3: Select the option Costs for Subcontract Items from Subcontract Manager, under the
heading Advanced Calculation Options, then select OK.
• The Subcontract Due Quantity total must equate to the Actual Quantities listed within the leading
contract Valuation; if there is a difference, a message displays, instructing users to make the
necessary corrections.
• The total of Final Awarded Quantities must equate to Final Bill Quantities - to ensure this, navigate to
‘Subcontract Manager’, select ‘Document Manager’, then ‘Document 2.1 BOQ with Subcontract
Allocation’.
• If the above rules get disobeyed, a message displays instructing users to make the necessary
corrections.
• Where the main contractor and subcontractors undertake work using the same Bill items, internal
variants get created.
The Allowable at Completion is calculated using the multiplication of Final Quantities and Net Rate, and
the Cost at Completion is the sum of Cost To-Date and Remaining Costs, these determine the financial
performance of the project at completion:
• Open and calculate the document 1.1 Cost and Allowables by Period.
The changes made to Resource Costs, Cost Worksheets and Subcontract Manager reflect in the above
document with the resultant variances to Allowables shown in Remaining Variance and At Completion
Variance.
Setting up new Valuations copies all ‘To-Date’ Quantities and Costs into such from the previous
Valuation.
• Step 1: In the Job Manager, right-click on the Job you wish to backup or copy.
• Step 3: Right-click on the duplicated job, then select Rename the Job.
• Step 2: Under the Valuations tab > Main > Valuation Setup Manager.