Method Statement & Risk Assessment Installation of Structured Cabling System
Method Statement & Risk Assessment Installation of Structured Cabling System
Approval Status
A. Approved [ ] B. Approved with Comments [ ] C. Rejected Revise & Resubmit [ ] D. For Information [ ]
RESIDENT ENGINEER
DATE :
Distribution:
METHOD STATEMENT
FOR
PURPOSE
SCOPE OF WORK
REFERENCE DOCUMENTS
RESPONSIBILITY
PROCEDURES
METHODOLOGY
QA/QC RECORDS
SAFETY
REQUIREMENTSREFERENCE
REFERENCE
ATTACHMENTS
1.0 PURPOSE
The purpose of this method statement is to describe the procedure and methodology to be adopted
as a part of Installation & Testing of Structured Cabling for Telephone & Data System for the above
mentioned project. This document should be read in conjunction with the Project Quality Plan and
Contract Specifications.
This procedure covers the installation of Structured Cabling for Telephone & Data System. This will
also ensure proper workmanship and conforms to contract documents.
3.0 REFERENCES
Technical Specification
Approved shop drawings for firefighting and sprinkler system layout.
Manufacturer’s recommendation
Approved material submittal
5.0 RESPONSIBILITY
Being a leader of MEP Team. Project Manager will be overall responsible for all MEP activities,
including these above-mentioned Installation activities.
Project Manager
Have a full authority and overall responsibility to manage, supervise, control the works and
have direct responsibility for ensuring safe working practices and compliance with
regulatory authorities' requirements, co-ordinate with engineers for execution of the
Contract Scope of Works. Implement the project quality systems to the satisfaction of the
project requirements.
Review changes and variations to evaluate impact of those on time and schedule.
Overall site supervision shall be the responsibility of the Supervising Engineer, who will
oversee all works pertaining to the ascribed method statement.
Ensure that the works are carried out according to the Contract Specifications approved
method statement and shop drawings.
To provide all necessary information and distribute responsibilities to his construction
team.
Tool Box Talks are performed
Work Method Statement is communicated to the workers performing the scope of work.
Review Risk Assessment for compliance Communicate the Risk Assessments to the
foreman.
Health and Safety inspection are performed
Work inspection - Issuing notification to the Clients appointed Supervising Engineer for
inspection and clearance.
QA/QC Engineer
Responsible for monitoring and making sure the works are in fulfilment with the
specified requirements, that all quality records related to the works are complete.
Ensure that all installations to be done are as per approved material, approved layout
shop drawing and coordination drawings, approved installation details, and approved
mock-up.
Coordinate and carry out all the inspections with the MEP Coordinators and QA/ QC
Engineers andConsulting Engineers.
Safety Officer
Prior to commencing any activity, we will ensure that there will be safe access to work site and
safe place for execution of work.
The labour force shall receive a toolbox talk on the project site safety regulation. Any
process that is adopted that may have a particular safety risk will be assessed and
addressed as required.
Ensure that the proper PPE (safety shoes, helmet, hand gloves, reflected jacket, hand
gloves, welding mask etc.) and safety work permits are available prior to commence any
activities at site.
The Designated safety officer shall have full authority to removed personnel from the
operational areas and/or suspend the work activities should any personnel not be
observing defined safety procedures.
Foreman / Supervisor
The designated Foreman will be accountable to the Supervising Engineer, and shall be
responsible for the efficient organization & control of the assigned operatives and scribed
work activities.
ReviewRisk Assessment for compliance.
Communicate the Risk Assessment
Communicate Tool Box Talks as required and return signed document to Supervising
Engineer.
Work method Statement is communicated to the workers performing the scope of
work.
Health and safety inspection are performed.
Storekeeper
Ensurethat the materials delivered to site shall be as per the material approval.
Check that the material quantity received against the order.
Check that the material received has a proper documentation.
Ensure that the proper storage and identification shall be provided and maintained as per
manufacturer's recommendations.
Ensure that the material inspection has been carried out prior to installation.
6.0 PROCEDURES
MATERIALS
In compiling this method statement, it has been assumed materials to be used in the defined
process will have been subjected to an approval process, and subsequently approved by client’s
nominated representative as per the contractual requirements.
The Structured Cabling used as per the material approvals & approved drawings
Material List
CAT-6 Cable, UTP Four Pair CAT6 Outlets and Patch Panel with Accessories
Cabinets
Delivery: If the material is to be transported the vehicles used should have a flatbed free from sharp
projections of any kind. Materials should not be dropped onto hard surfaces and should not be dragged
along the ground. Wherever possible the loading and unloading of materials should be carried out by
hand. Use safe lifting practices, involve extra people as possible. Carry out housekeeping before manual
lifting.
Ensure all the employees attend site-specific induction covering safety, environment, and
quality.
Acquire approvals and inspection for plant & machinery to enter inside the site locations if any.
Any PTW for General works will be applied and obtained prior to works on site.
All environmental control will be established in accordance with the Site Environmental Plan.
Ensure that all the necessary clearances from the Construction team are obtained prior to start
the work.
Check that the shop drawings and material submittals are approved and verify that the materials
are as per the approved by the Engineer.
Check that pipes are delivered pre-packed in standard quantities
Inspect the pipes stored on a reasonably flat surface free from large stones or sharp projections.
Loading and unloading of pipes should be carried out by hand and use of skids should be avoided
Pipes should not be dragged along a rough surface.
Extra care should be exercised in handling pipes to avoid damages.
Check work area is clean and safe to proceed for the installation & testing works.
7.0 METHODOLOGY
8.1 Preparation Work:
Before commencement of structured cabling, the following are required to be carried out:
Before pulling the cables, the ducts and trunking will be checked with the rope inside to be assured that
there are no blockages in the route.
Check material to be used are approved.
Check work area is clean and safe.
The works will be carried out by experienced foremen and labourers. Under the supervision of
experienced engineers from the Sub-Contractor.
The engineers will brief the personnel involved in the activity before the works Commence. This will
involve going through the method statement, emergency procedures.
CAT-6 cable run will not exceed a maximum installed length of 90 meters, and when routing shielded
cabling or sitting RJ-45 outlets a minimum separation distance will be maintained, from possible sources
of EMI (Electro Magnetic Interference).
The CAT-6 cables are to be pulled in manually ensuring that the pulling tension does not exceed the
manufacturers recommended guidelines.
Once cables are installed and to point they shall be cut to length and terminated to an RJ45 jack
terminating within the provided containment.
Before pulling the CAT-6 cable the conduits will be checked with the fish tape inside to be assured that
there are no blockages in the route.
Connect the strength member of the cable to the pull line. Unless cables are designed for such use,
basket grips and similar methods of attachment should not be used.
Use lots of large pull boxes and divide pulls in half or even thirds at corners or pull boxes. A pulling
operation must be stopped if pulling tensions reach the cable's limit. The discontinued pull will have to
be aborted, the cable pulled back out and replaced on the reel, and the pull started again using shorter
runs. The cable may be reused if the pull or extraction has not damaged it.
Identify exact terminating locations in advance, keeping in mind that the cable must be pulled all the
way to where it will be terminated, not just into the room. This obvious though often overlooked step
can lead to costly mistakes if forgotten.
Carefully measure the cable's path before the conduit pull to avoid the need for splices. Not only do
splices cost time and money, but they also cause loss in both signal quality and strength. In fact, most
designers specify point-to-point or device-to-device runs to avoid needless signal loss from splices.
Pull the pull tape into the conduit, or along the cable path, for an initial measurement, and add to that
extra length for terminations, and future access coils, if specified.
Aside from the regular work hazards of cuts, bruises, falls, etc., you must consider additional hazards.
Check for hazardous gases before anyone enters a manhole. Above all else: Examine each situation
carefully before you start work.
8.3 Procedure for Termination of CAT-6 Cable in Outlet & Patch Panel
The CAT-6 Cable will be prepared and dressed up to the Panel and the cable will be taken inside the
Panel and outlet.
Splicing of all CAT-6 cable shall be carried out by means of a punch down tool.
All data/voice jacks shall be terminated using the “T568B" wiring scheme.
Upon completion of the installation, testing to all outlets will take place using a Fluke copper cable
Tester.
Testing will comprise of the following elements - Headroom, Wire Map, NEXT and ELFEXT, Length,
Propagation Delay, Delay Skew, Impedance, Attenuation, Resistance, ACR, Return Loss, Power Sum
NEXT, Power Sum ELFEXT and Power Sum ACR.
Wall Mounted Cabinet shall be fixed on the wall at a height of 1.8 Meters from FFL to top of the cabinet
using 4 number of 10mm fixed bolt.
6 way PDU (Power Distribution Unit) and Fan shall be fixed in the wall mounted cabinets.
8.0 MANPOWER
The required manpower shall be reassessed for each activity. In general, the following Supervision &
resources will be in deployed:
MEP Engineer
Safety Officers
Foreman and charge hands
Technician
General Labors
Defects: If during the inspection any defects or snags are found then these will be cleared immediately
after the inspection or depends to the installation defect and the works re-offered for inspection.
Inspections (Hold Points): All inspection and testing shall be carried to be satisfy the criteria that shall
be the evidence in the relevant inspection documents as detailed in the inspection and test plan.
Records:
Removal Redundant Materials: The Foreman shall ensure that all non-hazardous waste materials are
cleared from the site and disposed it in approved manner.
Should hazardously waste to be identified within the Risk Assessment report then Work Safety Officer
shall define the procedure, and control the safe removal and disposal of the contaminants from the site
full compliance with the Authority requirements.
Environment: Safety Officer to ensure the endeavor reduces emissions and discharges of waste which
are known to have negative effect on the environment.
Safety officers to ensure the safe operation of the equipment and to protect the environment in
compliance with relevant regulations.
Hazardous Materials: The Safety officer and Site Engineer shall establish if hazardous materials will be
used to perform the scope of work.
If Hazardous Materials are used the Risk Assessment must detail the Safe Work Requirements. Material
Safety Data Sheets (MSDS) will be attached to the Risk Assessment and Work Method Statement.
Permit to Work: The Safety Officer shall establish the site permits required to perform the scope of
work.
EMERGENCY PROCEDURE
Fire: In the event of the occurrence of a fire outbreak during the course of the works, the deployment of
the first aid firefighting equipment shall be such as to be able to contain and neutralize a minor Outbreak.
The Safety Officer with coordination to Foreman/Supervisor shall determine if the site wide fire alarm
system should be activated in line with the assigned site procedures.
Should it not be possible to extinguish the fire with the available equipment, then the Foreman/Supervisor
shall initiate the procedure for the safe evacuation of the site, as defined within the Main Contractors Site
Safety procedural documentation.
It shall be the responsibility of the Foreman/Supervisor to report the incident to the designated Work
Safety Officer.
The Work Safety Officer shall compile a Site Report relating to the incident, and issue the report to their
immediate Project/Construction Manager for the onward transmission to the Main Contractor and clients
Construction Manager.
Accident: In the event of an accident the Foreman/Supervisor shall assess the situation and determine
the most appropriate action to take in order to ensure that the injured party is safe. If the injury is minor
then the Foreman/Supervisor shall assign another operative to accompany the injured person to the
designated site first aid facility.
All accident occurring on the site shall be reported to the designated Work Safety Officer and reported in
the Accident Record Log Book
Emergency Site Evacuation: The evacuation of the site during an emergency shall be dictated by the
Main Contractors designated Site Safety Plan procedural documentation.
11.0 REFERENCES
Approved shop drawings
Local Authority Guidelines and Regulations
Contract specification and documents
12.0 ATTACHMENTS
RISK ASSESEMENT
CAESARS PALACE LUXURY VILLA FIT OUT
BLUEWATERS ISLAND
DUBAI, UNITED ARAB EMIRATES
FOR
Prepared By : Safeland Electromechanical LLC Checked By : Hennessey LLC Approved By : U+A Architects
Shinos M Bavu
C PPEs
People involved in welding or gas cutting jobs must use the
standard PPEs required for that job
Status of Inspection
We have carried out all necessary inspections and verify that the above items/activities conform to the contract specifications / document.
Signature
Name
Company
Date