20.04.2022-Snag Report - A

1. The document is a snag report for two restaurants - Chicken & More and Grand Buffet - listing incomplete works ("snags") across various departments and the actions being taken to address them. 2. For both restaurants, common outstanding works include steel/aluminum door installations, light fittings, ventilation control panels, HVAC ducting/fitting works. Electrical modifications are also pending approval. 3. The report provides status updates on material delivery times, ongoing fabrication works, clearances required from other teams, and targeted completion dates ranging from 1 week to end of April 2022.

Uploaded by

Sooraj Vs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
62 views9 pages

20.04.2022-Snag Report - A

1. The document is a snag report for two restaurants - Chicken & More and Grand Buffet - listing incomplete works ("snags") across various departments and the actions being taken to address them. 2. For both restaurants, common outstanding works include steel/aluminum door installations, light fittings, ventilation control panels, HVAC ducting/fitting works. Electrical modifications are also pending approval. 3. The report provides status updates on material delivery times, ongoing fabrication works, clearances required from other teams, and targeted completion dates ranging from 1 week to end of April 2022.

Uploaded by

Sooraj Vs
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

SNAG REPORT - ALBARSHA / COMMERCIAL DATE: 20.04.

2022

S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN


Material & drawing approved and fabrication under process. Supplier replied will deliver material in 01 week.
Civil Steel door not fixed.

Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .

Material not received at site.


Control panel for Ventilation fan not Installed.
Electrical
DEWA drawing approval received on 19.04.2022. Material request sent to purchase department on 20.04.2022. Expected date for
SMDB modification work not done. modification work by supplier is 01 week after LPO.

Waiting for material. MR 5179 requested on 06/04/2022.


GI duct not installed for Kitchen Hood.

Craddle required.
Riser duct installation in OTS to roof not done .

HVAC
Steel frame fabrication ongoing. Material received on 19/04/2022.
Fan fixing on roof not done.
1 CHICKEN & MORE

Expected date for steel work completion is 23/04/2022.


Crane hoist work pending.

Work will be completed after final false ceiling clearance.


Sprinkler Installation 80% completed

Work will be completed after final false ceiling clearance.


Firefighting & Fire alarm Fire alarm Installation 80% completed

Subcontractor need to be arranged.


Wet chemical system work pending

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

Material & drawing approved and fabrication under process. Supplier replied will deliver material in 01 week.
Steel door not fixed.

Measurement taken by RALS Aluminium team and waiting for delivery.


Civil Aluminium door not fixed.

False ceiling Work will be completed 1 day after HVAC clearance.


Cooking area false ceiling clearance not received from HVAC.

Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .

Material not received at site.


Electrical Control panel for Ventilation fan not Installed.

DEWA drawing approval received on 19.04.2022. Material request sent to purchase department on 20.04.2022. Expected date for
SMDB modification work not done. modification work by supplier is 01 week after LPO.
Waiting for material. MR 5179, Req. Date: 06/04/2022
GI duct not installed for Kitchen Hood.

Waiting for material. MR 5180, Req. Date: 08/04/2022


VCD not installed.
2 GRAND BUFFET
Waiting for material. MR 5148, Req. Date: 07/03/2022
HVAC Motorized dampers are not fixed.

Craddle required.
Riser duct installation in OTS to roof not done .

Steel frame fabrication ongoing. Work will be complete on 23.04.2022


Fan shifting to roof not done.

Work will be completed after final false ceiling clearance.


Sprinkler Installation 60% completed

Work will be completed after final false ceiling clearance.


Firefighting & Fire alarm Fire alarm Installation 80% completed

Subcontractor need to be arranged.


Wet chemical system work pending

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

False ceiling Work will be completed 1 day after HVAC clearance.


False ceiling clearance not received from HVAC.
Civil
Waiting for quotation approval.
Main entrance door not fixed.

Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .

Material not received at site.


Electrical Control panel for Ventilation fan not Installed.

DEWA rejected modification request. Need EJARI for DEWA submission.


SMDB modification work not done.

Waiting for material , MR 5151, Req date: 16/03/2022


Fan Installation not done .

Electrical power required in isolators.


3 BAKERY HVAC AC units testing pending.

Waiting for material


MS & GI duct work pending.

Work will be completed after final false ceiling clearance.


Sprinkler Installation 90% completed

Work will be completed after final false ceiling clearance.


Firefighting & Fire alarm Fire alarm Installation 90% completed

Subcontractor need to be arranged.


Wet chemical system work pending

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

False ceiling Work will be completed 1 day after HVAC clearance.


Kitchen area - False ceiling clearance not received from HVAC.
Civil
Material & drawing approved and fabrication under process. Supplier replied will deliver material in 01 week.
Steel door not fixed.

Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .

Material not received at site.


Electrical Control panel for Ventilation fan not Installed.

DEWA drawing approval received on 19.04.2022. Material request sent to purchase department on 20.04.2022. Expected date for
SMDB modification work not done. modification work by supplier is 01 week after LPO.

Waiting for material , MR 5196 , Req date: 11/04/2022


GI duct installation to hood pending

Waiting for material , MR 5165 , Req date: 11/04/2022


MS duct installation to hood pending
4 LEVANT HVAC
Waiting for material , MR 5139 , Req date: 02/03/2022
GI duct work incomplete

Need craddle
Riser duct to roof not completed

Work will be completed after final false ceiling clearance.


Sprinkler Installation 60% completed

Work will be completed after final false ceiling clearance.


Firefighting & Fire alarm Fire alarm Installation 70% completed

Subcontractor need to be arranged.


Wet chemical system work pending

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

Need more manpower to speedup work completion.


Ceiling paint work ongoing.
Civil
Material & drawing approved and fabrication under process. Supplier replied will deliver material in 01 week.
Steel door not fixed.

Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .

Material not received at site.


Electrical Control panel for Ventilation fan not Installed.

DEWA drawing approval received on 19.04.2022. Material request sent to purchase department on 20.04.2022. Expected date for
SMDB modification work not done. modification work by supplier is 01 week after LPO.

Waiting for material , MR 5150 , Req date: 16/04/2022


Grills & diffuser fixing
5 NAHASH HVAC
Electrical power required on isolator
Testing & commissioning of AC

Work will be completed after final false ceiling clearance.


Sprinkler Installation 80% completed

Work will be completed after final false ceiling clearance.


Firefighting & Fire alarm Fire alarm Installation 80% completed

Subcontractor need to be arranged.


Wet chemical system work pending

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

Work ongoing.
Wall tile work not completed.

Floor tiling will be completed 1 day after Electrical clearance.


Civil Floor tile work not started.

Waiting for HVAC clearance.


False ceiling work not completed.

AC load & Ventilation fan loads not given by AC team.


Electrical work above false ceiling pending.

Need load details for kitchen equipments & AC.


Electrical DB - dressing not done.

After DEWA approval.


SMDB work pending.

Waiting for materials MR 5192 , Req date: 16/04/2022


Fan installation pending
6 PIZZA
Waiting for materials MR 5188 , Req date: 15/04/2022
HVAC GI, MS duting pending

Electrical power equired on isolators


AC testing pending

Waiting for false ceiling final clearance


Sprinkler dropping 50% completed

Material not delivered , MR 10007247


Firefighting & Fire alarm Fire alarm system Installation 50 % Completed

Subcontractor need to be arranged.


Wet chemical system work pending

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

Quotation received from subcontractor and sent to purchase dated on 26.03.2022


LPG Need to finalize subcontractor
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

Quotation approved on 20.04.2022.


Entry glass & automatic door not fixed.

Work ongoing.
Both entrance décor ceiling incomplete.

Civil
Waiting for materials.
Office area door not fixed.

Quotation approved on 20.04.2022.


Rolling Shutter not installed.

Work ongoing. Expected date for completion


AC wiring not completed

Work ongoing. Partial Material only received. Expected date for completion
Light fitting not completed

Work ongoing. Expected date for completion 27.04.2022


7 SUPERMARKET Electrical DB dressing not completed

Work ongoing. Expected date for completion 27.04.2022


Switch & socket fixing not completed

Work ongoing. Expected date for completion 27.04.2022


Cable pulling for compressor not completed.

Electrical power required.


HVAC Testing & Commissioning pending

False ceiling work pending nar entrance area


Firefighting Installation 90% completed

Firefighting & Fire alarm


Exit light not delivered ( MR 10007246)
Fire alarm & Exit light Installation 80% completed

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

Need HVAC clrearance to start .


Ceiling work not completed.
Civil
Material & drawing approved and fabrication under process. Supplier replied will deliver material in 01 week.
Steel door not fixed.

AC load & Ventilation fan loads not given by AC team.


Electrical work above false ceiling pending.

Need load details for kitchen equipments & AC.


DB - dressing not done.
Electrical
After DEWA approval.
SMDB work pending.

Waiting for fan load detail from HVAC team.


Ventilation fan cable pulling pending .

Waiting for material, MR 5194 , Req date: 19/04/2022


8 TSUKI GI & MS duct work pending
HVAC
Waiting for material, MR 5194 , Req date: 19/04/2022
Fans Installation not done

Waiting for false ceiling final clearance


Firefighting Installation 50% completed

Waiting for false ceiling final clearance


Firefighting & Fire alarm Fire alarm Installation 50% completed

Subcontractor need to be arranged.


Wet chemical system work pending

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

Quotation received from subcontractor and sent to purchase dated on 26.03.2022


LPG Need to finalize subcontractor
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN

Floor tile materials are not received.


Flooring not completed.

Need HVAC & Electrical clearance to start work.


Civil Ceiling not completed.

Rals Aluminium team will fix.


Fixed glass work pending.

Work ongoing. Expected date for completion 27.04.2022


DB - dressing balance

Work ongoing. Expected date for completion 27.04.2022


Electrical AC - Wiring Balance

9 SALOON
Work ongoing. Expected date for completion 27.04.2022
Switch & socket fixing not completed

Electrical power required for AC machine.


HVAC Testing & commissioning work pending

Waiting for false ceiling final clearance


Firefighting Installation 50% completed

Firefighting & Fire alarm


Waiting for false ceiling final clearance
Fire alarm Installation 50% completed

Work ongoing, Will be completed on 26.04.2022


Plumbing Sanitary ware installation pending

PREPARED BY , ALBARSHA ENGINEERS