20.04.2022-Snag Report - A
20.04.2022-Snag Report - A
2022
Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .
Craddle required.
Riser duct installation in OTS to roof not done .
HVAC
Steel frame fabrication ongoing. Material received on 19/04/2022.
Fan fixing on roof not done.
1 CHICKEN & MORE
Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN
Material & drawing approved and fabrication under process. Supplier replied will deliver material in 01 week.
Steel door not fixed.
Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .
DEWA drawing approval received on 19.04.2022. Material request sent to purchase department on 20.04.2022. Expected date for
SMDB modification work not done. modification work by supplier is 01 week after LPO.
Waiting for material. MR 5179, Req. Date: 06/04/2022
GI duct not installed for Kitchen Hood.
Craddle required.
Riser duct installation in OTS to roof not done .
Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN
Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .
Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN
Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .
DEWA drawing approval received on 19.04.2022. Material request sent to purchase department on 20.04.2022. Expected date for
SMDB modification work not done. modification work by supplier is 01 week after LPO.
Need craddle
Riser duct to roof not completed
Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN
Light Material request will be made after final ceiling décor work requirement.
Light fitting work pending ( Kitchen Area) .
DEWA drawing approval received on 19.04.2022. Material request sent to purchase department on 20.04.2022. Expected date for
SMDB modification work not done. modification work by supplier is 01 week after LPO.
Subcontractor applied for drawing approval. Expected date for DCD inspection for permanent lpg connection will be 05.05.2022
LPG DCD approval pending
S.NO RESTAURANT DEPARTMENT SNAG ACTION TAKEN
Work ongoing.
Wall tile work not completed.
Work ongoing.
Both entrance décor ceiling incomplete.
Civil
Waiting for materials.
Office area door not fixed.
Work ongoing. Partial Material only received. Expected date for completion
Light fitting not completed
9 SALOON
Work ongoing. Expected date for completion 27.04.2022
Switch & socket fixing not completed