0% found this document useful (0 votes)
69 views

Substructure

This document provides a bill of quantities for excavation, earthwork, concrete work, and masonry work for a building substructure. It includes line items for site clearing, excavation of footings and trenches, filling, dewatering, termite treatment, mass and reinforced concrete, formwork, reinforcement, and random rubble masonry wall foundations. The total amount carried to the summary is Rs. 1,664,740.20.

Uploaded by

Mohamed Risath
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
69 views

Substructure

This document provides a bill of quantities for excavation, earthwork, concrete work, and masonry work for a building substructure. It includes line items for site clearing, excavation of footings and trenches, filling, dewatering, termite treatment, mass and reinforced concrete, formwork, reinforcement, and random rubble masonry wall foundations. The total amount carried to the summary is Rs. 1,664,740.20.

Uploaded by

Mohamed Risath
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

ITEM DESCRIPTION Qty UNIT RATE AMOUNT

BILL NO 1 - SUBSTRUCTURE

B - EXCAVATION & EARTH WORK

Site Clearing
1.B.1 Clearing site including removal of roots and
growth of every description, removing top
soil up to a depth of 6" extended up to 10'-
0" beyond the outer walls of the proposed
building and carting away the waste
material from the site where directed &
leveling. (Approx. 2760.00 Sq.ft)
1 Item 3,600.00 3,600.00
Excavation & Earth work
Excavation commencing from existing
ground level, not exceeding 3'-4" deep in
any materials except rock requiring
blasting, part return fill in ram and surplus
disposed as directed.
1.B.2 For column footings 9.06 cube 1,959.00 17,748.54

1.B.3 For wall trenches 10.14 cube 1,959.00 19,864.26


Excavation commencing from existing
ground level, exceeding 3'-4" ft but not
exceeding 6'-8" deep in any material except
rock requiring blasting, part return fill in ram
and surplus disposed as directed.

1.B.4 For column footings 8.84 cube 2,828.00 24,999.52

Filling under floors


1.B.5 Filling under floors including leveling,
watering & compacting (well rammed and
consolidated) in 6" layers with imported,
selected earth. 16.55 cube 5,304.00 87,781.20

Corridust filling under column footings

1.B.6 Supplying corridust and filling 3'-0" thick


under column footings, well compacted in
layers 8.16 cube 7,486.00 61,085.76

Earthwork Supports
Earthwork supports, (Planking & Strutting)
total of depth excavation not exceeding 3'-
4" and distance between vertical sides
(opposing faces) not exceeding 6.56ft

Total Carried Forward 215,079.28

S07 - 3
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward 215,079.28

1.B.7 For wall trenches 1158.00 sq.ft 99.50 115,221.00

Earthwork supports, (Planking & Strutting)


total of depth excavation exceeding 3'-4"
but not exceeding 6'-8" and distance
between vertical sides (opposing faces)
not exceeding 6'-8"

1.B.8 For column footings 1790.00 sq.ft 99.50 178,105.00

Dewatering

1.B.9 Allow for dewatering, in the manner


approved by the engineer to keep all
excavation dry until all works in
substructure are completed. furnishing of
water pumps are considered under
Preliminary Item Number (36) . (payment
will be made only for the actually
exicution,on the order of the engineer ) 1 Item 10,000.00 10,000.00

Anti Termite Treatment

1.B.10 Allow for anti termite treatment for barrier


and colony elimination at preconstruction
stage. The service provider should hold a
valid license for termite treatment issued
from Department of Agriculture. Rate to
include for a complete treatment with
1.Treatment before placing the foundation.
2. Treatment before placing floor concrete
3. Treatment along the periphery of the
building. The service provider should give
minimum 10 years warranty against termite
treatment. the service provider should
submit the list of Termiticide intended to
use for Engineer's approval. the following
minimum requirements to be maintained.
1.Application rate 5l/m 2
2.Termiticide Concentration : 12.5ml/L
3. Termite pump pressure rate : 250 psi

1840.00 sq.ft 23.00 42,320.00

TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 8 560,725.28

S07 - 4
ITEM DESCRIPTION Qty UNIT RATE AMOUNT

C - CONCRETE WORK

Mass / Lean Concrete

3" thick lean concrete Grade 'C - 15 ' in


the following ;

1.C.1 Under column footings 153.00 sq.ft 93.60 14,320.80

Mass Concrete

Mass Concrete Grade 'C - 15 ' in the


following.

1.C.2 6" thick under wall foundations 507.00 sq.ft 187.20 94,910.40

Mass Concrete Grade 'C - 20 ' in the


following.

1.C.3 3" thick ground floor concrete with one


layer of gauge 1000 polythene membrane
under ground floor concrete. 1840.00 sq.ft 123.50 227,240.00

Reinforced Concrete

Reinforced cement concrete Grade 'C - 25


' in the following

1.C.4 In column footings 63.00 cu.ft 469.00 29,547.00

1.C.5 In column shafts 28.00 cu.ft 477.50 13,370.00

1.C.6 In plinth beam 202.00 cu.ft 469.00 94,738.00

Formwork

1.C.7 Vertical sides of column footings <1'-0"


high 204.00 L.ft 191.00 38,964.00

1.C.8 Vertical sides of column shafts 150.00 sq.ft 191.00 28,650.00

1.C.9 Vertical sides of plinth beam ≤ 1'-0" high 720.00 L.ft 254.00 182,880.00

Total Carried Forward 724,620.20

S07 - 5
ITEM DESCRIPTION Qty UNIT RATE AMOUNT
Brought forward 724,620.20

Reinforcement

In column footings

1.C.10 10mm dia. 8.40 cwt 9,194.00 77,229.60

In column shafts

1.C.11 16mm dia. 2.00 cwt 9,194.00 18,388.00

In Plinth beam

1.C.12 12mm dia. 8.60 cwt 9,194.00 79,068.40

Mild Steel Rod Reinforcement


(fy=250N/mm2)

1.C.13 6mm dia as links in column shaft 1.00 cwt 9,194.00 9,194.00

1.C.14 6mm dia as stirrups in plinth beams 5.00 cwt 9,194.00 45,970.00

TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 8 954,470.20

S07 - 6
ITEM DESCRIPTION Qty UNIT RATE AMOUNT

D - MASONRY WORK

Rubble Work

Random rubble masonry in cement and


sand 1:5 in wall foundation.

1.D.1 300mm thick 5.07 cube 29,496.00 149,544.72

TOTAL CARRIED TO COLLECTION ON PAGE S 07 - 8 149,544.72

S07 - 7
ITEM DESCRIPTION Qty UNIT RATE AMOUNT

BILL NO 1 - SUB STRUCTURE

COLLECTION

B - EXCAVATION AND EARTH WORK (From Page 4) Rs. 560,725.28

C - CONCRETE WORK (From Page 6) Rs. 954,470.20

D - MASONRY WORK (From Page 7) Rs. 149,544.72

TOTAL CARRIED TO SUMMARY ON PAGE S 07 - 27 Rs. 1,664,740.20

S07 - 8

You might also like