Pavement Layer Construction
Pavement Layer Construction
4.3 Proper curing and compaction of base layer according to the layer
specifications.
NTRODUCTION
The key successful project often lies in the understanding and cooperation that is essential from
all participants, each must be clearly aware of his duties and rights. The documentation is the
vital link between design and construction. Here, tenderers will assess the quality of
documentation partly because poor information can add to the time wasted by site supervisors
and partly because unreliable information can lead to claims. If a contractor has enough
information he can avoid guesswork, include all the important items in his tender and will not
need to add global sums for poorly defined elements of work. You must know that the main way
a building contractor obtains work is via the preparation and submission of tenders.
ii) Negotiated contract: Here the architect selects and approaches suitable contractors and ask
them to undertake the project. If the contractor is willing to undertake the project they will
negotiate with the quantity surveyor to reach an agreed price.
Advantages
Contractors can be selected early in the design stage and can assist in the design stage and
can assist in the contract planning.
Useful for extension of contracts
Useful for a job of a difficult or unusual nature
Useful where there is insufficient time to prepare full tender documentation
Establishes good relationships between client and contractor
Low overall cost of tendering
Disadvantages
The price may be higher than in open tendering
The design could be influenced by the selected contractor
Difficult for new firms to obtain work
iii) Serial tendering: This method of tendering is done for the large
projects and complex which will have different domains and therefore this project should be
executed in a long period. So it has the following:
Advantages:
A competitive price may be obtained.
The contractor is able to plan a long term program
The experience obtained in earlier projects may be used to the advantage of both parties
for the future projects.
Disadvantages:
If the contractor initially produces unsatisfactory work the client may be committed to a
long term programme.
3) Alternative Tenders
5) Currencies of Tender
6) Documents Establishing the Qualifications of the Tenderer : specify the items of plant
and equipment for which the Employer requires Manufacturer’s Authorisation form In
the event if the Employer intends to permit Tenderers to claim the experience and
capability of their parent companies for the purposes of meeting the qualification criteria,
a clear statement to this effect must be made in the tender documents. The tender
documents shall also specify the minimum requirements for acceptance of the Tenderers’
parent company guarantee by the Employer. The main purpose of such parent company
guarantee would be to ensure that the contract will be performed satisfactorily i.e. the
contractor’s parent company will provide the necessary resources and is fully committed,
along with its subsidiary, to ensuring such performance
8.Period of Validity of Tenders :Insert the number of days deemed appropriate by the Employer.
The period should be sufficient to permit completion of evaluation and comparison of
tenders, review of the evaluation report by the Bank (if so required), obtaining of all
necessary approvals, and notification of the award. Normally, the validity period should be
90 days. For major and complex contracts, the validity period should be longer. A realistic
period should be specified in order to avoid the need for extensions.
9.Tender Security :Insert the amount deemed appropriate by the Employer. The amount shall be
expressed as fixed amount. Tender security will be normally in the range of 2-5 per cent of
the estimated cost of the Works.
13.Contractor’s address
Friction
Unevenness
Light reflecting characteristics
Drainage of surface water
• The required camber of a pavement depends on type of pavement surface and amount of
rainfall
The values of camber recommended by IRC for different types of road surfaces are given
below:
v. Kerbs:
Kerb indicates the boundary between the pavement and median or foot path or shoulder.
• Kerbs may be mainly divided into three groups based on their functions:
a) Low kerb
b) Semi-barrier type kerb
c) Barrier type kerb
Horizontal curve
A horizontal highway curve is a curve in plan to provide change in direction to the central line of
a road.
o When a vehicle traverses a horizontal curve, the centrifugal force acts horizontally
outwards through the centre of gravity of the vehicle.
o The centrifugal force is given by the equation:
P = Wv²∕gR
where,
P=centrifugal force in kg
Analysis of Superelevation
• If the value of ‘e’ exceeds 7% or 0.07 then provides maximum superelevation equal to 7% or
0.07 and proceed with step-III or IV.
Step-III: Check the coefficient of friction developed for the maximum value of e =0.07 at the
full value of design speed.
f =v²∕ gR - 0.07 …..if ‘v’ is in m/sec
f =V²∕ 127R - 0.07 …..if ‘V’ is in kmph
• If the value of ‘f’ thus calculated is less than 0.15, the super elevation of 0.07 is safe for the
design speed. If not, calculate the restricted speed as given in Step -IV.
Step-IV: The allowable speed at the curve is calculated by considering the design coefficient of
lateral friction and the maximum superelevation.
e + f =0.07+0.15=va²∕ gR=Va²∕ 127R
e + f =0.22=va²∕ gR = Va²∕ 127R
• Safe allowable speed (va or Va) is calculated as:
• If the allowed speed, as calculated above is higher than the design speed, then the design is
adequate and provides a superelevation of ‘e’ equal to 0.07.
• If the allowable speed is less than the design speed, the speed is limited to the allowed speed
calculated above and appropriate warning sign and speed limit regulation sign are installed to
restrict and regulate the speed
Attainment of superelevation in the field:
The attainment of superelevation may be split up into two parts:
a. Elimination of crown of the cambered section
b. Rotation of pavement to attain full superelevation
Horizontal Transition Curve:
A transition curve has a radius which decreases from infinity at the tangent point to a designed
radius of the circular curve.
• The rate of change of radius of the transition curve will depend on the shape of the curve
adopted and the equation of the curve.
of the curve.
• Set back distance is required to provide adequate sight distance on the horizontal curve.
• Obstruction to the sight distance on horizontal curve may be buildings, trees, cut slopes on the
inner side of curve.
On narrow road, the sight distance is measured along the centre line of road.
• On wider road, the sight distance is measured along the centre line of inner side lane.
• Set back distance depends on:
a) Required sight distance, S
b) Radius of horizontal curve, R
c) Length of the curve, Lc
Vertical Alignment:
• The vertical alignment is the elevation or profile of the centre line of the road.
• The vertical alignment consists of grades and vertical curves.
• The vertical alignment of a highway influences:
i. Vehicle speed
ii. Acceleration and deceleration
iii. Sight distance
iv. Vehicle operation cost
v. Comfort while travelling at high speeds
Gradients:
Gradient is the rate of rise or fall along the length of road with respect to the
horizontal.
It is expressed as a ratio of 1 in n or also as percentage such as n%.
Types Of Gradients:
• Gradients are divided into four categories:
a) Ruling gradient
b) Limiting gradient
c) Exceptional gradient
d) Minimum gradient
a. Ruling gradient:
• Ruling gradient is the maximum gradient within which the designer attempts to design the
vertical profile of a road.
• Ruling gradient is also known as ‘Design gradient’.
• For selection of ruling gradient factors such as type of terrain, length of the grade, speed,
pulling power of vehicle etc are considered
b. Limiting gradient:
• Steeper than ruling gradient. In hilly roads, it may be frequently necessary to exceed ruling
gradient and adopt limiting gradient, it depends on
i. Topography
ii. Cost in constructing the road
c Exceptional gradient:
Exceptional gradient are very steeper gradients given at unavoidable situations.
They should be limited for short stretches not exceeding about 100 m at a stretch.
d. Minimum gradient:
This is important only at locations where surface drainage is important.
Camber will take care of the lateral drainage.
But the longitudinal drainage along the side drains require some slope for smooth
flow of water.
Therefore minimum gradient is provided for drainage purpose and it depends on
the rainfall,
type of soil and other site conditions.
A minimum of 1in500 may be sufficient for concrete drain and 1in 200 or 1 in
100 for open soil drains.
Grade Compensation:
When sharp horizontal curve is to be introduced on a road which has already maximum
permissible gradient, then gradient should be decreased to compensate for loss of tractive efforts
due to curve.
• This reduction in gradient at horizontal curve is called grade compensation.
Grade compensation, % = 30+R/R
IRC gave the following specification for the grade compensation:
1) Grade compensation is not required for grades flatter than 4% because the loss of tractive
force is negligible.
2) The maximum grade compensation is limited to 75/R%.
Compensated gradient = ruling gradient – grade compesation
Vertical Curves:
• The vertical curves used in highway may be classified into two categories:
a) Summit curves or crest curves
b) Valley curves or sag curves
a. Summit curves or crest curves:
a. When L>SSD
b. When L<SSD
Length of valley curve:
• The important factors to be considered in valley curve design are:
a) Impact free movement of vehicles at design speed or comfort to
passenger.
b) Providing adequate sight distance under head lights of vehicles for
night driving
c) Locating lowest point of valley curve for providing suitable cross
drainage facilities
.
highway geometric design has the following objectives:
1. Determine, within the allowance permitted by the design standard and right-of-way, the
routing of proposed highway.
2. Incorporate, within the design standard, various physical features of the road alignment to
ensure that drivers have sufficient view of the road (and obstacles) ahead for them to adjust their
speed of travel to maintain safety and ride quality.
3. Provide a basis for the highway engineers to evaluate and plan for the construction of a section
of the proposed highway.
Design Process
A highway designer is concerned with at least four major areas of design at different stages
of project planning and design phases:
1. location design
2. alignment design
3. cross sectional design; and
4. access design
Location design takes place at the earlier stage of project planning. It refers to the macro-level
routing of a planned highway connecting two points through the existing highways,
communities, natural terrain. Normally, information such as lane-use master plan; existing and
projected population distribution; survey maps; maps of existing infrastructure; geology,
ecological, biological, and environmental information; and aerial photographs are among the
essential inputs
Overall Alignment
The plan view gives the horizontal alignment of a highway. The length of the highway is
measured along the plan view, on a horizontal plane. The length is expressed in terms of distance
from a reference station, in terms of stations. Each station is 100 m. A highway normally starts
from a fixed reference station. The distance from the reference station, together with the
direction from the reference station or subsequent stations, spells out the horizontal alignment.
The vertical alignment (including the gradients and vertical curves) are represented in a profile
view.
The profile view is the view along the length (including the true length of horizontal curve) of
the highway. The elevations of all the points at regular intervals or when necessary are specified
in the profile view.
Horizontal Alignment
A horizontal curve provides the directional transition on the horizontal plane, between two
straight sections of the highway running in different directions. Horizontal curves are expressed
Figure below shows the properties of a curve with a constant radius ðRÞ connecting two straight
sections of a highway. The curve starts at point of curvature (PC), ends at point of tangent (PT).
The point of intersection (PI) is the intersecting point if the two straight lines are extended. D is
the central angle of the curve, expressed in degrees.
The length of tangent T is
The degree of curvature ðDÞ is the central angle subtended by a 100 m arc of the curve.
Vertical Alignment
A vertical curve provides a smooth transition between two tangent grades. There are two types of
vertical
curves: crest vertical curves and sag vertical curves. Example profiles of crest and sag vertical
curves are
shown in Figure with the initial grade G1; final grade G2; and their signs.
As a departure from the horizontal curve, the points of curvature, intersection and tangent of a
vertical
curve are denoted by PVC, PVI and PVT, respectively. The length of curve L is the distance
between PVC and PVT measured along the horizontal plane. The PVI is at the midpoint between
PVC and PVT
along the horizontal plane.
The verticalcurves are parabolic in form. The parabolic curve has been used for the purpose of
calculation
because it has a constant rate of change of slope and equal curve tangents on both ends of the
curve
A crest vertical curve is shown in Figure above .Note that an uphill is expressed in a positive
gradient while a downhill is expressed in a negative gradient.
A vertical curve starts at the point of vertical curvature (PVC) and ends at the point of vertical
tangent
(PVT). The length of highway between PVC and PVT is L: The initial and final grades are
denoted by G1 and
G2; respectively, expressed in %. Based on the equation of a parabolic curve, the vertical offset y
at any
distance x from the projected initial gradient is
Negative values of y mean a downward offset from the projected tangent from PVC (as in the
case of crest
vertical curves) while positive values of y mean a upward offset from the projected tangent from
PVC (in sag
vertical curves). The highest or lowest point on the curve is given by
Example
A highway must traverse a 6% followed by a -2% grade. The length of the crest vertical curve is
2040 m.
Calculate the elevation for the first 600 m of the vertical curve at 100 m intervals, and the highest
point of
the curve
The negative value means that the elevation is measured downward from the projected original
gradient, based on G1:
The highest point on the vertical curve is
Design Elements
Sight Distance
Sight distance is the roadway ahead that is visible to the driver. Various sight distance criteria
exist in highway geometric design to provide drivers with sufficient warning of potential
obstacle or conflict ahead.
Stopping sight distance is the distance traveled during a driver’s brake reaction time plus the
braking distance for the vehicle to come to a complete stop. The equation to compute stopping
sight distance without vehicle skidding is
where V is the design speed, a the constant deceleration rate, G the grade (in decimal, positive
value for upgrade, and negative value for downgrade), and g = 9.81 m/sec2. AASHTO
recommends that t =2.5 sec and a = 3.4 m/sec2 be used in determining the minimum stopping
sight distance.
Decision sight distance is the distance needed for a driver to detect and perceive an obstacle or
information, and select an appropriate maneuver. This is important when a driver is approaching
a traffic
control device, or posted information signs. Because decision sight distance is for drivers to a
maneuver
or evasive action rather than just to stop, it is greater than stopping sight distance. The decision
sight distance for change in speed, path or direction on rural, suburban, and urban road may be
calculated from
d =Vt
AASHTO (2001) recommends a range of 10.2 ≤ t ≤ 14.5 sec
d =d1 +d2 + d3 + d4
where d1 is the initial maneuver distance, which is the sum of distances traveled during
perception and
reaction time plus the initial period of acceleration until the vehicle encroaches the passing lane.
The
corresponding time for this initial maneuver is t1.d1 is given by the expression:
in which v is the average speed of the passing vehicle, and m is the relative speed of the passed
and passing
vehicles, and a is the average acceleration. d2 is the distance traveled while the vehicle is
occupying the passing lane. The corresponding time is t2:
d2 = vt2
d3 is the clearance length, for margin of safety between the passing and opposing vehicles.
AASHTO recommends that 30 ≤ d3 ≤ 90 m for 56 ≤ v ≤ 100 km/h. d4 is the distance traveled
by the opposing vehicle during the passing maneuver during time t1 + t2: AASHTO recommends
that the opposing vehicle may be assumed to travel with speed v; and d4 may be taken as
The design of horizontal curves should be based on a combination of design speed, curvature,
and superelevation, subject to the laws of physics and limitations of human comfort and
tolerance
where:
e = rate of super-elevation, in decimal;
f = side friction factor between the tire and the
pavement surface;
v = vehicle speed.
Example
This WHS Management Plan has been developed to outline our approach to managing work
health and safety (WHS) at the site
We will:
make this plan available to all workers and contractors on this project and ensure
they have the opportunity to read, understand, clarify and ask questions
keep a copy of the WHS Management Plan readily available for the duration of the
project
review the plan regularly throughout this project and make any revisions known to
those working on the project
preparing, updating and implementing this WHS Management Plan, including all
associated procedures
ensuring that all works are conducted in a manner without risk to workers
investigating hazard reports and ensuring that corrective actions are undertaken
dispute resolution
1.3 Contractors
Contractors who are engaged for this project are responsible for:
identifying all high risk construction work associated with their activities and
ensuring safe work method statements are developed and implemented
undertaking site-specific induction before starting work and signing off that they
have completed this induction
ensuring they have the correct tools and equipment and these are in a serviceable
condition for the task
1.4 Workers
All workers on this project (including those employed by contractors) are responsible for:
taking reasonable care that their conduct does not adversely affect others
Mandatory/regulatory signs:
Informatory signs:
Road Markings
Soil
Aggregate
Sand
Cement
Bitumen
Water
Rock
Paraffin
Sealing product
Steel bars
Binding wire
Timber
Master cure
Geotextile
Pipe
Nail
Admixtures
disc
Measurement tools
Spirit Level
Folding Steel Rule
Tape Measure.
Digging tools
Hoe
Pick axe
Other useful tools
Categories of equipment used on road layer construction
Excavation equipment
Bulldozers
Front-end loaders
Motor graders
Scrapers
Trucks
BULLDOZERS
A bulldozer is a tractor unit with a blade attached to its front. The blade is used to push,
shear, cut, and roll material ahead of the tractor
FRONT-END LOADERS
Front-end loaders typically are tractor powered and operate on tires. They are typically
articulated and very maneuverable, making them ideal for constricted areas
MOTOR GRADERS
This type of equipment has been around since the start of road building, though originally
powered by a team of oxen, mules, or horses. The need for a smooth stable travel surface has
always been an important part of a road system This name is appropriate because this equipment
is typically used to maintain
grade and a smooth surface for rural non paved travel roads or haul routes on construction
sites
SCRAPERS
Scrapers are designed to load, haul, and dump loose material. The greatest advantage is their
versatility. They can be used for a wide variety of material types and are economical for
a range of haul distances and conditions. They are a compromise between a bulldozer, an
excavator, and a dump truck
EXCAVATORS
The excavator combines digging and lifting abilities
Excavators are ideal for underground utility construction. For trenching, the operator
fills the bucket and dumps to the side above grade.
Excavator parts
Backhoes
Backhoes are probably the most common piece of construction equipment found on
commercial construction projects. They come in many sizes and are ideal for light excavation,
trenching, material moving, and loading.
Grading equipment
The function of grading equipment is to bring the earthwork to the desired shape and elevation.
Major types of grading equipment include motor graders and grade trimmers
Paver machine
Compaction equipment
Concrete mixer
Derricks are commonly used to lift equipment of materials in industrial or building construction.
A derrick consists of a vertical mast and an inclined boom sprouting from the foot of the mast
Tower cranes are used to lift loads to great heights and to facilitate the erection of steel building
frames.
Sprayer machine
Cleaning machine
Cutting machine
Trucks
TRUCKS
Trucks are an extremely important part of the earthmoving and material-moving process.
Concrete vibrator
Rock drill
Pavement Purpose
1. Load support. Pavement material is generally stiffer than the material upon which it
2. is placed, thus it assists the in situ material in resisting loads without excessive
deformation or cracking.
3. Smoothness. Pavement material can be placed and maintained much smoother than
in situ material. This helps improve ride comfort and reduce vehicle operating
costs.
4. Drainage. Pavement material and geometric design can effect quick and efficient
drainage thus eliminating moisture problems such as mud and ponding (puddles).
The top soil or sub-grade is a layer of natural soil prepared to receive the stresses from the layers
above. It is essential that at no time soil sub-grade is overstressed. It should be compacted to the
desirable density, near the optimum moisture content.
Layer of natural soil prepared to receive layers of pavement placed over the loads on pavement
are received by soil subgrade for dispersion to the earth mass
Materials- Selected Soil , Moorum , Gravel , Aggregate maximum 50 mm.
Construction Method –
•The subgrade is constructed by spreading the loose soil and compacting the same at optimum
moisture content of the soil in layer.
•The maximum compacted thickness of each layer is generally limited to 200 mm as per
MORTH.
The subbase course is between the base course and the subgrade. It functions primarily as
structural support but it can also:
1. Minimize the intrusion of fines from the subgrade into the pavement structure.
2. Improve drainage.
The subbase generally consists of lower quality materials than the base course but better
than the subgrade soils. A subbase course is not always needed or used.
For example, a pavement constructed over a high quality, stiff subgrade may not need the
additional features offered by a subbase course so it may be omitted from design. However, a
pavement constructed over a low quality soil such as a swelling clay may require the additional
load distribution characteristic that a subbase course can offer. In this scenario the subbase
course may consist of high quality fill used to replace poor quality subgrade (over excavation).
Compaction method
Static
Impact
Vibrating
Rolling
Curing process
Checking methods
dipping
Measurement tools
Base Course
The base course is immediately beneath the surface course. It provides additional load
distribution and contributes to drainage and frost resistance. Base courses are usually
constructed out of:
1. Aggregate. Base courses are most typically constructed from durable aggregates (see
Figure 2.5) that will not be damaged by moisture or frost action. Aggregates can be
either stabilized or unstabilized. ,it may be composed of crushed stone, crushed slag, and
other untreated or stabilized materials
HMA. In certain situations where high base stiffness is desired, base courses can be constructed
using a variety of HMA mixes. In relation to surface course HMA mixes, base course mixes
usually contain larger maximum aggregate sizes, are more open graded and are subject to more
lenient specifications
Base Material
Base material shall be manufactured from hard, durable stone or recycled building materials free
+of clay lumps, organic matter and other deleterious substances. The material may be crusher run
or screened and recombined. 0788276771
If materials of different type or from different sources are delivered to the site, they shall be
placed in separate layers or separate lots.
compaction method
o Static
o Impact
o Vibrating
o Rolling
Curing process
Check compaction degree
checking methods
Using pegs and measuring tools based on surveying data
Digging
Final check of base slope and thickness
Surface Course
The surface course is the layer in contact with traffic loads and normally contains the
highest quality materials. It provides characteristics such as friction, smoothness, noise control,
rut and shoving resistance and drainage. In addition, it serves to prevent the entrance of
excessive quantities of surface water into the underlying base, subbase and subgrade (NAPA,
2001). This top structural layer of material is sometimes subdivided into two layers (NAPA,
2001):
1. Wearing Course. This is the layer in direct contact with traffic loads. It is meant to take
the brunt of traffic wear and can be removed and replaced as it becomes worn. A
properly designed (and funded) preservation program should be able to identify pavement
surface distress while it is still confined to the wearing course. This way, the wearing
course can be rehabilitated before distress propagates into the underlying
intermediate/binder course.
Intermediate/Binder Course. This layer provides the bulk of the HMA structure. It's chief
purpose is to distribute load
Prime coat is an application of low viscous cutback bitumen to an absorbent surface like granular
bases on which binder layer is placed. It provides bonding between two layers. Unlike tack coat,
prime coat penetrates into the layer below, plugs the voids, and forms a water tight surface.
5.2.Spray tack coat
Heating of bitumen
Tack coat is a very light application of asphalt, usually asphalt emulsion diluted with water. It
provides proper bonding between two layer of binder course and must be thin, uniformly cover
the entire surface, and set very fast.
Seal Coat:
Seal coat is a thin surface treatment used to water-proof the surface and to provide skid
resistance.
Surface course
Surface course is the layer directly in contact with traffic loads and generally contains superior
quality materials. They are usually constructed with dense graded asphalt concrete (AC). The
functions and requirements of this layer are:
It provides characteristics such as friction, smoothness, drainage, etc. Also it will prevent
the entrance of excessive quantities of surface water into the underlying base, sub-base
and sub-grade,
It must be tough to resist the distortion under traffic and provide a smooth and skid-
resistant riding surface,
It must be water proof to protect the entire base and sub-grade from the weakening effect
of water.
Binder course
This layer provides the bulk of the asphalt concrete structure. It's chief purpose is to
distribute load to the base course The binder course generally consists of aggregates
having less asphalt and doesn't require quality as high as the surface course, so replacing
a part of the surface course by the binder course results in more economical design.
5.4. Spread asphalt material
-CEMENT
Cement is an essential ingredient in making the concrete as the material hardens with time and
Holds other particles in a definite relationship to each other it is a well binding material
When all the ingredients are mixed, the cement and water react together and the resulting
reaction products bind the sand and coarse aggregate together to form concrete
This reaction process is known as hydration.
There two states of concrete
Plastic state refers to the state of concrete before it has set and hardened.
During this state, concrete is placed in a formwork and compacted. It should be workable so that
it can be easily mixed, placed, compacted and finished at the surface. After the concrete has been
placed in the formwork, it hardens and gains strength. Hardened concrete should be durable,
impermeable and should have adequate strength.
Workability
Is defined as the property of concrete that determines the amount useful interval work needed to
Overcome internal friction between individual particles of mix to produce full compaction.
Factors affecting workability of concrete
Water cement ratio
Mix proportion
Surface texture of aggregates/shape
Size of aggregates
Temperature
Time
Segregation
It is a separation of coarse aggregate from mortar which results in their non- uniform distribution
(nonhomogeneous).
Causes of segregation
Difference in sizes of particles ingredients of concrete
Difference in specific gravities of ingredients of concrete
Improper mix proportions
Mixing of concrete
A thorough (careful) mixing of the materials is important for the production of uniform
concrete. The mixing should ensure that the mass becomes homogeneous, uniform in color and
consistency.
Concrete may be mixed on the site, or at works for precast concrete or for delivery to the site as
ready mixed concrete.
Methods of mixing concrete
Concrete can be mixed by two methods as follow:
Hand mixing
Machine mixing
1. Hand mixing
It is used for mix for small scale unimportant concrete works
Disadvantages
The concrete mix is not uniform
The concrete output is small
The time consumption is high
The quality of concrete is poor
2. Machine mixing
It is achieved by the use of concrete mixers at the construction sites for medium and large scale
mass concrete work.
Advantages of machine mixing of concrete
The concrete mix is uniform
Concrete output is large
Time consumption is less
Concrete quality is excellent
It is economical for large scale concrete work.
Leveling process
Setting out
Conduct concrete leveling to the layer level
Low modulus
silicone sealant
Preformed
Preparation of working place
Curing methods
Shading of concrete work
Covering concrete surfaces
Membrane curing
Steam curing
Ponding curing
Curing tank
Curing trucks
Curing of concrete
One of the most important operations in which concrete is kept continuously damp (wet) for
some days to enable the concrete to gain more strength. Under normal conditions it would be
expected to stay plastic for approximately 3-4 hours.
It can be described as the process of maintaining satisfactory moisture content and a favorable
temperature in concrete during the period immediately following placement, so that hydration of
Cement may continue until the desired properties are developed to a sufficient degree to meet
the requirement of service.
Curing replaces the loss of moisture from the concrete due evaporation, absorption and heat of
reaction.
Water Curing
This is by far the best method of curing as it satisfies all the requirements of curing, namely,
promotion of hydration, elimination of shrinkage and absorption of the heat of hydration.
Water curing can be done in the following ways:
1. Immersion
2. Spray water at regular intervals
3. Impounding water in earthen or sandy bunds in squares over the floors slabs
4. Spraying or Fogging
5. Wet Covering by putting saw dust, wet sand
The precast concrete items are normally immersed in curing tanks for a certain duration.
Pavement slabs, roof slab etc. are covered under water by making small ponds. Vertical retaining
wall or plastered surfaces or concrete columns etc. are cured by spraying water. In some cases,
wet coverings such as wet gunny bags, hessian cloth, jute matting, straw etc.,
Membrane Curing
Sometimes, concrete works are carried out in places where there is acute shortage of water.
Curing does not mean only application of water; it means also creation of conditions for
promotion of uninterrupted and progressive hydration.
Temperature curing or Application of heat
The development of strength of concrete is a function of not only time but also that of
temperature.
When concrete is subjected to higher temperature it accelerates the hydration process resulting in
faster development of strength.
The exposure of concrete to higher temperature is done in the following manner:
1. Steam curing at ordinary pressure
2. Steam curing at high pressure
3. Curing by Infra-red radiation
4. Electrical curing.
5. Hot water curing
1. Finishing of concrete
This is the last operation in production of concrete. Finishing does not apply to all concrete
operations.
For example, finishing may not apply to beam concreting while concrete road pavement
needs finishing.
Concrete is incapable of offering pleasant architectural appearance and finish. This disadvantage
of concrete is now being corrected and concretes these days are made to show pleasant surface
finishes.
The appearance of concrete members is governed by either surface finish, and this is influenced
by three main factors: colour, texture and surface profile.
Types of waste
Biodegradable waste
Chemical waste
Demolition waste
E-waste
Industrial waste
Recyclable waste
Removing method
Manual
Mechanized method
What is pavement
A structure consisting of superimposed layers of processed materials above the natural
soil subgrade, whose primary function is to distribute the applied vehicle loads to the sub-
grade.
The ultimate aim is to ensure that the transmitted stresses due to wheel load are suciently
reduced, so that they will not exceed bearing capacity of the sub-grade.
Types of Pavement
Two types of pavements are generally accepted namely flexible pavements and rigid
pavements.
PURPOSE OF PAVEMENT-
1. Load support.
2. Smoothness.
3. Drainage.
4. All weather operation.
5. Direction and guidance.
The main determining factors when designing a road pavement are as follows:
• quality of sub-grade soils,
• distance to appropriate building materials – and their resulting costs,
• amount and type of traffic (heavy or light),
• traffic projections,
• weather conditions,
• maintenance demand.
Pavement Types
Rural roads can be categorised according to the main building materials used in the pavement:
earth,
gravel or aggregate,
bituminous mixes,
concrete, and
stone or brick.
The term earth road is often used for any road without a bound surface layer, i.e. a road without a
bituminous or cement based surface treatment. Often, gravel surfaced roads are incorrectly
referred to as earth roads.
Flexible pavement
Flexible pavements are those which on a whole have low or negligible flexural strength and
rather flexible in their structural action under load
Load transfer:
The wheel load acting on the pavement will be distributed to a wider area, and the stress
decreases with the depth. Flexible pavement layers reflect the deformation of the lower layers on
to the surface layer
Contact pressure - It determines the contact area and the contact pressure between the
wheel and the pavement surface. For simplicity elliptical contact area is consider to be
circular.
Axle configuration - the axle configuration is important to know the way in which the
load is applied on the pavement surface.
Repetition of loads :Each load application causes some deformation and the total
deformation is the summation of all these. Although the pavement deformation due to
single axle load is very small, the cumulative effect of number of load repetition is
significant.
Therefore, modern design is based on total number of standard axle load (usually 80 KN single
axle)
Climatic Factor
1. Temperature -
Wide temperature variations may cause damaging effects.
Pavement becomes soft in hot weather and brittle in very cold weather.
2. Variation in moisture condition –
It depends on type of the pavement, type of soil type, ground water variation etc.
It can be controlled by providing suitable surface and subsurface drainage.
Design procedures for flexible pavements:
Mechanistic-empirical design
1. It can be used for both existing pavement rehabilitation and new pavement construction
2. It can accommodate changing load types
3. It uses material proportion that relates better with actual pavement performance
4. It provides more reliable performance predictions IRC:37-2012 is based on Mechanistic
Empirical Design
Failures of flexible pavements:
Different types of failure encountered in flexible pavements are as follow.
1) Alligator cracking or Map cracking (Fatigue)
2) Consolidation of pavement layers (Rutting)
3) Shear failure cracking
4) Longitudinal cracking
5) Frost heaving
6) Lack of binding to the lower course
7) Reflection cracking
8) Formation of waves and corrugation
9) Bleeding
10) Pumping
Wearing of the surface course along the wheel path resulting shallow ruts.
LONGITUDINAL CRACKING:
This types of cracks extents to the full thickness of pavement.
The following are the primary causes of longitudinal cracking.
Differential volume changes in subgrade soil
FROST HEAVING:
REFLECTION CRACKING:
This type of failure occurs, when bituminous surface course is laid over the existing cement
concrete pavement with some cracks. This crack is reflected in the same pattern on bituminous
surface.
9. BLEEDING:
10. PUMPING:
Seeping or ejection of water and fines from beneath the pavement through cracks is called
pumping
Flexible Pavements
• Flexible pavements will transmit wheel load stresses to the lower layers by grain-to-grain
transfer through the points of contact in the granular structure
The wheel load acting on the pavement will be distributed to a wider area, and the stress
decreases with the depth.
Jointed Plain Concrete Pavement: are plain cement concrete pavements constructed with
closely spaced contraction joints. Dowel bars or aggregate interlocks are normally used for load
transfer across joints. Theynormally has a joint spacing of 5 to 10m.
and spalling.
• The current practice is to provide these joints only when concrete slab
abuts with bridge or culvert.
• They allow expansion of slabs due to temperature
• They permit contraction of slabs Normal Details of these joints are given in
IRC:SP62.
• They are about 20 mm in width
• A joint filler board of compressible material conforming to IRC:SP:62 is used
to fill the gap between the adjacent slabs at the
• joint.
• The height of the filler board is such that its top is 23-25mm below the
surface of the pavement.
• The joint groove is filled by a sealant .
Construction joints
The need for such joint arises when construction work is
required to be stopped at a place other than the location of
contraction or an expansion joint, due to some breakdown of
the machinery or any other reason.
Such joints are of butt type and extend to the full depth of
the pavement.
The sealing of such joints shall be done in the same manner as
for contraction joints, by cutting a groove 10-12 mm wide and
20-25 mm deep.
Generally, such joints are avoided in highways. The work is
normally terminated at a contraction or expansion joint
Failure of Rigid Pavement
Fatigue crack
Pumping
Faulting
Spalling
Deterioration
Faulting
Two slabs next to each other have different levels
Pumping
• Pumping is the ejection of soil slurry through the joints and cracks of cement concrete
pavement, caused during the downward movement of slab under the heavy wheel loads.
Spalling
• Spalling, taking place at the transverse cracks or joints in Portland cement concrete
pavement, is a distress where a visible surface distress is caused by pieces of concrete being
dislodged from the surface of the pavement.
Deterioration
Friction
Friction between the wheel and the pavement surface is a crucial factor in the design of
horizontal curves and thus the safe operating speed. Further, it also act the acceleration and
deceleration ability of vehicles. Lack of adequate friction can cause skidding or slipping of
vehicles.
Skidding happens when the path traveled along the road surface is more than the
circumferential movement of the wheels due to friction
Slip occurs when the wheel revolves more than the corresponding longitudinal movement
along the road.
Various factors that affect friction are:
Type of the pavement (like bituminous, concrete, or gravel),
Condition of the pavement (dry or wet, hot or cold, etc),
Condition of the tyre (new or old), and Speed and load of the vehicle.
Drainage
The pavement surface should be absolutely impermeable to prevent seepage of water into the
pavement layers. Further, both the geometry and texture of pavement surface should help in
draining out the water from the surface in less time.
Camber
Camber or cant is the cross slope provided to raise middle of the road surface in the transverse
direction to drain of rain water from road surface. The objectives of providing camber are:
Surface protection especially for gravel and bituminous roads
Sub-grade protection by proper drainage
quick drying of pavement which in turn increases safety
Too steep slope is undesirable for it will erode the surface. Camber is measured in 1 in n or n%
The common types of camber are parabolic, straight, or combination of them
Kerbs
Kerbs indicate the boundary between the carriage way and the shoulder or islands or footpaths.
Different types of kerbs are
Low or mountable kerbs: these types of kerbs are provided such that they encourage the
traffic to remain in the through traffic lanes and also allow the driver to enter the shoulder
area with little difficulty. The height of this kerb is about 10 cm above the pavement edge
with a slope which allows the vehicle to climb easily. This is usually provided at medians
and channelization schemes and also helps in longitudinal drainage.
Semi-barrier type kerbs: When the pedestrian traffic is high, these kerbs are provided.
Their height is 15 cm above the pavement edge. This type of kerb prevents encroachment
of parking vehicles, but at acute emergency it is possible to drive over this kerb with
some difficulty.
Barrier type kerbs : They are designed to discourage vehicles from leaving the
pavement. They are provided when there is considerable amount of pedestrian traffic.
They are placed at a height of 20 cm above the pavement edge with a steep batter.
Submerged kerbs : They are used in rural roads. The kerbs are provided at pavement
edges between the pavement edge and shoulders. They provide lateral confinement and
stability to the pavement.