ESTIMATE
ESTIMATE
A. Materials
Portland cement 168.00 bags 330.00 55,440.00
Sand 10.00 cu.m 2,300.00 23,000.00
Gravel 19.00 cu.m 2,300.00 43,700.00
Sub-Total 122,140.00
B. Labor
Foreman 7.00 day/s 1.00 800.00 5,600.00
Skilled 7.00 day/s 4.00 600.00 16,800.00
Unskilled 7.00 day/s 6.00 400.00 16,800.00
Sub-Total 39,200.00
Wall Footing, Columns & Footings, Floor Slab, Roof Beam and Septic Tank
Wall Area
Total Wall Perimeter 61.00 m
Height 2.50 m
Area 153.00 sq.m
Eaves sq.m
Stairs sq.m
Septic Tank 35.00 sq.m
Area accummulated by Doors and windows sq.m
Total Wall Area 188.00 sq.m
CHB Laying
A. Materials
4''CHB 2,350.00 pcs 35.00 82,250.00
Portland Cement 62.00 bags 330.00 20,460.00
Sand 9.00 cum 2,300.00 20,700.00
Sub-Total 123,410.00
B. Labor
Foreman 7.00 day/s 1.00 800.00 5,600.00
Skilled 7.00 day/s 6.00 600.00 25,200.00
Unskilled 7.00 day/s 6.00 400.00 16,800.00
Sub-Total 47,600.00
Plastering
A. Materials
Portland Cement 170.00 bags 330.00 56,100.00
Sand 10.00 cum 2,300.00 23,000.00
Sub-Total 79,100.00
B. Labor
Foreman 5.00 day/s 1.00 800.00 4,000.00
Skilled 5.00 day/s 6.00 600.00 18,000.00
Unskilled 5.00 day/s 6.00 400.00 12,000.00
Sub-Total 34,000.00
D - 1, (4m x 2.10m) Double Bi-Fold Longspan Door on Steel Frame 4.00 set 10,000.00 40,000.00
Prepared by: