O & M Manual
O & M Manual
C ADPorts Projects
Contract No./Title: 4201-232
Operation and Maintenance Manual for Emergency Lighting System at (KLP 6& 7)
by M/s Manufacturer:- Shield & Supplier:- Naffco Electromechanical LLC (by NPC Infra)
Consultant/Contractor’s Project Manager: Code 4: Review not required. Work may proceed.
The statement "work may proceed" applies to the following work activities
associated with the matters contained within the contractor's document:
Eng.
A00 28-Sep-2022 Issued for Approval Eng. Laith Eng. Jasim
Awsam
Rev Date Reason For Revision Prepared Checked Approved
Holders of registered copies receive revisions to this document, should they occur, with a request that the superseded copy be destroyed. Registration of copies
eases at taking over date. The revision number is included at the end of the document number, which is noted in the right of the bottom of each page. When
amendments occur, the whole document is re-issued with the revision number updated accordingly.
(1) Revisions are shown in italics. Deletions are hidden. Earlier additions revert to normal text in subsequent amendments
(2) The QA Manager reviews and the project Manager approves amendments by signature on the cover sheet to the document
(3) The document controller maintains a Register of the holders of this document
(4) Amendments to the document are distributed according to (1) above and this I reflected in the register
The document controller keeps the original of the latest version of this document
Section 39
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
INDEX
1. INTRODUCTION TO SYSTEM
2. TECHNICAL & EQUIPMENT DATA
3. OPERATING PROCEDURES & INSTRUCTIONS
4. PREVENTIVE (SCHEDULED) & PREDICTIVE MAINTENANCE
5. CORRECTIVE MAINTENANCE
6. TESTING & COMMISSIONING REPORTS / CERTIFICATES
7. EQUIPMENT GUARANTEES & WARRANTY CERTIFICATES
8. SPARE PARTS & LIST OF EQUIPMENT
9. AS BUILT DRAWING (A3)
10. TRAINING MATERIAL
11. MANUFACTURER & SUPPLIER CONTACT DETAILS
12. MANUFACTURER’S LITERATURE & VENDOR USER MANUALS
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Section 39.1
INTRODUCTION TO SYSTEM
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
32.1.1 PROJECT OVERVIEW
The project for the Design and Construction of KIZAD Critical Warehousing
Capacity Enhancement Project for Abu Dhabi Ports is located at KIZAD, Abu Dhabi.
The whole project is compromised of the following Buildings.
KLP 21 Buildings 1, 2 ,3 & 4, KLP 4 & 5 Buildings 1, ,2, 3, 4, 5, 6, 7, 8, 9, 10, 11 & 12
KLP 6 & 7 Blocks A, B, C, D, E & F The new Warehouses located at Kizad,
Taweelah, Abu Dhabi is on a site with a gross area of approximately 609,071,35
m² with a built-up area of 219,715.50 m²
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
32.1.2 PROJECT STAKEHOLDERS
PROJECT ORGANIZATIONS
STAKEHOLDERS
CLIENT Abu Dhabi Ports Group
P.O. Box: 54477 Abu Dhabi, UAE Telephone: + 971 2
695 2000 (HQ)
Telephone: + 971 2 800 2030
KIZAD
Al Samha, Abu Dhabi – UAE
Tel: 800 10 20 30
Email : [email protected]
Website: www.adports.ae
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
32.1.3- INTRODUCTION TO SYSTEM
The purpose of this Operation and Maintenance manual is to offer the personnel
concerned with the operation and maintenance of the CENTRAL BATTERY SYSTEM
within the building, assistance in the performance of their duties. It is intended that this
manual will be used to assist skilled engineers, experienced in the operation and
maintenance of building services, to provide them comprehensive working knowledge
of the various system installed within the project. Although the manual functions as a
complete entity, each section is self-contained and provides information on differing
aspects of the installation. Familiarization with all sections prior to formulating an
operating and maintenance regime will prepare the building maintenance personnel for
the occasions when a particular problem occurs.
The information within this manual will allow maintenance to be carried out safely and
reliably, as well as providing important data upon which calculations may be made for
design of alterations and/or additions, should the need arise.
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Emergency Lighting System
Section 39.2
TECHNICAL & EQUIPMENT DATA
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
TECHNICAL & EQUIPMENT DATA
EMERGENCY LUMINAIRES
EXIT LUMINAIRES
15 EXIT LIGHT, 5.2W HANGING TYPE, IP64 SHIELD NAFFCO X10UL + LX10 + 2PW
17 EXIT LIGHT, 3.15W RECESSED TYPE, IP43 SHIELD NAFFCO X30UL + RFX30
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Section 39.3
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Central Power Supply System ML96 Series
Setup & Commissioning
illustration
Manufacturer No.:
Commissioning / Object:
Device No:
Contents
1 General ............................................................................................................................................................................ 5
1.1 Further applicable documents ................................................................................................................................................... 5
1.2 Liability and warranty ................................................................................................................................................................ 5
1.3 Copyright protection ................................................................................................................................................................. 5
1.4 Spare parts............................................................................................................................................................................... 5
1.5 Disposal ................................................................................................................................................................................... 5
2 Safety .............................................................................................................................................................................. 6
2.1 Content of the instruction manual ............................................................................................................................................. 6
2.2 Changes and modifications of the system .................................................................................................................................. 6
2.3 Responsibility of the operator.................................................................................................................................................... 6
2.4 Staff requirements .................................................................................................................................................................... 6
2.5 Safety at work ........................................................................................................................................................................... 7
2.6 Personal protection equipment ................................................................................................................................................. 7
3 Preface ............................................................................................................................................................................ 8
3.1 Installation location and environmental conditions .................................................................................................................... 8
4 Danger and information signs............................................................................................................................................. 9
5 Scope of delivery............................................................................................................................................................. 10
6 System overview ............................................................................................................................................................. 11
6.1 Overview electronic housing back view..................................................................................................................................... 12
7 Mounting and installation of the power supply system ........................................................................................................ 13
7.1 Connection of the charger and switch unit ............................................................................................................................... 13
7.1.1 Mains connection (terminal X01) ...................................................................................................................................... 13
7.1.2 Battery fuse ...................................................................................................................................................................... 13
7.1.3 Battery connection (terminal X21) ..................................................................................................................................... 13
7.1.4 Outgoing substation – ABUS (terminal X3x) ....................................................................................................................... 14
7.1.5 Outgoing sub-distributor - ABUV (terminal X4x).................................................................................................................. 14
7.1.6 Outgoing sub-distributor – single wire supply – ABUV-E (terminal X4x) ............................................................................... 14
7.1.7 SDM24 switching inputs (terminal X03) ............................................................................................................................ 15
7.1.8 Ethernet interface (terminal X10) ...................................................................................................................................... 15
7.1.9 Switch contacts (terminal block X02) ................................................................................................................................ 16
7.1.10 2nd error messages (terminal X18) (optional) .................................................................................................................... 17
7.1.11 Error messages 2nd SIOM (terminal X19) (optional) ........................................................................................................... 17
7.1.12 Critical circuit (terminal block X22 F7/F8, optional CCIF) .................................................................................................. 18
7.1.13 Bus-compatible modules (terminal block X07) .................................................................................................................. 18
7.1.14 Output circuits (terminal block X30) .................................................................................................................................. 19
7.2 Mounting and installation of the battery system ....................................................................................................................... 20
7.2.1 Mounting ......................................................................................................................................................................... 20
7.2.2 Battery connection ........................................................................................................................................................... 21
7.2.3 Connection of the battery blocks ....................................................................................................................................... 22
8 Commissioning of the power supply system ....................................................................................................................... 23
9 Setting up your system..................................................................................................................................................... 24
9.1 General operating instructions ................................................................................................................................................ 24
9.2 System state........................................................................................................................................................................... 25
9.3 Selecting circuits and checking their state ............................................................................................................................... 26
Central Power Supply System ML96 Series
Page 4 Setup & Commissioning
9.4 Viewing and changing of the circuit setup ................................................................................................................................ 27
9.4.1 Setting the circuit monitoring mode .................................................................................................................................. 28
9.4.2 Programming the SDM-module ......................................................................................................................................... 28
10 Tests .............................................................................................................................................................................. 29
10.1 Execution of a function test ..................................................................................................................................................... 29
10.2 Programming automatic function tests .................................................................................................................................... 30
10.2.1 Setting the schedule ......................................................................................................................................................... 30
10.2.2 Setting the current monitor window ................................................................................................................................... 30
10.2.3 Activating/deactivating the preheating phase and finishing the programming .................................................................... 31
10.3 Execution of a capacity test ..................................................................................................................................................... 31
10.4 Test results ............................................................................................................................................................................. 32
10.5 Reset errors ............................................................................................................................................................................ 32
10.6 Checking the state of the charger ............................................................................................................................................ 33
10.7 System information & system log ............................................................................................................................................ 33
11 De-energising the power supply ........................................................................................................................................ 36
12 The central control and monitoring unit ............................................................................................................................. 37
12.1 Menu – quick reference guide ................................................................................................................................................. 38
13 Operation, maintenance and servicing of the batteries ........................................................................................................ 39
13.1 Charging and discharging ....................................................................................................................................................... 39
13.2 Recommended working temperature ....................................................................................................................................... 39
13.3 Servicing and inspections ....................................................................................................................................................... 40
13.4 First inspection ....................................................................................................................................................................... 40
13.5 Repeating inspection .............................................................................................................................................................. 41
13.6 Inspection before commissioning ............................................................................................................................................ 42
13.7 Procedure in case of failure ..................................................................................................................................................... 43
13.8 Decommissioning, storing and transport ................................................................................................................................. 43
14 General information on your system .................................................................................................................................. 44
14.1 Used battery type .................................................................................................................................................................... 44
15 Technical data ................................................................................................................................................................ 45
16 Module descriptions........................................................................................................................................................ 47
16.1 Electric circuit module SCM .................................................................................................................................................... 47
16.2 Charger module SLDM ............................................................................................................................................................ 47
16.3 Input/Output-module ............................................................................................................................................................. 48
16.4 Switch query module SDM24 (optional)................................................................................................................................... 48
16.5 ML96 Series Line Monitor SLM (optional) ................................................................................................................................ 48
16.6 SPC230 (optional) .................................................................................................................................................................. 49
16.7 SLCD15(S) / SLCD15U(S) (optional) ....................................................................................................................................... 49
17 Connection examples ...................................................................................................................................................... 50
18 Revision history............................................................................................................................................................... 56
19 Circuit table.................................................................................................................................................................... 57
20 Measurement protocols battery ........................................................................................................................................ 60
Central Power Supply System ML96 Series
Setup & Commissioning
1 General
This instruction manual is aimed at electrically skilled people according to DIN VDE 0105 or authorised technical staff and explains the safe
and professional handling of the central battery system. The general safety regulations and the local accident prevention regulations which
are valid for the area of use as well as safety instructions have to be observed. The instruction manual, especially the chapter safety, has to
be read completely prior to any works on the system.
Components from other manufacturers are mounted in the systems. The manufacturers of these components carried out a hazard assessment
and declared their compliance with existing European and national regulations.
This instruction manual was created considering existing standards. It has to be kept near the system and easily accessible for all staff working
on and with the system.
Additionally, all laws, standards and regulations of the country, in which the system is mounted and operated, have to be observed.
The manufacturer does not assume liability or warranty for damages or consequential damages occurring through:
non-intended use
non-authorised or non-professional changes of the connections, settings or programming of the system
non-observance of rules and regulations for safe operation
Operation of unauthorised or unsuitable devices on the Low Power System
Only original spare parts of the manufacturer must be used. Wrong or defective spare parts can lead to damages, malfunctions or total failure
of the system. Furthermore, the use of unauthorised spare parts voids all guarantee, warranty, service, compensation, and liability claims.
1.5 Disposal
Packaging materials are no waste but reusable materials which have to be recycled.
Batteries and electronic components contain materials which can lead to damages to health and the environment when inappropriately dis-
posed. National rules and regulations for the appropriate disposal of used batteries and electronic components have to be observed!
Central Power Supply System ML96 Series
Page 6 Setup & Commissioning
2 Safety
The group supply system is safe to operate and complies with valid and recognised rules of engineering at the time of its development and
production. There is, however, the risk of danger when the system is used by non-professional staff or when it is used in a non-professional or
non-intended way.
The system and the connected parts must only be operated in perfect condition. The following have to be observed:
safety instructions and hazard notes in the instruction manual
specified work and safety instructions of the operator
Errors which influence the function or safety of the system have to be reported to the responsible person and cleared immediately.
Each person working on or with the system has to read and understand the instruction manual completely prior to any work on the system or
battery, even when this person has already worked with this system or a similar one or has been trained by the manufacturer.
Any changes or extensions to the system, which are not authorised by the manufacturer, are prohibited in order to avoid hazards and to guar-
antee an optimal performance of the system. Extensions, modifications or maintainance works, which are not described in the instruction
manual, have to be carried out by trained service personnel only!
As described in point 1.2, this instruction manual has to be kept near the system and easily accessible for all staff working on and with the
system.
The system must only be operated in technically perfect and operationally reliable condition. Additionally, prior to its commissioning, the
system has to be checked for intactness.
Only skilled technicians or authorised qualified personnel are permitted to work on or with the system after being briefed about possible
hazards.
Staff are considered qualified if they are able to judge the work to be done and recognise possible hazards based on their training, expertise
and experiences as well as their knowledge of the respective regulations.
If the staff lacks the necessary knowledge, they need to get a professional instruction. You also have to make sure that the tasks are clearly
defined and understood and the works are carried out under supervision of skilled technicians.
Central Power Supply System ML96 Series
Setup & Commissioning Page 7
Observance of safety notes and instructions is the basis of safe working and thus damage to persons and property while working on and with
the system can be avoided.
Always wear protection gear while working on and with the system:
protective clothing (tight-fitting, low tensile strength, no wide sleeves, no rings or other jewellery)
safety shoes (ESD-shoes according to standard EN 345)
Central Power Supply System ML96 Series
Page 8 Setup & Commissioning
3 Preface
Thank you very much for buying an “ML96 Series” power supply system with central battery! This system complies with the standards DIN EN
50171, DIN VDE 0108-100 as well as DIN VDE 0100-718 (versions relevant on delivery) and guarantees the correct functioning of your emer-
gency lighting system by means of a state-of-the-art micro-processor-controlled function control system. This documentation has been cre-
ated for you to quickly commission and operate the system in an uncomplicated way.
Chapter 12 provides a description of the central control unit and a menu – quick reference guide. Instruction for operation and maintenance
of the batteries as well as the technical data of the system you can find in chapters 13 and 14. The exact circuit diagram along with other
information on your system can be found in the separate document “Information on your ML96 Series”.
Note: The table in chapter 14 with the key data of the batteries used in the system has to be completed by the installer.
Note: For maintenance works and modifications the system has to be de-energised by a specialist. The necessary steps are described in
chapter 0.
Note: Instructions regarding the programming of the system by means of the WebInterface can be found on the web homepage of the manu-
facturer.
The system and the battery system can be operated at an altitude of up to 2000m above standard elevation zero, without any power reduction,
and must be placed in an appropriate room satisfying the following environmental condition:
When selecting the operation room, make sure that sufficient ventilation according to DIN VDE 0510; EN 50272-2 and EltBauVO is assured.
Also, please make sure that the room fulfills the conditions corresponding to the protection class of the system (see DIN EN 60529 and
60598).
Note: The power and capacity of the battery system depends on the temperature. The recommended temperature range is 10°C to 30°C, the
ideal operating temperature is 20°C ± 5K. Technical data given is valid for a nominal operating temperature of 20°C.
Note: The system must be located in the building such that the allowed cable lengths allowed for emergency lighting circuits will not be ex-
ceeded (see chapter 7.1.14).
Central Power Supply System ML96 Series
Setup & Commissioning Page 9
Please strongly obey the safety instructions when installing and using your ML96 Series system.
Observe instructions and keep them located near the battery system for future reference!
Work on the battery system should only be carried out by qualified personel!
No guaranty in cases of non-observance of instruction manual, repair using non-original parts or unauthor-
ised intervention!
Do not smoke! Do not use any naked flame or other sources of ignition. There is the danger of explosion
and fire hazards!
While working on batteries wear protective eye-glasses and clothing!
Observe the accident prevention rules as well as DIN VDE 0510, VDE 0105 part 1 (version relevant on
delivery)!
Any acid splashes on the skin or in the eyes must be flushed with plenty of water immediately. Then
seek medical assistance. Spillages on clothing should be rinsed out with water!
Explosion and fire hazard, avoid short circuits! Caution! Metal parts of the battery are always e ne r -
g i s e d ; therefore do not place items or tools on the battery!
Electrolyte is strongly corrosive and acidic. In normal working conditions the contact with electrolyte i s
nearly impossible; electrolyte may leak from the vent valves in case of overcharging the battery or in
case of mechanical damage to the container. In case of any contact with electrolyte please flush with
water abundantly and seek medical assistance.
Batteries / cells are heavy! Ensure adequate mounting security and always use adequate handling
equipment for transportation.
Disposal of batteries
Batteries marked with the recycling symbol should be processed via a recognised recycling agency. By
agreement, they might be returned to the manufacturer. Batteries must not be mixed with domestic or
industrial waste.
Central Power Supply System ML96 Series
Page 10 Setup & Commissioning
5 Scope of delivery
Other tools and materials necessary for installation (brought by the installer):
6 System overview
1
2
3
illustration illustration
*similar to illustration
Central Power Supply System ML96 Series
Page 12 Setup & Commissioning
6.1 Overview electronic housing back view
13
14
15
illustration illustration
*similar to illustration
Central Power Supply System ML96 Series
Setup & Commissioning Page 13
Make sure that the mains power line is de-energised and dimensioned accord-
L1 L2 L3 N PE L1 L2 L3 N
ing to the maximum connected load. Connect the mains line to the mains ter-
minals (Fig. 2; Number 5) for which you have to remove the mains fuses.
F1
Caution: The mains power line gets energised at a later time (see chapter 8).
X01
X01
L1
L2
L3
N
N
System type L1 L2 L3 type
ML96 Series
The following table shows the type of the battery fuse (D02 Innozed or NH00)
for the systems ML96 Series in Ampere. The type is depending on the size of
the battery fuse.
F2 / B+ F3 / SYM F4 / B-
F11
F10
F11
X21
X21
ML96 Series
Connect appropriately labelled cables to the three contacts (B+, B- and SYM) B+ B- SYM
of the battery connection as shown in Fig. 7, which are then led to the battery
system (see chapter 7.2).
B+
B-
The ABUS is used for the protected voltage supply of a substation and is
B+ B- LDM+
mounted in the main unit of a system. The ABUS consists of the terminals for
AC supply (L1, L2, L3, N, PE), DC supply (B + / B-) and the start signal (SLDM L1 L2 L3 N
+). The backup dimensioning of the ABUS is stored in the technical data. It is
LDM+
B+
B-
not permissible to disconnect the AC supply of the substation from the local
general light distributor! Since the line cross section depends on both the fuse
dimensioning and the connection power and the cable length, this must be de-
F9x
X3x
L1
L2
L3
fined by the installer.
N
A port or terminals for networking are not provided for the ABUS; networking is
done via the internal port or switch (X10).
The network is networked and is used to monitor the substation (s) through the Fig. 8: Outgoing substation - ABUS
main unit.
Note: If there are several outgoings, please refer to the attached circuit diagram
documents for the fuses from the fuse list.
The ABUV is used for the protected voltage supply and data transmission of a B+ B-
ML96 Series sub-distributor (MC-UV) and is mounted in the main unit of a sys-
tem assembly. The ABUV consists of the terminals for AC supply (L1, L2, L3, N, L1 L2 L3 N
PE), DC supply (B + / B-) and the terminals for the data line. The fuse dimen-
B+
B-
sioning of the ABUV is stored in the technical data. The AC supply of the MC-UV
on the local general light distributor is not permitted! Since the line cross sec- 1 4
tion depends on both the fuse dimensioning and the connection power and the
X3x
2 5
3 6
L1
L2
L3
Note: If there are several outgoings, please refer to the attached circuit diagram
documents for the fuses from the fuse list.
The ABUV-E is used for the protected voltage supply and data transmission of L/+ N/- PE
a ML96 Series sub-distributor (MCUV-E) and is mounted in the main unit of a
system assembly. The ABUV-E consists of the terminals for AC/DC supply (l/+
/ N/-) and the terminals for the data line. For the power supply of the MCUV-E,
only a 3-wire cable is required in this system. The fuse dimensioning of the
ABUV-E can you find in the technical data. Because the cable cross-section de-
SC
X4x
+12V
GND
pends on the fuse dimensioning, as well as on the connected load and cable
L/+
N/-
B
A
Note: If there are several outgoings, please refer to the attached circuit diagram
documents for the fuses from the fuse list.
Fig. 10: Outgoing sub-distributor single wire
supply – ABUV-E
Central Power Supply System ML96 Series
Setup & Commissioning Page 15
24V
responding number of three-pole terminals are available to which the switch-
ing voltage (220 / 230V 50 / 60Hz, 24-255V DC) is to be connected.
GND
E02
E03
E05
E06
E08
E04
E07
E01
A switching voltage of 24V DC is provided at an additional terminal.
X03
Optionally, the integrated 3-phase mains monitor as well as the COM port2
can be provided on terminals.
The ML96 Series system has an Ethernet interface by means of which it can be
embedded in a network for remote monitoring. Fig. 12 shows the network con-
nection inside the cabinet. Please use standard network cable (Cat. 5 / RJ45)
for connection. 100
1
+
The simple adapter is installed as standard. Optionally, the installation of a
switch is possible (in conjunction with Panel-PC, GLT or networking of systems) 2
X10
3
X10
The network connections of the ML96 Series have the following characteristics:
4
• 10Mbps 5
• Half-duplex LNK/ACT
voltage supply:
F5 GND (positive potential)
LUAN1
LUAN2
LUAN3
F6 -24V DC (negative potential)
de-energised contacts:
contact 1/2 closed: malfunction
contact 2/3 closed: system works properly
contact 4/5 closed: battery operation
contact 5/6 closed: mains operation 1 4 7 14 30
contact 7/8 closed: ready to operate
F5
F6
X02
2 5 8 10 15 16 16 31 L1 N
contact 8/9 closed: charging mode
3 6 9 11 17 17 L2 L3
contact 16/17 closed[1][3]: fan control de-energised (LUAN1)
energised contacts:
contact 10/11 [1]: battery cabinet temperature sensor
contact 14/15 closed: system in charging mode
contact 16/17 closed[1]: fan control single-phase (LUAN2)
contact 30/31 closed: configurable
Fig. 13: Switch contacts
contact L1/L2/L3/N [1]: fan control three-phase (LUAN3)
[1] optional
[3] Fan control active: while fast charge + 10min follow up time
de-energised contacts:
X18
2 5 8
de-energised contacts:
2 5 8 11
The critical circuit is used to monitor a residual current / mains monitor loop
about SPC230 line monitors. When a mains monitor is triggered, emergency
operation (mod. management [AC]) is triggered in the entire system.
CCIF
CCIF: The CCIF is available as an option and registers both the interruption of
the network monitoring loop and the clumping (termination on the line) and
F7
F8
X22
triggers emergency operation in the system.
The voltage on the line monitor loop is 24V DC. Fire-resistant cable material is +
not necessary.
Please note the product information.
C
Applying voltage to these terminals is not permitted and will destroy the sys-
tem! -
SC
+12V
X07
GND
GND
B
B
A
Note: During all installation work on the RS485 bus (add / remove modules
and address changes), the device must be switched completely free of voltage.
Fig. 18 shows the terminal block X30 to which the consumer circuits (luminaires) can be connected. Pay attention to the correct polarity and
use mains-compatible cables; comply with the standards MLAR, EltBauVo as well as DIN VDE 0100.
Note: The circuits to be connected have to be checked for installation errors such as short circuit and earth fault prior to connection.
Note: Maximum cable length of 500m and maximum 20 luminaires per final circuit.
...
K02
K03
K05
K06
K08
K09
K04
K12
K07
K10
K01
K11
Kxx
X30
Mount the battery rack and position it at the designated place. When choosing the battery room, pay attention to sufficient ventilation ac-
cording to DIN VDE 0510; EN 50272-2 and EltBauVO (versions relevant on delivery). Now place the battery blocks on the respective level in
the battery rack. The temperature difference between the individual battery blocks must not exceed 3°C.
Note: Before commissioning all blocks have to be checked for mechanical damage, correct polarity and that the cables are firmly connected.
26 165*176*127 M5 6 D x
RV165: 15*350mm
EVL165: 2*1000mm
RV165: 15*350mm
EVL165: 2*1000mm
RV165: 15*350mm
EVL165: 2*1000mm
X X
RV165: 15*350mm
EVL165: 2*1000mm
28 165*125*175 M5 6 x
RV165: 15*350mm
EVL165: 2*1000mm
RV165: 15*350mm
EVL165: 2*1000mm
RV165: 15*350mm
EVL165: 2*1000mm
X X
RV165: 15*350mm
EVL165: 2*1000mm
RV166: RV166: RV166: RV166:
33 195*130*155 M6 16 C x
15* 350mm
EVL166:
15* 350mm
EVL166:
15* 350mm
EVL166:
X X
15* 350mm
EVL166:
2* 1000mm 2* 1000mm 2* 1000mm 2* 1000mm
RV166: RV166: RV166: RV166: RV166:
40 197*165*170 M6 16 x
15* 350mm
EVL166:
15* 350mm
EVL166:
15* 350mm
EVL166:
12* 350mm
EVL166:
X
15* 350mm
EVL166:
2* 1000mm 2* 1000mm 2* 1000mm 5* 1000mm 2* 1000mm
D RV166: RV166: RV166: RV166:
45 197*165*170 M6 16 x
15* 350mm
EVL166:
15* 350mm
EVL166:
15* 350mm
EVL166:
X X
15* 350mm
EVL166:
2* 1000mm 2* 1000mm 2* 1000mm 2* 1000mm
RV166: RV166: RV166: RV166: RV166:
50 257*132*200 M6 16 x x
15* 350mm
EVL166:
15* 350mm
EVL166:
12* 350mm
EVL166:
12* 350mm
EVL166:
15* 350mm
EVL166:
2* 1000mm 2* 1000mm 5* 1000mm 5* 1000mm 2* 1000mm
RV166: RV166: RV166: RV166: RV166: RV166:
55 229*138*208 M6 16 x
15* 350mm
EVL166:
15* 350mm
EVL166:
15* 350mm
EVL166:
12* 350mm
EVL166:
12* 350mm
EVL166:
15* 350mm
EVL166:
2* 1000mm 2* 1000mm 2* 1000mm 5* 1000mm 5* 1000mm 2* 1000mm
RV166: RV166: RV166:
60 260*168*211 M6 16 x x x x
12* 350mm
EVL166:
12* 350mm
EVL166:
15* 350mm
EVL166:
5* 1000mm 5* 1000mm 2* 1000mm
RV166: RV166: RV166:
65 350*167*179 M6 16 x x x x
12* 350mm
EVL166:
12* 350mm
EVL166:
15* 350mm
EVL166:
5* 1000mm 5* 1000mm 2* 1000mm
RV166: RV166: RV166:
75 260*168*211 M6 16 x x x x
12* 350mm
EVL166:
12* 350mm
EVL166:
15* 350mm
EVL166:
5* 1000mm 5* 1000mm 2* 1000mm
RV265: RV265: RV265:
80 260*168*211 M6 16 x x x x
12* 450mm
EVL265:
12* 450mm
EVL265:
15* 450mm
EVL265:
5* 1000mm 5* 1000mm 2* 1000mm
RV265: RV265: RV265:
90 306*169*211 M6 16 C x x x x
12* 450mm
EVL265:
12* 450mm
EVL265:
15* 450mm
EVL265:
5* 1000mm 5* 1000mm 2* 1000mm
RV265: RV265: RV265:
100 330*171*214 M8 25 x x x x
12* 450mm
EVL265:
12* 450mm
EVL265:
15* 450mm
EVL265:
5* 1000mm 5* 1000mm 2* 1000mm
RV265: RV265: RV265:
110 330*171*214 M8 25 x x x x
12* 450mm
EVL265:
12* 450mm
EVL265:
15* 450mm
EVL265:
5* 1000mm 5* 1000mm 2* 1000mm
3*BATT9 2*BATT18
120 409*176*225 M8 25 x x
K25: 1*3000mm
RV258: 9*450mm
x
K25: 1* 3000mm
RV258: 12*450mm
RV258: 12*450mm
EVL258: 5*1000mm
x
EVL258: 7*1000mm EVL258: 4* 1500mm
2*BATT18
134 342*172*280 M8 25 x x x x
K35: 1* 3000mm
RV358: 12*450mm
RV358: 12*450mm
EVL358: 5*1000mm
X
EVL358: 4* 1500mm
2*BATT18
3*BATT9
K35: 1* 3000mm
150 485*172*240 M8 35 x x
K35: 1*3000mm
RV358: 9*450mm
x RV358: 6*450mm
RV358: 12*450mm
EVL358: 5*1000mm
X
EVL358: 10*
EVL: 7*1000mm
1000mm
3*BATT18
180 530*172*240 M8 35 x x x x K35: 2*3000mm
RV358: 12*450mm
EVL358: 5*1000mm
x
EVL358: 15*1000mm
3*BATT18
200 522*238*218 M8 25 x x x x
K35: 2* 3000mm
EVL358: 15*
RV358: 12*450mm
EVL358: 5*1000mm
X
1000mm
E 3*BATT18 2*BAT20
260 521*269*220 M8 25 x x x x
K50: 2* 3000mm
EVL508: 15*
K50 : 1*3000mm
RV508: 6*450mm
X
1000mm EVL508: 10*1000mm
Central Power Supply System ML96 Series
Setup & Commissioning Page 21
B+ SYM B-
1 2 3
- - -
+
+
6 5 4
- - -
+
7 8 9
- - -
+
+
+
12 11 10
- - -
+
13 14 15
- - -
+
+
+
18 17 16
- - -
+
Disconnect the battery fuses by opening F2 and F4. Connect the battery blocks in series as shown in Fig. 19. Afterwards connect the cables
coming from F2 (Fig. 2, Number 12) as illustrated Fig. 19 (red = B+/positive pole to the positive pole of block 1, grey = symmetry to the
negative pole of block 9 and blue = B-/negative pole to the negative pole of block 18). If necessary, put on the pole covers.
After correct connection of the cables the following measurements should be carried out:
Open the housing for commissioning the system. Fig. 2 schematically shows the view of an open system cabinet. Continue as follows (the
numbers in brackets refer to Fig. 1 and Fig. 2):
1. Operation mode switch to charging mode. Turn the operation mode switch (Fig. 1, Number 1) to charging mode (position „0“).
2. Connect battery fuses. Connect the battery fuses (Fig. 2, Number 12) again by closing F2.
3. Supply mains power. Supply mains power and check the power terminals for correct configuration by conducting the below-listed meas-
urements. In case of a misconfiguration (connection error) abort commissioning:
4. Connect mains fuses. Connect the mains fuses (Fig. 2, Number 5) by closing F1. The system is now activated.
5. Await the end of the boot process. After switching on the system (accoustic signal) it starts booting. This process can last several minutes.
During and after the boot process the LC-Display should show the following (see Fig. 20):
6. Check battery voltage. Check the battery voltage by means of the status information in the LC-Display. It should range from 192V to 250V
(Fig. 20, right picture, arrow).
7. Operation mode switch to “ready-to-operate”. Turn the operation mode switch (1) to “ready-to-operate” (position “1”). This activates the
electric circuits (by default maintained lighting).
Caution: Make sure that nobody works on the electric circuits before switching the system on as circuits in maintained lighting
mode get energised when activated. If there are still circuits that are worked on, remove the respective fuses before switching
on the system.
8. Check voltage at circuit outputs. By default all end circuits are configured as maintained lighting mode.
Check the voltage on all circuit connection terminals (7) (see also chapter 7.1.14, Fig. 18). The measured voltage on each circuit and connec-
tion in maintained lighting should correspond to the mains voltage.
9. Check the battery for sufficient capacity. During battery discharge, the system must be operated with the actual load for the specified time.
A manual capacity test is recommended (see 10.3). The results are to be logged. Systems which do not pass this test must be repeat the test.
If the repeat test is not sufficient, the system must not be put into operation (see measuring protocol battery).
Central Power Supply System ML96 Series
Page 24 Setup & Commissioning
9 Setting up your system
9.1 General operating instructions
Your system can be operated and configured completely via the front control
elements (Fig. 21). For text input (e.g. circuit denomination) we recommend
connecting an external keyboard to the PS2-interface (1). MMC
NETZ/
MAINS +24V
ETHERNET
BATTERIE/
BATTERY +5V
STÖRUNG/
FAILURE +12V
The LCD-screen (2) displays Menues and Informationen. In the bottom line you
LADUNG/
CHARGE -12V
TIEFENTLADUNG/
DEEP DISCHARGE
can see – if active – the softkey functions which are reachable via the 3 softkeys
(3) (Fig. 22). For navigation and data input please use the arrow keys ˂,˃, ˄
Erdschluss/earth fault
TEST
and ˅ (4) as well as the enter key (5). The up˄and down˅ keys are mostly
used for selecting menus and input fields. A selected menu item is indicated
by inverted colouring. The right ˃ and left ˂ keys are used to change values; in
some cases you have to confirm your input with the enter key . An arrowhead 1 2 3 4 5
> on the right indicates a submenu which can be selected with the right ˃ or
enter key. You can return from there using the softkey back or done. Fig. 21: Control elements
The following paragraphs give some basic instructions for configuring your sys-
tem. The LCD-screen shows the necessary functions which can be navigated to
and then selected. The line under the headline of each paragraph describes
how to get to the required menu item:
Central Power Supply System ML96 Series
Setup & Commissioning Page 25
After commissioning the LC-display shows the state of the system (Fig. 22) i.e.
time: 08:00 ─1
time (1) and date (2), current battery voltage (3) and battery charging current 01.01.17 ─2
(in battery operation – discharging current) (4), system state (5, 6). Via the soft- battery: 245.0 V ─3
keys (8) you can select the help-function, conduct a test or reach the 0.0 A ─4
menu. state: mains ok ─5
off (charging) ─6
─7
Note: The system returns from each display to the status after ca. two minutes test menu ─ 8
if no input is made.
Status Explanation
Zeile 5
mains ok mains connected and OK
mains failure mains voltage failed
Zeile 6
(off) charging luminaires switched off, emergency operation blocked, battery is being charged
operational maintained lighting luminaires (DS) switched on, emergency operation possible
off mains failure, but no emergency operation possible
active (battery) mains failure, emergency operation active
active (mains) all luminaires with mains connection on
line 7 (if required, additional messages possible)
crictical circuit break of quiescent current loop
SDM 1 E 1 or similar modified non-maintained lighting activated by SDM or SLM (text configurable)
RS485 fault failure of RS485 bus interface
earth fault earth fault in mains operation
earth fault (B) earth fault in battery operation
maintenance required carry out maintenance (service)
deep discharge 1 battery deeply discharged
charger fault charger module failed/fuse activated
Plug & Play error wrong component used
SCM fault SCM failed
ACM fault ACM failed
SIOM fault SSIOM failed
battery fuse battery fuse defect
battery voltage battery voltage out of tolerance
battery current battery current out of tolerance
battery discharge battery is being discharged in mains operation
luminaire fault luminaire failure after testing
luminaire current fault total current value out of set tolerance
circuit fault error in electric circuit (fuse activated etc.)
sub-station fault (communication) failure of sub-station
sub-station mb sub-station in modified non-maintained operation
sub-station mains fail mains failure of sub-station
fan failure fan failed
batt. temp. sensor temperature sensor inserted
internal fan failure internal fan
external fan failure external fan
UV-C failure failure of sub-distributor
UV-C mains failure mains failure of sub-distributor
battery symmetry battery symmetry unbalanced
SIOM fault SIOM module fault
test locked test blocked by boost charge, battery voltage or emergency operation
system temperature system temperature >55°C
circuits unpowered end circuits and test locked
L1/L2/L3/N failure voltage on neutral conductor
test aborted Function-/capacity test is aborted (mains failure, …)
Central Power Supply System ML96 Series
Page 26 Setup & Commissioning
9.3 Selecting circuits and checking their state
State INFO-pushbutton SCM (select circuit)
The electric circuits are numbered beginning with 1; each SCM-module has two
circuits named A and B. The circuits are numbered according to their slot posi- SCM SCM SCM
S8
tion from left to right, so that the A-circuits have an uneven and the B-circuits S7
S6
S5
1 3 5
S4 A A A
an even number Fig. 23. If a slot is not used, the respective circuit numbers do S3
S2
S1
not exist either. This means you can add circuits to the system without changing
E2
E4
A7
A6
INFO-pushbutton SCM-modules
After pressing the INFO-pushbutton on the SCM-module (Fig. 23), the display
shows the status of the respective circuits. Now the display shows the following ------ SCM 42 -------
information for circuits A and B (Fig. 24): A: circuit 1 >
P = 0W ( 0W) ─ 1
1 – circuit number ok ─2
2 – current output (in brackets: reference value for the circuit monitoring) B: circuit 2 >─ 3
3 – status of the circuit P = 0W ( 0W) ─ 1
ok ─2
The number of the selected circuit is marked by inverted colouring (Fig. 24 for test back ─ 3
circuit A with number 1). With the up and down keys you can change
between circuits A and B. Repeated pressing of these keys takes you to the cir- Fig. 24: Circuit state
cuit status display of the other modules. Pressing or Enter takes you to
the setup of the selected circuit (see next paragraph). For each circuit the fol-
lowing status messages can be displayed in line 3 (Fig. 24):
4 – monitoring mode (sub-menu) (Fig. 25, Number 4). You can reach the
setup screen for the monitoring mode with or Enter (see next
chapter 9.4.1).
5 – name (two lines) (Fig. 25, Number 5). You have 42 digits for naming !"#$%&'()*+,-./01234
each circuit. After selecting a line you can change to edit mode by 56789:;<=>?@ABCDEFGHI
pressing Enter . With and you choose the position to be JKLMNOPQRSTUVWXYZ[\]^
changed; the character can be chosen with and (available char- _`abcdefghijklmnopqrs
acters see Fig. 26). You finish the input by pressing Enter or done. tuvwxyz{|}
Tip: Use an external keyboard for entering the names.
Fig. 26: Survey of all available characters
[2] stop delay: When switching back from “modified non-maintained lighting”
(failure of mains monitor) to “ready to operate”, all luminaires remain on for the
programmed stop delay time. When switching back from battery operation, all
luminaires keep being supplied with battery voltage for another minute;
afterwards the programmed stop delay time starts running. After this time has
elapsed, the circuits are switched back to their programmed operation mode
(Fig. 25, Number 3).
[3] manual:Turn the operation mode switch briefly to “charging mode” (0) and
then back to “ready to operate” (I) for switching back from battery operation.
Central Power Supply System ML96 Series
Page 28 Setup & Commissioning
9.4.1 Setting the circuit monitoring mode
State INFO-pushbutton SCM (select circuit) Enter monitoring Enter
The monitoring setup screen (Fig. 27) shows the number of the circuit in the top
line (Fig. 27, Number 1). Using the keys and you can reach the following
setup options:
----- circuit 1 -----
1 – highest address of luminaires with single luminaire monitoring existing
lamp monitoring
in the circuit, settable from 01 to 20. This number mostly corresponds lamp count: 00 ─ 1
with the number of luminaires existing in this circuit. The setting 00
deactivates the single luminaire monitoring. circuit monitoring
2 – tolerance for the current monitoring. Possible settings: off (no cur- current window: off ─ 2
rent monitoring), 5%, 10%, 20% (recommended), 50% (Fig. 27, measure reference > ─ 3
Number 2). help back
3 – measuring of the reference current (Fig. 27, Number 3). You start the
measuring by pressing or Enter and the measured value is saved
as a reference for the current monitoring. Fig. 27: Setting of the circuit monitoring
save
changes?
yes no
10 Tests
10.1 Execution of a function test
State test/F2
When the display shows the system state (see chapter 9.2), press test/F2 in -----manual test-----
order to start a function test. If the softkey test is not shown there, this indi-
cates a mains failure or that the system is running in modified non-maintained circuits: 001 – 007 ─1
lighting mode. The test function is blocked then. If you hear an acoustic signal preparing test ─2
on pushing test/F2, the test function is blocked by boost charge or a battery ─3
please wait ...
voltage below 230V. If there is no signal tone, a so-called manual test is carried
out. cancel ─ 4
The LC-display shows the tested circuits (Fig. 31, Number 1). These circuits are
Fig. 31: Test programming
“prepared” prior to the test, i.e. they are switched on with mains voltage and
brought to working temperature for an exact current measurement (Fig. 31, -----manual test-----
Number 2). The duration of this process can be set between 0 and 30 minutes.
The progress is indicated by a line of dots behind the words “please wait” (Fig. circuits: 001 – 007 ─1
31, Number 3). preparing test ─2
cancel ─ 4
circuit error ─3
cancel ─ 4
The softkey done/F3 finishes the input and takes you back to the func- Fig. 36: Setting schedule
tion test display (see chapter 10.2).
The softkey done/F3 finishes the input and takes you back to the display
function test (see chapter 10.2). The confirmation prompt save help done
changes? appears again (see Fig. 30). If confirmed with yes/F1, the new
values are saved.
Fig. 37: Setting current monitor window
Note: This function should only be programmed for systems with an additional
contactor switchover. When using SCM / ACM circuit modules, the selective
current monitoring must be programmed individually for each circuit.
Central Power Supply System ML96 Series
Setup & Commissioning Page 31
After selecting this line you can activate or deactivate the preheating phase prior to a test using and . Afterwards you finish the test
programming with the softkey done/F3. The confirmation prompt save changes? appears again (see Fig. 30). If confirmed with
yes/F1, the new settings are saved.
In the state display press menu/F3 and navigate with and to config-
uration, press or Enter , and navigate with and to capacity
test time. Then press or Enter again. Now you are in the capac- ----capacity test----
test 1 of 4: ─1
ity test (shown in Fig. 38). Here you can: duration: 1h ─2
1 – programm 4 different capacity tests, time (hour): 00 ─3
2 – set the duration time, time (min): 00
3 – configure the time (hours, minutes) when the capacity test will start, day: 01 ─4
4 – configure the date (day, month) when the capacity test will start. month: 01
help done
You finish the test programming with the softkey done/F3. Then the confirma-
tion prompt save changes? appears. If you confirm with yes/F1, the Fig. 38: Test programming
new settings are saved.
Central Power Supply System ML96 Series
Page 32 Setup & Commissioning
10.4 Test results
State menu/F3 test results Enter
Press menu/F3, navigate with and to test results and press
or Enter . Now you are in the test results (shown in Fig. 39). You can now see
a survey of the saved results of function or capacity tests:
----test results-----
1 – last test: the test carried out last on the system last test ─1
2 – function tests: automatically executed function tests function tests > ─2
3 – capacity tests: automatically executed capacity tests capacity tests > ─3
4 – manual tests: manually initiated tests manual tests > ─4
5 – print test log: print of all test results print test log > ─5
By pressing or Enter after selecting a category with and you can see help menu
information on the selected test (Beispiel in Fig. 40). The display shows the type
of test (Fig. 40, Number 1), execution date and time (Fig. 40, Number 2), the Fig. 39: Survey test results
number of tested lamps (Fig. 40, Number 3) as well as the battery characteris-
tics (Fig. 40, Number 4). If there are results of several tests, you can browse
them with and . When circuit monitoring is activated, these circuits are
displayed as well.
----function test---- ─ 1
--01.01.17 14:06:36-- ─ 2
By pressing details/F2 you can see further details on the test; back/F3
takes you back to the previous display or the menu item test results.
errors ok
The menu item print test log (Fig. 39, Number 5) lets you print the lamps: 13 42 ─ 3
saved data of the test log or store in files. You can do this either via internal 19- bat: 226.9V - 5.3A ─ 4
help details back
inch printer (if available) or via Centronics–interface and thus an external
printer.
Fig. 40: Info function test
Note: In case of a charger failure an error message is shown in the state display (see chapter 9.2).
Note: An indicated charger failure although all LEDs on the respective charger are green (red LEDs off) as well as an SLDM not reacting to the
INFO-pushbutton are signs for a communication fault.
The key parameters page (Fig. 44) shows the number of installed circuits, the ----key parameters---
circuit: 13
nominal capacity of the battery, the set supply time, the set cut-off voltage, the
battery: 017Ah
number of connected charger modules, and the programmed duration of the supply time: 001h
capacity test. cut off voltage: 185V
charger: 001
capacity test: off
done
Before conducting maintenance works or making changes to the system, it has to be de-energised by a specialist. For this the following in-
structions have to be observed:
1. Operation mode switch to charging mode. Turn the operation mode switch (Fig. 1, Number 1) to charging mode (position “0”).
2. Disconnect mains fuses. Disconnect the mains fuses by opening F1 (Fig. 2, Number 5).
3. Disconnect battery fuses. Disconnect the battery fuses by opening F2 (Fig. 2, Number 11). The system is now shut down.
Central Power Supply System ML96 Series
Setup & Commissioning Page 37
The central control and monitoring unit (Fig. 46) is the main control element of this emergency lighting system. It is used to monitor, program
and control charging and switching processes. The system status is shown in the backlit LC-display as well as by five multicoloured LEDs. The
central control and monitoring unit has the following front interfaces:
MMC/SD – Slot for importing Firmware-updates
Ethernet for service tasks
Parallel interface (Centronics) for the connection of a printer with HP-emulation PCL5/6
PS/2-interface for an external keyboard (included in delivery)
The system can be operated via key pad with four arrow keys and one enter key as well as three function keys (F1, F2, F3). The system can
also be operated via external keyboard using the Same keys (arrows, F1, F2, F3, and enter). The system firmware can be updated via front
MMC slot.
MMC
NETZ/
MAINS +24V
ETHERNET
BATTERIE/
BATTERY +5V
STÖRUNG/
FAILURE +12V
LADUNG/
CHARGE -12V
TIEFENTLADUNG/
DEEP DISCHARGE
Erdschluss/earth fault
TEST
Main Menu
Diagnosis
Battery Show battery state and conduct capacity test
Mains Check mains voltages
Modules
Circuit modules Show states of SCM – modules and conduct test
Charger modules Show states of charger modules (SLDM)
SDM/SIOM inputs Check states of SDM– and SIOM– inputs
Sub-distribution Check states of sub-distributions
Subsystems Check states of subsystems
System information Serial number, MAC, show firmware and hardware version
Key parameters Number of circuits, battery capacity, supply time etc.
Show log F4 Show internal system log
Test results View last test
Last test Show results of the last function or capacity test
Function test Show function test results
Capacity test Show capacity test results
Manual test Show results of a manual test
Print log Print test results over a certain period of time
Installation
Modules Setup modules (operation mode, follow-up time, monitoring…)
Calibrate c-monitor Calibrate current of the circuit modules
Lamps Check number of luminaires
Service Service menu
Detect modules Detect modules in the system
Operation mode Define BAS – controlled, ready-to-operate, charging mode
Configuration
Administration
Network
IP – addresses F6 Set addresses for the network adapter (front + internal)
Communication Configure status query (system communication)
LCD – Contrast Set contrast of LC-display
Timer Configure all timers (switch times, electric circuits)
SIOM – inputs Configure SIOM – inputs
SDM – inputs Configure SDM – inputs
Language selection Change display language (German, English, French…)
Password Change authorisation level
Date / Time Set system time
Function test Turn on/off pre-heating during function test
Schedule Set time schedule for function test
Current monitor Set parameters for circuit monitoring
Capacity test time Set duration, time and date for capacity test
Reset errors Reset error messages
Show errors Show all error messages
Service address Show contact address for maintenance service
Note: With a connected external PS2-keyboard (included in delivery) you can directly access the following menu items by pressing the function
keys F4 and F6
Diagnosis > System information > Show log (F4) and
Configuration > Administration > Network > IP-addresses (F6).
Central Power Supply System ML96 Series
Setup & Commissioning Page 39
The batteries used in this system are so-called maintenance-free, valve-regulated lead acid batteries. These are lead acid batteries with
sealed cells, where no water re-filling is necessary over the whole service life (and which is thus prohibited). The cells are equipped with relief
valves to protect them against overpressure. Diluted sulphuric acid absorbed in a glass mat is used as electrolyte.
Note: Opening the valves leads to their destruction and thus to the destruction of the battery.
The system uses an IUTQ-controlled charger unit with a maximum output current of each 2.5A for charging. Several SLDM25 connected in
parallel in the output ensure a charging current adapted for larger batteries. Batteries, which are later built in a battery assembly as replace-
ment, do not need an equalisation charge with normal float charge voltage in order to adjust to the terminal voltage of other batteries.
The cut-off voltage of the battery, assigned to the discharge current, must not be underrun. For this purpose the power supply system is
equipped with a deep discharge protection. The connected load must not exceed the nominal power of the system. Normal mains operation
has to be restored as soon as possible after a discharge, also partial discharge, which leads to a re-charging of the batteries. A faulty charger
unit has to be repaired.
The recommended working temperature range for lead acid batteries is 10°C to 30°C. The ideal working temperature range is 20°C ± 5K.
Higher temperatures shorten the service life. The technical data apply to the nominal temperature of 20°C. Lower temperatures reduce the
available capacity. Do not exceed the limit temperature of 50°C. Avoid permanent working temperatures higher than 40°C (see chapter
10.6).
Temperature (°C) Charging voltage boost charge (V/Cell) Float charge voltage (V/Cell)
10 2,48 2,30
20 2,45 2,28
30 2,40 2,24
Note: The charging and maintenance voltages stated apply exclusively to batteries of type OGiV.
Central Power Supply System ML96 Series
Page 40 Setup & Commissioning
13.3 Servicing and inspections
Always keep the batteries clean and dry in order to avoid creeping currents. Cleaning the batteries should be carried out according to the ZVEI-
leaflet “Cleaning of batteries“. All plastic parts of the batteries must only be cleaned using water without cleansing additive. Do not use
organic cleansers. At least every six months the following parameters should be measured and recorded:
battery voltage
voltage of some cells/block battery
surface temperature of some cells/block battery
battery cabinet temperature
If the cell voltage deviates from the average float charge voltage by ± 0.1 V/cell or if the surface temperature of several cells/blocks deviates
by more than 5°C, call a service technician immediately. The following parameters should be measured and recorded annually:
voltage of all cells/block batteries
surface temperature of all cells
battery cabinet temperature
insulation resistance according to DIN 43539 T l (version relevant on delivery)
Check the batteries in compliance with DIN 43539 part l and 100 (draft); furthermore obey the special checking instructions e.g. DIN VDE
0107 and DIN VDE 0108 or also EN 50272-2 (most recent applicable versions). In order to guarantee a reliable power supply, change the
entire battery set after the expected service life considering the operational conditions and temperatures.
The first inspection has to be carried out according to E DIN EN 50171 (VDE 0558-508):2013-07 by the installation technician when com-
missioning the system.
First inspections have to be carried out in compliance with the local, national regulations and comprise the following points:
check the correct selection of modules. Observe the selectivity of the distribution network of the emergency power supply
check the correct selection and setting of the automatic transfer and switching device (ATSD)
visual check of the settings of the protection devices
check the batteries for sufficient capacity. The system has to be operated with the actual load over the defined time when discharg-
ing the batteries. The results have to be logged. When systems do not pass these tests, they have to be tested again. If the system
fails again, it must not be commissioned. (see measurement protocol battery)
check the function by disconnecting from mains
check the ventilation of the mounting room and the battery according to EN 50272-2
check the mounting rooms in terms of fire protection, equipment and facilities.
Inspections must only be carried out by electrically skilled technicians, who are trained and qualified.
Central Power Supply System ML96 Series
Setup & Commissioning Page 41
The repeating inspection has to be carried out in compliance with the local/national regulations. If there are no local/national regulations,
the following intervals are recommended:
protection devices:
visual inspection of the settings: yearly
1. check the battery voltage as well as the symmetry voltage (chapter 7.2.3) with a measuring device (see chapter 5)
2. check the battery current (status screen or chapter 9.2, Fig. 22) by imitating a mains failure (see "testing through imitation of a
mains failure") with a measuring device (see chapter 5) or a suitable and calibrated clamp-on ammeter
batteries:
function test over a sufficient time period with the full consumer load: monthly
This is done through weekly function tests.
capacity test over the rated operating time with the full consumer load: yearly
see maintenance schedule
Beyond the requirements of EN 50272-2, paragraph 14[5], the battery has to be charged according to the manufacturer's instructions and
then, after 24h trickle charging, undergo a discharge test. During the discharging process the central emergency power supply system has to
be operated with the full consumer load and it must reach the rated operating time.
Batteries and their operating conditions must be checked regularly for correct functioning and safety. In compliance with the manufactur-
[5]
er's requirements, the following has to be checked in an inspection: voltage setting of the charger, voltages of the cells or the block batteries,
electrolyte density and electrolyte level (if applicable), cleanliness, leak tightness, tightness of the connectors (if necessary), ventilation, plugs
and valves, battery temperature.
Central Power Supply System ML96 Series
Page 42 Setup & Commissioning
13.6 Inspection before commissioning
After mounting the central power supply system, the installation technician must carry out the inspections according to HD 60364-6 chapter
61.
Part of them is the visual inspection of the stationary electrical system before the central emergency power supply system is commissioned
as well as testing and measuring, preferably in this order:
conductivity of the cables
insulation resistance of the electrical system
protection through SELV, PELV or protective separation
protection through automatic switch-off of the power supply
additional protection
voltage polarity
phase sequence of the external conductors
function and operation test
voltage drop
If an error is detected during the testing and measuring, this and each previous test, which might have been influenced by this error, have to
be repeated after clearing the error.
If the installation technician of the central emergency power supply system is not the installation technician of the stationary electrical system,
he must be provided with the test log of the first inspection of the stationary electrical system, which the emergency power supply system is
meant for, before he can carry out the first inspection of the emergency power supply system.
The observance of the requirements as defined in the instruction manual of the manufacturer has to be proven and confirmed prior to testing
and measuring by visual inspection. Particularly the following has to be inspected:
the condition of the mounting location, marking and equipment according to standards (operating devices, means of body protec-
tion, tools, utilities)
protection against intrusion of solid foreign objects and liquids
protection against external mechanical impact
observance of the surrounding temperature (lower and upper limit)
observance of the maximal humidity
ensuring the necessary ventilation
EMV-environment (A or B)
checking if special operating conditions can disturb the operational safety and functionality of the central emergency power supply
system such as vibrations, extraordinary shocks, corrosive atmosphere, strong electric or magnetic fields, explosion hazard
the existence of necessary operation and maintenance areas for the central emergency power supply system
the correct selection of modules of the emergency power supply system and check if the requirements of the user according to 5.2
have been met by the manufacturer
checking the settings of the protection devices
If a system fails an inspection according to E DIN EN 50171 (VDE 0558-508):2013-07 paragraph 8.2.4 sub-paragraph g) [6], it must not be
commissioned!
[6] checkingthe battery concerning sufficient capacity, the emergency power supply system must be operated during the battery discharge
with the rated output current over the rated operating time. Systems, which do fail this test, have to be tested again. If the requirements are
not met in this test either, the system must not be commissioned.
Central Power Supply System ML96 Series
Setup & Commissioning Page 43
If you notice malfunctions of the battery set or the charger unit, call the customer service immediately. A service contract with your dealer
enables an early recognition of failures.
If batteries are stored for a longer time or decommissioned, store them fully charged in a dry frost-free room.
Storage time in relation to the production date Charging voltage/cell at 20°C Charging time
shorter than 9 month 2,28V/cell logner than 72 hours
up to one year 2,35V/cell 48 to 144 hours
1 to 2 Jahre 2,35V/cell 72 to 144 hours
Transport note: Batteries, which show no defects whatsoever, are not treated as dangerous goods according to Dangerous Goods Ordinance
Road (GGVS) or Dangerous Goods Ordinance Railway (GGVE), if they are secured against short circuit, slipping, falling over and damage
(GGVS, volume no. 2801 a). The batteries to be transported must not show signs of acid on the outside. The respective exception regulations
apply to all sealed batteries and cells whose tanks are untight or damaged.
Note: The charging voltage stated apply exclusively to batteries of type OGiV.
Central Power Supply System ML96 Series
Page 44 Setup & Commissioning
14 General information on your system
System type:
ML96 Series
Nominal voltage UN: Number of cells (2V): Number of blocks (6V): Number of blocks (12V):
216V --- 18
Ventilation requirements:
according to EN 50 272-2, paragraph 8
15 Technical data
Conductor cross-section
power supply wire 0,5-16mm² rigid
battery-cable NSGAFÖU +/- 2,5-35mm² rigid
symmetry 0,2-6mm² rigid
final circuit 0,25-4mm² rigid
potential-free messages 0,25-4mm² rigid
mains-cable MCUV
battery cable MCUV
data lines MCUV
fuse mains MCUV (L1, L2, L3) (in A) For multiple outgoings see Note at 7.1.5.
fuse battery MCUV (B+, B-) (in A)
Central Power Supply System ML96 Series
Page 46 Setup & Commissioning
mains-cable MCUS
battery cable MCUS
data lines MCUS
fuse mains MCUS (L1, L2, L3) (in A) For multiple outgoings see Note at 7.1.4.
fuse battery MCUS (B+, B-) (in A)
supply-cable MCUV-E
data lines MCUV-E
fuses supply-cable MCUV-E (in A)
Central Power Supply System ML96 Series
Setup & Commissioning Page 47
16 Module descriptions
Several modules which are integrated in your system or optionally available are briefly described in the following paragraphs. These data can
also be downloaded from your dealer’s homepage.
Characteristics at a glance:
Characteristics at a glance:
Fig. 48:SLDM
The 19“ charger module SLDM supplies a charging current of up to 2.5A. It is connected to the primary voltage of the respective iso-
lating transformer via terminals on the rear bus plate. Additionally, the SLDM has an integrated battery voltage monitor which protects
the battery from overloading. The processor-controlled charging curve enables the SLDM to load the batteries independent from the
control computer.
Central Power Supply System ML96 Series
Page 48 Setup & Commissioning
16.3 Input/Output-module
Characteristics at a glance:
The SIOM-module has 7 relay outputs 230V/6A with potential-free changeover contacts. SIOM-module Nr. 1 is pre-programmed for
the connection of a conventional message display and control unit. It is furthermore equipped with 4 galvanically isolated, reverse
polarity tolerant switch inputs 18-120V DC. Individual message texts are programmable for each input.
Characteristics at a glance:
8 (7+1) reverse-polarity tolerant control inputs for detecting the gen-
eral lighting
integrated mains monitor (active through DIP-switch)
2 COM ports for feed-through or star-shaped wiring
integrated repeater function for COM port2 (COMboost)
integrated terminating resistor (active through DIP-switch)
integrated function monitoring of the BUS line
communication via RS485 Bus Fig. 50: SDM24-module
The interface module SDM24 allows the direct interfacing of an emergency lighting system with a general lighting installation. It is to
monitor the operation status of the general lighting system in order to achieve a joint switching of emergency lights and the general
lighting when mains-operated. Normally-closed contacts as well as normally-open contacts of the general lighting can be monitored;
it is also possible to directly connect phases of the general lighting in order to activate the emergency lighting in case of a general
lighting failure. Up to 16 SDM interface modules can be connected to the emergency lighting system via the BUS line, which provides
a sufficient number of inputs.
characteristics at a glance:
The SHIELD Line Monitor SLM mainly monitors the general mains installation (voltage supply of the general lighting). The SLMs are
bus-compatible mains monitors for the connection to the multi-bus (RS485) of an ML96 Series emergency lighting system and they
are suitable for switching the integrated maintained and non-maintained light changeover switchings in the system. The SLM can mon-
itor three phases of e.g. a mains distribution. 85% of the nominal mains voltage (230V AC), i.e. at ca. 195V AC, is the switch threshold
for the recognition of a mains failure or an intense mains voltage fluctuation. The SLM can be addressed separately and are connected
to the ML96 Series system in series (feed through wiring) via screened 4-core data line; up to 16 of these SLM can be connected via
this line. J-Y(St)-Y or similar in compliance with DIN VDE 0815 and 0816 (versions relevant on delivery) have to be used as data line.
Central Power Supply System ML96 Series
Setup & Commissioning Page 49
characteristics at a glance:
The Power-Control (SPC230) monitors voltages in sub-distributions of the general lighting. Three phases can be monitored. If fewer
phases are monitored, unused monitoring contacts have to be bridged with connected contacts. The upper switch threshold is limited
to 195 V, i.e. 15% lower than mains voltage of 230V. The state of the changeover contacts can be queried from the module. Usually
one of these contacts is integrated in a monitoring loop of an emergency lighting system. The NC-contact [18-15] or [28-25] has to be
wired. If the contacts are used for other purposes, please strongly observe the power rating of 2A-30V/DC, 0.3A-110V/DC or maximal
0.5A-230 V/AC/50Hz. This module has a plastics housing designed for rail mounting (TS35).
Characteristics at a glance:
The remote panels SLCD-15 and SLCD-15S are designed to provide a decentralised display of the statuses of emergency lighting
systems of types MC-series. The panel provides visual and acoustic indications of the respective system status. Visual indications are
provided in the form of plain text and LED. In the event of faults, an acoustic signal is also issued. The acoustic signal can be
acknowledged with the „RESET acoustic signal“ button although this does not influence the error message (visual indication).
In addition to these indications, statuses such as Mod non-maintained, test operation, mains OK, batt. OK, SCM fault etc. are also
displayed in plain text. By using the (ON/OFF) button or key switch on the SLCD-15, it is possible to switch the system operating
mode from charging mode to standby mode or vice versa. By pressing the Switch „DS On/Off“ the maintained circuits of the system
can be turned on and off.
However, in the event that no key switch is integrated into the indicator panel it is necessary to ensure that the SLCD-15 is safe-
guarded against access by unauthorised personnel (DIN VDE 0108 part 1 section 6.4.3.11). In order to be able to trigger the external
test function, the test button must be pressed until the message „ready“ appears in the display. This is necessary to prevent an acci-
dental triggering of the test function. Please refer to the wiring documentation for connection variants and connection schematics.
17
Page 50
Anschlussbeispiel SDM24
connection example SDM24
Klemme 0,5 - 1,5mm² Klemme 0,5 - 1,5mm² Klemme 0,5 - 1,5mm²
terminal 0,5 - 1,5mm² terminal 0,5 - 1,5mm² terminal 0,5 - 1,5mm²
L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N L N
E01 E02 E03 E04 E05 E06 E07 E08 E01 E02 E03 E04 E05 E06 E07 E08 E01 E02 E03 E04 E05 E06 E07 E08 E01 E02 E03 E04 E05 E06 E07 E08
UE1...E8: 18...250V DC UE1...E8: 18...250V DC UE1...E8: 18...250V DC UE1...E8: 18...250V DC
Connection examples
S2: Anschluss COM 2 > ON S2: Anschluss COM 2 > ON S2: Anschluss C OM 2 > ON S2: Anschluss COM 2 > ON
in t e r fa c e COM 2 in t er fa c e COM 2 int e r fa ce COM 2 i nt e r fa c e COM 2
S3: permanent > ON S3: permanent > ON S3: pe rmane nt > ON S3: pe r mane nt > ON
S4: Net zw äc ht er aktiv > ON
DIP-Schalter SAM-Code S4: Net z w äc ht er aktiv > ON
DIP-Schal ter SAM-Code S4: Net zw äc ht er aktiv >
DIP-Schalter SAM-Code DIP-Schalter SAM-Code
mains moni t or a c ti v e
ON S4: Net zw äc ht er aktiv > ON
mains moni tor a c ti v e mains moni t or a cti ve
mains moni tor a c ti v e
1 2 34 PC230
1 2 34 PC230
1 2 34 PC230 1 2 34
1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 1 2 3 4 5 6 7 8 PC230
Ok Er ror U/BUS aktiv Ok Error U/BUS aktiv Ok Error U/BUS aktiv 1 2 3 4 5 6 7 8 Er ror U/BUS akt iv
Ok
A
B
A
B
A
B
A
A
N
A
A
N
A
N
A
B
B
B
B
B
B
B
A
A
N
B
B
L1
L3
L1
L2
L3
L1
L3
SC
L2
SC
L2
SC
L1
L3
SC
L2
SC
SC
SC
SC
SC
SC
SC
SC
GND
GND
GND
GND
GND
GND
GND
GND
+12V
+12V
GND
+12V
GND
+12V
+12V
+12V
GND
+12V
+12V
+12V
GND
+12V
+12V
+12V
Klemme 0,5 - 1,5mm² Klemme 0,5 - 1,5mm²
terminal 0,5 - 1,5mm² terminal 0,5 - 1,5mm²
1 2 34 PC230
1 2 3 4 5 6 7 8 Ok Err or U/BUS aktiv
Netzw ächter
COM Eingang / input COM1 aus/out: COM2 aus/out: PC 230/mains moni tor
A
B
A
A
N
B
B
L1
L3
SC
L2
SC
SC
GND
GND
GND
+12V
+12V
+12V
SC
SC
GND
GND
X07
+12V
+12V
A
A
B
B
J-Y(ST)Y 02x2x0,8mm²
Es ist ein Anschluss von insgesamt16 Modulen (SDM, SLM (auch gemischt) möglich).
Am Ende ist eineTerminierung einer Modulkette notwendig (Dip-Schalter 1).
Werden die Modulesternförmig vernetzt (Com2), ist auch ein Anfangswiderstand vorzusehen.
It is possibleto connect atotal of 16 modules (SDM, SLM (also mixed)).
At the end, atermination of a modulechain is necessary (dip switch 1).
stance must also be provided.
If the modules are networked in astar-shaped manner (Com2), an initial resi
Setup & Commissioning
Anschlussbeispiel SPC230
connection example SPC230
L1 L2 L3 N L1 L2 L3 N L1 L2 L3 N
Hz
Netz / mains: 3x 230V / N 50 Hz
Netz / mains: 3x 230V / N 50 Hz
Netz / mains: 3x 230V / N 50
Nich t beleg te Eingänge mit beleg ten verbinden / Nic h t beleg te Eingänge mit beleg ten v erbinden / Nich t beleg te Eingänge mit beleg ten ve rbinden /
Conne c t unused inputs to used one Conne ct unused inputs to used one Conne ct unused inputs to used one
18 15 16 28 25 26 18 15 16 28 25 26 18 15 16 28 25 26
A
Central Power Supply System ML96 Series
Abschlusswiderstand
terminating resistance
CCIF
+
( DC)
z.B. NYM mind. 0,75mm²24V
( DC)
p.e. NYM min. 0,75mm²24V
C
Achtung: ~24V DC
attention: ~24V DC
-
Page 51
Page 52
Anschlussbeispiel SPC230
connection example SPC230
L1 L2 L3 N L1 L2 L3 N L1 L2 L3 N
Hz
Netz / mains: 3x 230V / N 50 Hz
Netz / mains: 3x 230V / N 50 Hz
Netz / mains: 3x 230V / N 50
Nich t beleg te Eingänge mit beleg ten verbinden / Nic h t beleg te Eingänge mit beleg ten v erbinden / Nich t beleg te Eingänge mit beleg ten ve rbinden /
Conne c t unused inputs to used one Conne ct unused inputs to used one Conne ct unused inputs to used one
18 15 16 28 25 26 18 15 16 28 25 26 18 15 16 28 25 26
Central Power Supply System ML96 Series
F7
F8
X22
( DC)
z.B. NYM mind. 0,75mm²24V
( DC)
p.e. NYM min. 0,75mm²24V
Achtung: ~24V DC
attention: ~24V DC
Setup & Commissioning
Anschlussbeispiel SLM
connection example SLM
J-Y(ST)Y 02x2x0,8mm²
Setup & Commissioning
5
5
1 1 1
51
8 9 101
8 9 101
8 9 101
16 1 2 3
6 1 2 3
16 1 2 3
4 5 6 7 4 5 6 7 4 5 6 7
A
A
A
A
A
A
B
B
B
B
B
B
SC
SC
SC
SC
SC
SC
16 123
16 123
16 123
101112
101112
101112
GN D
GN D
GN D
GN D
GN D
GN D
+12 V
+12 V
+12 V
+12 V
+12 V
+12 V
nächste SLM / Adresse / add. Eingang / input nächste SLM / Adresse / add. Eingang / input nächste SLM / Adresse / add. Eingang / input
next SLM ON OFF
next SLM ON OFF
next SLM ON OFF
nicht belegen / leave open Netz / mains nicht belegen / leave open Netz / mains nicht belegen / leave open Netz / mains
230V / AC 50Hz 230V / AC 50Hz J-Y(ST)Y 02x2x0,8mm² 230V / AC 50Hz
L1 L2 L3 N L 1 L 2 L3 N L1 L2 L3 N
J-Y(ST)Y 02x2x0,8mm²
Klemme 0,5 - 1,5mm² Klemme 0,5 - 1,5mm² Klemme 0,5 - 1,5mm²
terminal 0,5 - 1,5mm² terminal 0,5 - 1,5mm² terminal 0,5 - 1,5mm²
L1 L2 L3 N L1 L2 L3 N L1 L2 L3 N
SC
SC
Es ist ein Anschluss von insgesamt16 Modulen (SAM, MC-LM (auch gemischt) möglich).
GND
GND
X07
+12V
+12V
A
B
A
B
Anschlussbeispiel SLCD15
connection example SLCD15
SC
A
B
SC
A
B
SC
A
B
+12V
GND
+12V
GND
+12V
GND
Klemme 0,4 - 0,8mm² Eingang / Ausgang Klemme 0,4 - 0,8mm² Eingang / Ausgang Klemme 0,4 - 0,8mm² Eingang / Ausgang
terminal 0,4 - 0,8mm² input / output terminal 0,4 - 0,8mm² input / output terminal 0,4 - 0,8mm² input / output
SC
SC
GND
GND
X07
+12V
+12V
A
A
B
B
L NT24
-
N +
Setup & Commissioning
L‘ L
Ansteuerung über Allgemeinli cht (230V AC) * KNX, EIB
1 2 34 PC230
1 2 3 4 5 6 7 8 Ok Er r or U/BUS ak tiv
L
N
A
A
N
B
B
L1
L3
SC
L2
SC
SC
GND
GND
GND
+12V
+12V
+12V
separate Netzeinspeisung
separate mains supply -
Netz-Unterverteiler
mains sub-di stribution
L1 L2 L3 N Allgemeinbeleu chtung
general lighting
Page 55
Central Power Supply System ML96 Series
Page 56 Setup & Commissioning
18 Revision history
19 Circuit table
Number of
Circuit Location P(VA)
luminaires
1
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
Central Power Supply System ML96 Series
Page 58 Setup & Commissioning
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
Central Power Supply System ML96 Series
Setup & Commissioning Page 59
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
Central Power Supply System ML96 Series
Page 60 Setup & Commissioning
20 Measurement protocols battery
Date: Time:
Block 01 Block 02 Block 03 Block 04
Block 05 Block 06 Block 07 Block 08
Block 09 Block 10 Block 11 Block 12
Block 13 Block 14 Block 15 Block 16
Block 17 Block 18 Symmetry Total
Date: Time:
Block 01 Block 02 Block 03 Block 04
Block 05 Block 06 Block 07 Block 08
Block 09 Block 10 Block 11 Block 12
Block 13 Block 14 Block 15 Block 16
Block 17 Block 18 Symmetry Total
Date: Time:
Block 01 Block 02 Block 03 Block 04
Block 05 Block 06 Block 07 Block 08
Block 09 Block 10 Block 11 Block 12
Block 13 Block 14 Block 15 Block 16
Block 17 Block 18 Symmetry Total
Date: Time:
Block 01 Block 02 Block 03 Block 04
Block 05 Block 06 Block 07 Block 08
Block 09 Block 10 Block 11 Block 12
Block 13 Block 14 Block 15 Block 16
Block 17 Block 18 Symmetry Total
Date: Time:
Block 01 Block 02 Block 03 Block 04
Block 05 Block 06 Block 07 Block 08
Block 09 Block 10 Block 11 Block 12
Block 13 Block 14 Block 15 Block 16
Block 17 Block 18 Symmetry Total
Date: Time:
Block 01 Block 02 Block 03 Block 04
Block 05 Block 06 Block 07 Block 08
Block 09 Block 10 Block 11 Block 12
Block 13 Block 14 Block 15 Block 16
Block 17 Block 18 Symmetry Total
Central Power Supply System ML96 Series
Setup & Commissioning Page 61
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
PREVENTIVE MAINTENANCE CHECKLIST
FOR
CENTRAL BATTERY SYSTEM
SERVICE TO BE PERFORMED
SL #. PREVENTIVE MAINTENANCE ACTIVITY ACTUAL CONDITION REMARKS
Check condition of the panel/ Clean cabinets if it is
1
rusty.
2 Inspect the overall system
Check over all condition of the emergency and Exit
3
lights
4 Check Battery Charger and Batteries
5 Clean Emergency and Exit light Body if it is rusty
6 Check proper identification is provided
Check the interface between Fire Alarm Panel & Central
7
Battery System.
Should be mentioned next maintenance date in the
8
label
LOCATION:
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Section 39.5
CORRECTIVE MAINTENANCE
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
CORRECTIVE MAINTENANCE
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
32.6 -TESTING & COMMISSIONING REPORTS /
CERTIFICATES
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
NAFFCO ELECTRO MECHANICAL CO. L.L.C.
Fire Fighting & Safety Equipment Division
WARRANTY CERTIFICATE
There are no warranties, expressed or implied, made by NAFFCO on new equipment, except a warranty against defects
in material and workmanship set out below:
1. NAFFCO warrants that the following products, supplied against your SO: …………… shall be free from defects
in material and workmanship:
Project : CRITICAL WAREHOUSING CAPACITY ENHANCEMENT
Plot Names : PLOT KHIA8-59B (KLP 06 & 07) - KIZAD
Client/ Employer : M/S. ABU DHABI PORTS
Consultant : M/S. HDR BRADBROOK CONSULTANT
Main Contractor : M/S. TROJAN GENERAL CONTRACTING L.L.C
Infra Contractor : NPC (NATIONAL PROJECT & CONSTRUCTION LLC)
Infra Electrical Contractor : FREIBURG CONTRACTING & GENERAL
MAINTENANCE LLC
Systems : SELF-CONTAINED MONITORED EMERGENCY/ EXIT
LIGHTING SYSTEM – M/s. NAFFCO
2. NAFFCO’s obligation and liability under this warranty being limited to replacing free of charge at its factory, any part
proving defective under normal use and service, and reasonable cost of repair and replacement of said part or partswithin
12 months from the date of Handing Over Certificate.
3. This Warranty Certificate must be presented to obtain services pursuant to the warranties set forth herein.
4. This warranty does not cover sets repaired by workshops not authorized by NAFFCO.
5. THIS WARRANTY IS IN LIEU OF ALL OTHER WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING
ANY IMPLIED WARRANTY OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE AND
THE OBLIGATION AND LIABILITY OF NAFFCO UNDER THIS WARRANTY SHALL NOT INCLUDE ANY
TRANSPORTATION, ANY OTHER CHARGES, LIABILITY FOR DIRECT, INDIRECT OR CONSEQUENTIAL
DAMAGES AND DELAY RESULTING FROM THE DEFECT OR ANY OTHER OBLIGATIONS OR LIABILITY
ON THE PART OF NAFFCO, AND NAFFCO NEITHER ASSUMES NOR AUTHORIZES ANY OTHER PERSON
TO ASSUME FOR IT ANY OTHER LIABILITY IN CONNECTION WITH SUCH EQUIPMENT. ANY IMPROPER
USE OR APPLICATION OF THE PRODUCT OR THE SUBSTITUTION OF ANY PARTS NOT APPROVED BY
NAFFCO SHALL VOID THIS WARRANTY. FAILURE TO PROVIDE REGULAR MAINTENANCE IN
ACCORDANCE WITH SAFETY REGULATIONS SHALL LIKEWISE VOID THIS WARRANTY. THIS
WARRANTY COVERS ONLY THE PRODUCTS LISTED IN PARAGRAPH 1 ABOVE.
For NAFFCO,
FP/2414
NAFFCO
ISO 45001 I ISO 14001 I ISO
9001
20006591
Abu Dhabi Office: P. 0 Box: 4192, Abu Dhabi, United Arab Emirates, Tel: +971 2 690 4555, Fax: +971 2 690 4666
Head Quarter - Factory: P O Box: 262169 Dubai, Tel: +971 4815 1111. Fax +971 4 815 1222
Email : [email protected] Website : www.naffco.com ; NAFFCO Customer Service @ 800 NAFFCO (800623326)
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Section 39.8
SPARE PARTS & LIST OF EQUIPMENT
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
SECTION 39.9
AS-BUILT DRAWINGS
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
MODEL MO's
SYMBOL DESCRIPTION CONTRACTOR'S VERIFICATION STAMP
MD32SERIES
CB
CENTRAL BATTERY SYSTEM PANEL WE, [TROJAN], VERIFY THAT THIS CONTRACTOR'S DOCUMENT
A ML96SERIES A
E1 EMERGENCY LIGHT, 5.2W SURFACE TYPE, IP54 - 560LM X10UH · HAS BEEN PRODUCED AND CHECKED IN ACCORDANCE
WITH CONTRACTOR'S QUALITY ASSURANCE PLAN
E2 EMERGENCY LIGHT, 9.4W SURFACE TYPE, IP54 - 560LM M50UH · IS OF A STANDARD THAT WILL ENABLE THE EMPLOYER
TO ACCEPT IT IN ACCORDANCE WITH THE CONTRACT
EX-1 EXIT LIGHT, 5.2W WALL MOUNTED TYPE, IP64 X10UL+LX10 · COMPLIES WITH ALL REQUIREMENTS OF THE CONTRACT
2C X 2.5sq. mm. FIRE RATED MULTI STRANDED CABLE
FOR CENTRAL BATTERY SYSTEM CIRCUIT
FOLLOWING DEVIATIONS TO CONTRACT ARE REFERENCED
ABBREVIATIONS FOR WHICH A DISPENSATION HAS BEEN ACCEPTED BY THE
EMPLOYER:
B T/A TO ABOVE F/A FROM ABOVE B
T/B TO BELOW F/B FROM BELOW OTHER RELATED LETTERS/CTIs WHICH DOCUMENT
CLARIFICATIONS ASSOCIATED WITH THIS DOCUMENT ARE
GENERAL NOTES: (CBS) LISTED BELOW:
6. FOR THE EXACT LOCATION OF EMERGENCY & EXIT LIGHTS DOCUMENT STATUS STAMP
REFER TO PLAN LAYOUT
7. FOR DEVICE & CIRCUIT DETAILS REFER SCHEMATIC DIAGRAM CODE 1 WORK MAY PROCEED
ABU DHABI CIVIL DEFENSE AUTHORITYGENERAL NOTES
1. All the shop/executive drawings architectural layout shall be as per ADCD approved fire life safety
CODE 2 REVISE & RESUBMIT. WORK MAY PROCEED
initial architectural drawings.
SUBJECT TO INCORPORATION OF
2. Any architectural changes like addition, deletion, modification during construction or in future shall
be submitted to ADCD for both architectural and shop approvals.
COMMENTS INDICATED
3. Fire Alarm, Fire Fighting, Emergency/Exit Light System and Voice Evacuation System
and all other active systems shall be installed as per approved Shop drawing. CODE 3 REVISE & RESUBMIT. WORK MAY NOT
D 4. All the Materials, Systems, Assemblies, equipment, Products and Accessories, referred to in this PROCEED D
drawing with respect to Life Safety, Fire Safety and Emergency Services and all other systems shall
be Listed, Approved and Registered by the Civil Defence Material Approval Department.
CODE 4 REVIEW NOT REQUIRED. WORK MAY
5. All portable fire extinguishers shall be provided as per (UAE fire and life safety code and NFPA 10).
PROCEED
6. Emergency light and exit signs shall be provided according to (UAE fire and life safety code and
NFPA 101).
7. All portions of these buildings and common and services areas shall be fully cover by smoke detections
THE STATEMENT "WORK MAY PROCEED" APPLIES TO THE
and fully covered by voice announcement system according to (NFPA 72). FOLLOWING WORK ACTIVITIES ASSOCIATED WITH THE
8. All portions of these building shall be fully protected by automatic sprinklers system according to (NFPA 13). MATTERS CONTAINED WITHIN THE CONTRACTOR'S
9. Standpipe system shall be provided in these building according to (NFPA 14). DOCUMENT:
10. All special system like Clean agent,Foam, water spray, water mist, wet chemical kitchen hood systems shall be DESIGN / PROCUREMENT / CONSTRUCTION / ALL * ACTIVITIES
installed in this building in accordance to the relevant NFPA code and standards.
11. All fire door and windows shall be according to (NFPA 80) ANY REVIEW, COMMENT OR ACCEPTANCE BY EMPLOYER
12. All types of smoke ventilation systems shall be installed in this building in accordance (UAE fire and life UNDER THIS CONTRACT WITH RESPECT TO ANY OF
safety code (and other international codes and standards only if a requirement of these systems is not CONTRACTOR'S DOCUMENTS SHALL NOT IN ANY WAY BE, OR
E mention on UAEFC).
DEEMED TO BE, AN APPROVAL OF ANY WORKS OR AN
E
13. Fire and smoke damper or (combination of Fire and smoke damper systems) shall be installed in this building
according to UAE fire and life safety code and relevant NFPA codes and standards.
ACCEPTANCE THAT THE CONTRACTOR'S DOCUMENTS MEET
14. All interiors finishing material shall be provided as (UAE fire and life safety code and NFPA 101). accordance with THE REQUIREMENTS OF THE CONTACT, AS CONTRACTOR HAS
(UAE fire and life safety code and NFPA 101). THE SOLE RESPONSIBILITY FOR PERFORMING THE WORKS IN
15. Fire pump and fire water tank shall be listed and tested and installed according to Civil Defense
requirement and international standards.
ACCORDANCE WITH THE REQUIREMENTS OF THIS CONTRACT.
16. Emergency power system and standby system shall be installed in this building in accordance to UAE fire and life
safety code (including local power authority standards) and relevant NFPA codes and standards.
17. All penetrations through fire resistance rated walls shall be protected by approved fire stop system
and materials, installed and tested in accordance with (UAE fire and life safety code and other relevant international standards.).
18. All means of aggress components details and dimensions shall be provided and constructed according
----------------------------- --------------- ------------------
to (UAE fire and life safety code and NFPA 101 and 5000).
ABU DHABI PORTS APPROVAL CODE DATE
19. Consultant and contractor shall comply with UAE fire and life safety code chapter 12 in terms of
requirements of building under construction.
20. Emergency action plan shall be implementing in these buildings according to UAE fire and life safety code.
F UAE fire and life safety code. 1 2 3 4 5 30325 6 7 F
21. All decoration design and materials and all service systems in the building shall not obstruct all fire
A00 21.09.2022 AD/ISSUED FOR APPROVAL AP SU MA
safety system especially sprinkler system.
3500 3300 3300 7100 9800 3325 C03 13.08.2022 SD/ISSUED FOR APPROVAL AP SU MA
22. Air condition equiptment's is not aloowed inside a protected staircase.
23. Consultant and contractors must comply with the general notes and applicable codes and standards C02 13.01.2022 SD/ISSUED FOR APPROVAL AP SU MA
even if the code requirement was missed during plan review. A JUNCTION BOX
C01 04.01.2022 SD/ISSUED FOR APPROVAL AP SU MA
C00 16.09.2021 SD/ISSUED FOR APPROVAL AP SU MA
Consultant
J J
K Electrical Sub-Contractor K
FOR MORE DETAILS PLEASE REFER SCHEMATIC DIAGRAM
Contracting General
(4201-232-VF-7100-08108_C02) ة اعلل ترببرقالباغرابيارف
Tel. : 00971-2-4910080, Fax : 00971-2-4910081
P.O. Box : 43206, Abu Dhabi, U.A.E.
Website : www.freiburgcgm.ae
NAFFCO
R
MEMBERS OF:
41113786
ELECTROMECHANICAL CO. L.L.C
UKAS
QUALITY
ISO 9001:2000 MANAGEMENT
P.O. BOX 4192, ABU DHABI - U.A.E. TEL.: 02 - 690 4555 FAX : 02 - 690 4666
LPCB
WEBSITE : www.naffco.com E-MAIL : [email protected]
NFPA
130004
Drawing Title
L KLP-6 & KLP-7 KHIA8-59B SUBSTATION TYPE A L
(SUBSTATION - 1,2&3) GROUND FLOOR
PARTY MAIN CONSULTANT MAIN CONTRACTOR CB CONTRACTOR THIRD PARTY (FIRE CONSULTANT) EMERGENCY LIGHTING LAYOUT
Sheet Scale Paper Size
1 OF 1 1:100 A1
STAMPS
Drawing Status
6. FOR THE EXACT LOCATION OF EMERGENCY & EXIT LIGHTS DOCUMENT STATUS STAMP
REFER TO PLAN LAYOUT
7. FOR DEVICE & CIRCUIT DETAILS REFER SCHEMATIC DIAGRAM CODE 1 WORK MAY PROCEED
ABU DHABI CIVIL DEFENSE AUTHORITYGENERAL NOTES
1. All the shop/executive drawings architectural layout shall be as per ADCD approved fire life safety
CODE 2 REVISE & RESUBMIT. WORK MAY PROCEED
initial architectural drawings.
SUBJECT TO INCORPORATION OF
2. Any architectural changes like addition, deletion, modification during construction or in future shall
be submitted to ADCD for both architectural and shop approvals.
COMMENTS INDICATED
3. Fire Alarm, Fire Fighting, Emergency/Exit Light System and Voice Evacuation System
and all other active systems shall be installed as per approved Shop drawing. CODE 3 REVISE & RESUBMIT. WORK MAY NOT
D 4. All the Materials, Systems, Assemblies, equipment, Products and Accessories, referred to in this PROCEED D
drawing with respect to Life Safety, Fire Safety and Emergency Services and all other systems shall
be Listed, Approved and Registered by the Civil Defence Material Approval Department.
CODE 4 REVIEW NOT REQUIRED. WORK MAY
5. All portable fire extinguishers shall be provided as per (UAE fire and life safety code and NFPA 10).
PROCEED
6. Emergency light and exit signs shall be provided according to (UAE fire and life safety code and
NFPA 101).
7. All portions of these buildings and common and services areas shall be fully cover by smoke detections
THE STATEMENT "WORK MAY PROCEED" APPLIES TO THE
and fully covered by voice announcement system according to (NFPA 72). FOLLOWING WORK ACTIVITIES ASSOCIATED WITH THE
8. All portions of these building shall be fully protected by automatic sprinklers system according to (NFPA 13). MATTERS CONTAINED WITHIN THE CONTRACTOR'S
9. Standpipe system shall be provided in these building according to (NFPA 14). DOCUMENT:
10. All special system like Clean agent,Foam, water spray, water mist, wet chemical kitchen hood systems shall be DESIGN / PROCUREMENT / CONSTRUCTION / ALL * ACTIVITIES
installed in this building in accordance to the relevant NFPA code and standards.
11. All fire door and windows shall be according to (NFPA 80) ANY REVIEW, COMMENT OR ACCEPTANCE BY EMPLOYER
12. All types of smoke ventilation systems shall be installed in this building in accordance (UAE fire and life UNDER THIS CONTRACT WITH RESPECT TO ANY OF
safety code (and other international codes and standards only if a requirement of these systems is not CONTRACTOR'S DOCUMENTS SHALL NOT IN ANY WAY BE, OR
E mention on UAEFC).
DEEMED TO BE, AN APPROVAL OF ANY WORKS OR AN
E
13. Fire and smoke damper or (combination of Fire and smoke damper systems) shall be installed in this building
according to UAE fire and life safety code and relevant NFPA codes and standards.
ACCEPTANCE THAT THE CONTRACTOR'S DOCUMENTS MEET
14. All interiors finishing material shall be provided as (UAE fire and life safety code and NFPA 101). accordance with THE REQUIREMENTS OF THE CONTACT, AS CONTRACTOR HAS
(UAE fire and life safety code and NFPA 101). THE SOLE RESPONSIBILITY FOR PERFORMING THE WORKS IN
15. Fire pump and fire water tank shall be listed and tested and installed according to Civil Defense
requirement and international standards.
ACCORDANCE WITH THE REQUIREMENTS OF THIS CONTRACT.
16. Emergency power system and standby system shall be installed in this building in accordance to UAE fire and life CONNECTED FROM NEAREST CBP
safety code (including local power authority standards) and relevant NFPA codes and standards. * SUBSTATION 4 CONNECTING WITH CBP-1 BLOCK-A (P1/C22/D01)
17. All penetrations through fire resistance rated walls shall be protected by approved fire stop system * SUBSTATION 5 CONNECTING WITH CBP-1 BLOCK-A (P1/C21/D01)
and materials, installed and tested in accordance with (UAE fire and life safety code and other relevant international standards.).
* SUBSTATION 6 CONNECTING WITH CBP-3 BLOCK-C (P3/C21/D01)
18. All means of aggress components details and dimensions shall be provided and constructed according
* SUBSTATION 7 CONNECTING WITH CBP-6 BLOCK-F (P6/C24/D01) ----------------------------- --------------- ------------------
to (UAE fire and life safety code and NFPA 101 and 5000).
ABU DHABI PORTS APPROVAL CODE DATE
19. Consultant and contractor shall comply with UAE fire and life safety code chapter 12 in terms of
requirements of building under construction.
20. Emergency action plan shall be implementing in these buildings according to UAE fire and life safety code.
F UAE fire and life safety code.
F
21. All decoration design and materials and all service systems in the building shall not obstruct all fire
safety system especially sprinkler system.
1 2 3 4 5
24800 A00 21.09.2022 AD/ISSUED FOR APPROVAL AP SU MA
22. Air condition equiptment's is not aloowed inside a protected staircase.
23. Consultant and contractors must comply with the general notes and applicable codes and standards 3325 9800 7100 4575 C02 13.08.2022 SD/ISSUED FOR APPROVAL AP SU MA
even if the code requirement was missed during plan review. JUNCTION BOX C01 04.01.2022 SD/ISSUED FOR APPROVAL AP SU MA
A C00 16.09.2021 SD/ISSUED FOR APPROVAL AP SU MA
G E1 E1 E1 E1 E1 Client
G
P6/C24/D01 P6/C24/D02 P6/C24/D03 P6/C24/D04 P6/C24/D05
CONTROL/IDF ROOM TR ROOM HV ROOM
3000x5000 LV ROOM 6900x5000 4200x5000
9600x5000
B
Contract No. & Project Title
CONTRACT NO. 4201-232
H CRITICAL WAREHOUSING CAPACITY ENHANCEMENT H
Independent Checking Engineer
SUBSTATION TYPE B
1 GROUND FLOOR PLAN Signature
SCALE 1:100
Contractor
Consultant
J J
(4201-232-VF-7100-08107_C02)
DO NOT SCALE FROM THIS DRAWING
K
(4201-232-VF-7100-08109_C02) Electrical Sub-Contractor K
(4201-232-VF-7100-08112_C02) Contracting General
ة اعلل ترببرقالباغرابيارف
Tel. : 00971-2-4910080, Fax : 00971-2-4910081
P.O. Box : 43206, Abu Dhabi, U.A.E.
Website : www.freiburgcgm.ae
NAFFCO
R
MEMBERS OF:
41113786
ELECTROMECHANICAL CO. L.L.C
UKAS
QUALITY
ISO 9001:2000 MANAGEMENT
P.O. BOX 4192, ABU DHABI - U.A.E. TEL.: 02 - 690 4555 FAX : 02 - 690 4666
LPCB
WEBSITE : www.naffco.com E-MAIL : [email protected]
NFPA
130004
Drawing Title
L KLP-6 & KLP-7 KHIA8-59B SUBSTATION TYPE B L
(SUBSTATION - 4,5,6&7) GROUND FLOOR
PARTY MAIN CONSULTANT MAIN CONTRACTOR CB CONTRACTOR THIRD PARTY (FIRE CONSULTANT)
EMERGENCY LIGHTING LAYOUT
Section 39.10
TRAINING MATERIAL
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
CENTRAL BATTERY SYSTEM
CENTRAL BATTERY EMERGENCY
LIGHTING SYSTEM
MADE IN GERMANY
CENTRAL BATTERY PANEL
Features:-
Auto monitoring & testing
According to DIN EN 62034.
Remote monitoring & Controlling via web browser (TCP/IP)
Memory for test results over 5 years.
Password protection .
Illuminated large LCD display with plain text display.
Induvial battery monitoring.
Memory card of software update
Easy and understandable programming with 8 buttons.
Up to 96 circuits in one cabinet.
CENTRAL BATTERY PANEL
Model: SCM 42
The mains circuit module SCM is an electronic module in service-friendly
19“ rack technology and used for the power supply of safety and rescue
sign luminaires in mains circuits of security lighting. The circuit module is
equipped with two separate circuits inclusive of hedging, each circuit has
its own independent switching.
Features
Universal Mounting for wall/ceiling/recessed ceiling/pendant
Indoor or outdoor application IP65
Can be supplied as an Emergency or Exit
Lumen output 520lm(4W,LED)
Protection Class II Models: X10UL/X10UH
Different Viewing Distance availability
Accessories
EMERGENCY LIGHT
M20 Series:
Model:M20CSH
List of models: M20CSH, M20CRH, M20RSH, M20RRH, M20HSH, M20HRH, M20SSH, M20SRH
Accessories:
EMERGENCY LIGHT
M20 Series:
Features
Accessories
PANEL OPERATION
THANK YOU…
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Section 39.11
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Company
Name
M/s NAFFCO ELECTROMECHANICAL LLC
Address P.O BOX : 4192, AL REEM ISLAND, ABU DHABI
SUPPLIER TEL. NO: 02‐ 690 4555
Contact
FAX. NO: 02‐ 690 4666
details
www.naffco.com
Company
M/s SHIELD
Name
UNIT 3, ENDEAVOUR DRIVE, BASILDON-ESSEX, SS3 14WF,
Address
UNITED KINGDOM
MANUFACTURER
TEL. NO: 377731 1708 44+
Contact
FAX NO: 347637 1708 44+
details
www.shieldglobal.com
Contract
4201-232KIZAD Critical
Warehousing Capacity
Enhancement Project-
KLP6&7
Volume D
(Instrumentation & Controls)
OPERATIONS & MAINTENANCE MANUAL
SUBSTATION
Section 39.12
MANUFACTURER’S LITERATURE & VENDOR
USER MANUALS
Document Number
4201-232-V3-8510-08018
Revision
A00
Date
27 Sep 2022
Electronic documents, once printed, are uncontrolled and may have become outdated.
Refer to electronic documents on the ADPORTS UCM system for current revisions
Central Battery System
ML96 panel is a modular 19” central battery system according Type Fusing Maximum Load
to EN 50171 and BGV A3 featuring single light monitoring Per Module
without additional wiring, free programmable circuits and a SCM32 2 x F5A 3A / 2 x 650 VA
5-year log-book. The system is available in different cases SCM42 2 x F6.3A 4A / 2 x 860 VA
with internal or external battery compartment. SCM62 2 x F10A 6A / 2 x 1300 VA
SCM12E 2 x F5A A / 2 x 250 VA
The built-in Web interface with integrated visualization
software makes it possible to display even large projects The ML96 panel allows the connection of LED lamps,
clearly on a building plan. In addition, the test results and fluorescent lamps or low-voltage halogen lamps. Up to 256
incidents of a particular date are retrieved and displayed main stations and 32 substations per panel can be linked
together with all relevant operating parameters. This via a serial or TCP / IP connection to a network. This allows a
minimizes the maintenance costs. The system can be maximum of a million lights to be connected and monitored to
configured by keyboard, on the device itself or through a TCP the whole system.
/ IP network connection to a remote PC. The 19” rack design
allows to upgrade or exchange modules individually.
Specifications
Case Material Steel-sheet, Gray RAL 7035
Dimensions (H x W x D) Various
Insulation Class I
MLW: 900 x 600 x 450 mm
(without battery cabinet)
MLX: 1850 x 800 x 600 mm
Dimensions (H x W x D)
MLS: 1800 x 600 x 450 mm
MLG: 1500 x 600 x 450 mm
MLK: 1000 x 600 x 450 mm
from top (900 mm cabinet from
Cable Entry
below also)
Voltage 3 x 230V AC 50/60Hz +/- 10%
Max. 96 circuits with switchover
Output Circuits for non-maintained or maintained
operation
Maintenance-free, closed lead
Battery acid cell OGiV, OGi, OPzS or
low-maintenance NiCd batteries
Permissible Temperature 10 °C to 35 °C
* IP21 option available only for ML96 series panels upto 24 circuits.
** IP54 option available only for MC6, MN, MNXL,MD32 & ML96 (MLG, MLS & MLW) series
panel with additional cost.
9 www.shieldglobal.com
Central Battery System
Features
• Redundancy in CPU.
• Multilingual switch-selectable.
• Password protected.
device (PS/2).
• Ethernet interface.
www.shieldglobal.com 10
Our central power supply systems can be built in various
housing sizes or types. All housings are in-house
developments and have been designed according
to the requirements and standards (EN 50171, EN 50272-2).
In principle, the electronic components
are accommodated separately from the battery.
* IP21 Option available only for ML96 series panels upto 24 circuits.
** IP54 Option available only for MC6, MN, MNXL, MD32 & ML96 (MLG, MLS & MLW) series
panel with additional cost.
www.shieldglobal.com 2
Central Battery System
Features
• Central power supply system acc. to DIN EN 50171 for security • Centronics printer interface included.
lighting systems acc. to DIN EN 50172 and systems acc. to • Ethernet interface.
DIN VDE 0100-718. • Control and monitoring over webbrowser.
• Automated monitoring system acc. to DIN EN 62034 for • Display of lamp positions and state in a building ground plan.
regular testing of all connected luminaires. • Free programmable circuits.
• Microprocessor-based function control system. • Up to 6 control inputs can be assigned to each circuit .
• Memory for test results over 5 years. • Adaptive mains monitoring at every circuit.
• Illuminated large LCD display with plain text display. • Selective earth fault check of every circuit.
• Multilingual switch-selectable. • Up to 32 circuits in one 19” cabinet.
• Password protected. • Use of electrical circuits modules SCM42.
• Service contact preprogrammed. • Battery charger with IUTQ characteristic for a maximum of
• Easy and understandable programming with 8 buttons. battery life.
• Extern PC keyboard for the fastly configuration of the device (PS2). • Extern modules (network guardian etc.) can be connected
• Memory-Card (Multi Media Card) Slot for software updates. and controlled over a bus system.
• RS-232 interface. • Integrated stand socket.
Option Model
Printer BD04
BAT-LOGG® Set for MidiControl Plus System (18x BTLG-SENS / 1x BTLG-INTF) BTLG-MC18
www.shieldglobal.com 8
Modules
MAXIMUM
FUSING PER
TYPE LOAD PER
CIRCUIT
MODULE
SCM12E 2x F5A 2x 250 VA
www.shieldglobal.com 34
Modules
E1: Connection external operating mode selector Voltage on – emergency light blocked; 0 volts – operative
E2: Connection temperature sensor Voltage on – temperature too high / low; 0 volts – temp okay
E3: Connection air stream monitor Voltage on – fan error; 0 volts – fan okay
E4: Connection external test switch or Voltage on – test function; 0 volts– no test function
shutdown for firefighter emergency switch Voltage on – emergency lighting system off; 0 volts – operative
www.shieldglobal.com 36
Modules
Line monitor
Ethernet switch
www.shieldglobal.com 38
Batteries
Battery cabinets
The integrated ventilation slots are designed for the maximum possible battery capacity.
41 www.shieldglobal.com
Batteries
The table below helps you selecting the correct system configuration: First, find the total number of circuits of your system in
the leftmost column. The column "System Type" shows you the matching system types. Now, in the column corresponding to
the required Supply Time (3h), look for the row showing a battery power (value in Watts to the left of the slash*) greater than
or equal to the required total DC power consumption of the planned system. The value to the right of the slash now gives the
number of charger modules the system must have**, while the right-most column shows you the Battery Type required***.
www.shieldglobal.com 46
Batteries
OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV
Type 1236 1252 1270 1290 12120 12170 12260 12280 12330 12400 12450 12550
LP LP LP LP LP LP LP L LP LP LP LP
198 346 355 501 674 944 1.501 1.544 1.642 2.117 2.376 3.256
Output max. 3h in W*
(158) (276) (284) (401) (539) (755) (1,201) (1,236) (1,313) (1,693) (1,901) (2,604)
Number of Cabinets Needed for a Set (18 pcs) of Batteries of The Entire Capacity
MC-Cabinet 1000mm 1 1 1 1 1 1 - - - - - -
MC-Cabinet 1500mm 1 1 1 1 1 1 1 1 1 1 1 -
Battery Cabinet
BATT90 1 1 1 1 1 1 1 1 1 1 1 1
900 x 600 x 450mm
Battery Cabinet
BATT60 1 1 1 1 1 1 1 1 1 1 1 1
900 x 600 x 600mm
Battery Cabinet
BATT20 1 1 1 1 1 1 1 1 1 1 1 1
1850 x 800 x 600mm
47 www.shieldglobal.com
OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV OGiV
12600 12650 12750 12800 12800 12900 121000 121200 121200 121340 121500 122000 122000 122600
LP LP LP LW LPL LP LP LPS LP LP LP LPE LP L
3.262 3.359 4.104 4.104 4.212 4.666 5.238 5.746 6.318 7.366 7.700 9.979 11.988 12.834
(2.609) (2.687) (3.283) (3.283) (3.370) (3.732) (4.190) (4.596) (5.054) (5.892) (6.160) (7.983) (9.590) (10.267)
- - - - - - - - - - - - - -
- - - - - - - - - - - - - -
1 - 1 - - - - - 3 3 3 - - -
1 - 1 1 - - - - 2 - - - 3 -
- - - - - - - - 3 3 3 - - -
1 1 1 1 1 1 1 1 2 2 2 3 3 3
1 1 1 1 1 1 1 1 1 1 1 1 1 2
2.6 2.9 3.3 3.5 3.5 3.9 4.4 5.2 5.2 5.8 6.5 8.7 8.7 11.3
72.8 81.2 92.4 98 98 109.2 123.2 145.6 145.6 162.4 182 243.6 243.6 316.4
www.shieldglobal.com 48
Datasheet
HP 290 G3 Microtower PC
Maximize your investment
Available Graphics Integrated: Intel® HD Graphics 610; Intel® UHD Graphics 6302,12
Discrete: AMD Radeon™ R7 430 Graphics (2 GB GDDR5 dedicated)2
Audio Realtek ALC3601 codec, optional internal speaker, combo microphone/headphone jack
1 full-height PCI; 1 PCIe x1; 1 PCIe x16; 2 M.2; One 3-in-1 SD card reader 9,10,25,27 (1 M.2 slot for WLAN and 1
Expansion slots
M.2 2242/2280 slot for storage.)
Front: 1 3-in-1 SD card reader; 1 headphone/microphone combo; 4 USB 3.1 Gen 131
Ports and Connectors Rear: 1 HDMI; 1 line in; 1 line out; 1 power connector; 1 RJ-45; 1 VGA; 4 USB 2.022
Internal: 1 parallel; 1 PS/223
Optional: 1 4x Serial; 1 serial
Input devices HP USB Keyboard5,6; HP USB Optical Mouse5,7,15;
Communications LAN: Integrated 10/100/1000M GbE ; WLAN: Realtek 802.11a/b/g/n/ac (1x1) and Bluetooth® 4.2 Combo 11,32;
Drive Bays One 3.5" HDD; One 3.5" (2.5") HDD
Environmental Operating temperature: 0 to 40°C; Operating humidity: 10 to 90% RH
HP Audio Switch; HP Documentation; HP Setup Integrated OOBE Win10; HP Support Assistant; HP System
Available Software
Event Utility; McAfee LiveSafe™; Buy Office (sold separately); HP JumpStarts 16
Security management Integrated accessories cable lock; Lock slot; Trusted Platform Module (TPM) 2.020,21,33
Power 180 W internal power supply, up to 90% efficiency, active PFC14
Dimensions 15.5 x 30.3 x 33.7 cm (System dimensions may fluctuate due to configuration and manufacturing variances.)
Weight 4.7 kg (Exact weight depends on configuration.)
Ergonomic features ##displaytiltswiv##
Energy efficiency compliance CCC; CE; CECP; CEL; ENERGY STAR® certified; EPEAT® 2019 registered where applicable; FCC; RoHS; SEPA; UL8
1 year (1-1-1) limited warranty and service offering includes 1 year of parts, labor and on-site repair. Terms
Warranty
and conditions vary by country. Certain restrictions and exclusions apply.
Data sheet | HP 290 G3 Microtower PC HP recommends Windows 10 Pro for business
HP 290 G3 Microtower PC
Get fast data entry and quick USB connectivity with the HP USB Business Slim Keyboard,
designed to complement the 2015 class of HP Business PCs. Proven performance and
reliability to deliver maximum investment protection. Offering the perfect combination of
performance, reliability and investment protection to any IT environment. For businesses that
HP USB Slim Business Keyboard require superior stability and manageability with low lifecycle costs, or desktops with proven
technology, superior price/performance and a wide choice of features, or even entry-level PCs
that balance price and essential computing capabilities – the HP Desktop family holds the
solution.
Product number: N3R87AA
Expand the storage capabilities of your desktop with the HP TLC 256 GB SATA SSD1, which
includes TLC flash and the same reliability you already get from current from SSD drives.
Expand the storage capabilities of your desktop with the HP TLC 256 GB SATA SSD1, which
includes TLC flash and the same reliability you already get from current from SSD drives.
Offering the perfect combination of performance, reliability and investment protection to any
HP TLC 256 GB SATA SSD IT environment. For businesses that require superior stability and manageability with low
lifecycle costs, or desktops with proven technology, superior price/performance and a wide
choice of features, or even entry-level PCs that balance price and essential computing
capabilities – the HP Desktop family holds the solution.
Product number: P1N68AA
HP 3 year Next business day Onsite Receive 3 years of next business day onsite HW Support from an HP-qualified technician for
your computing device, if the issue cannot be solved remotely.
Desktop Only Hardware Support Product number: U6578E
Data sheet | HP 290 G3 Microtower PC HP recommends Windows 10 Pro for business
HP 290 G3 Microtower PC
Messaging Footnotes
1 Not all features are available in all editions or versions of Windows. Systems may require upgraded and/or separately purchased hardware, drivers, software or BIOS update to take full advantage of Windows functionality. Windows 10 is
automatically updated, which is always enabled. ISP fees may apply and additional requirements may apply over time for updates. See http://www.windows.com.
2 For hard drives, GB = 1 billion bytes. TB = 1 trillion bytes. Actual formatted capacity is less. Up to 36GB of system disk (for Windows 10) is reserved for system recovery software.
3 Multicore is designed to improve performance of certain software products. Not all customers or software applications will necessarily benefit from use of this technology. Performance and clock frequency will vary depending on application
workload and your hardware and software configurations. Intel’s numbering, branding and/or naming is not a measurement of higher performance.
4 Sold separately or as an optional feature.
1 Not all features are available in all editions or versions of Windows. Systems may require upgraded and/or separately purchased hardware, drivers, software or BIOS update to take full advantage of Windows functionality. Windows 10 is
automatically updated, which is always enabled. ISP fees may apply and additional requirements may apply over time for updates. See http://www.windows.com.
5 Sold separately or as an optional feature. Wireless access point ad internet service required. Availability of public wireless access points limited. The specifications for the 802.11ac WLAN are draft specifications and are not final. If the final
specifications differ from the draft specifications, it may affect the ability of the notebook to communicate with other 802.11ac WLAN devices.
automatically updated, which is always enabled. ISP fees may apply and additional requirements may apply over time for updates. See http://www.windows.com/
2 HD content required to view HD images.
3 For hard drives and solid state drives, GB = 1 billion bytes. TB = 1 trillion bytes. Actual formatted capacity is less. Up to 36 GB (for Windows 10) of system disk is reserved for the system recovery software.
4 Optical drives are optional or add on features. Duplication of copyrighted material is strictly prohibited. Actual speeds may vary. Double Layer media compatibility will widely vary with some home DVD players and DVD-ROM drives.
5 Keyboards and mice are optional or add-on features.
6 USB Wired Business Slim Antimicrobial Keyboard: China only.
7 USB Antimicrobial Mouse: China only.
8 Based on US EPEAT® registration according to IEEE 1680.1-2018 EPEAT®. Status varies by country. Visit www.epeat.net for more information.
9 Card sold separately.
10 (1) full-height PCI.
11 Wireless cards are optional or add-on features and requires separately purchased wireless access point and internet service. Availability of public wireless access points limited.
12 Integrated Intel Wi-Di software is available on select models only and requires separately purchased projector, tv or computer monitor with an integrated or external Wi-Di receiver. External Wi-Di receivers connect to the projector, tv or
computer monitor via a standard VGA, HDMI cable, also sold separately.
13 Full availability of 4 GB or more of memory requires a 64-bit operating system. With Windows 32-bit operating systems, the amount of usable memory is dependent upon your configuration, so that above 3 GB all memory may not be
available due to system resource requirements. Memory modules support data transfer rates up to 2666 MT/s; actual data rate is determined by the system’s configured processor. See processor specifications for supported memory data
rate.
14 All power supplies are not available in every region.
15 USB Hardened Mouse: India only.
16 McAfee LiveSafe™: 1 year subscription for LATM, 30 days for other regions except LATM.
18 Your product does not support Windows 8 or Windows 7, In accordance with Microsoft’s support policy, HP does not support the Windows 8 or Windows 7 operating system on products configured with Intel® 8th generation and forward
application workload and your hardware and software configurations. Intel’s numbering, branding and/or naming is not a measurement of higher performance.
20 Security cable lock supported (sold separately).
21 TPM 2.0 support (dTPM): TPM feature will not be supported on machine pre-configured with FreeDOS. In same cases, machines pre-configured with Windows OS might ship with TPM turned off.
22 HDMI/VGA ports will be covered up when a non-internal graphics processor is configured on shipped machine.
23 PS/2 Port: optional.
24 Intel® Turbo Boost technology requires a PC with a processor with Intel Turbo Boost capability. Intel Turbo Boost performance varies depending on hardware, software and overall system configuration. See
technology is dependant on 3rd party software providers. Compatibility with future "virtual appliances" is yet to be determined.
31 (1) 3-in-1 SD card reader: Sold separately or as an optional feature.
32 For full Intel® vPro™ functionality, Windows, a vPro supported processor, vPro enabled chipset, vPro enabled wired LAN card and discrete TPM 2.0 are required. See http://intel.com/vpro.
33 Physical cable lock for better cable management.
© Copyright 2019 HP Development Company, L.P. The information contained herein is subject to change without notice. The only warranties for HP products and services are set forth in the
express warranty statements accompanying such products and services. Nothing herein should be construed as constituting an additional warranty. HP shall not be liable for technical or editorial
errors or omissions contained herein.
Intel, Celeron®, Core, Pentium, Intel vPro™ are registered trademarks or trademarks of Intel Corporation in the U.S. and/or other countries. Bluetooth is a trademark of its proprietor, used by HP Inc.
under license. NVIDIA, GeForce, are trademarks and/or registered trademarks of NVIDIA Corporation in the U.S. and other countries. AMD and Radeon are trademarks of Advanced Micro Devices, Inc.
ENERGY STAR is a registered trademark owned by the U.S. Environmental Protection Agency. All other trademarks are the property of their respective owners.
4AA7-6452, December 2019
DOC-M
HP ProDisplay P191 18.5-inch LED Backlit Monitor
Your everyday business monitor just got an upgrade. Practical, reliable,
stylish, and environmentally conscious. What’s not to love?
Efficiently grow and maintain your business with proven HP Stability now and peace of mind for the future
quality and reliability, a stable lifecycle, HP accessory Maintain product consistency across staggered
compatibility, and energy savings. Do more every day and deployments, ease transitions, and help reduce support
help save money with a monitor that goes the distance. costs with a minimum one-year lifecycle commitment from
Essential business features HP. Support identical installations and unify operations
worldwide with product availability in 145+ countries. Get
Support your business needs wherever you need a solid improved reliability from HP quality testing that puts our
performing monitor at a competitive price with an monitors through their paces before you do. Rest assured
18.5-inch diagonal LED business display that delivers with the three-year standard limited warranty. Select
vibrant text and graphics presentation and is thin, light, and optional HP Care Pack Services2 to extend your protection.
easy to position on the desk.
Earn your environmental stripes
Deliver clear views for single and multiple users with wide
viewing angles. High contrast ratios and fast response Help reduce power consumption and energy costs with an
times keep your content crisp and readable. Work intelligent, energy-efficient design. Mercury-free LED
comfortably with up to 30 degrees of tilt, and easily backlighting, a BFR/PVC-free design3, and arsenic-free4
connect to devices with the convenient VGA input. Minimize display glass are just a few of the display’s responsible
clutter and simplify setup and deployment with the internal details. Lower your overall bottom line with award-winning
power supply. eco-certifications, including ENERGY STAR®, EPEAT® Gold5,
and TCO.
Compatibility with HP accessories
Customize your work space with options like the HP Quick
Release, HP Speaker Bar, and HP USB Graphics Adapter.1
Free up valuable space and lift the monitor off the desk
with a 100-mm standard VESA pattern that supports swing
arm and wall mounting.1
HP ProDisplay P191 18.5-inch LED Backlit Monitor
Part number C9E54AA
Panel type TN with LED backlight
Viewable image area 47 cm (18.5 in) diagonally measured
Viewing angle Horizontal: 170 degrees
Vertical: 160 degrees
6
Brightness 250 nits (cd/m2)
6
Contrast ratio Static: 1000:1
Dynamic: 3,000,000:1
Response rate6 5 ms
Frequency Horizontal: 24 KHz-83 KHz
Vertical: 50 Hz-76 Hz
Aspect ratio 16:9
Native resolution 1366 x 768 @ 60 Hz
Resolutions supported 640 x 480 @ 60 Hz, 720 x 400 @ 70 Hz , 800 x 600 @ 60 Hz, 1024 x 768 @ 60 Hz, 1280 x 720 @ 60 Hz
1280 x 1024 @ 60 Hz, 1366 x 768 @ 60 Hz
Input signal VGA
User controls Menu, Minus (“-“), Plus (“+”), “OK"/Auto and Power
(on-screen display)
Power consumption Maximum: 25 W
Typical: 20 W
Power saving: 0.5 W
Dimensions Unpacked: 44.93 x 4.75 x 34.1 cm (17.69 x 1.87 x 13.43 in)
(w x d x h) Head only: 44.93 x 4.75 x 27.59 cm (17.69 x 1.87x 10.86 in)
Weight Unpacked: 3,0 kg (6.6 lb)
Head only: 2,7 kg (6.0 lb)
Base features Tilt: -5 degrees to +25 degrees
Environmental Operating: 5° to 35° C (41° to 95° F)
Non-operating: -20° to 60° C (-34° to 140° F)
Certification and TCO Displays, ISO 9241-307, CISPR Requirements, VCCI Approvals, KC and KCC (Korean) Requirements, CSA 60950-1,
compliance UL 60950-1, EN55022 Class B, CNS 13438 Class B, IEC 60950-1, China Energy Label (CEL), China MEPS, Korea MEPS
(pending, Energy Boy), SmartWay – NA only - Energy logistics, EUP Lot 6 Tier 1 AS/NZS 3548 Class B Approval, “GS”
Mark, TUV Approvals, GEEA, CE Marking, FCC Part 15 class B Approval, ENERGY STAR® qualified, EN55024 Class B,
EN60950 -1, CUL, CCIB, CCEE, IT ECO (EDS), EPEAT® Gold5 (select regions)
Limited warranty Three-year parts, labor, and on-site service (3/3/3) standard limited warranty. Optional HP Care Pack Services2 are
extended service contracts that extend your protection beyond the standard warranties.
© Copyright 2012 Hewlett-Packard Development Company, L.P. The information contained herein is subject to change without notice. The only
warranties for HP products and services are set forth in the express warranty statements accompanying such products and services. Nothing
herein should be construed as constituting an additional warranty. HP shall not be liable for technical or editorial errors or omissions contained
herein. ENERGY STAR is a registered mark owned by the U.S. government. November 2012
Data sheet
HP LaserJet Pro MFP M28a Printer HP LaserJet Pro MFP M28w Printer
1/6
Data sheet | HP LaserJet Pro MFP M28 Printer series
Product walkaround
HP LaserJet Pro MFP M28w shown
Series at a glance
Model HP LaserJet Pro MFP M28a Printer HP LaserJet Pro MFP M28w Printer
Product number W2G54A W2G55A
Print speed up to 18 ppm, A4
Input/Output capacity 150-sheet input capacity, 100-sheet output
LED display Yes
Cartridge yield, black/colour (in pages) In-box: ~500 A: ~1000
Networking Not available Wireless networking (802.11b/g/n)
Apple AirPrint™; Google Cloud Print 2.0; Mopria-certified; Wi-Fi Direct;
Mobile printing capability Not available
HP Smart App
2/6
Data sheet | HP LaserJet Pro MFP M28 Printer series
Technical specifications
Model HP LaserJet Pro MFP M28a Printer HP LaserJet Pro MFP M28w Printer
Product number W2G54A W2G55A
Functions Print, copy, scan
Control panel LED ICON LCD
Print
Print technology Laser
Print speed1 Black (A4, normal) Up to 18 ppm;
First page out Black (A4, ready):
ready) As fast as 8.2 sec; Black (A4, ready):
ready) As fast as 8.2 sec;
Black (A4, sleep):
sleep) As fast as 8.2 sec; Black (A4, sleep):
sleep) As fast as 8.3 sec;
Print resolution Black (best):
(best) Up to 600 x 600 dpi;
Technology: HP FastRes 600;
Technology
Monthly duty cycle2 Up to 8,000 pages A4; Recommended monthly page volume:
volume 100 to 1,000
Printer smart software features HP Auto-On/Auto-Off Apple AirPrint™, Mopria-certified, HP Auto-On/Auto-Off, Wi-Fi Direct, HP
Smart App
Standard print languages PCLmS; URF; PWG
Print area Print margins Top: 2 mm, Bottom: 2 mm, Left: 2 mm, Right: 2 mm; Maximum print area: 216 x 297 mm
Copy
Copy speed Black (A4):
(A4) Up to 18 cpm
Copier specifications Number of Copies; Lighter/Darker; Optimise; Paper; Maximum number of copies:
copies Up to 99 copies; Copy resolution:
resolution 600 x 400 dpi; Reduce/Enlarge
Reduce/Enlarge: 25 to
400%;
Scan
Scan file format JPG, RAW (BMP), PNG, TIFF, PDF
Scanner specifications Scanner type: Flatbed; Scan technology: CIS; Scan input modes: Scanning via HP LaserJet Software Scan or TWAIN-compliant or WIA-compliant software;
Twain version: Version 2.1 (Windows 7 or higher); Scan size maximum (flatbed, ADF): 216 to 297 mm; Optical scan resolution: Up to 600 ppi
3/6
Data sheet | HP LaserJet Pro MFP M28 Printer series
Model HP LaserJet Pro MFP M28a Printer HP LaserJet Pro MFP M28w Printer
Product number W2G54A W2G55A
Scanner advanced features No
Recommended monthly scan volume 250 to 2,000
Scannable area Maximum media size (flatbed):
(flatbed) 216 to 297 mm;
Bit depth/ Grey scale levels 24 bit / 256
Fax
Fax specifications Telecom compliance:
compliance Wireless: EU RED 2014/53/EU, EN 301 489-1 V2.1.1,
EN 301 489-17 V3.1.1, EN 300 328 V2.1.1.
Processor speed 500 MHz
Connectivity
Standard Hi-Speed USB 2.0 port Hi-Speed USB 2.0 port; Built-in Wi-Fi 802.11b/g/n
Wireless No Yes
Mobile printing capability No Apple AirPrint™; Google Cloud Print 2.0; Mopria-certified; Wi-Fi Direct; HP
Smart App
Supported network protocols No TCP/IP: IPv4; IPv6; IP Direct Mode; LPD; SLP; Bonjour; WS-Discovery;
BOOTP/DHCP/AutoIP; SNMP v 1/2/3; HTTP/HTTPS
Memory Standard: 32 MB; Maximum
Standard Maximum: 32 MB
Media handling
Number of paper trays Standard 1 input tray ; Maximum:
Standard: Maximum 1 input tray
Media types Plain paper, envelope, postcard, label
Media size Custom (metric):
(metric) 105 x 148 to 216 to 297 mm ; Supported (metric):
(metric) A4; A5; A6; Envelopes (C5, DL); Custom
Media handling Standard input:
input 150-sheet input tray
Standard output:
output 100-sheet output bin
Media weight 65 to 120 g/m²;
4/6
Data sheet | HP LaserJet Pro MFP M28 Printer series
Model HP LaserJet Pro MFP M28a Printer HP LaserJet Pro MFP M28w Printer
Product number W2G54A W2G55A
Input capacity Tray 1:
1 Sheets: 150; Envelopes: 10
Maximum: Up to 150 sheets
Maximum
Standard: Up to 100 sheets
Standard
Output capacity Envelopes: Up to 10 envelopes
Maximum: Up to 100 sheets
Maximum
Windows® 10, 8.1, 8, 7: 32/64-bit, 2 GB available hard disk space, CD-ROM/DVD drive or Internet connection, USB port, Internet Explorer. Apple® macOS
Compatible operating systems High Sierra (v10.13), macOS Sierra (v10.12), OS X EI Capitan (v10.11); 1.5 GB available hard disk space; Internet required; USB Linux (For more information,
see https://developers.hp.com/hp-linux-imaging-and-printing)
Compatible network operating Windows® 10, 8.1, 8, 7: 32-bit/64-bit, 2 GB available hard disk space, CD-ROM/DVD drive or Internet connection, USB port, Internet Explorer. Apple®
systems macOS High Sierra (v10.13), macOS Sierra (v10.12), OS X EI Capitan (v10.11); 1.5 GB available hard disk space; Internet required; USB Linux (For more
information, see https://developers.hp.com/hp-linux-imaging-and-printing)
Minimum system requirements Windows: Windows® 10, 8.1, 8, 7: 32/64-bit, 2 GB available hard disk space, CD-ROM/DVD drive or Internet connection, USB port, Internet Explorer.;
Windows
Mac: Apple® macOS High Sierra (v10.13), macOS Sierra (v10.12), OS X EI Capitan (v10.11); 1.5 GB available hard disk space; Internet required; USB
Mac
For Windows OS: HP Software Installer; HP Software Uninstaller (exclude Win8+); HP PCLmS Printer Driver; HP Device Experience (DXP); HP Web Services
Software included Assist (HP Connected); Device Setup & Software; Online user manuals; HP Printer Assistant; HP Scan Driver; HP Scan Application; HP Product Improvement
Study. For Mac OS: Welcome Screen (directs users to http://www.hp.com or OS App Source for LaserJet Software)
Security management Password-protected network embedded Web server Password-protected network embedded Web server; Enable/disable
Network ports; SNMPv1 community password change
Printer management HP Printer Assistant (UDC); HP Device Toolbox; HP Utility (Mac)
Dimensions and weight
Printer dimensions (W x D x H) Minimum 360 x 264 x 197 mm; Maximum
Maximum: 360 x 427 x 347 mm;
Package dimensions (W x D x H) 398 x 248 x 306 mm
Printer weight 5.4 kg
Package weight 6.9 kg
Operating environment Temperature: 10 to 32.5°C; Humidity
Temperature Humidity: 30 to 70% RH
Storage conditions Temperature: -20 to 60°C; Humidity
Temperature Humidity: 10 to 90% RH
Acoustics Acoustic power emissions:
emissions 6.5 B(A); Acoustic pressure emissions:
emissions 52 dB(A)
Requirements: 220V - 240V nominal at +/-10% (min 198V, Max 264V), 50 - 60Hz nominal at +/- 3Hz (min 47Hz, max 63Hz);
Requirements
Consumption: 365 watts (active printing), 2.9 (ready), 0.6 watts (sleep), 0.1 watts (auto-off /manual on) , 0.1 watts (manual off), 0.6 watts (auto-off/wake
Consumption
Power on USB);
Typical Electricity Consumption (TEC)3: Blue Angel: 0.456 kWh/Week; Energy Star: 0.417 kWh/Week;
Power supply type:
type Power requirements are based on the country/region where the printer is sold. Do not convert operating voltages. This will damage the
printer and void the product warranty.;
Energy savings feature technology HP Auto-on/Auto-off Technology
CISPR 22:2008 & CISPR 32:2012/EN 55032:2012 - Class B, EN 61000-3- CISPR 22:2008 & CISPR 32:2012/EN 55032:2012 - Class B, EN 61000-3-
Certifications 2:2014, EN 61000-3-3:2013, EN 55024:2010 2:2014, EN 61000-3-3:2013, EN 55024:2010
ENERGY STAR® qualified; EPEAT® Silver ENERGY STAR® qualified; EPEAT® Silver
Blue Angel compliant Yes, Blue Angel DE-UZ 205 Blue Angel compliant Yes; Blue Angel RAL-UZ 205
HP LaserJet Pro M28a Printer; Preinstalled HP Original Introductory Black HP LaserJet Pro M28w Printer; Preinstalled HP Original Introductory Black
What's in the box4 LaserJet Toner Cartridge (500 pages); Getting started guide; Setup poster; LaserJet Toner Cartridge (500 pages); Getting started guide; Setup poster;
Support flyer; Warranty guide; Software drivers and documentation on CD- Support flyer; EU declaration flyer (EU only); Warranty guide; Software
ROM; Power cord drivers and documentation on CD-ROM; Power cord; USB cable
Warranty One-year limited warranty
5/6
Data sheet | HP LaserJet Pro MFP M28 Printer series
Footnotes
1
World's smallest in-class footprint compared only to dimensions of majority of worldwide personal laser printers (defined as monochrome laser printers < €100 and monochrome laser MFPs < €150); HP internal research of
printer manufacturers' published specifications as of October 9, 2017 and Keypoint Intelligence-Buyers Lab 2017 study commissioned by HP. Market share as reported by IDC CYQ2 2017 Hardcopy Peripherals Tracker. Measured
footprint for HP LaserJet Pro M15 printer series is 649,30 square centimetres and for HP LaserJet Pro MFP M28 series is 956,13 square centimetres. For details, see http://www.keypointintelligence.com/products/samples/new-
hp-laserjet-series.
2
Available only on the HP LaserJet Pro MFP M28w only.
3
Requires the HP Smart app download. Features controlled may vary by mobile device operating system. Full list of supported operating systems and details at http://support.hp.com/us-en/document/c03561640. For details on
local printing requirements see http://www.hp.com/go/mobileprinting.
4
Measured using ISO/IEC 24734, excludes first set of test documents. For more information, see http://www.hp.com/go/printerclaims. Exact speed varies depending on the system configuration, software application, driver, and
document complexity.
5
Requires an Internet connection to the printer. Services may require registration. App availability varies by country, language, and agreements. For details, see http://www.hpconnected.com.
6
HP Auto-On/Auto-Off Technology capabilities subject to printer and settings; may require a firmware upgrade.
7
For details on local printing requirements see http://www.hp.com/go/mobile printing.
8
Wireless operations are compatible with 2.4 GHz operations only. Learn more at http://www.hp.com/go/mobileprinting. Wi-Fi is a registered trademark of Wi-Fi Alliance®.
9
Mobile device needs to be connected to Wi-Fi Direct® signal of a Wi-Fi Direct-supported AiO or printer prior to printing. Details at http://www.hp.com/go/mobileprinting. Wi-Fi Direct® is a registered trademark of Wi-Fi Alliance®.
document complexity.
2 Duty cycle is defined as the maximum number of pages per month of imaged output. This value provides a comparison of product robustness in relation to other HP LaserJet or HP Color LaserJet devices, and enables appropriate
deployment of printers and MFPs to satisfy the demands of connected individuals or groups.
3 Power requirements are based on the country/region where the printer is sold. Do not convert operating voltages. This will damage the printer and void the product warranty. Energy Star value typically based on measurement of
115V device.
4 HP Original Introductory Black LaserJet Toner Cartridge (500 page yield). Actual yields vary considerably based on images printed and other factors. For details see http://www.hp.com/go/learnaboutsupplies.
http://www.hp.com/uk
The product could differ from the images shown. © Copyright 2018 HP Development Company, L.P. The information contained herein is subject to change without notice. The only warranties for HP
products and services are set forth in the express warranty statements accompanying such products and services. Nothing herein should be construed as constituting an additional warranty. HP
shall not be liable for technical or editorial errors or omissions contained herein.
Published in EMEA 4AA7-2094, December 2018
DOC-M
6/6
Emergency & Exit Luminaires
X10
LED exit sign / emergency light according to DIN EN 60598-1,
EN 60598-2-22, EN 7010 and DIN EN 1838.
Model Description
X10UL Universal Mount Emergency Luminaire, 340 lm
X10UH Universal Mount Emergency Luminaire, 560 lm
Technical Data
Emergency Duration 3 hours
Protection Class II
IP64
Accessories
excluded universal LED 14-30m
**
**
2DW
2PW
DSA
70 Depth 60mm
50
25
26
7 312
www.shieldglobal.com 24
Emergency & Exit Luminaires
X40
Slightly curved high-grade exit sign and emergency luminaire
in Polycarbonate for Universal mounting. Signage with plugga-
ble, solvent-free, internally mounted pictogram. Pictogram set
included. This luminary can be used without pictogram as an
emergency lighting luminary with a clear cover. Escape route/
Exit sign/ emergency luminary according EN 60598-1, EN
60598-2-22 and EN 1838 norms.
Model Description
Universal Mount Emergency / Exit
X40WL
Luminaire, 300 lm
Universal Mount High Power
X40WH
Emergency Luminaire, 520 lm
Technical Data
Emergency Duration 3 hours
Accessories
BALL2 FBX40
Dimensions wall
170 170
340 60 340 90
27 www.shieldglobal.com
Emergency Luminaires
M10
Compact emergency luminaire for lighting of escape routes
with prismatic cover for optimized light distribution. The optional
recessed mounting frame hides the luminaire elegant within
the ceiling.
Model Description
M10UL Universal Mount Emergency Luminaire
Technical Data
Emergency Duration 3 hours
Accessories
IP54
LED
ø5 250
180
295mm 275mm
www.shieldglobal.com 20
Emergency Luminaires
M20
The M20 LED emergency luminaire is a true all-rounder series
of emergency lights. They are ready for almost all
requirements and provide always the right solution. As many as
four different lenses for different light distribution are
available and make a perfect adaptation to the respective
mounting situation possible. These units can be used in surface
and recessed mount locations.
Model Description
M20CSH Corridor Illumination Surface Mount, IP40
M20CRH Corridor Illumination Recessed Mount, IP20
M20RSH Radial Illumination Surface Mount, IP40
M20RRH Radial Illumination Recessed Mount, IP20
M20HSH High Ceilings Surface Mount, IP40
M20HRH High Ceilings Recessed Mount, IP20
M20SSH Spotlight High Ceiling Surface Mount, IP40
M20SRH Spotlight High Ceiling Recessed Mount, IP20
Technical Data
Emergency Duration 3 hours
Max. Consumption 4.6 W LED
Lumen Output 360 lm
-5 °C up to +40 °C
Ambient Temperature -20 °C up to +30 °C
(in M20 - IP65 housing) IP20
Ingress Protection IP20 (recessed) LED
Accessories
IP65 housing for surface mount luminaires
(white or anthrazite).
M20 1P65
Square covers.
M20B1 / M20B2
M20S-APA
M20R-OEF
21 www.shieldglobal.com
Emergency Luminaires
M 0
Classic bar-shaped polycarbontate luminaire for wall or ceiling
mounting. Straight lines as well as the robust construction with
a high ingress protection allow versatile use.
Technical Data
Model Description
M50DH Ceiling Mount Emergency Luminaire, IP65, Shield
www.shieldglobal.com 20
Emergency Luminaire for Fluorescent Lamps EXLUX Home
Series 6009/5
WebCode 6009A
The 6009 series EXLUX emergency luminaire is suitable for use as safety lighting. It is lightweight and
requires minimal maintenance. The battery is housed in the external enclosure and powers the emergency
lighting for 1.5 or 3 hours. If one lamp is faulty, the luminaire switches to the working lamp. When the central
lock is opened, the luminaire is always disconnected from the power supply at all poles.
◤
ATEX / IECEx
Zone 0 1 2 20 21 22
Installation in ● ● ● ●
◤
Selection Table
Design size 2
Lamp wattage 18 W
Drilled holes Threaded plate Screw connections Stopping plug Connection terminals Product Type Art. No. Weight
solid max. kg
3 x M20 2x SS430 stainless steel Can be ordered as Can be ordered as 4 mm² 6009/522-9617-1622-71 238147 7.600
accessories accessories
Can be ordered as Can be ordered as 6 mm² 6009/522-9617-2622-71 239095 7.600
accessories accessories
3 x M25 2x plastic 2 x M25 Ø 7 – 17 mm 2 x M25 x 1.5 4 mm² 6009/522-9617-1611-71 225723 7.600
2 x M25 Ø 7 – 17 mm 2 x M25 x 1.5 6 mm² 6009/522-9617-2611-71 239270 7.600
Design size 4
Lamp wattage 36 W
Drilled holes Threaded plate Screw connections Stopping plug Connection terminals Product Type Art. No. Weight
solid max. kg
3 x M20 2x SS430 stainless steel Can be ordered as Can be ordered as 4 mm² 6009/542-9617-1622-71 238148 9.600
accessories accessories
Can be ordered as Can be ordered as 6 mm² 6009/542-9617-2622-71 239096 9.600
accessories accessories
3 x M25 2x plastic 2 x M25 Ø 7 – 17 mm 2 x M25 x 1.5 4 mm² 6009/542-9617-1611-71 225725 9.650
2 x M25 Ø 7 – 17 mm 2 x M25 x 1.5 6 mm² 6009/542-9617-2611-71 239301 9.600
Screw connections and stopping plugs made from moulded material are included loose with the product (installation required).
Threaded plate included.
The light fittings are supplied without fluorescent lamps or mounting material. These parts must be ordered as accessories.
11.12.2019 · PO·en Lighting
Emergency Luminaire for Fluorescent Lamps EXLUX
Home Series 6009/5
E2 ◤
Technical Data
Explosion Protection
Ambient temperature °C -30 … +50 °C
IECEx gas explosion protection Ex de mb IIC T4 Gb
IECEx dust explosion protection Ex tb IIIC T80 °C Db
ATEX gas explosion protection E II 2 G Ex de mb IIC T4 Gb
ATEX dust explosion protection E II 2 D Ex tb IIIC T80 °C Db
EAC gas explosion protection 7 1 Ex d e mb IIC T4 Gb
EAC dust explosion protection 7 Ex tb IIIC T80°C Db
Certificates ATEX (PTB), Brazil (ULB), China (CQST), IECEx (PTB), Polen (CNBOP)
Ship approval BVIS, DNVGL
Electrical Data
Rated operational voltage AC 220 – 240 V
Frequency range 50 – 60 Hz
Battery operating voltage 6 V
Battery capacity 7 Ah
Self-test function With (standard)
Notes Disconnection of the light:
When opening the light
Switch with safety lock; when opening the central lock, all poles of the voltage supply to the ballast are disconnected; contacts of the
switching element are NC contacts, they can only switched on again when the lamp cover and the central locking system are closed.
In case of a lamp fault, the electronic ballast disconnects the defective lamp from the power supply.
Lighting Data
Number of lamps 2
Emergency light mode Continuous light Or stand-by light
Operating time 1.5 / 3h emergency lighting operation
Lamp G13 lamp base
Mechanical Data
Degree of protection IP (IEC 60598) IP66 / IP67
Protection class I (with inner PE connection)
Enclosure material Polyester resin, Glass fibre reinforced
Sealing material Silicone
Material translucent cover Polycarbonate
Lighting lock Central lock , For box spanner actuation
Installed terminal strip PE + N + L1 + L2 + L3 + L´
Type of connection cable Finely stranded
Solid
Enclosure colour Light grey (RAL 7035)
Impact strength (IK code) IK10 (IEC 62262)
Notes Connection terminals: Spring clamp terminal (2 free clamping units per pole)
Components
Ballast 6043-792-201
Through wiring With 6 conductors 2.5 mm²
Battery-Version NiCd battery, gas-tight
Material cable gland Polyamide, black
Lighting 11.12.2019 · PO·en
Exit Luminaires
X30
Emergency sign luminaire in accordance to DIN EN 60598-1,
DIN EN 60598-2-22 and DIN EN 1838.
Model Description
X30UL Universal Mounting Exit Luminaire
Technical Data
Emergency Duration 3 hours
3,5 17
RFX30 FBX30
ø5
180
Dimensions
34
125
90 ø15
33
wall
17
174
ø5
140
250 10
www.shieldglobal.com 26