Manchester City Stadium - Structural Case Study
Manchester City Stadium - Structural Case Study
- Siri
- Tushar
- Tejal
- Yuvan
- Tapish
Introduction
The Manchester City Stadium in Manchester,
England is also known as Etihad Stadium for
sponsorship reasons.
Home ground for Manchester City Football club with
a domestic footfall capacity of 53,400.
Fifth-largest in the Premier League and Tenth-largest
in the United Kingdom.
The roller-coaster like roof, toroidal in shape, visible
from miles around with a similar lightweight canopy
that swoops up and down over the stands in one
almost continuous wave.
Held up together by a tensioned system of
thread-like cables connected to 70 m high masts.
Design Background
Designed to accommodate over 60,000 and to cater to
variety of sporting events as well as non sporting ones.
Initial design was for athletics events for Commonwealth
games, and was later converted to football stadium.
Design of stadium to be based on the type of event to be
hosted.
The required seating bias dictated a bowl with high sides
on the east and west and low ends north and south,
allowing a single roof geometry to cover all seating and
leaving large open areas in the corners for pitch
ventilation and video screens.
Bowl structure of
stadium
Geotechnical and geological
properties
The made ground was contaminated to varying degrees with hydrocarbons, heavy
metals, and waste containing obstructions from old foundations.
The site had several mineshafts, and in the master planning the Stadium was positioned
to avoid them (though there was the possibility of old unrecorded shafts). Shallow
groundwater was encountered below rock head
The coal workings were predominantly collapsed where encountered, probably from
longwall mining beneath (in which a cutting head moves back and forth along a coal
face)
Remedial Works
These were designed to mitigate the effects of the abnormal features previously
identified, and included large-scale earthworks to form the platform.
As for contamination, the levels of chemicals acceptable to be left with respect to end
use were agreed with the regulators. Several 'hotspots'. primarily hydrocarbons, were
identified, excavated and disposed offsite.
Of the total 250 000m3 of material excavated, however, only 10% left the site
Playing area and seating bowl -
Spatial concept
The toroidal geometry of the roof combines with
the radial plan geometry to create a rising and
falling perimeter, with the roof, visually
separated from the seating, projecting overhead
to create a dynamic space that draws the eye
into the field of play.
Drainage Slope—The only gutter is located at the rear edge of the roof. Each rafter and
cladding panel was assessed such that there was always a positive fall of 1.5° under all
service-load conditions.
Visual Deformation—The performance of the rafters was maintained at 1:100 for the
cantilever and 1:200 for the back spans. However the overall total deflection was controlled
by the deflection of the cable net, which was also limited to 1:100.
Shear Strain and Warping—The shear strain
was measured as the change in angle, and
the warping was measured as the mean
change in distance.
- https://en.wikipedia.org/wiki/City_of_Manchester_Stadium
- https://www.aisc.org/globalassets/modern-steel/archives/2003/12/2003v12_building_tension.pdf
- https://www.newsteelconstruction.com/wp/award-south-stand-expansion-etihad-stadium/
THANK YOU!