Standard Operation Procedure (In English)

The document outlines the application process for building permits and completion certificates in Yangon, Myanmar. It details the necessary documents, procedures, fees, and timelines for (1) building permits with a demarcation map, (2) building permits without a demarcation map, and (3) building completion certificates. The process involves submitting an online application with required documents, paying fees, inspections, and approval through the Yangon Building Permit System website.

Uploaded by

Martin Naing
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
112 views25 pages

Standard Operation Procedure (In English)

The document outlines the application process for building permits and completion certificates in Yangon, Myanmar. It details the necessary documents, procedures, fees, and timelines for (1) building permits with a demarcation map, (2) building permits without a demarcation map, and (3) building completion certificates. The process involves submitting an online application with required documents, paying fees, inspections, and approval through the Yangon Building Permit System website.

Uploaded by

Martin Naing
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 25

16.

Yangon City Development


Committee
1. Procedure of the application for building permit and building completion permit

1.1 Low Risk Building

1.1.1 Building Permit with D-Map

Necessary a) Application form for building permit (online fill-up)


documents b) Power of Attorney (if needed)
submitted by
c) Declaration of Responsibility of the Applicant
applicant
d) Declaration of Responsibility signed by the Certified Professional
In-Charge of the Architectural Design and Construction

e) The scanned original National Registration Card of the


applicant (NRC)

f) The scanned original Demarcation Map (D-Map) issued by


respective department within 3 years and grant or Evidence of
Land Ownership

g) Recommendation letter of the Engineering Department


(Roads & Bridges) (if needed)

h) Architectural Drawings

i) Photo Report of the existing environment of the projected


building

j) Suggestion letter of the Fire Services Department (if building


concerned by the section 17 of Myanmar Fire Force Law)

k) Recommendation letter signed by (10) neighboring plots of


land (if needed)

Procedures a) The bulding permit together with the necessary documents


and Building Design which is recommended by the certified
professional Engineer or architecture shall be submitted on
the YBPS website.

16-3
b) The Development Area Permit Section scrutinizes the building
design and necessary documents

c) If the file is complete, the applicant is informed that 100%


Scrutinization Fees is paid through the system. If some
elements are missing in the application file, the applicant is
informed to modify its application.

d) The applicant pays fees through the system.

e) Once the payment has been made, the Development Area


Inspection Team conducts site inspection.

f) The Development Area Inspection Team sends the site


inspection report to the Development Area Permit Section.

g) In accordance with the rules, regulations and specifications,


the Development Area Permit Section scrutinizes the site
inspection report, the projected building design and
documents.

h) After having the instruction to approve, the building permit is


sent to the applicant through the system.

Service Fee See the Table of Service Fees.

Time 15 working days

Place for www.ybps.ycdc.gov.mm


Submission

The Signing Deputy Director (Assistant Chief Engineer)


Status/ Rank

Remarks Checklists of Development Area Permit Section and the Inspection


Team, Building Categorization Matrix, necessary documents,
Declaration Forms, Procedures, Mapping Procedures, Service
Fees are uploaded on www.ybps.ycdc.gov.mm website to easily
download by public and the original documents are needed to
scan and submit.

16-4
1.1.2 Building Permit Without D-Map

Necessary a) Application form for building permit (online fill-up)


documents b) Declaration of Responsibility of the Applicant
submitted by
c) Declaration of Responsibility signed by the Certified Professional
applicant
In-Charge of Architectural Design and Construction

d) The scanned original National Registration Card of the


applicant (NRC)

e) Land Ownership document agreement

f) Clearance Letter from ward office on no disputes of tenant


and Landlord

g) Consent Letter from adjacement land owners

h) Architectural Drawings

i) Recommendation letter of the Engineering Department (Roads


& Bridges) (if needed)

j) Photo Report of the existing environment of the projected


building

k) Suggestion letter of the Fire Services Department (if building


concerned by the section 17 of Myanmar Fire Force Law)

Procedures a) The bulding permit together with the necessary documents


and Building Design which is recommended by the certified
professional engineer or architecture shall be submitted on
the YBPS website.

b) The Development Area Permit Section will scrutinize the


building design and necessary documents.

c) If the file is complete, asked for the payment of the Land Registry
verification fees and site inspection fees to Urban Land
Administration Department (ULAD) through the system. If the

16-5
Urban Land Administration Department (ULAD) replies, the
applicant is electronically informed to pay 100% Scrutinization
fees, Land Registry verification fees and site inspection fee. (If
some elements are missing in the application file, the
applicants is informed to modify its application)

d) The applicant pays fees through the system.

e) Once the payment has been made, the Development Area


Inspection Team conducts site inspection.

f) The inspection team sends the inspection report to the


Development Area Permit Section.

g) In accordance with the rules, regulations and specifications, if


the plot is kind of which can be permitted, it is posted in the
newspapers whether there is any objection. If the plot is kind
of which cannot be permitted, the applicant is informed
through the system that the application is cancelled.

h) If there is any other objection within the deadline, the application


is instructed to approved and the Building Permit is sent to
the applicant through the system.

Service Fee See the Table of Service Fees.

Time 15 working days (It counts from when the press release date is
over.)

Place for www.ybps.ycdc.gov.mm


Submission

The Signing Deputy Director (Assistant Chief Engineer)


Status/ Rank

Remarks Checklists of Development Area Permit Section and the Inspection


Team, Building Categorization Matrix, necessary documents,

16-6
Declaration Forms, Procedures, Mapping Procedures, Service Fees
are uploaded on www.ybps.ycdc.gov.mm website to easily download
by public and the original documents are needed to scan and
submit.
1.1.3 Building Completion Certificate (BCC)

Necessary Low Risk


documents a) As-built Architectural and Structural Drawing
submitted by
b) Declaration of Responsibility of Certified Professional
applicant
In-charge of Structural and Construction (if any)

c) Fire Safety Certificate (if any)

d) If the elevator is installed in the building, Elevator/


Escalator Usage Certificate of the Directorate of Industry
Supervision and Inspection (the Electricity Inspection
Department)

e) Photos of the building taken from front/ back/ left/


right

Procedures a) After building completion, the Development Area


Inspection Team comments to apply for Building
Completion Certificate (BCC) by submitting necessary
documents in E Log Book, and informs the certified
professional in charge of design and construction to
apply for BCC.

b) The Building Completion Certificate (BCC) together with


the necessary documents shall be submitted on the
YBPS website.

c) The Development Area Inspection Team conducts site


inspection whether the submitted documents are
complete or not.

16-7
d) If it is complete, the applicant is informed through the
system to pay 25% of scrutinizing fee.

e) The scrutinizing fee is electronically paid by the applicant


through the system.

f) After getting instruction to approve, the Building Completion


Certificate is sent to the applicant through the system.

Service Fee 25% of scrutinizing fee (within the permit period)

Time 7 working days

Place for Submission www.ybps.ycdc.gov.mm

The Signing Status/ Assistant Director (Executive Engineer)


Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, necessary documents, Declaration Forms,
Procedures, Mapping Procedures, Service Fees are
uploaded on www.ybps.ycdc.gov.mm website to easily
download by public and the original documents are
needed to submit by scanning.

1.2 Medium Risk Building

1.2.1 Building Permit

Necessary Approval in Principle


documents a) Application form for building permit (online fill-up)
submitted by
b) Power of the Attorney (if needed)
applicant
c) Declaration of Responsibility of the Applicant

d) Declaration of Responsibility signed by the Certified


Professional in-charge of Architectural Design

16-8
e) The scanned original National Registration Card of the
applicant (NRC)

f) The scanned original Demarcation Map (D-Map) issued


by respective department within 3 years and grant or
Evidence of Land Ownership

g) Suggestion letter of the Engineering Department (Roads &


Bridges) (if needed)

h) Architectural Drawings

i) Photo Report of the Existing Environment of the


projected building

j) Traffic Impact Assessment Report (if needed)

k) Environmental Compliance Certificate (if needed)

l) Theodolite Reading of the adjacent buildings (if the


adjacent building is above 3 storey)

m) Recommendation letter signed by (10) neighboring


plots of land (if needed)

Final Building Permit

n) Declaration of Responsibility signed by the Certified


Professional In-charge of the Structural Design

o) Declaration of Responsibility signed by the Certified


Professional In-charge of the Construction

p) Declaration of Responsibility signed by the Certified


Professional In-charge of the Water Supply and
Sanitation

q) Declaration of Responsibility signed by the Certified


Professional In-charge of the Deep Excavation Design
(if needed)

16-9
r) Declaration of Responsibility signed by the Piling
Company (if needed )

s) Updated Drawings (Architecture and Structure)

t) Structural Calculation and Soil Investigation Report

u) Water connection and sanitation designs

v) Suggestion letter of the Fire Services Department

w) Approved Drawings from the Fire Services Department

x) Persons with Reduced Mobility (PRM) study (if needed


by the chapter 2.7 of the MNBC)

Procedures Approval in Principle

a) The approval in principle together with the necessary


documents and Building Design which is recommended
by the certified professional engineer or architecture
shall be submitted on the YBPS website.

b) The Development Area Permit Section will scrutinize


the building design and necessary documents.

c) If the file is complete, the applicant is informed that


10% Scrutinization Fees to be paid through the system.
If some elements are missing in the application, the
applicant is informed to submit missing facts.

d) The applicant pays fees through the system.

e) Once the payment has been made, the Development


Area Inspection Team conducts site inspection.

f) The inspection team sends the inspection report to the


Development Area Project Section through the system

16-10
g) In accordance with the rules, the regulations and
specifications, the Development Area Permit Section
scrutinizes the site inspection report, the projected
building design and documents.

h) If the file is complete, approval in principle is sent to


the applicant through the system.

Final Building Permit

Final Building permit is applied for within 6 months after


having approval in principle.

i) The certified professional engineer or architecture


submits building design in accordance with Approval in
Principle on the YBPS website.

j) The Development Area Permit Section scrutinizes the


building design and necessary documents.

k) If the file is complete, Development Area Permit Section


scrutinizes the structural calculation and send to
Engineering Department (Water & Sanitation) through
the system.

l) After receiving the comments and reviews, the


Development Area Permit Section scrutinizes necessary
documents in accordance with the rules, regulations
and specifications. If there are any requirements, the
applicant is informed through the system.

m) If the file is complete, the applicant is informed to pay


90% Scrutinization Fees through the system.

n) The applicant pays fees through the system.

o) Once the payment has been made, the Building Permit


is sent to the applicant through the system.

16-11
p) To start the construction, the Licensed Contractor in-charge
of the building pays the guarantee deposit fees for
Building Construction through the system.

Service Fee See the Table of Service Fees.

Time Approval in Principle - 15 working days

Final Building Permit - 15 working days

Place for Submission www.ybps.ycdc.gov.mm

The Signing Status/ Deputy Director General (Chief Engineer)


Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, Building Categorization Matrix, necessary
documents, Declaration Forms, Procedures, Mapping Procedures,
Service Fees are uploaded on www.ybps.ycdc.gov.mm website
to easily download by public and the original documents
are needed to scan and submit.

1.2.2 Building Completion Certificate (BCC)

Necessary Medium Risk


documents a) As-built Architectural and Structural Drawing
submitted by
b) Water and Sanitation Design Drawings
applicant
c) Elevator/Escalator Usage Certificate of the Directorate
of Industry Supervision and Inspection (the Electricity
Inspection Department) if the elevator is installed in
the building

d) Recommendation letter of Yangon Electricity Supply


Corporation if transformers are needed to be installed

e) Fire Safety Certificate of Fire Services Department (if any)

16-12
f) Theodolite reading

g) Recommendation letter of the Internal Revenue


Department, claiming that tax matter are done

h) Photos of the building taken from front/ back/ left/


right and photos of meter, water motor, sewage lake

i) Outside the façade of the building to install 2 digital


CCTV camera of outdoor type with night vision, of 2
mega pixel and memory storage for up to 30 days and
of UPS or Battery Back Up that can continue to use
cameras and DVRs for 1 hour when electricity goes off.
Proof of availability for public use to cover the road in
front of the building for security

Procedures a) After building completion, the Development Area Inspection


Team comments to apply for Building Completion
Certificate (BCC) by submitting necessary documents in
E Log Book, and informs the certified professional
Engineer or Architecture to apply for BCC.

b) Building Completion Cerificate (BCC) together with the


necessary documents which is recommended by the
certified professional engineer or architecture shall be
submitted on the YBPS website.

c) After scrutinizing whether the submitted documents are


complete or not, the Development Area Inspection Team
conducts site inspection cooperated with Engineering
Department (Water & Sanitation), Engineering
Department (Water Flow Management), Engineering
Department (Roads & Bridges).

d) If the inspection report is resent, the Development Area


Inspection Team scrutinizes it in accordance with
regulations and specifications and if there is any
requirements, the applicant is informed through the
system.

16-13
e) If the application is complete and the instruction to
approve is got, the applicant is informed through the
system to pay 25% of scrutinizing fee for the Building
Completion Certificate.

f) The applicant makes payment electrically.

g) Once the payment has been made, the Building


Completion Certificate is sent to the applicant through
the system.

Service Fee 25 % of Scrutinizing Fee (during the permit period)

Time 7 working days

Place for Submission www.ybps.ycdc.gov.mm

The Signing Status/ Assistant Director (Executive Engineer)


Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, necessary documents, Declaration Forms,
Procedures, Mapping Procedures, Service Fees are uploaded
on www.ybps.ycdc.gov.mm website to easily download by
public.

1.3 High Risk Building

1.3.1 Building Permit

Necessary Approval in Principle


documents a) Application form for building permit (online fill-up)
submitted by
b) Power of the Attorney (if needed)
applicant
c) Declaration of Responsibility of the Applicant

d) Declaration of Responsibility signed by the Certified


Professional in-charge of Architectural Design

e) The scanned original National Registration Card of the


applicant (NRC)

16-14
f) The scanned original Demarcation Map (D-Map) issued by
relevant department within 3 years and grant or Evidence
of Land Ownership

g) Recommendation letter of Engineering Department


(Road & Bridges) (if needed)

h) Architectural Drawings

i) Photo Report of the existing environment of the projected


building

j) Traffic Impact Assessment Report (if needed)

k) Environment Compliance Certificate (if needed)

l) Theodolite Reading of the adjacent buildings (if the


adjacent building is above 3 storey)

m) Recommendation letter signed by (10) neighboring


plots of land (if needed)

Final Building Permit

n) Declaration of Responsibility signed by the Certified


Professional in-charge of the Structural Design

o) Declaration of Responsibility signed by the Certified


Professional in-charge of the Construction

p) Declaration of Responsibility signed by the Certified


Professional in-charge of the Electrical Study

q) Declaration of Responsibility signed by the Certified


Professional in-charge of the Mechanical Study (if
needed)

r) Declaration of Responsibility signed by the Certified


Professional in-charge of the Water Supply and
Sanitation

s) Declaration of Responsibility signed by the Certified


Professional in-charge of the Air-conditioning and
Mechanical Ventilation (ACMV) Study (if needed)

16-15
t) Declaration of Responsibility signed by the Certified
Professional in-charge of the Deep Excavation Design
(if needed)

u) Declaration of Responsibility signed by the Piling


Company (if needed)

v) Architectural and Structural Drawings

w) Structural calculations and soil investigation report

x) Mechanical Drawings (if needed )

y) Electrical Drawings and calculation report

z) The Water and Sanitation Designs and Calculations

aa) ACMV Drawings

bb) The Suggestion letter of the Fire Services Department

cc) The approved designs by the Fire Services Department

dd) A Person with Reduced Mobility (PRM) study if the


building is concerned by the list of buildings contained
in the chapter 2.7. of the MNBC)

Procedures Approval in Principle

a) The approval in principle together with the necessary


documents and Building Design which is recommended
by the certified professional Engineer or architecture
shall be submitted on the YBPS website.

b) The Development Area Permit Section will scrutinize


the building design and necessary documents.

c) If the file is complete, the applicant is informed that


10% Scrutinization Fees to be paid through the system.
If some elements are missing in the application, the
applicant is informed to submit missing facts.

d) The applicant pays fees through the system.

16-16
e) Once the payment has been made, the Development
Area Inspection Team, Engineering Department (Water
Flow Management), Engineering Department (Water &
Sanitation), Engineering Department (Roads & Bridges)
and Urban Land Administration Department make
inspection on the construction site.

f) In accordance with the rules, regulations and


specifications, the Development Area Permit Section
scrutinizes the site inspection report, the projected
building design and documents.

g) If the file is complete, it will be necessary to submit to


the YCDC Committee Members' Meeting to get approval
in principle for the buildings from 9 storey to 12 storey.
The Yangon Regional Cabinet Meeting is reported to
get approval in principle for commercial buildings,
which will be built within the restricted area of the
Shwedagon Pagoda and are not more than 190 feet
above the mean sea level, and for above 12 storey
buildings.

h) After receiving the approval from the respective


meetings, Approval in Principle is sent to the applicant
through the system.

Final Building Permit

After getting the approval in principle, final building


permit is applied through the system.

i) The certified professional in-charge of design and


construction submits building design in accordance
with Approval in Principle on the YBPS website.

16-17
j) The Development Area Permit Section will scrutinize
the building design and necessary documents.

k) If the file is complete, the Development Area Permit


Section scrutinizes architecture, structure and M&E design
of the buildings having from 9 storey to 12 storey. If the
buildings are 13 storey and above, architecture, structure
and M&E design are sent to HPBC and scrutinized by
the High-Rise and Public Building Projects Committee
(HPBC).

l) If the project is satisfactory, the applicant is informed


that 90% Scrutinizing Fee to be paid through the
system.

m) The applicant pays fees through the system.

n) Once the payment has been made, the Building Permit


is issued through the system.

o) To start the construction, the Licensed Contractor in


charge of the building pays the guarantee deposit fees
for Building Construction through the system.

Service Fee See the Table of Service Fees.

Time From 9 to 12 storey,

Approval in Principle - 21 working days

Final Building Permit - 21 working days

Above 12 storey,

Approval in Principle - 21 working days

Final Building Permit - 28 working days

Place for Submission www.ybps.ycdc.gov.mm

16-18
The Signing Status/ Deputy Director General (Chief Engineer)
Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, necessary documents, Declaration Forms,
Procedures, Mapping Procedures, Service Fees are uploaded
on www.ybps.ycdc.gov.mm website to easily download by
public.
1.3.2 Building Completion Certificate (BCC)

Necessary High Risk


documents a) As-built Architectural and Structural Drawing
submitted by
b) Water and Sanitation Design Drawings
applicant
c) Electrical Design Drawings

d) Mechanical Design Drawings

e) Air-conditioning and Mechanical Ventilation (ACMV)


Design Drawings

f) If the elevator is installed in the building, Elevator/


Escalator Usage Certificate of the Directorate of
Industry Supervision and Inspection (the Electricity
Inspection Department)

g) Recommendation letter of Yangon Electricity Supply


Corporation if transformers are needed to be installed.

h) Recommendation letter of Fire Service Department

i) Theodolite Reading

j) Recommendation letter of the Internal Revenue


Department, claiming that tax matter are done

k) Photos of the building taken from front/ back/ left/


right and photos of meter, water motor, sewage lake

16-19
l) Outside the façade of the building to install 2 digital
CCTV camera of outdoor type with night vision, of 2
mega pixel and memory storage for up to 30 days and
of UPS or Battery Back Up that can continue to use
cameras and DVRs for 1 hour when electricity goes off.
Proof of availability for public use to cover the road in
front of the building for security

Procedures a) After building completion, the Development Area Inspection


Team comments to apply for Building Completion
Certificate (BCC) by submitting necessary documents in
E Log Book, and informs the certified professional in
charge of design and construction to apply for BCC.

b) The certified professional in charge of design and


construction applies for the BCC attached with
necessary documents on YBPS website.

c) After scrutinizing whether the submitted documents


are complete or not, the Development Area Inspection
Team conducts site inspection cooperated with Engineering
Department (Water & Sanitation), Engineering Department
(Water Flow Management), Engineering Department
(Roads & Bridges), Pollution Control & Cleansing
Department.

d) If the inspection report is resent, the Development Area


Inspection Team scrutinizes it in accordance with
regulations and specifications and if there is any
requirements, the applicant is informed through the
system.

e) If the application is complete and the instruction to


approve is got, the applicant is informed through the
system to pay 25% of scrutinizing fee for the Building
Completion Certificate.

16-20
f) The applicant makes payment electrically.

g) Once the payment has been made, the Building


Completion Certificate is sent to the applicant through
the system.

Service Fee 25 % of Scrutinizing Fee (during the permit period)

Time 7 working days

Place for Submission www.ybps.ycdc.gov.mm

The Signing Status/ Assistant Director (Executive Engineer)


Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, necessary documents, Declaration Forms,
Procedures, Mapping Procedures, Service Fees are
uploaded on www.ybps.ycdc.gov.mm website to easily
download by public.

2. Minor Building Works and Temporary Structural

Necessary a) Building Permit Application Form (online fill-up)


documents b) Power of Attorney (if needed)
submitted by
c) Declaration of Responsibility of Applicant
applicant
d) Declaration of Responsibility signed by the Certified
Professional in-charge of Architectural Design and
Construction

e) The scanned original National Registration Card of the


applicant (NRC)

f) Evidence of Land Ownership (D-Map is needed for


fencing)

g) Architectural Drawings (To paint red on the parts to be


renovated)

16-21
h) Photo Report of the existing environment of the projected
building

Procedures a) The bulding permit together with the necessary


documents and Building Design which is recommended
by the certified professional engineer or architecture
shall be submitted on the YBPS website.

b) The Development Area Permit Section scrutinizes the


building design and necessary documents.

c) If the file is complete, the applicant is informed that


100% Scrutinization Fees to be paid through the
system. If some elements are missing in the application
file, the applicant is informed to modify its application.

d) The applicant pays fees through the system.

e) Once the payment has been made, the Development


Area Inspection Team carries out site inspection.

f) The Development Area Inspection Team sends the site


inspection report to the Development Area Permit
Section.

g) The Development Area Permit Section scrutinizes the


inspection report as well as the submitted design and
documents with respect to rules, regulations and
specification.

h) If the application complete, the Minor Building Works


and Temporary Structural Permit is sent to the applicant
through the system.

Service Fee See the Table of Service Fees.

Time 7 working days

Place for Submission www.ybps.ycdc.gov.mm

16-22
The Signing Status/ Staff Officer (Assistant Engineer)
Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, necessary documents, Declaration Forms,
Procedures, Mapping Procedures, Service Fees are uploaded
on www.ybps.ycdc.gov.mm website to easily download by
public and the original documents are needed to scan and
submit.

3. Technical Administrative Information Sheet (TAIS)

Necessary a) Application Form (online fill-up)


documents b) Receipt of Scrutinization Fees For TAIS
submitted by
c) Power of Attorney (if needed)
applicant
d) Location Map of the plot

e) Evidence of Land Ownership

f) The scanned original National Registration Card of the


applicant (NRC)

g) Brief about the Projected Development

h) Documents related to the project

Procedures a) The land owner or the certified professional in-charge


of design submits TAIS together with necessary documents
on the YBPS website.

b) The Development Area Permit Section scrutinizes the


building design and necessary documents.

c) If the application is complete, the Development Area


Inspection Team conducts site inspection and sends
the application to the Urban Planning Department.

16-23
d) The Inspection Team sends the Report to the
Development Area Permit Section through the system.

e) The Development Area Permit Section scrutinizes the


inspection report, comments of the Urban Planning
Department, the projected design and documents in
accordance with Rules, Regulations and Specifications
and the applicant is informed the project information
through the system.

Service Fee See the Table of Service Fees.

Time 10 working days

Place for Submission www.ybps.ycdc.gov.mm

The Signing Status/ Deputy Director General (Chief Engineer)


Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, necessary documents, Declaration Forms,
Procedures, Mapping Procedures, Service Fees are uploaded
on www.ybps.ycdc.gov.mm website to easily download by
public and the original documents are needed to scan and
submit.
4. Demolition Permit

Necessary a) Application form (online fill-up)


documents b) Power of Attorney (if needed)
submitted by
c) Grant or Evidence of Land Ownership
applicant
d) The scanned original National Registration Card of the
applicant (NRC)

e) Photo Report of the existing environment of the building


to be demolished

16-24
f) Declaration of Responsibility of the Certified Professional
in-charge of supervising the demolition works

g) Declaration of Responsibility of Applicant

Procedures a) The bulding permit together with the necessary


documents and Building Design which is recommended
by the certified professional Engineer or architecture
shall be submitted on the YBPS website.

b) The Development Area Permit Section scrutinizes the


building design and necessary documents.

c) If the file is complete, the applicant is informed through


the system to pay 100% Demolition Form Scrutinizing
Fee. If it is incomplete, the applicant will be informed
to resubmit the required documents.

d) The applicant pays fees through the system.

e) Once the payment has been made, the Development


Area Inspection Team conducts the site inspection.

f) The inspection report is sent to the Development Area


Permit Section.

g) The Development Area Permit Section scrutinizes the


site inspection report and the submitted documents in
accordance with rules, regulations and specifications.

h) After getting instruction for approval, the Demolition


Permit is informed to the applicant through the system.

Service Fee See the Table of Service Fees.

Time 10 working days

Place for Submission www.ybps.ycdc.gov.mm

16-25
The Signing Status/ Deputy Director (Assistant Chief Engineer)
Rank

Remarks Checklists of Development Area Permit Section and the


Inspection Team, necessary documents, Declaration Forms,
Procedures, Mapping Procedures, Service Fees are uploaded
on www.ybps.ycdc.gov.mm website to easily download by
public and the original documents are needed to scan and
submit.

16-26