RISK MANAGEMENT PLAN TEMPLATE v0.1
RISK MANAGEMENT PLAN TEMPLATE v0.1
<Project Name>
Classification Public
Risk Management Plan <Customer logo>
Version: 0.1
Copyright Notice
The information contained in this document is subject to change without notice and does
not carry any contractual obligation for COMPANYNAME. COMPANYNAME reserves the right
to make changes to any products or services described in this document at any time without
notice. COMPANYNAME shall not be held responsible for the direct or indirect consequences
of the use of the information contained in this document.
Revision History
Date Version Description Author (s)
04/01/2020 0.1 Draft Version John Doe
The reviewer signoff shall signify the recommendation for acceptance of this document.
Sign Off
Prepared By Acknowledged By
<Name> <Name>
Title: <Position> Title: <Position>
COMPANYNAME COMPANYNAME
Date: Date:
Accepted By Accepted By
<Name> <Name>
Title: <Position> Title: <Position>
<Customer Company Name > <Customer Company Name >
Date: Date:
Table of Contents
List of Tables........................................................................................................................6
List of Figures.......................................................................................................................7
1 Introduction.................................................................................................................8
4 Risk Identification......................................................................................................11
Appendix............................................................................................................................16
List of Tables
Table 1: Roles and responsibilities...........................................................................................................11
List of Figures
Figure 1: Probability and impact..............................................................................................................13
1 Introduction
Because Risks can have multiple impacts to a project, steps must be taken to identify,
mitigate, manage and control them. This document should detail these aspects including
information about how each team member or role provides support to these activities.
The Introduction should provide a general description of why risk management is essential
to effectively managing a project. It should also provide a brief overview of the important
definitions related to risk management, and the high-level sections that the document will
contain.
A risk is an event or condition that, if it occurs, could have a positive or negative effect on a
project’s objectives. The purpose of the Risk Management Plan for is to establish the
framework in which the project team will identify risks and develop strategies to mitigate or
avoid those risks. This plan also defines how risks associated with the project will be
recorded, and monitored throughout the lifecycle of the project.
Risk Management Approach – Deciding how to approach and conduct the risk
management activities for the project
Roles & Responsibilities – Defining how each team role contributes to managing the
risk process
Risk Identification – An initial and continuous effort to identify, quantify and
document risks as they are identified.
Risk Prioritization & Categorization – Evaluate identified risks to determine
probability of occurrence, impact, and timeframe.
Risk Response Planning - Establish an action plan for risk and assign responsibility.
Risk Monitoring, Controlling, & Reporting – Capture, compile, and report risk using
the Risk Register
This section provides a general description for the approach to be taken to identify and
manage the risks associated with the project. It should be a short paragraph or two
summarizing the approach to risk management on this project.
The basic Risk Management approach for is to identify critical risks and take necessary
action before issues arise that impact project objectives. Many different tools will be used as
part of this strategy.
The approach taken to manage risks for this project will include a methodical process by
which the project team will identify, score, and rank various risks. Risk information
identified by the project team will be entered into the Risk Register. The Senior Project
Director will maintain the Risk Register, and Risk information will be a principal topic in all
status meetings. New risks will be reviewed to determine if mitigation action is required.
The most likely and highest impact risks will be added to the project plan to ensure that the
assigned risk managers take the necessary steps to implement the mitigation response at
the appropriate time during the project. Risk managers will provide status updates on their
assigned risks in bi-weekly project team meetings, but only when the meetings include their
risk’s planned timeframe. Upon completion of the project, during the closing process, the
Senior Project Director will analyze each risk and review the risk management process.
Based on this analysis, the Senior Project Director will identify any improvements that can be
made to the risk management process for future projects. These improvements will be
captured as part of the lessons learned knowledge base.
The table below provides an overview of the Roles & Responsibilities for the Risk
Management activities.
Role Responsibilities
Role Responsibilities
4 Risk Identification
This section explains the process by which the risks associated with this project will be
identified. It should describe the method(s) for how the project team will identify risks, the
format in which risks are recorded, and the forum in which this process will be conducted.
Typical methods of identifying risks are conducting expert interviews, reviewing historical
information from similar projects, and conducting risk assessment meetings with the project
team and key stakeholders
Risk identification will involve the project team, and appropriate stakeholders, and will
include an evaluation of environmental factors, organizational culture and the project
625692386.docx Public Page 11 of 16
Risk Management Plan <Customer logo>
Version: 0.1
management plan including the project scope, schedule, cost, or quality. Careful attention
will be given to the project deliverables, assumptions, constraints, Work Breakdown
Schedule, cost/effort estimates, resource plan, and other key project documents.
The following methods will be used to assist in the identification of risks associated with
:
Expert Interviews
Risk Assessment Meetings
Historical Reviews of Similar Projects
Brainstorming
Interviewing
SWOT (Strengths, Weaknesses, Opportunities and Threats)
Diagramming
The Risk Register will be updated as needed and will be stored electronically in the project
library located at <file location>.
Once risks are identified it is important to determine and revisit the probability and impact
of each risk in order to allow the project manager to prioritize the risk avoidance and
mitigation strategy. Risks which are more likely to occur and have a significant impact on
the project will be the highest priority risks while those which are more unlikely or have a
low impact will be a much lower priority. This is usually done with a probability – impact
matrix. This section explains risks were qualified and prioritized for this project.
In order to determine the severity of the risks identified by the team, a probability and
impact factor will be assigned to each risk. This process will allow the Senior Project Director
to prioritize risks based upon the potential impact to the project.
As risks are assigned a probability and impact, the Senior Project Director will move forward
with risk mitigation/avoidance planning.
The probability and impact of occurrence for each identified risk will be assessed by the
Senior Project Director, with input from the project team using the following approach:
Probability
High – Between 80% and 100% probability of occurrence
Medium – Between 20% and 79% probability of occurrence
Low – Below 20% probability of occurrence
Impact
High – Risk that has the potential to greatly impact H
project cost, project schedule or performance
M
Medium – Risk that has the potential to slightly impact
project cost, project schedule or performance L
Impact
Low – Risk that has relatively little impact on cost, L M H
schedule or performance
Probability
Risks that fall within the RED and YELLOW zones will have a risk response plan which may
include both a risk response strategy and a risk contingency plan.
Each major risk (those falling in the Red & Yellow zones) will be assigned to a risk owner for
monitoring and controlling purposes to ensure that the risk will be addressed and managed
appropriately.
For each major risk, one of the following approaches will be selected:
Avoid – Eliminate the threat or condition, or avoid impact to the project objectives
by eliminating the cause. The project plan may need to be altered to account for
the risk avoidance. Avoidance may be achieved by changing scope, adding time, or
adding resources.
Mitigate – Identify ways to reduce the probability or the impact of the risk. These
steps may be costly and time-consuming, but could be preferable to allowing the
risk to go forward in an unmitigated state.
Accept –The project team accepts that the risk exists and makes no change to the
project plan to address the risk. No response strategy is identified.
Contingency –Define actions to be taken in response to risks.
Transfer – Shift the consequence and ownership of a risk by making another party
responsible (buy insurance, outsourcing, etc.).
The Senior Project Director will lead the project team in developing responses to each
identified risk. As more risks are identified, they will be qualified and the team will develop
the response. These risks will also be added to the Risk Register and the project plan to
ensure they are monitored at the appropriate times and are responded to accordingly.
For each risk that will be mitigated, the project team will identify ways to prevent the risk
from occurring or reduce its impact or probability of occurring. This may include
prototyping, adding tasks to the project schedule, adding resources, etc. Any secondary
risks that result from risk mitigation response will be documented and will follow the same
risk management protocol as primary risks.
This section should discuss how the risks in the project will be actively monitored. An
effective way to monitor project risks is to add those risks with the highest scores to the
project plan & schedule with an assigned risk manager. This allows the project manager to
recognize when these risks need to be monitored more closely and when to expect the risk
manager to provide status updates at the bi-weekly project team meetings. The key to risk
monitoring is to ensure that it is continuous throughout the life of the project and includes
the identification of trigger conditions for each risk and thorough documentation of the
process.
The Risk Register for is a log of all identified risks, their probability and impact to the
project, the category they belong to, mitigation strategy, and when the risk is estimated to
occur. This register will be created in the early planning phase of the project. Based on the
identified risks and timeframes in the risk register, applicable risks will be added to the
project plan. At the appropriate time in the plan—prior to when the risk is most likely to
occur—the project manager will assign a risk manager to ensure adherence to the agreed
upon mitigation strategy.
The level of risk on will be tracked, monitored, controlled and reported throughout the
project lifecycle. The most likely and greatest impact risks will be added to the project
schedule to ensure that proper monitoring occurs during the time of risk exposure. As risks
are added to the project schedule, a Risk Manager will be assigned. During the bi-weekly
project team meeting, the Risk Manager will discuss the status of their assigned risks. Only
risks which fall in the current time period will be discussed. Risk monitoring will be a
continuous process throughout the life of this project.
Critical risks will also be assigned a risk owner(s) who will track, monitor, and control their
assigned risks. The risk owner will also provide a weekly status report to the Project
Manager and Risk Management Team. This report should contain an assessment of the
effectiveness of each risk response action.
As Risk Events occur, the list will be re-prioritized during weekly reviews and risk
management plan will reflect any and all changes to the risk lists including secondary and
residual risks.
The Senior Project Director will notify the Project Sponsor of important changes to risk
status as in the weekly Project Status Report.
Appendix