ITP For Instrumentation Works
ITP For Instrumentation Works
Abbreviations:
CONTENTS
Section A
SECTION – A
GENERAL NOTE
The enclosed ITP's shall be followed for the works to be performed by the contractor. The
provisions indicated for stage wise inspection by EIL/Owner (For specific activities), which may be
modified in line with EIL scope of services as per the contract between EIL and Owner Activities
for which ITP's are not given, contractor to develop and get the same approved by EIL/Owner well
before start of the work. In general role of EIL has been specified in the document. The role of
owner to be specified during preparation of site specific ITPs.
Contractor to submit required reporting formats and job procedures for each activity listed in ITP's
and submit to EIL/Owner for approval, well before commencement of the activity. If the contractor
has to deviate from the given ITP for a valid reason, he shall obtain prior written approval of
EIL/Owner. Contractor to carry out 100% examination of all activities.
LEGEND
HP : Hold Point ;
W : Witness Point ;
Responsibility for execution of the inspection/testing is with the Contractor; Owner/EIL only
verifies examination or testing done by the Contractor at important stages
SHOP FABRICATION
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A
Format No.
5. NDT WC Rw Yes
Note :1) For Incoming material Inspection please refer ITP no: 6-82-1010
2) For cleaning & painting, please refer ITP No. 3501
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A
Format No.
Availability of approved standard calibrated
1. WC HP Format I-2
testing equipments
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
1. Incoming material Inspection WC Note-1 ---
Note :1) For Incoming material Inspection please refer ITP no: 6-82-1010
2) For cleaning & painting, please refer ITP No. 2501
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
1. Correct size and routing of tray/ angle WC S Format I-11
Note: 1) For cleaning & painting, please refer ITP No. 2501
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
1. Incoming material Inspection WC Note-1 ---
Note :1) For Incoming material Inspection please refer ITP no: 6-82-1010
2) For cleaning & painting, please refer ITP No. 2501
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
Availability of approved location plans,
1. piping GADs, P&ID, vendor’s manual, etc. WC Rw Yes
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A CAT B Format No.
Direction of flow, tapping orientation,
1.
standard, piping material, installation WC HP S Format I-14
standard.
Availability of materials as per Bill of
2. WC W S Yes
Material/ Installation Std.
3. Fabrication as per Installation Std. WC W S Yes *
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
1. Correctness of cable type as per schedule WC Note 1 Format I-17
2. Measurement & routing WC S Format I-17
Check cable for continuity, insulation
3. WC W/Rw Format I-16
resistance, megger values
Identification tags/ tag plates and proper
4. WC S Format I-17
dressing & clamping
Separation of signal/ thermocouple and power
5. WC S ---
cables
Proper glands as per area classification, size of
6. WC HP Format I-17
cable, JB entry, etc
Identification/ ferrule and dressing inside
7. WC S Format I-17
junction boxes and instrument
8. Crimpable type lugs and proper crimping WC S ---
9. Telephone wire connection inside JB WC S ---
10. Shield wire dressing/ sleeving and termination WC S Format I-17
11. Insulation of shield wire on instrument end WC S ---
Rating of cables through MCT blocks
including ensuring proper size of MCT blocks
and location as per MCT details and routing
12. WC S Yes
dressing and segregation of cables inside
trench/control/rack room wherever applicable
of cables
INSPECTION & TEST DOCUMENTS
Review Test and Inspection Document WC Rw Yes
Note :1) For Incoming material Inspection please refer ITP no: 6-82-1010
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
1. Incoming material Inspection WC Note 1
Note : 1) For Incoming material Inspection please refer ITP no: 6-82-1010
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
Availability of AFC drawings for air /
1. pneumatic distribution line and tubing hook- WC Rw ---
up for CV/SDV
Usage of correct size, thread, etc. Jigs/ die sets
2. WC -- ---
for threading of pipes
Proper packing material/ sealant used at thread
3. WC -- Yes
joints
Providing three piece union at each loop for
4. WC -- Format I-19
easy maintenance
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
Check Tapings provided at vessels/stand pipes
are matching with centre to centre distance on
1. respective instruments & connection size WC S Yes
ratings are matching with instruments.
Check tapings provided at vessels/stand pipes
2. are matching with process WC S ---
requirements/P&IDs and its Orientation
Note : 1) For Incoming material Inspection please refer ITP no: 6-82-1010
EIL Records to be
Sl.
Activity Contractor Submitted/
No.
Format No.
CAT B
Correctness of range, rating, immersion length
1. (U length) as per P&ID/ Instrument data WC Note-1 Format I-21
sheets
Check for tapping size, orientation, location as
2. per P&ID, projection above pipe as per WC -- Format I-21
drawing/ standard.
Usage of correct size, rating & type of gasket
3. WC Note-1 Format I-21
and stud/nuts as per PMS
Installation of temperature element head &
4. assemblies and checking availability of WC S Yes
sufficient space for removal.
5. Tightness of studs/ nuts WC S Format I-21
Note :1) For Incoming material Inspection please refer ITP no: 6-82-1010
LOOP CHECKING
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A Format No.
Completeness of installation as per standards
1. WC Rw ---
& specifications
Yes,
3. Availability of standard calibrated equipment WC Rw
Format I-2
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A CAT B
Format No.
A. PRIOR TO FABRICATION
1. Incoming Material
Contractor to check all free issue materials and
a) Owner’s supply maintain records of MIV for material issued by
owner/EIL
b) Contractors supply WC Note -1 Format I-1
Welding Filler Material Approval/
2.
Qualification
a) Review of Manufacturer’s Test
WC* HP* HP* Format IM3, IM4
Certificates/Documents & Sampling
b) Laboratory Testing, if any WC HP Rw Format IM3, IM4
3. WPS/PQR
For NACE filler metals, corrosion tests like HIC, SSCC, etc. to be carried out for every batch.
However, HIC/SSCC tests done earlier & duly witnessed by a reputed third party, will be acceptable.
Format IM13,
10. PT/MPT WC W S
IM14
Identification of Joints for Radiography (for
11. WC S -- Format IM15
Random Radiography only)
Review of Radiographs interpreted by the
12. WC HP W Format IM16
Contractor
(Sheet 3 of 4)
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CATA CAT B
Format No.
PROOF TESTING
C (See enclosed checklist in Annex-1)
Annex-2,
5. Correctness of Testing arrangements WC S --
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A CATB
Format No.
Boxing up including reinstallation of
13. WC S -- Annex-2
flappers of check valves
Note : 1) For Incoming material Inspection please refer ITP no: 6-82-1010
2) Pre-commissioning activities such as chemical cleaning, card board blasting, system
testing are not covered by these ITP's. The Contractor shall develop ITP's for such
activities and obtain Owner/ EIL/ Licensor's approval.
** Refer Procedure for Identification and Boxing up of flange joints not subjected to hydrostatic test
at site No. 5-7700-0120, enclosed elsewhere in the contract.
CAT A: All services involving hydrogen and hydrogen bearing fluid All CS SS, AS, NACE, LTCS
impulse piping for process lines
CAT B: Piping for “D” class fluid, Non IBR portion of condensate & steam lines
ANNEX – 1
Checklist for Mechanical Clearance - IMPULSE Piping
Line No (Isometric No.) / Rev. Installation Std. Rev. P&ID No. Rev.
Tag No No.
6. Flanged Joints
Total Nos.
Check for type of flange
Check for Rating
Check for Alignment, (proper gap & parallelity
Check for Correct Studs & nuts – dia., length, Material, uniform
protrusion of studs, anti seize compound
Check for correct gasket ( type, size, spec., thickness, etc.)
Torque values used for tightening
9. Orifice Flanges :
Check for Tag No., tapping orientation, tap valve, jack screw,
straight run length of upstream & downstream
Remarks
EIL
Sign :
Date :
Name : Designation :
ANNEX – 2
Sign : Sign:
Date : Date:
Name : Designation Name: Designation:
ANNEX - 3
PUNCHLIST
Description : _________________________________________________________________
____________________________________________________________________________
Punch
Prio- Description of Prepared Action Due Completion
Item Location
rity Punch Items By By date Acceptance
No.
Priority: 1. Needed for pressure test 2. Needed for commissioning 3. Needed for start up
4.Needed for plant acceptance
Contractor : EIL :
Sign : Sign :
Date : Date :
Name : Designation : Name : Designation :
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
Receipt of materials/ panels as per purchase
Yes,
1. requisition, inspection release note, bill of WC Note 1
Format I-1
materials, etc
2. Storage of materials at site WC S ---
Note: 1) For Incoming material Inspection please refer ITP no: 6-82-1010
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
Availability of latest revision of approved tray
1. WC Rw Yes
layout drawings
Welding & painting of supports before
2. WC --- ---
erection of panels
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT B Format No.
Correct size & type of cables as per cable
1. WC Note 1 Format I-1
schedule
Testing of cable before laying as per Yes,
2. specification (continuity, megger, etc.), as WC Rw Formats I-16,
applicable I-22
Check for exact distance and cables cutting
3. WC Rw Format I-24
accordingly
Note :1) For Incoming material Inspection please refer ITP no: 6-82-1010
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A Format No.
1. Check for earth pit resistance WC HP Yes
EIL Records to be
Sl.
Activity Contractor Submitted/
No. CAT A Format No.
Coordination with field contractor for loop
1. WC S ---
checking.
Availability of record as per loop checking
2. WC HP Yes
sheet duly signed
Availability of record as per loop checking
3. WC W ---
sheet duly signed
Operation of sub systems and peripheral
4. WC W ---
systems
SECTION - B
FORMATS
FOR
INSTRUMENTATION WORKS
CONTENTS
MTC No./
Material IRN No. Heat/
Sl. SOR Item Date of Qty. Qty. Manufacturer/ Ref. Invoice/ Observation/Remarks/
description/Tag with Date/ Batch
No. No. Receipt Received Accepted Vendor Challan No. Storage Instruction
Field,Lab No.
no test,etc
Notes :
_______________________
EIL Field Supervisor EIL Lead Engineer/Area coordinator/Spread Incharge
(countersigned)
Report No. :
Date :
Note : Ensure measuring/test equipment is sent to laboratory prior to expiry of present certificate
Ascending Descending
Sl. No. Input Desired Actual Error Desired Actual Error Remarks
Remarks
% Unit Unit Unit Unit Unit Unit
1. 0
2. 25
3. 50
4. 75
5. 100
NOTE :
i) Acceptance criteria as per instrument data sheet
ii) For Diff. Pressure gauge, LP side shall be open to atmosphere
NOTE :
i) Acceptance criteria as per instrument data sheet
ii) For Diff. Pressure gauge, LP side shall be open to atmosphere
Report No. :
Date :
Project :
Job No. : Client :
Name of work : Contractor :
________________ ____________________
Contractor EIL
Report No. :
Date :
Valve Details
Service :
Calibration Validity :
Test Result
________________ ______________
Contractor EIL
________________ ______________
Contractor EIL
Report No. :
Date :
Valve Details
Service :
Calibration Validity :
Test Result
________________ ____________________
Contractor EIL
________________ ______________
Contractor EIL
________________ ______________
Contractor EIL
Sl.No. Tray size From To Location Support Painting Welding, Fire Remarks
if any Proofing *
________________ ______________
Contractor EIL
Project :
Job No. :
Name of work :
Client :
Contractor :
Verification by Remarks
Sl. Tag Inst. Accessories
Location Elevation Installation Support Alignment Canopy
No. No. STD installation*
Contractor EIL
Project :
Job No. :
Name of work :
Client :
Contractor :
Pr. Held
Test Gauge details Verification by Remarks
Mechanical/ Operating Test Time
Service/ NDT
Sl Tag Pressure Pressure Test Calibr- Test Draining/
Line No./ Clearance
No. No. medium Sl/Model Range ation Result Drying
Eqpt. No (Min) Contractor EIL
(Kg/Cm2) (Kg/Cm2) No. (Kg/Cm2) Validity
upto
Remarks, if any:
________________ ____________________
Contractor EIL
Report No. :
Date :
Project :
Job No. :
Name of work :
Client :
Contractor :
Report No. :
Date :
Project :
Job No. :
Name of work :
Client :
Contractor :
Report No. :
Date :
Project :
Job No. :
Name of work :
Client :
Contractor :
Report No. :
Date :
Project :
Job No. :
Name of work :
Client :
Contractor :
Report No. :
Date :
Project :
Job No. :
Name of work :
Client :
Contractor :
Inductivity/capacity of loop
Pneumatic Properties
- Terminals/connections tagging
- Type of junction boxes in Acc.
with area classification
50 SOV Energisation :
75 ZSH : OK/Not OK
100 ZSL : OK/Not OK
0
25
Analog
Signal
50
75
100
0 Type of Alarm OK/NOK Remarks
25 Trip Set Input
Pressure/
Switches
(Digital)
Level
50 High Differential
75 Very High Type of contact: No/ NC
100 Low
Very Low
0 Physical condition OK/NOK Type of Contact OK/NOK Remarks
25 Open NO/NC
Digital
Signal
Other
50 Close NO/NC
75
100
0
25
Other
Any
50
75
100
Remarks :
Ref. documents : 1) Instrument data sheet 2) Loop wiring diagram 3) Functional schematic
_______________ ____________________
Contractor EIL
Report No. :
Date :
Length as
Dr
Sl. Cable/Tube Drum per Actual Test
From To um Balance Remarks
No. Size Length Cable/tube Length Reports
No.
Schedule
________________ ______________
Contractor EIL
(Sheet 1 of 3)
UTS YS % Elongation
Size of
Identification Kgs/mm2 Kgs/mm2 Gauge length
Electrode
Code Actual Code Actual Code Actual
(Sheet 2 of 3)
Format No. 8-00-0001-F1 Copyright EIL – All rights reserved
o
IMPACT TEST RESULTS : C
Size of I
Identi- Cooling I1 I2 I3 I4 I5 Code
Elect- Average
fication Medium Kgf-m Kgf-m Kgf-m Kgf-m Kgf-m Kgf-m
rode Kgf-m
Size
Iden- C Mn P S Si Ni Cr Mo V Cu Co/Nb
of % As per
tifi-
Elec- Code
cation
trode
% As per
Actual
Code/Act
Size of F H V OH
Identification
Electrode Flat Horizontal Vertical Over Head
(Sheet 3 of 3)
TENSILE AND BEND TEST RESULT
Identification : _____________________
I
I1 I2 I3 I4 I5 Code requirements
Location average
Kgf-m Kgf-m Kgf-m Kgf-m Kgf-m Kgf-m
Kgf-m
WELD
HAZ
Material ________________________
Plate size ________________________
Visual __________________________ Radiography Result ________________
Identification _____________________
2G
3G
4G
Index
T = Tensile Test
S = Side Bend
F = Face Bend Witnessed by Approved by
R = Root Bend
I = Impact Test
To
Manager of Construction
(Sheet 1 of 2)
Report No. : __________
Date : __________
(Sheet 2 of 2)
TECHNIQUE (QW-410)
String or Weave Bead ________________________________________________________________
Orifice or Gas Cup size _______________________________________________________________
Initial and Interpass Cleaning (Brushing, Grinding etc.) _____________________________________
__________________________________________________________________________________
Method of Back Gouging _____________________________________________________________
Oscillation _________________________________________________________________________
Contact Tube to Work Distance ________________________________________________________
Multiple or SinglePass (per side) _______________________________________________________
Multiple or Single Electrodes __________________________________________________________
Travel Speed (Range) ________________________________________________________________
Peening ___________________________________________________________________________
Other _____________________________________________________________________________
__________________________________________________________________________________
__________________________________________________________________________________
FORMAT NO. : IM -6
SUGGESTED FORMAT FOR PROCEDUREQUALIFICATION
RECORD (PQR)
(Section IX, ASME Boiler and Pressure Vessel Code)
(Sheet 1 of 2)
Report No. : __________
Date : __________
JOINTS (QW-402)
(Sheet 2 of 2)
Results-Satisfactory : Yes________ No _____ Penetration into Parent Metal : Yes _______ No _____
Type and Character of Flt: Micro ______________________ Macro-Results ____________________
Other Tests
………………………………………………………………………………………………………….....
Manufacturer _________________________
Date ______________________________ By _________________________________
(Details of record of tests are illustrative only and may be modified to conform to the type and number of test required by the Code.)
FORMAT NO. : IM -7
SUGGESTED FORMAT FOR MANUFACTURER’S
RECORD OF WELDER OR WELDING OPERATOR
QUALIFICATION TESTS
(Section IX, ASME Boiler and Pressure Vessel Code)
Report No. : __________
Date : __________
Fracture Test (Describe the location nature arrange of any check ring of the specimen)
Organization _________________________
Date :_____________________ by __________________________________
(Detail of record of tests are illustrative only and may be modified to conform to the type and number of tests required by the
Code)
Note : Any essential variables in addition to those above shall be recorded.
FORMAT NO. : IM -8
WELDER’S IDENTIFICATION CARD
Report No. : __________
Date : __________
NAME :
Identification :
Date of Testing :
Plate/Pipe size :
Welding process :
Filler material
Classification :
Position :
Qualified to weld :
Valid until :
WELDING ENIGNEER
(Contractor)
____________________ ___________________________________
(NAME & DATE) EIL
DETAILS OF QUALIFICATIONS :
BACKSIDE OF IDENTITY CARD
FORMAT NO. : IM -9
MATERIAL TRACEABILITY REPORT
Contractor : ___________________________________
S. Line/ Heater Area Dia. Joint Spool Piping Manufacturer Material Heat/ Colour Verified Remarks
No. No. No. No. No. Component Batch Code Sub- Contractor EIL/
No. Contractor Owner*
(Contractor) (EIL)
TOTAL TOTAL
INCH DIA. INCH MTR
(*)
G - BUTT WELD
S - SOCKET WELD
B - BRANCH WELD _____________ ______________
M - MITRE WELD CONTRACTOR EIL
Total
Inch Dia.
(*)
G = BUTT WELD
S = SOCKET WELD TOTAL IN DIA. =
B = BRANCH WELD PREVIOUS =
M = MITRE WLED TILL DATE =
_____________ ______________
CONTRACTOR EIL
______________ __________________
CONTRACTOR EIL
__________________________________________________________________________________
Surface Temperature
& Penetrant Time ______________ oC ____________ Minute
__________________________________________________________________________________
Penetrant
Remover
Developer
__________________________________________________________________________________
__________________________________________________________________________________
______________ ________________
CONTRACTOR EIL
1. Test Condition
2. Acceptance Observations
3. Sketch
4. Result
Remarks
______________ ________________
CONTRACTOR EIL
TO
______________________
______________________
______________________
Please arrange to radiograph the following welds and submit the results with in 24 hours
positively.
Radio-
Sl. Heater/Line Accepted
Area Dia Joint No. Welder No. graphy Remarks
No. No. Date
No.
______________ ____________
Contractor EIL
SWSI - SINGLE WALL SINGLE IMAGE, DWDI - DOUBLE WALL DOUBLE IMAGE
DWSI - DOUBLE WALL SINGLE IMAGE
_____________ ____________
CONTRACTOR EIL
Line No. /ISO Drg. No : ______________ Make & Serial No.: ________________
/Heater No./Drawing No
Result
Sr. Material Material
Part Identification (Accepted/Rejected/
No. As per Drg./spec as per PMI
Retest)