Checklist For Podium Waterproofing
Checklist For Podium Waterproofing
Check for completion of plumbing lines, electrical lines, provision of pipe Yes No NA
3
sleeves , bore packing & finishing of wall chasing
Check for completion of plastering of wall and coving in slab and wall joints Yes No NA
4
as per methodology
Check for rendering of defect identified areas if noted and finishing as per Yes No NA
5
methodology
Check for preponding test prior waterproofing for 24 hrs and ensured no Yes No NA
6
leakages in slab
B During Waterproofing
Yes No NA
7 Check for all surface must be cleaning and free from looser mortar.
Check For all corner with coving with Acrylic Polymer Modified Cementitious Yes No NA
8
SBR Latex waterproofing membrane Cement and sand
Check for Protective coating Flexcoat 2K Mix ratio (1:3) is an Acrylic Yes No NA
10
Cementitious Polymer Modified elastomeric.
Check for Main coating Apply of SETIPOL - PU from Teecnopol Modified Yes No NA
11
single components.
Check for apply the first coat, with a consumption of about 0.75 Kg/m2, Yes No NA
12
imprehnating glass fiber reinforcement and let dry.
Check for apply a second layer with an approximate consumption 0.75 - 1 Yes No NA
13
Kg/m2.
14 Check for applying uniformly with brush / roller Yes No NA
C After Waterproofing
Check for protection of waterproofing by restriction of movement and curing Yes No NA
15
after 24 hrs of final coat
16 Check for post ponding test for 48 hours after waterproofing Yes No NA
17 Check for laying screed for 30mm above the waterproofing applied area Yes No NA
Check for cleaning and removal of all unwanted materials after completion of No
18 Yes NA
work