Quantity Surveying Lecture Notes

This document contains an estimate for construction of a residential building. It includes: 1) Earthwork excavation for foundation totaling 29.52 cubic meters. 2) Plain cement concrete for foundation at 5.90 cubic meters. 3) Random rubble masonry for foundation totaling 28.64 cubic meters and basement walls at 10.39 cubic meters. 4) Brick masonry for walls totaling 26.83 cubic meters after deductions for openings, and parapet walls at 2.22 cubic meters.

Uploaded by

Sam Sam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
90 views

Quantity Surveying Lecture Notes

This document contains an estimate for construction of a residential building. It includes: 1) Earthwork excavation for foundation totaling 29.52 cubic meters. 2) Plain cement concrete for foundation at 5.90 cubic meters. 3) Random rubble masonry for foundation totaling 28.64 cubic meters and basement walls at 10.39 cubic meters. 4) Brick masonry for walls totaling 26.83 cubic meters after deductions for openings, and parapet walls at 2.22 cubic meters.

Uploaded by

Sam Sam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/361909006

QUANTITY SURVEYING Lecture Notes 2

Presentation · July 2022


DOI: 10.13140/RG.2.2.18069.60646

CITATIONS READS
0 310

1 author:

Kiran S R

46 PUBLICATIONS   19 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Structural Design-1 View project

Structural Design-2 View project

All content following this page was uploaded by Kiran S R on 11 July 2022.

The user has requested enhancement of the downloaded file.


QUANTITY SURVEYING I
PREVIOUS YEAR QUESTION AND SOLUTION

Prepare the estimate of the building shown below.

Doors: Windows:
D1: 1100 X 2100 W1: 1500 x 1500
D2: 1000 X 2100 W2: 1500 x 1100
D3: 900 X 2100
Ventilators:
V: 1000 x 500

Section of frames of Door, Window & ventilator: 75 x 100

All dimensions in mm

Prepared by Kiran S. R., Lecturer in Civil Engineering, Central Polytechnic College Trivandrum
Sl.
No. Item of Work No. L (m) B (m) H (m) Quantity Remarks

1. Centreline lengthn for earthwork:

Earthwork in excavation Outer:


using manual or 3.60+0.20+3.60+0.20+2.70+0.20+3.00+0.
mechanical means for 20+1.70+0.20+1.70+0.20+1.80+0.20+4.5
foundation trenches 1 49.20 0.80 0.75 29.52 m3 0+0.20+2.40+0.20+3.60+0.20+4.20+0.20
=35.00m
Inner (right hand wall of hall):
4.20+0.20-0.80
=3.60m
Inner (left hand wall of kitchen):
3.00+0.20-0.80
=2.40m
Inner (bedside & kitchenside wall of
Dining):
3.60+0.20+2.70+0.20-0.80
=5.90m
Inner (right hand wall of Dining):
1.70+0.20+1.70+0.20-0.80
=3.00m
Total centerline length:
35.00+3.60+2.40+5.90+3.00
=49.90m
2. Plain Cement Concrete
of mix 1:4:8 in
foundation 1 49.20 0.80 0.15 5.90 m3 Total centerline length same as item1

3. Random Rubble
masonry in cement
mortar 1:6 Centreline length for foundation:
(a) In Foundation 1 50.70 0.60 0.60 18.25 m3 Outer:
(b) In Basement 1 51.30 0.45 0.45 10.39 m3 =35.00m
Total: 28.64 m3 Inner (right hand wall of hall):
4.20+0.20-0.60
=3.80m
Inner (left hand wall of kitchen):
3.00+0.20-0.60
=2.60m
Inner (bedside & kitchenside wall of
Dining):
3.60+0.20+2.70+0.20-0.60
=6.10m
Inner (right hand wall of Dining):
1.70+0.20+1.70+0.20-0.60
=3.20m
Total centerline length:
35.00+3.80+2.60+6.10+3.20
=50.70m

Centreline length for basement:


Outer:
=35.00m
Inner (right hand wall of hall):
4.20+0.20-0.45
=3.95m
Inner (left hand wall of kitchen):
3.00+0.20-0.45
=2.75m
Dining):
3.60+0.20+2.70+0.20-0.45
=6.25m
Inner (right hand wall of Dining):
1.70+0.20+1.70+0.20-0.45
=3.35m
Total centerline length:
35.00+3.95+2.75+6.25+3.35
=51.30m
4. Brickmasonry in cement
mortar 1:6 in
superstructure Centreline length for brickwalls:
(a) Walls 1 52.30 0.20 2.85 29.81 m3 Outer:
(b) Parapet 1 36.95 0.10 0.60 2.22 m3 =35.00m
Inner (right hand wall of hall):
Deductions: 4.20+0.20-0.20
D1 2 1.10 0.20 2.10 -0.92 m3 =4.20m
D2 2 1.00 0.20 2.10 -0.84 m3 Inner (left hand wall of kitchen):
D3 2 0.90 0.20 2.10 -0.76 m3 3.00+0.20-0.20
W1 5 1.50 0.20 1.50 -2.25 m3 =3.00m
Inner (bedside & kitchenside wall of
W2 1 1.50 0.20 1.10 -0.33 m3 Dining):
V 1 1.00 0.20 0.50 -0.10 m3 3.60+0.20+2.70+0.20-0.20
=6.50m
Total: 26.83 m3 Inner (right hand wall of Dining):
1.70+0.20+1.70+0.20-0.20
=3.60m
Total centerline length:
35.00+4.20+3.00+6.50+3.60
=52.30m

Height of brickwork= 3.00-0.15= 2.85m


The parapet (thickness 10cm) is
constructed on a projection beyond the
outer wall, the value of which is not given
in the question, let us assume it to be
15cm.
Centreline length of parapet is given by:
(0.15+0.20+3.60+0.20+3.60+0.20+2.70+0
.20+0.15-0.10)+
(0.15+0.20+3.00+0.20+1.70+0.20+1.70+0
.20+0.15-0.10)+
(0.15+0.20+1.80+0.20+4.50+0.20+0.15-
0.10)+ (2.40+0.20)+ (3.60+0.20)+
(0.15+0.20+4.20+0.20+0.15-0.10)
=36.95m
5. Centring & shuttering
for roof slab
Hall 1 3.60 4.20 15.12 m2
Bedroom 1 3.60 3.00 10.80 m2
Kitchen 1 2.70 3.00 8.10 m2
Dining 1 4.50 3.60 16.20 m2
Toilet 2 1.80 1.70 6.12 m2
Total: 56.34 m2
6 Reinforced cement Assuming lintel is provided all throughout
concrete of mix 1:1.5:3 the wall
(a) Roof slab
Area1 1 11.00 4.90 0.12 6.47 m3
Area2 1 7.20 2.60 0.12 2.25 m3
(b) Lintel beams 1 52.30 0.20 0.15 1.57 m3 Centreline length for lintel beam:
Total: 10.28 m3 same as centreline length of wall
=52.30m
7 Providing, cutting and
placing in position steel
reinforcements - TMT
bars of Fe500
For roof slabs & lintel
beams @ 80kg/m3 of
concrete
For 10.28m3 concrete 10.28 80.00 822.40 kg
(see item no.6)
8 12mm thick cement
plaster of mix 1:6 on
walls
(a) Inner walls:
Hall 1 2(3.60+ 3.00 46.80 m2
4.20) Outer length of walls: (See figure)
Bedroom 1 2(3.60+ 3.00 39.60 m2
3.00) 10.70+7.20+6.90+2.60+3.80+4.60
Dining 1 2(4.50+ 3.00 48.60 m2
3.60) =35.80m
Kitchen 1 2(2.70+ 3.00 34.20 m2
3.00)
Toilets 2 2(1.80+ 3.00 21.00 m2
1.70)
(b) Outer walls: 1 35.80 3.87 138.55 m2
Height over which outer wall is platered:
3.00+0.15 (roofslab projection)+
0.12(roofslab thickness)+ 0.60(parapet
Deductions: wall height)
D1 2 1.10 2.10 -4.62 m2 =3.87m
D2 2 1.00 2.10 -4.20 m2
D3 2 0.90 2.10 -3.78 m2
For Openings of area >0.5m2 and <3m2,
deduction for doors & windows shall be
W1 5 1.50 1.50 -11.25 m2 made for one face only.
W2 1 1.50 1.10 -1.65 m2
V 1 1.00 0.50 -0.50 m2

Total: 302.75 m2

9 6mm thick plaster of mix


1:3 on ceiling
Hall 1 3.60 4.20 15.12 m2
Bedroom 1 3.60 3.00 10.80 m2
Dining 1 4.50 3.60 16.20 m2
Kitchen 1 2.70 3.00 8.10 m2
Toilets 2 1.80 1.70 6.12 m2
Total: 56.34 m2
10
Providing and laying in
position Cement
Concrete of grade 1:2:4
PCC flooring for: Assume a PCC flooring 75mm thick
Hall 1 3.60 4.20 0.075 1.13 m3
Bedroom 1 3.60 3.00 0.075 0.81 m3
Dining 1 4.50 3.60 0.075 1.22 m3
Kitchen 1 2.70 3.00 0.075 0.61 m3
Toilets 2 1.80 1.70 0.075 0.46 m3
Beneath doors:
D1 2 1.10 0.20 0.075 0.033 m3
D2 2 1.00 0.20 0.075 0.030 m3
D3 2 0.90 0.20 0.075 0.027 m3
Total: 4.32 m3
11 Providing and laying
vitrified floor tiles of
approved make on
20mm thick cement
mortar 1:4
PCC flooring for:
Hall 1 3.60 4.20 15.12 m2
Bedroom 1 3.60 3.00 10.80 m2
Dining 1 4.50 3.60 16.20 m2
Kitchen 1 2.70 3.00 8.10 m2
Toilets 2 1.80 1.70 6.12 m2
Beneath doors: 0.00 m2
D1 2 1.10 0.20 0.44 m2
D2 2 1.00 0.20 0.40 m2
D3 2 0.90 0.20 0.36 m2
Total: 57.54 m2
12
Providing woodwork in
frames of doors,
windows, etc. and fixed
in position with holdfast
etc. all complete
a)Door D1
2 verticals 2x2 2.10 0.075 0.10 0.063 m3
1 horizontal 2x1 1.40 0.075 0.10 0.021 m3
b)Door D2
2 verticals 2x2 2.10 0.075 0.10 0.060 m3
1 horizontal 2x1 1.30 0.075 0.10 0.020 m3
c)Door D3
2 verticals 2x2 2.10 0.075 0.10 0.063 m3
1 horizontal 2x1 1.20 0.075 0.10 0.018 m3
d)Window W1
3 verticals 5x3 1.50 0.075 0.10 0.169 m3
2 horizontals 5x2 1.80 0.075 0.10 0.135 m3
e)Window W2
3 verticals 1x3 1.10 0.075 0.10 0.025 m3
2 horizontals 1x2 1.80 0.075 0.10 0.027 m3
f)Ventilator V
2 verticals 1x2 0.50 0.075 0.10 0.008 m3
2 horizontals 1x2 1.30 0.075 0.10 0.020 m3

Total: 0.63 m3
13 Providing woodwork in
shutters of doors,
windows, etc. all
complete Provide 15mm rebate
a)Door D1 2 0.98 2.04 4.00 m2 L=1.10-(2x0.075)+(2x0.015)=0.98m
H=2.10-(0.075)+(0.015)=2.04m
b)Door D2 2 0.88 2.04 3.59 m2 L=1.00-(2x0.075)+(2x0.015)=0.88m
H=2.10-(0.075)+(0.015)=2.04m
c)Door D3 2 0.78 2.04 3.18 m2 L=0.90-(2x0.075)+(2x0.015)=0.78m
H=2.10-(0.075)+(0.015)=2.04m
d)Window W1 5 1.365 1.38 9.42 m2 L=1.50-(3x0.075)+(6x0.015)=1.365m
H=1.50-(2x0.075)+(2x0.015)=1.38m
e)Window W2 1 1.365 0.98 1.34 m2 L=1.50-(3x0.075)+(6x0.015)=1.365m
H=1.10-(2x0.075)+(2x0.015)=0.98m
f)Ventilator V 1 0.88 0.38 0.33 m2 L=1.00-(2x0.075)+(2x0.015)=0.88m
H=0.50-(2x0.075)+(2x0.015)=0.38m
Total: 21.86 m2
14
Apply one coat of water
thinnable cement primer
of approved brand on
wall surface
a)on walls(same as item
no.8) 302.75 m2
b)on ceiling(same as
item no.9) 56.34 m2
Total 359.09 m2
15
Finishing with emulsion
paints on new work
a)on walls(same as item
no.8) 302.75 m2
b)on ceiling(same as
item no.9) 56.34 m2
Total 359.09 m2
16
Applying priming coat
with ready mixed pink or
grey primer of approved
brand on wood work
a)panelled doors (on
both sides) Coeff. Use coefficient 1.30 for panelled/framed/
D1 2x2 1.10 2.10 1.30 12.01 m2 braced doors&windows.
D2 2x2 1.00 2.10 1.30 10.92 m2
D3 2x2 0.90 2.10 1.30 9.83 m2
b)glazed windows (on
both sides) Coeff. Use coefficient 0.80 for glazed/gauzed
W1 5x2 1.50 1.50 0.80 18.00 m2 doors & windows.
W2 1x2 1.50 1.10 0.80 2.64 m2
V 1x2 1.00 0.50 0.80 0.80 m2
Total 54.20 m2
17 Painting with synthetic
enamel paint of
approved brand to give
an even shade (2 or
more coats)
a) On panelled doors &
glazed windows
(same as item 16) Total 54.20 m2
18
Providing and fixing
Indian type W.C.
pan with P or S trap, 10
litre low level white
P.V.C. flushing cistern,
including flush pipe,
with manually controlled
device (handle lever),
with all fittings and
fixtures complete.
a)For each toilet 2 nos
19. Providing and fixing
wash basin with C.I.
brackets, 15 mm C.P.
brass pillar taps, 32 mm
C.P. brass waste of
standard pattern, all
complete
a)One for each toilet
and one for the dining 3 nos
20 Providing and fixing
Stainless Steel kitchen
sink as with C.I.
brackets and stainless
steel plug 40 mm, all
complete
a)For kitchen 1 no.
21 Providing and fixing
brass bib cock of
approved quality of
15mm nominal bore
One for each toilet 2 nos.
22 Providing and fixing
C.P. brass long body
bib cock of approved
quality conforming to IS
standards and 15 mm
nominal bore
a)for kitchen 1 no.
23
Constructing brick
masonry chamber for
underground inspection
chamber and bends
with bricks in cement
mortar 1:4 C.I. cover
with frame 455x610 mm
internal dimensions,
R.C.C. top slab with
1:2:4, foundation
concrete 1:5:10, inside
plastering 12 mm thick
with cement mortar
1:3, finished smooth
with a floating coat
of neat cement on walls
and bed concrete etc.
complete as per
standard design:
-Inside dimensions
455x610 mm and 45 cm
deep for single
pipe line 2 nos.
24 Providing and fixing
Polyvinyl Chloride
(PVC) pipes, having
thermal stability for hot
& cold water supply.
This includes jointing of
pipes & fittings with one
step PVC solvent
cement, trenching,
refilling & testing of
joints complete as per
direction of Engineer in
Charge

a) 25mm nominal outer


dia (for water supply) 30 m
b) 62.5mm nominal
outer dia (for washbasin
waste) 10 m
c) 110mm nominal outer
dia (for water closet
waste) 10 m

Prepared by Kiran S. R., Lecturer in Civil Engineering, Central Polytechnic College Trivandrum