0% found this document useful (0 votes)
95 views

Intro S4HANA Using Global Bike Notes SD en v3.3

Intro_S4HANA_Using_Global_Bike_Notes_SD_en_v3.3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
95 views

Intro S4HANA Using Global Bike Notes SD en v3.3

Intro_S4HANA_Using_Global_Bike_Notes_SD_en_v3.3
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

LECTURER NOTES

Sales and Distribution (SD)


Case Study
This document is intended to help instructors understand the case study
process and manage the learning process in and outside the classroom.
The main focus lies on prerequisites and common tasks such as testing
and trouble-shooting.

Product MOTIVATION
SAP S/4HANA 1809 Theoretical lectures explain The main goal of this document is to
Global Bike concepts, principles, and theories help instructors prepare the SAP
through reading and discussion. system for the Sales and Distribution
Level They, therefore, enable students to case study process and to support
acquire knowledge and gain them trouble-shoot problems that
Instructor
theoretical insights. might occur during the course.
In contrast, case studies allow
Focus them to develop their abilities to Beside technical and didactic
Sales and Distribution analyze enterprise problems, learn prerequisites, the lecturer notes list
and develop possible solutions, SAP transactions for testing and
Author and make sound decisions. correcting student results in the SAP
Stefan Weidner system. In addition, this document
The main objective of the Global describes common problems and
Bike case studies in general is for explains their reason and solution.
Version students to understand the
3.3 concept of integration. These
descriptive and explanatory case
Last Update studies will allow students to
May 2019 understand the importance and the
advantages of integrating
enterprise areas using an
S/4HANA system.

© SAP UCC Magdeburg


LECTURER NOTES

Prerequisites

Note Before using this case study in your classroom please make sure that all technical (month-
end closing, user management etc.) and didactic prerequisites are fulfilled. Such prerequisites are
briefly pointed out below. Detailed documentation can be displayed at and downloaded from the
Learning Hub of SAP UA or the UCC web sites.

Technical Prerequisites

The Sales and Distribution case study is based on a standard SAP S/4HANA
client with the current Global Bike dataset. Before processing the case study
on your own or with your students all general setting should be checked.

This includes month-end closing in Materials Management (transaction Month-end closing in


MM
MMPV) which is documented on the UCC web sites. MMPV

Note: With the current version of the Global Bike client a year-end closing Year-end closing
is not necessary, because it has already been automated or because it is not
needed for the process described in the curriculum material.

User accounts in the SAP system need to be created or unlocked. User management

These student user accounts should end with a three-digit numeric number
(e.g. LEARN-001, LEARN-002 etc.). This number will be represented by
### in the case study and helps differentiate customer accounts, products etc.

In an SAP S/4HANA Global Bike client already exist 1000 user accounts LEARN-000 to LEARN-
999
from LEARN-000 to LEARN-999. These users need to be unlocked. The
initial password for each LEARN-### account is set to tlestart. tlestart

Transaction ZUSR was developed in the Global Bike client in order to mass ZUSR
maintain SAP user accounts. For a detailed description of this and SAP
standard transactions for user management (SU01 and SU10) please refer to SU01
the lecturer notes “User Management“ (see: current Global Bike curriculum SU10

 chapter 99 – Instructor Tools).

All LEARN-### user accounts have been assigned to the role


Z_UCC_GBI_SCC and have authorizations to use all applicative transactions
in the SAP S/4HANA system. The role allows access to all transactions
necessary for Global Bike exercises and case studies. If you need access to
system-critical transactions, i.e. for development purposes, you may assign
the composite profile SAP_ALL to your student accounts.

It is useful for the instructor to have a user account available for testing that
has the same authorizations as the student accounts. You may use the Instructor account
predefined instructor account LEARN-000 for this purpose. LEARN-000

© SAP SE Page 2
LECTURER NOTES

Didactic Prerequisites

In order to successfully process this case study, students should be familiar


Navigation
with the navigation in SAP systems, especially the SAP Easy Access menu,
the SAP transaction concept as well as possible documentation and help
options. We highly recommend using the navigation slides and the
navigation course (see: current Global Bike curriculum  chapter 2 –
Navigation).

In addition, it has been proven beneficial that students have a thorough


Company background
understanding of the historic background and the enterprise structure of the
Global Bike concern before they start working on the SAP system. For this
purpose we recommend the case study „Global Bike Inc.“ (see: current GB
curriculum  chapter 3 – Global Bike).

Because the case study is not based on the exercises, it is not necessary to
have processed the SD exercises (SD 1 to SD 5) before you start with the
case study. However, it is recommended.

In order to function properly this case study needs a Global Bike client GBI client version
version that is equal to or higher than the case study version (see cover
page). Please check. If you do not know the client version please use the
transaction ZGBIVERSION within your SAP S/4HANA system or contact
your UCC team.

GBI Mobile App

With Global Bike the App GBI DataViewer was released for all compatible
Android and iOS devices. It can be downloaded through Google Play Store
and Apple Store. The purpose of this app is to show the possibility of
platform-independent support of business processes. Therefore, some task of
the case study can optionally substituted by using the Global Bike
DataViewer App.
Please keep in mind that this app is an additional functionality designed by
the UCC Magdeburg and you might encounter a bug. Therefore we kindly
ask you to send any feedback or detailed error descriptions to the following
address: [email protected].

Global Feedback

Do you have any suggestions or feedback about Global Bike? Please send it
to our new email-address [email protected] which is used to gather feedback
globally. All emails will be evaluated by the persons responsible for the
curriculum bi-weekly. This way your feedback might influence future
releases directly.
Please note that any support requests send to this email-address will be
ignored. Please keep using the common support channels for your support
requests.

© SAP SE Page 3
LECTURER NOTES

Student Assessment

Note With the transactions listed below you can check and correct master and transactional data
that your students have created during your course.

Master Data

BP Change Customer
BP Display Customer
OV51 Display Mass Customer Changes
VAP2 Change Contact Person
VAP3 Display Contact Person

Transactional Data

VA12 Change Inquiry


VA13 Display Inquiry
VA22 Change Quotation
VA23 Display Quotation
VA02 Change Sales Order
VA03 Display Sales Order
VA06 List of Sales Orders
MMBE Stock Overview
MC.9 Mass Material Stock Analysis
VL02N Change Outbound Delivery
VL03N Display Outbound Delivery
VL06O Outbound Delivery Monitor
VF02 Change Billing Document
VF03 Display Billing Document
FB02 Change Financial Document
FB03 Display Financial Document

GBI Monitoring Tool (beta)

Also we are developing a Global Bike Monitoring Tool, which is available


for the Global Bike release. Since it is still in development the beta version
does not support all case studies yet.

© SAP SE Page 4
LECTURER NOTES

A detailed tutorial for this tool is available in the module 99 Instructor Tools
of the current Global Bike curriculum.
Please keep in mind that this transaction is an additional functionality
designed by the UCC Magdeburg and still in development. Therefore, we
kindly ask you to send any feedback or detailed error descriptions to the
following address: [email protected]

© SAP SE Page 5
LECTURER NOTES

Process Monitoring

Note During the case study the SAP system creates documents which are automatically logging
all business process steps. These documents rely on master data that were either predefined by the
curriculum development team or created by your students.

The Document Flow visualizes all documents related to a given root Document flow
document and thus helps you monitor individual business processes and is as
a starting point for trouble-shooting student problems.

VA03 is the code for transaction Display Sales Order. Please enter the sales VA03
Sales order number
order document number in the respective field and press Enter.

Note Should your student and you not remember the sales order number, you
may search for it using the F4 help. Here, you navigate to the Sales
document according to customer PO number tab and enter the user account
(e.g. LEARN-001) in the Created by field as the only search criterion.

In the Display Sales Document please click on .

After a successful SD case study cycle the following result is displayed by


the SAP system for an individual student’s sales order.

© SAP SE Page 6
LECTURER NOTES

Problem: Goods issue cannot be posted

Symptom You receive error messages when trying to post the goods issue.
Reason A common cause for this error is that either the Storage Location and/or the Picked
Quantity are not entered correctly.
Solution Please correct the outbound delivery document (Storage Location FG00 and Picked
Quantity 5 respectively 2 both the two line items).

Error Message

The screenshot below displays two common problems that might occur when
posting a goods issue:
1) For material DXTR1###, no storage location has been specified.
2) For material PRTR1###, no picked quantity has been entered.

Solution

Please run the transaction VL02N, enter the outbound delivery document VL02N
Outbound delivery
number, and confirm with Enter. The screen below should appear. number

Check and correct the respective entries. Storage location FG00 should be FG00
5
entered for both line items. Picked quantities are 5 and 2. Save with . 2

Finally, post the goods issue again.

© SAP SE Page 7
LECTURER NOTES

Problem: Insufficient material stock level

Symptom An insufficient amount of materials on stock lead to the situation that a sales order
cannot be fully delivered.
Reason Error messages may be caused by unplanned or unintentional material consumption or by
entering incorrect (too high) quantities during the case study process.
Solution Basically, sufficient stock levels for all materials used in the exercises and case studies
have been predefined in the Global Bike client. However, you can receive missing materials on
stock using transaction MB1C. In this specific case, please use movement type 501, plant MI00,
storage location FG00 and the particular material (DXTR1### and/or PRTR1###).

Display Material Stock Level

With transaction MMBE you can display the stock level of a given material. MMBE

Enter the number of the material in question and click on .

The following window lists available quantities on the storage location,


plant, and company code level.

Correct Material Stock

In the transaction MIGO, change the Material Document drop down to MIGO
Goods Receipt, adjust the type of Goods Receipt to Other.

On the Goods Receipt Other screen, select the Tab Where enter Movement 501
MI00
Type 501, Plant MI00 and Storage Location FG00. Then, confirm with FG00
Enter.

© SAP SE Page 8
LECTURER NOTES

Note For stock level problems in the Sales and Distribution case study please
use plant MI00 and storage location FG00. Dependent on the cause of a
given problem the organizational units may differ.

Enter the desired Material, the Quantity and the Storage Location. As an Material number
Quantity
example, the screenshot below shows the posting of 100 black Deluxe Storage Location
Touring Bikes (DXTR1###) into the finished goods storage location (FG00).

Post the goods receipt with .

© SAP SE Page 9
LECTURER NOTES

Problem: Incoming payment cannot be posted

Symptom You receive an error message when trying to post the incoming payment.
Reason When creating or displaying an invoice you realize that the invoice was not successfully
transferred from Sales and Distribution (SD) to Financial Accounting (FI). This is usually caused
by missing or incorrect data in the customer master record.
Solution Correct the customer master record.

Change Customer Master Record

To solve this problem please open your customer master record and check
whether all sales data has been entered correctly. In order to change a
customer master record, use transaction VD02. VD02

Please verify the data you have entered on the initial screen with the data
shown on the screenshot above. Only the customer number may vary in your
case. Enter Sales Organization UE00, Distribution Channel WH and UE00
WH
Division BI. After clicking on the screen below should appear. BI

© SAP SE Page 10
LECTURER NOTES

Please check whether Currency USD, Cust.pric.proc. 1 and Cust.Stats.Grp 1 USD


1
have been entered. Then, navigate to the Shipping tab and enter the following 1
values.

© SAP SE Page 11
LECTURER NOTES

As shown above, type in Delivery Priority 2 (Normal item), Delivering Plant 2


MI00
MI00, Shipping Conditions 01 (Standard) and Max.Part.Deliveries 3. Then, 01
navigate to the Billing Documents tab. 3

Enter FOB and Miami as Incoterms, Payment terms 0001, Acct assgmt FOB Miami
0001
group 01 and Tax classification 0 for all three categories. Then, save with 01
0
. Now, the customer master record has been checked and updated.

If the invoice had already been created and saved and the error only occurred
when the student tried to display the invoice, the existing invoice needs to be
canceled. In order to do so, please use the transaction VF11. VF11

Enter the invoice document number if the system has not already populated Invoice number

the Document field automatically. Click on to cancel the invoice.


The screen below should appear next.

In addition to the existing invoice document, a reverse invoice document is


created in the system. Click on to save your changes. Now, you can
create a new invoice. To do so, resume with the task Create Invoice for
Customer in the SD case study and continue with the following process
steps.

© SAP SE Page 12
LECTURER NOTES

Problem: Pricing error in inquiry, quotation or order

Symptom You receive a pricing error about missing a mandatory condition PR00, while trying to
create, change or save an inquiry, a quotation or an order.
Reason A common reason for this problem is a missing date (Valid from) during the creation of
an inquiry. This date will be automatically copied and reused as the pricing date value, which is
an important value for pricing.
Solution Enter the Valid from date and check if it was transferred to the Pricing date value.

Error Message

In the following screenshot you can see the detailed text of the appearing
error message.

Solution

Pricing conditions have validity periods. Therefore it is necessary to enter a


pricing date to automatically select the correct condition during pricing.

Please use the specific change transaction of document type (inquiry,


quotation or order) in order to enter the missing date. In case you
experienced the problem during the validity check of the transaction while
trying to save, you can enter the date without leaving the transaction. How to
solve the problem will be shown through the following example inquiry.

© SAP SE Page 13
LECTURER NOTES

Please open transaction VA12 and select your inquiry. Press enter to proceed VA12
and ignore all system notification which may pop up.

For Valid From enter the date which is stated within the case study.

Validate your entry by pressing Enter and select the tab Item detail
afterwards. Make sure that your value got copied to the field Pricing date as
well.

Press to save and leave the transaction.

© SAP SE Page 14
LECTURER NOTES

Solution: SD Challenge

Learning Objective Understand and perform an integrated order-to-cash-process.

Create Inquiry

In the course of the transaction VA11, you create an inquiry for 5 mountain VA11
bikes for men (ORMN1###), 5 mountain bikes for women (ORWN1###),
and 10 off-road helmets (OHMT1###).

Please enter the following data: IN for Inquiry Type, UE00 for Sales IN
UE00
Organization, WH for Distribution Channel, and 00 for Division. Press WH
00
.

In the following screen Create Inquiry: Overview, please enter your Sold-To Sold-To Party
###
Party. Subsequently, please enter your Group Number as Cust. Reference, Today’s Date
Today’s Date as Cust. Ref. Date and as Valid From, and One Month from Today’s Date
One Month from Today
Today as Valid To.

© SAP SE Page 15
LECTURER NOTES

The Bike Zone needs an offer for three products – the mountain bike for men ORMN1###
ORWN1###
(ORMN1###), the mountain bike for women (ORWN1###), and off-road OHMT1###
helmets (OHMT1###). Please enter 5 as Order Quantity for both mountain 5
5
bikes and 10 for the off-road helmets. 10

Please change the order probabilities for both mountain bikes to 70% and
70
the order probability for the off-road helmets to 100% since they are added 70
to the order for free. Click Enter to update the inquiry and notice the new 100
expected order value of 17,650,000.

Press to save the inquiry. The SAP system will allocate a unique
number to the inquiry.

Create Quotation

In the course of the transaction VA21 you create the quotation as described VA21
in the case study. Until the Conditions, which you create as follows.

To mark the off-road helmets as free-of-charge items, please choose the


corresponding Item lines and click on the tab header Item Detail. In the field
Item Category, please choose the entry AGNN. AGNN

© SAP SE Page 16
LECTURER NOTES

To grant $50,00 discount for each ordered mountain bike, please choose the
line Mountain Bikes for Men and press Conditions. Subsequently, please
enter K005 (Customer/Material) as Condition Type and enter an amount of K005
50 USD. Subsequently, please do the same for the mountain bikes for 50
women.

To apply the 3% discount on the complete purchase, please follow the menu
path:
Go To ► Header ► Conditions

To apply the 3% discount, please enter RA00 (% Discount from Net) as RA00
3
Condition Type and an amount of 3. Press Enter. Please notice that the
discount is not yet included in the price.

To activate the 3% discount, please click the button Activate.

Save the new quotation.

Create Sales Order with Reference to the Quotation

In the course of the transaction VA01, please enter OR as Order Type. The VA01
OR
other fields are optional to fill. Please press to create
the following pop-up screen.

© SAP SE Page 17
LECTURER NOTES

Please enter your quotation number. In case you forgot your quotation
number, please use F4-help and search for your purchase order number ###.

Having entered your quotation number, please click to copy the


information concerning the quotation to the sales order.

Please enter ### as Purchase Order Number and Today’s Date as Purchase Today’s Date
Order Date. Notice that the requested delivery date was copied from the
quotation. Save the sales order. The SAP system will create a unique
number.

Create Outbound Delivery

In the course of the transaction VL01N, please proceed as described in the VL01N
case study.

Pick Material

In the course of the transaction VL02N, you will see the following screen. VL02N
Please confirm this screen by pressing Enter.

© SAP SE Page 18
LECTURER NOTES

In the screen that appears, please click on the tab header Picking and enter
FG00
FG00 as Storage Location for the mountain bikes and TG00 as Storage TG00
Location for the off-road helmets. Furthermore, please enter the
corresponding amounts for Picked Quantity (5 for ORWN1###, ORMN1### 5
and 10 for OHMT1###). Save your entries. 5
10

Outbound Logistics

In the course of the transaction VL02N, please proceed as described in the VL02N
case study.

Create Customer Invoice

In the course of the transaction VF04 , please proceed as described in the VF04
case study.

Post Incoming Payments

In the course of the transaction F-28 , please proceed as described in the case F-28
23,280.00
study, but enter 23,280.00 as amount.