Project Reporting Template
Project Reporting Template
22EO0002
PREPARATION OF BOLLARDS
PREPARATION OF BOLLARDS
Unit Quantity Unit Price Amount PREVIOUS ACC. THIS PERIOD TO DATE
Item No. Description % WT AMOUNT % WT. ACC. REMARKS
(pesos) QTY QTY QTY
PART A Facilities for Engineers
A1.1 Offices and Laboratory for the Engineer
Provision Combined field office, laboratory and living quarters building for
A1.1(6) mos. 7.40 P 52,702.70 P 389,999.98 0.28
theEngineer (Rental Basis)
Provision Furniture/(fixtures, equipment and appliances for the field office
A1.1(11) l.s. 1.00 P 265,850.00 P 265,850.00 0.19
for the Engineer
Provision of Laboratory Testing Equipment, Apparatus & Publications for
A.1.1(14) l.s. 1.00 P 195,000.00 P 195,000.00 0.14
the Engineer
Operation & Maintenance of Temporary Field Office, Laboratory and Living
A.1.1 (15) mos. 7.40 P 13,000.00 P 96,200.00 0.07
Quarters Building for the Engineer
A1.2 Vehicles for the Engineer
A.1.2(4) Provision of 4x2 Pick Up Type Service Vehicle for the Engineer on Bare Rental mos.
Basis 7.40 P 36,400.00 P 269,360.00 0.19
A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineermos. 7.40 P 19,500.00 P 144,300.00 0.10
A.1.3 Assistance to the Engineer
A.1.3(3) Provision of Survey Personnel for the Assistance to the Engineer mos. 7.40 P 58,500.00 P 432,900.00 0.31
A1.4 Photographs
A.1.4(1) Provision of Progress Photographs each 370.00 P 32.50 P 12,025.00 0.01
PART B OTHER GENERAL REQUIREMENTS
B.2 Medical Room and First Aid Facilities l.s. 1.00 P 65,000.00 P 65,000.00 0.05
B.5 Project Billboard/Signboard each 2.00 P 5,460.00 P 10,920.00 0.01 2.00 2.00 P 10,920.00 0.01
B.7(2) Occupational Safety and Health Program l.s. 1.00 P 404,300.00 P 404,300.00 0.29 0.50 0.50 P 202,150.00 0.14
B.8(1) Traffic Management mos. 7.40 P 16,689.19 P 123,500.01 0.09
B.9 Mobilization/Demobilization l.s. 1.00 P 390,000.00 P 390,000.00 0.28
PART C EARTHWORKS
100(3)a1 Individual Removal of Trees, 150 - 300 mm.dia (Small) each 36.00 P 716.44 P 25,791.84 0.02
100(3)a2 Individual Removal of Trees, 301 - 500 mm.dia (Small) each 11.00 P 1,172.36 P 12,895.96 0.01
100(3)a3 Individual Removal of Trees, 501 - 750 mm.dia (Small) each 2.00 P 3,224.00 P 6,448.00 0.00
100(3)a4 Individual Removal of Trees, 751 - 900 mm.dia (Small) each 4.00 P 4,030.00 P 16,120.00 0.01
100(4) Individual Removal of Trees, above 900 mm.dia, Large each 1.00 P 6,448.00 P 6,448.00 0.00
101(1) Removal of Structures and Obstruction L.s 1.00 P 97,760.00 P 97,760.00 0.07
103(3) Foundation Fill cu.m. 25.00 P 2,020.20 P 50,505.00 0.04
104(1)a Embankment from Roadway Excavation, common soil cu.m. 2,056.00 P 879.81 P 1,808,889.36 1.29
104(2)a Embankment from Borrow, Common Soil cu.m. 33,065.00 P 787.63 P 26,042,985.95 18.63 850.00 850.00 P 669,485.50 0.48
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course cu.m. 7,751.00 P 1,036.55 P 8,034,299.05 5.75
PART E SURFACE COURSE
311(1)a PCCP (unreinforced, 0.15m thk,14 days) sq.m. 8,828.00 P 1,357.66 P 11,985,422.48 8.57
311(1)e1 PCCP (unreinforced, 0.28m thk,14 days) sq.m. 29,757.00 P 2,002.16 P 59,578,275.12 42.61
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
500(1)b3 Pipe Culverts .91m dia. Class IV RCPC l.m. 120.00 P 6,996.64 P 839,596.80 0.60
500(1)b5 Pipe Culverts 1.22m dia. Class IV RCPC l.m. 40.00 P 11,764.51 P 470,580.40 0.34
506(1) Stone Masonry cu.m. 1,168.00 P 3,652.72 P 4,266,376.96 3.05
508(1) Handlaid Rock Embankment cu.m 63.00 P 1,118.99 P 70,496.37 0.05
PART H MISCELLANEOUS STRUCTURES
603(3)a1 Metal Guardrails (Metal beam) Including Post, Single W-Beam l.m. 2,366.00 P 2,179.55 P 5,156,815.30 3.69
603(4)a Metal Beam End Piece, Fish Tail each 8.00 P 1,878.16 P 15,025.28 0.01
605(6)e1 Hazard Markers, Chevron Signs, 450mm x 600mm each 38.00 P 14,254.87 P 541,685.06 0.39
607(3)b Internally Illuminated (Solar) Pavement Levelled Marker/Stude Flush Type, each 1,827.00 P 9,393.09 P 17,161,175.43 12.27
612(1) Reflectorized Thermoplastic Pavement Markings (White) sq.m. 730.00 P 903.28 P 659,394.40 0.47
612(2) Reflectorized Thermoplastic Pavement Markings (Yellow) sq.m. 201.00 P 871.83 P 175,237.83 0.13
P 139,821,579.58 100.00 852.50 852.50 P 882,555.50 0.63