Goodchild (2016) Concrete Basements
Goodchild (2016) Concrete Basements
Concrete Basements
Introduction/background
Planning a basement
• Types & Waterproofing strategy
Concrete Basements • Site Constraints
Ground movements & Methods of
Guidance on the design and construction of in‐situ construction
concrete basement structures
Materials
20 April 2016 Structural design
• Loads
Charles Goodchild • ULS
CEng., MCIOB, MIStructE • SLS
Principal Structural Engineer • Example
MPA ‐ The Concrete Centre Specification and construction
Case studies
Then: BS 8007:1987
Concrete Basements Then:
BS 8102:1990
Introduction/background
Planning a basement BS8102
• Types & Waterproofing strategy
• Site Constraints
Ground movements & Methods of
construction Basements
Materials
Structural design
• Loads
• ULS
• SLS
• Example
Specification and construction
Case studies
Then:
Design & Construction of Deep Basements: 2004 CIRIA C660
• Debate
• S Alexander, TSE Dec 06
• B Hughes, TSE Aug 08?
• ICE project 0706 on reinforcement to control
cracking (report Feb 2010)
• an holistic
approach Space Planning
• an understanding Construction
Services
sequence
of both the ground
and the structural
behaviour
Structure
• formal Cost and risk Architecture
consideration of
construction
methods
Geotechnics Waterproofing
• communication:
Concrete Basements Concrete Basements
Planning a basement
• Types & Waterproofing strategy
1. Establish Clients requirements
• Site Constraints
Ground movements & Methods of 2. Site surveys, etc
Planning a basement Planning a basement
Grades Types of water‐resisting construction vs risk BS 8102:2009 :
BS 8102:2009 Table 2 provides guidance:
Grade of use
Grade 1 Some leakage, some damp.
Parking, Plant rooms
Grade 2 No water penetration or damp patches.
Plant rooms, workshops
Grade 3 Dry environment. Ventilation required.
Residential, Commercial
(Grade 4) (totally dry and vapour proof)
Archives, stores …. go to BS 5454
As an aid . .
Combinations possible
Planning a basement Planning a basement
Grades BS 8102:2009 Forms of rc basement construction related to site conditions
and use of basement space:
Cost Water Level Form of Method of construction
increasing construction
Low: RC box In open excavation or within
generally below temporary works
floor level Contiguous Basement excavated after piling
piling with the floors acting as props in
Medium to high: Secant piling the final condition with/without
permanently or sheet piling etc subsequent concrete facing
above lowest Diaphragm Basement excavated after dia-
floor level walling phragm with the floors acting as
props in the final condition
Planning a basement Planning a basement
Types BS 8102:2009
Other subjects
Type A • Surveys and ground investigations
Barrier protection • Precautions near underground tunnels, sewers & service
mains
• Working adjacent to existing structures: Party walls
Planning a basement Planning a basement
Exploratory works
NEEDED EARLY - commission early! Space requirements
desk study
• geological maps, borehole records,
• ordnance survey, water courses, utilities.
site surveys
• boundaries, adjoining buildings and roads,
liaison with adjacent owners, party walls,
• incoming services, tunnels
subsoil investigation
• bearing capacity, water level, pile design,
earth pressures, settlements, (modulus of
subgrade reaction) contaminants. See BS EN
1997-2
• money well spent!
assess
• risk of risk of flooding (EA), likely obstructions,
foundation details of adjoining buildings,
disposal of groundwater
Planning a basement Planning a basement
• 3m and 6m notices
• Distortions cause damage – not absolute movement Guide wall?
• 10 mm often used as a trigger
Planning a basement Planning a basement
Pile tolerances
Space planning:
Check for:
• room for temporary works- clearances for piling rigs.
diaphragm wall equipment takes up considerable space.
• restrictions imposed by owners of underground tunnels
and utility companies
• dimensions of guide walls for contiguous piles (may be
around pile diameter + 800 mm);,
• wall thicknesses : zone for cavity drains if relevant;,
• tolerances for piling and temporary works;
• capping beams
• projecting features of adjoining structures.
• superstructure – follow through into basement,
• Fire – means of escape, compartmentation, access
Ground movements Construction methods
Vertical load Construction methods:
& relief • Open excavation
• Bottom – up
• Top – down
• Semi-top down
Groundwater
Options for basement walls:
• In open excavations: R C walls
• Incorporating temporary embedded
Horizontal retaining walls:
load relief o King post walls
o Steel sheet piling
o Contiguous piled wall
o Secant piled wall
o Diaphragm walls
Facing walls
Temporary works
Ground movements Construction methods
Portcullis House:
Observed vertical and
horizontal movements
around the Palace of
Westminster car park
Construction methods Construction methods
Contiguous Piled Wall
Secant Piles
Construction methods Construction methods
Contiguous Piled Wall
Secant Piles
600 mm diam. Rakers every 2 m Facing wall(courtesy GCL Ltd)
http://www.oasys-software.com
Construction methods Construction methods
Diaphragm Wall
Construction methods Construction methods
Sheet Piles
Reality
Construction methods
Top Down Construction
Cart
away
Raise
Move
Dig
Propped Excavation
http://www.terraingeotech.com/index.html
Construction methods
Grouting
Propped Excavation
Liquid applied membranes…generally
Concrete Basements applied as a bitumen solution, elastomeric
urethane or modified epoxy
Introduction/background
Planning a basement
• Types & Waterproofing strategy
• Site Constraints
Ground movements & Methods of
construction
Materials
Structural design
• Loads
• ULS
• SLS
• Example
Specification and construction
Case studies
Mastic asphalt…applied in 3 coats as a
Selection of materials
hot mastic liquid
Type A construction:
Waterproofing membranes and systems:
• Category 1 – Bonded sheet membranes
• Category 2 – Cavity drain membranes
• Category 3 – Bentonite clay active membranes
• Category 4 – Liquid applied membranes
• Category 5 – Mastic asphalt membranes
• Category 6 – Cementitious crystallisation active systems
• Category 7 – Proprietary cementitious multi-coat
renders, toppings and coatings
Bonded sheet membranes…modified Proprietary cementitious multi‐coat
bitumen on a range of carrier films renders, toppings and coatings
Proprietary cementitious multi‐coat
Selection of materials
renders, toppings and coatings
Admixtures
Selection of materials Selection of materials
Type A construction: Admixtures
Waterproofing membranes and systems:
• Category 1 – Bonded sheet membranes It’s the cracks that matter – not (usually) the concrete!
• Category 2 – Cavity drain membranes
• Category 3 – Bentonite clay active membranes Concrete Society Working Group on Water Proofing
• Category 4 – Liquid applied membranes admixtures:
• Category 5 – Mastic asphalt membranes
• no conclusive evidence to support their use (- from a
• Category 6 – Cementitious crystallisation active systems
material scientist’s point of view).
• Category 7 – Proprietary cementitious multi-coat
renders, toppings and coatings • from data there is some evidence to suggest that they may
reduce drying shrinkage (less permeability) and therefore
Types B & C construction: reduce onset of cracking and reduce crack widths
Concrete
Admixtures for watertightness Cost and risk:
Traditional: Engineering, workmanship, supervision issues, risk & £££
possible remedials and upheavals and contractual issues
vs vs
Admixtures: warranties, supervision & possible remedials and upheavals ££££
but few contractual issues ?
Whatever the basement should still be designed properly!
Selection of materials Selection of materials
Type A construction:
Concrete: Waterproofing membranes and systems:
• Benign soils: • Category 1 – Bonded sheet membranes
• Category 2 – Cavity drain membranes
RC30/37? Cement IIB-V (CEM I + 21%-35% fly ash) • Category 3 – Bentonite clay active membranes
or IIIA (CEM I + 36% - 65% ggbs). • Category 4 – Liquid applied membranes
cf BS 8007 C35A?: C28/35 (equiv) WCR 0.55 CC 325 CEM I, IIB-V,) • Category 5 – Mastic asphalt membranes
BS 8500 RC30/37: C30/37 S3 WCR 0.55 CC 300 CEM I, IIA, IIB-S, IIB-V, IIIA, IVB-V B) • Category 6 – Cementitious crystallisation active systems
• Aggressive soils: • Category 7 – Proprietary cementitious multi-coat
renders, toppings and coatings
Advise producer of DC Class.
Types B & C construction:
For DC-2: FND-2? (C25/30)?
Concrete
More aggressive soils: Cement IIIB (CEM I + 66% - 80% ggbs) or Admixtures for watertightness
IIVB-V (CEM I + 36%-55% fly ash)
Water stops
• Car Parks: C32/40? + provisos (PAV2?) • Preformed strips – rubber, PVC, black steel
• Water-swellable water stops
• Fibres? • Cementitious crystalline water stops
Possibly. Fibres only help once the concrete has cracked. • Miscellaneous post-construction techniques
• (Re) injectable water bars
• Rebate and sealant
Construction, inspection and testing
Cavity drain
Hydrophilics
Photo credit Watermans
Construction, inspection and testing
Sump pump
Resin injection
Photo credit Max Frank
1800
Concrete Basements Structural design :
Soil-structure interaction:
Introduction/background Consider a 8m x 1m base with 1000 kN loads each end on a
very stiff clay (Es = 150 MPa):
Planning a basement 1000 kN
1000 kN
• Types & Waterproofing strategy
• Site Constraints t = 0.5, 0.7, 0.9
or 1.1 m
Ground movements & Methods of Settlement
construction
Materials
Structural design
≡ UDL
settlement
• Loads 250kN/m2
16.7 mm
• ULS @ SLS
• SLS
• Example
Specification and construction
Case studies
e.g:
• F for ground water T1 for a 400 mm
wall, 350 kg/m3
o Normal F = 1.35 CEM I using 18 mm
o Most unfavourable F = 1.20 (≡ ‘Accidental)
ply removed after
7 days ≈ 30oC
• Structural design
o As ‘normal’ elements
o 3D nature of design
Serviceability
Pour configuration R
Limit State Thin wall cast on to massive concrete base 0,6 to 0,8 at base
≡ 0,1 to 0,2 at top
usually 0.5
Control Massive pour cast onto blinding 0,1 to 0,2
Beware: effects
Massive pour cast onto existing concrete 0,3 to 0,4 at
ofbase
creep
of included
0,1 to 0,2 at top
CS TR 67
wk = sr,max cr = sr,max (sm - cm) cm ≈ ctu /2 See Concrete Basements Section 9.7
long term Construction construct at low temperatures, use GRP or steel formwork,
Short term Medium term (≡ > 10000 days) sequential pours
(≡ 3 days) (≡ 28 days)
Detailing: use small bars at close centres, avoid movement joints,
prestress
(Thick sections > say 750 mm) (Thick sections > say 750 mm)
(Thick sections > say 750 mm) Concrete Basements
Introduction/background
CIRIA C660
Fig 4.18
Planning a basement
• Types & Waterproofing strategy
• Site Constraints
Ground movements & Methods of
construction
Materials
Structural design
• Loads
• ULS
Time • SLS
• Example
Specification and construction
Case studies
• Game changer!
• Internal restraint:
T1 becomes large and internal restraint (difference in temperature
and stiffness between core and surface) dominates (external
restraint still relevant).
– Try to restrict differential temperature across section.
– Insulate (cf steel shutters).
– See CIRIA C660 (and HA BA 24/87, HA BD 28/87). Slab 300 mm
Walls 250 mm
GFS 250 mm
C30/37
Class R cement
wk max =0.2 mm
No ground
Asreqd slab (as an upside down flat slab)
Ground
water
water
ULS: Reinforcement for SLS: Reinforcement
vertical and uplift cases for 0.20 mm crack
(mm2 /m) width assuming end
Support# Span# restraint
Cement class
Concrete Basements
Materials
Introduction/background
Planning a basement
• Types & Waterproofing strategy Inspections
• Site Constraints
Ground movements & Methods of
construction
Materials Waterstops
Structural design
• Loads
• ULS
• SLS
• Example
Ties
Specification and construction
Case studies
Specification and construction
Kickers Construction
Workmanship is key
Inspections
Supervision?
Forms of contract
Contractors’
choice of Risk vs £
materials
Discuss with client!
Guidance
Performance
Spec
Concrete Basements
Additives
Introduction/background
Planning a basement
• Types & Waterproofing strategy
Ties • Site Constraints
Ground movements & Methods of
construction
Joints Materials
Structural design
• Loads
Waterstops • ULS
• SLS
• Example
Specification and construction
Case studies
Construction, inspection and testing Concrete Basements
NSCS Max pour sizes Case study - institutional
Maximum Maximum
Construction Area (m )
2 Dimension (m )
Water – resisting walls 25 5
Water – resisting slabs 100 10
Slabs with major restraint at both ends 100 13
Slabs with major restraint at one end only 250 20
Slabs with little restraint in any direction 500 30
Walls 40 10
Salient features
• 4 m deep basement (depth of excavation about 5 m)
• Use – archives, exhibition and public spaces
• Soil – gravels
• Water table about 1 m below ground level
• Propped secant piling to facilitate excavations GA &
• Concrete box designed to be inside the secant piles details:
• Vapour barrier membrane sandwiched between the Temp
piles (faced with polystyrene) and the concrete box works
• Drained cavity inside walls and above floor
By courtesy Clark Smith Partnership
Sections
Construction methods
GA
Concrete Basements Concrete Basements
Pictures! Case study - residential
Concrete Basements
The Fusion Shoreditch
Domestic case study
Buczkowski
Thanks to
Chris
Steelwork Formations
Temp. Works
Steel Paint
Spec Extg structure
Drains
Welds, bolts
& bolting. Bed joint reinf.
Straps
Ties.
A London basement
My house (I wish!)
Concrete Basements: Summary
Introduction/background
Planning a basement
• Types & Waterproofing strategy Concrete Basements
• Site Constraints Guidance on the design and construction of in‐situ concrete basement
structures
Ground movements & Methods of
construction
Having done it
Materials
once go back and
Structural design refine it, Charles Goodchild
• Loads CEng., MCIOB, MIStructE
again,
• ULS Principal Structural Engineer
and again preferably in The Concrete Centre
Thank you
• SLS
• Example league with the constructor
Specification and construction
Case studies
Concrete Basements
CS meeting 8/3/16
Basement issues.
• Clients don’t understand Grades 1, 2 and 3.
• Many specifications and designs looking for two or even 3 types of
Concrete Basements etc
Developments – what is being considered
water resisting construction (membrane + integral + drained cavity).
Within BS8102 but £££?
• NHBC looking for combination of 2 types
• Members of the WG convinced that water resisting construction is a
lot to do with workmanship. Admixtures are a load of ********– which Charles Goodchild
are just insurance policies. CEng., MCIOB, MIStructE
Principal Structural Engineer
• Designers saying ‘we’ve designed it properly now any cracks will be
The Concrete Centre
down to workmanship’. Concentrates minds!
Structural design ‐ SLS
Revision to EC2-3?
Crack widths and watertightness
Tightness Classes - notes BS EN 1992-3 Cl 7.3