TX Parallel Ops
TX Parallel Ops
The above picture shows six transformers in parallel operation. Image source: Mirage
Electronic devices
Table of contents
Conditions for successful parallel operation of transformers
o 1. Equal line voltage ratios.
o 2. Equal per-unit impedances and the same ratio of equivalent leakage reactance to
equivalent resistance.
o 3. The polarity of all transformers must be equal
o 4. All transformers must have the same phase sequence.
o 5. The phase displacement between the primary and secondary terminals must be the
same.
o Operative Parallel Connections of Three-Phase Transformers – (connecting two
transformers in parallel)
Parallel operation of single phase transformers
Advantages of parallel operation of transformers
Summary
The primary of parallel operating transformers are connected to the same source busbar
whereas their secondary windings are connected to a common load busbar. In order to
successfully connect two or more transformers in parallel certain conditions needs to be
satisfied. In the following sections we will discuss in detail on those conditions.
Conditions for successful parallel operation of transformers
The following five principal characteristics needs to be satisfied for a successful parallel
operation of transformers:
The line voltage ratio of all transformers operating in parallel must be equal, otherwise, it will
result in improper loading between the transformers. For example, if two transformers
connected in parallel have slightly different voltage ratios, under no-load conditions, the
inequality in the secondary induced EMFs will result in circulating currents in the loop
formed by the secondary windings.
Due to the low impedance of the windings, the magnitude of the circulating currents will be
quite high. When the transformers are loaded, the circulating currents cause unequal loading.
It is possible that one of the transformers may be fully loaded or even overloaded while the
other is no-loaded. In order to avoid such situations during the parallel operation, the turns
ratios of all the transformers must be equal.
In order to ensure equal load sharing the per-unit impedances of the transformers must be
equal. Suppose two transformers of the same rating are operating in parallel, their per-unit
leakage impedances should be equal. If the ratings are unequal, their per-unit leakage
impedances based on their rating should be equal.
If two transformers with different ratio of equivalent reactance to equivalent resistance of per
unit impedance are paralleled, the current carried by those transformers will not be equal. The
one with the lower power factor carries more current while the one with the higher power
factor carries a lesser current. This will result in improper load sharing. Hence, for proper
parallel operation of transformers, per-unit impedances and the same ratio of equivalent
leakage reactance to equivalent resistance must be equal.
3. The polarity of all transformers must be equal
The polarity of the primary and secondary windings of the transformer must be taken into
account while connecting transformers in parallel. If the polarity of the windings is not the
same, it will result in a short circuit.
4. All transformers must have the same phase sequence.
The phase sequence of transformers in parallel operation must be identical. Mismatch in the
phase sequence will result in short circuits.
The following table shows all operative combinations of transformer windings that can be
followed while connecting transformers in parallel.
TRANSFORMER-1 TRANSFORMER-2
The availability of transformers for service can be increased by connecting two or more of
them in parallel. During maintenance, only those transformers that requires maintenance
can be taken out of service while the other can still supply the loads.
The parallel operation of transformers improves the reliability of the system. Even if any
one of the transformers fails due to some internal faults, the other will be available for the
service.
The efficiency of a transformer is always maximum at full load conditions. By operating
transformers in parallel, maximum efficiency of power distribution can be achieved by
switching only the number of transformers required to supply the total demand.
As transformers can operate in parallel, the power system can be easily scaled for
increasing load demands.
Summary
There are certain conditions that needs to be satisfied during parallel operation of
transformers. Voltage ratios, polarity markings, phase sequence, resistance reactance ratio
and phase displacements needs to be taken care of during the parallel connection.