Method Statement For Hardscape Works
Method Statement For Hardscape Works
IR 146
LANDSCAPE AND IRRIGATION SYSTEM FOR INTERCHANGE OF GARN AL
SHABKHA RD WITH SH. ZAYED ROAD (IC 5.5)
TABLE OF CONTENTS
1. Project Information
3. Responsibility
4. Work Procedure
5. Safety Procedure
7. Material Reference
8. Risk Assessment
2|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
1. Project Information
3. Responsibility
The following personnel shall be responsible for the activity at site
1) Project Engineer
2) Site Supervisor
3) Safety Engineer
3|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
4. Work Procedure
4.1 Setting out
Setting out for the locations as per the approved drawing.
Bending and cutting of reinforcement steel bars as per the project specification
equipment. Personnel duly qualified shall be employed for cutting and bending
operations.
referred for bending. Dimensions shown in the bar bending schedule shall be
permitted on bars. Load shall be applied gradually. Bar once bent shall
Engineer-in-charge.
4|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
All reinforcement shall be placed and maintained in the positions shown on the
drawings. 18 swg G.I wire shall be used as binding wire. All bars crossing one
another shall be bound with this wire twisted tight to make the skeleton on
network rigid. Bars must be cleaned with dry gunny bags if they are coated lightly
with rust or other impurities. Required number of MS chairs & spacer bars shall be
Place the reinforcement as per drawings ensuring the following aspects properly.
Cover to reinforcement:
All cover blocks shall be of cement mortar (1:2). The minimum cover to be
Unless specified otherwise, actual concrete cover should not deviate from the
materials like PVC, Micro concrete will be permitted after approval from Project
Manager.
Welding:
properly tagged, segregated out and recorded to prevent for inadvertent use.
5|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
All such defective and rejected items shall be physically separated from the
usable item. In case, any of these items are proposed to be used in works, the
same shall be recorded in the form of design concession request and forwarded
to the Project Manager who will forward the same to the designer for review
and after his acceptance shall be recorded in “as built condition’. The
HYSD bars will be transported from the fabrication yard by trailers. While
transporting, care will be taken for ensuring that the bars do not suffer any
damage and are safely handled. HYSD bars will be properly stacked and
identification and trace ability should be properly ensured in the places of work
6|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
7|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
A prop should not be used if it is bent, creased or, rusted or has a bent head
or base plate, damaged pin etc.
Proper release of agent shall be used so that it can be removed without
damaging the surface finish of the concrete.
New timber and plywood forms shall be given first coat of the appropriate
release agent 36 hours in advance, then a second coat just before they are
used. Avoid excessive use of release agent as this can cause staining or
retardation of the concrete.
A close watch should be kept on all wedges and fastenings. Make sure that
they do not work loose. Grout loss is an indication that some movement has
occurred.
When un-sleeved tie bars are being used, ease them slightly before the
concrete sets, and remove them as soon as it is safe.
8|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
9|Page
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
whenever required.
Concrete cube test report shall be submitted to the Engineer
5. Safety
All works shall comply with the safety procedure or instruction as set out in
equipment machine.
Proper precautions shall be taken while cutting using gloves and goggles.
All worker should wear required PPE’s (safety helmet, shoes, safety belts)
10 | P a g e
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
8. Risk Assessment
11 | P a g e
METHOD STATEMENT FOR
PROJECT SIGN BOARD WORKS
12 | P a g e