Infrastructure Design Manual - Version - 5.30
Infrastructure Design Manual - Version - 5.30
Local Government
Infrastructure Design Association
PO Box 212, GOLDEN SQUARE, 3555
www.designmanual.com.au
VERSION 5.30
TABLE OF CONTENTS GENERAL CLAUSES
Clause 1 Introduction 15
1.1 Background 15
1.2 Benefits of a Common Manual 15
1.3 Consultation 15
1.4 Objectives 15
1.5 Principles 16
1.6 Council Approval 16
1.7 Variation to IDM Clauses 16
1.8 Township Character 16
1.9 Innovation and Advances in Technology 17
1.9.1 General 17
1.9.2 Sustainable Infrastructure Guidelines 17
1.10 Councils That Have Adopted the Manual 17
1.11 Applicable Standards 19
1.12 Revision 19
Clause 2 Definitions 22
VERSION 5.30
5.1 Objectives 34
5.2 General 34
5.3 Checklists and Auditing 35
5.4 Developer’s Representatives 35
5.5 Pre-Design Site Inspection 36
5.6 Coordination of Works by Developers 36
5.7 Variation from Design Guidelines 36
5.8 Documents to be Submitted 36
5.8.1 Approval of Functional Layout Submission 36
5.8.2 Detailed Design Submission 38
5.8.3 Final Design Submission 39
Clause 6 Documentation 40
6.1 Objectives 40
6.2 General Requirements 40
6.3 Plans 40
6.3.1 Sheet Size 40
6.3.2 Scales 40
6.3.3 Datum 41
6.3.4 Standard Details 41
6.3.5 Drawing Numbers 41
6.4 Specifications 41
6.5 Standard Drawings 42
6.6 Information to be shown on Plans 42
VERSION 5.30
8.3 Commencement of Defects Liability Period 51
8.4 Guarantee of Work 51
8.5 Bonding of Outstanding Works 52
8.6 Defective Items 52
8.7 Release from Defects Liability 52
VERSION 5.30
Table 5 Turning Movement Plans 70
12.7.14 Proof-Rolling 86
12.7.15 Soft Areas in Pavements 86
VERSION 5.30
12.7.16 Pavement Wearing Course 86
12.7.17 Alternative Treatments 87
12.8 Traffic Control Devices 88
12.8.1 Signposting and Pavement Marking 88
12.8.2 Guard Fence 88
12.9 Vehicular Access 88
12.9.1 Urban Vehicle Crossings 89
12.9.2 Rural Vehicle Crossings 91
12.10 Requirement for Dust Suppression Works 92
VERSION 5.30
Table 9 Annual Exceedance Probabilities for Minor Drainage
in Urban Areas 104
VERSION 5.30
17.4 Minor Drainage 120
VERSION 5.30
20.3.1 General Requirements 135
20.3.2 Gross Pollutant Traps 135
20.3.3 Bioretention Swales 136
20.3.4 Bioretention Basins and Rain Gardens 136
20.3.5 Vegetated Swales, Grassed Swales, and Buffer Strips 138
20.3.6 Sand Filters 139
20.3.7 Sedimentation Basins 140
20.3.8 Constructed Wetlands 140
20.3.9 Ponds and Shallow Lake Systems 141
20.3.10 Rainwater Tanks 141
VERSION 5.30
24.3.4 Public Open Space Provision (Residential Development) 153
24.3.5 Fencing of Public Reserves 154
24.4 General Requirements 154
24.4.1 Information to be provided 154
24.4.2 Maintenance Period 155
24.4.3 Defect Liability Period 155
24.4.4 Protection of Existing Vegetation 155
24.4.5 Vehicular Access 157
24.4.6 Clear Zones 157
24.4.7 Entrance Features 157
24.4.8 Street Tree Planting Requirements 157
VERSION 5.30
TABLE OF CONTENTS APPENDICES
Appendix A: Model Conditions for Planning Permits 166
VERSION 5.30
TABLE OF CONTENTS SELECTION TABLES
Selection Table 3.5 Sustainable Infrastructure Guidelines 30
Selection Table 7.9.1 Councils Requiring CCTV Verification of Underground Drainage Assets 49
Selection Table 16.10.1 Ribbed Polypropylene or High Density Polyethylene Stormwater Pipes 109
Selection Table 20.3.5 Vegetated Swales / Grass Swales / Buffer Strips 139
VERSION 5.30
Clause 1 Introduction
1.1 Background
This Infrastructure Design Manual (Manual) was originally prepared by the Cities of Greater Bendigo and Greater
Shepparton and the Shire of Campaspe. Their joint initiative was one which recognised the benefits of municipalities
working together towards consistent requirements and standards for the design and development of Infrastructure.
Since the preparation of the Manual many other Councils have adopted the Manual. These Councils have formed the
Local Government Infrastructure Design Association (LGIDA) which now owns and maintains the Manual.
• Developing more consistency amongst design requirements for Consultants and Developers working in the
participating municipalities.
• Providing a better point of reference for all parties at the Victorian Civil Appeals Tribunal (VCAT).
• Sharing ideas and practices to help the municipalities to adopt best practice.
• Documenting the requirements of participating Councils for the design and development of Infrastructure.
• Providing a clear framework to enable new subdivisions and development to respond to and enhance township
character, deliver diversity and high-quality urban outcomes.
1.3 Consultation
This Manual has been prepared following consultation and liaison with Councils, Council staff, Consultants and
Developers. Each Council was responsible for its own consultation process. The consultative processes have ensured
that the policies, procedures and guidelines in this Manual achieve, as far as practicable, the three main aims of
appropriate, affordable and equitable Infrastructure that serves the community and promotes growth.
1.4 Objectives
This Manual is designed to be used within the boundaries of all the municipalities who have adopted this Manual. The
primary objectives of the Manual are:
• To clearly document Council’s requirements for the design and development of Infrastructure that is or will become
Council’s Infrastructure.
• To standardise development criteria as much as possible and thus expedite Council’s engineering reviews.
• To ensure that minimum design criteria are met in regard to the design and construction of Infrastructure within the
municipalities regardless of whether it is constructed by Council or a Developer.
1.5 Principles
Several principles have been used to formulate the provisions of the IDM. Where that has occurred the word “principle” is
attached as a superscript to the particular clause. For example
Developments that contain more than 200 lots in a development plan may be required to establish bicycle
routes through the development PRINCIPLE.
By hovering the mouse above the superscript principle, the principle is displayed. Principles are also listed in Appendix J
Notes on Engineering Principles.
In neither context does Council approval absolve the Design Engineer and the Construction Engineer of ultimate
responsibility respectively for the design and the construction of the works in question.
• Renewing an existing asset which does not comply with the standards specified in this Manual.
• Protecting native vegetation or the existing streetscape
• Where adopting the IDM standards would result in detriment to the neighbourhood character of an area.
• Infrastructure located in a heritage precinct or heritage significant area.
• Infill Development where Council wants to maintain the surrounding or abutting standards
In addition, Council may exempt particular developments from specified requirements of this Manual where the
Developer can demonstrate that the objectives of the IDM have been met. Developers should apply in writing seeking
providing compelling arguments to justify the granting of the exemption or exemptions requested.
While the Manual sets minimum standards, Councils and developers may wish to consider adopting alternative
standards to achieve residential development outcomes that are more appropriate to the character of a particular rural or
regional township.
1.12 Revision
The Manual is a living document and may be revised and amended from time to time.
To ensure that everyone has access to the latest version, the Manual will only be available electronically on the LGIDA
website at www.designmanual.com.au.
Suggestions on how this Manual can be improved can be forwarded by email to the Executive Officer of the LGIDA at
[email protected] All submissions made in accordance with these provisions will be considered by the LGIDA
Technical Committee, which will provide regular reports to the LGIDA Board and, when considered appropriate,
recommend changes to be incorporated into the IDM.
Engineering queries relating to individual development submissions, status of the review process or further technical
direction regarding Infrastructure design should be directed to the following people at the relevant municipalities:
• Coordinator Civil Asset Planning • Coordinator Design and Development, Ballarat City
Baw Baw Shire Council Council.
• Team Leader Design and Development, • Transport and Development Coordinator, Mitchell
Warrnambool City Council Shire Council.
• Asset Engineer, Yarriambiack Shire Council • Manager Infrastructure, Southern Grampians Shire
Council.
• Design and Project Management Coordinator, Ararat • Design and Development Engineer, Glenelg Shire
Rural City Council. Council.
• Works Manager, Golden Plains Shire Council. • Senior Development Engineer, Wodonga City
Council.
• Engineering Development Officer, Macedon Ranges • Manager of Assets, Towong Shire Council
Shire Council
• Senior Development Engineer, Moorabool Shire • Manager Infrastructure Services, Indigo Shire
Council Council
• Development Engineer, Hepburn Shire Council • Senior Design Engineer, Swan Hill Rural City
Council.
• Manager Engineering, Waste Operations Contracts, • Development Engineer, Colac Otway Shire Council
Pyrenees Shire Council
• Coordinator Development Engineering, Surf Coast • Team Leader – Engineering, Mount Alexander Shire
Shire Council Council
• Manager Engineering Services, Horsham Rural City • Assets Engineer, Moyne Shire Council
Council
Contact can be made with the people listed above via the LGIDA website at www.designmanual.com.au.
COUNCIL DEPARTMENT
Ararat Rural City Council Council Services
Ballarat City Council Design and Delivery
Bass Coast Shire Council Asset Management
Baw Baw Shire Council Assets and Recreation
Benalla Rural City Council Infrastructure Services
Campaspe Shire Council Asset Department
Design Engineer or Designer Unless otherwise agreed by Council, all road and drainage designs should
be completed by a Qualified Engineer, who will hereafter be referred to as
the Design Engineer or Designer.
Developer(s) The person or company that undertaking the land development.
Developer’s Representative The Developer’s Representative is preferably the Superintendent where
there is a contract between the Developer and the Contractor for the
provision of Infrastructure that will be vested in Council. When there is no
contract in place for the works the Developer’s Representative will be the
Construction Engineer or the Design Engineer as required by the context.
Development Refers to "the carrying out of building, engineering, mining or other operations
in, over or under land or the making of any material change in the use of any
building or other land".
Infrastructure Refers to physical works including roads, paths, playground and recreation
equipment, landscaping and drainage systems (including retardation and
treatment facilities) and ancillary assets such as signs.
Low Density Residential Development For the definitions of the different types of Low Density Residential
Development (LDRZ) see clause 12.2.
Maintenance Period Is the period of time specified in Section 17(4) of the Subdivision Act 1988, or
planning permit or elsewhere in the IDM, whichever is the greater period, that
the developer is responsible for maintenance of the completed works in good
condition and repair unless otherwise agreed to in writing.
Manual The Infrastructure Design Manual.
MUSIC The Model for Urban Stormwater Improvement Conceptualisation (MUSIC) is
a software tool that simulates the behaviour of stormwater in catchments.
Qualified Engineer A person eligible to be registered as a civil engineer on the National l
Engineers Register and experienced in the relevant field of practice.
Road Verge The distance between the invert of kerb and the near road reserve boundary.
Superintendent The appropriately experienced and qualified person appointed by the
Developer to carry out the functions of the Superintendent as defined in the
General Conditions of Contract – AS 2124 or AS4000 when there is a contract
As a general principle, plans and calculations submitted to and accepted by Council at any stage in the planning approval
process should not normally require major adjustments at a later stage, unless there have been significant changes in
circumstances during the intervening period.
3.3.1.1 General
Unless the Developer has requested that the Planning Scheme Amendment be considered in conjunction with a
Planning Permit application, Council will not normally require that a Traffic Management Strategy [TMS] as defined in
Clause 9 of this Manual or a Stormwater Management Strategy [SMS] as defined in Clause 11 of this Manual be
submitted at this stage in the planning approval process. The information requirements for this stage of the process are
set out below.
3.3.1.3 Stormwater
The Developer should, where relevant, engage a Qualified Engineer to prepare a preliminary stormwater assessment
which addresses, at an appropriate level of detail, the arrangements for collecting, conveying, storing, and discharging
stormwater from the planned development and achieving water quality improvements consistent with established WSUD
principles. The assessment should consider:
• the relevant catchment and sub-catchment areas; and
• practicable routes and destinations for the major and minor stormwater networks; and
• pre-development agreements required for offsite stormwater management; and
• the possible scale and location of any stormwater retardation basins; and
• the possible scale and location of WSUD quality treatment facilities; and
• Required design intensities
• AEP of major and minor storm events
• Model selection in line with ARR2019
• Modelling technique in line with ARR2019
3.3.1.4 Flooding
When any substantial proportion of the land in question may be subject to fluvial or pluvial flooding, the Developer should
engage a Qualified Engineer to prepare and submit a Flood Impact Report to satisfy Council and any relevant floodplain
3.3.3.1 General
The engineering information requirements for a Development Plan [DP] are specified in the relevant Development Plan
Overlay Schedule in the Planning Scheme. In the absence of any more detailed guidance from that source, the Developer
should provide sufficient engineering information to validate the framework in which future Planning Permit applications
are intended to be considered, having regard to the following sub-clauses.
3.3.3.3 Stormwater
Council will not normally require that a Stormwater Management Strategy [SMS] as defined in Clause 11 of this Manual
be submitted at this stage in the planning approval process. The Developer should, where relevant, engage a Qualified
Engineer to prepare a stormwater assessment which addresses, at a level of detail appropriate to the objectives of a
Development Plan, the arrangements for collecting, conveying, storing, and discharging stormwater from the planned
3.3.3.4 Flooding
When any substantial proportion of the land in question may be subject to fluvial or pluvial flooding, the Developer should
engage a Qualified Engineer to prepare and submit a Flood Impact Report in order to satisfy Council and any relevant
floodplain authority that the proposed development can be carried out without having any adverse impact on other
properties and/or on the natural environment.
3.3.4.1 General
Unless the relevant information has been provided earlier in the planning approval process, the Developer should identify
the approximate size, range, shape and orientation of the allotments, and demonstrate that all allotments will have legal
and practical access. Note that carriageway easements are the least preferred option and requires the specific written
approval of Council.
3.3.4.3 Stormwater
When any of the circumstances defined in Clause 11 of this Manual apply to the proposed development, Council may
require the Developer to engage a Qualified Engineer to prepare and submit a Stormwater Management Strategy
[SMS] prior to issuing a Planning Permit.
3.3.4.4 Flooding
Unless the relevant information has been provided earlier in the planning approval process, when any proportion of the
land in question may be subject to fluvial or pluvial flooding, the Developer should identify suitable building envelopes,
located at or above the predicted peak flood levels, and provide sufficient information to satisfy Council and any relevant
flood-plain authority that these envelopes can be established without detriment to other properties and/or to the natural
environment, and without having any significant impact on flood levels and velocities.
These Councils will expect the Design Engineer to complete the Sustainability Checklist provided in Appendix B of the
SIG when submitting proposals for Significant Developments within their municipal boundaries. This will provide evidence
For the purposes of this clause, developments will be considered “significant” when they involve EITHER a subdivision
(including all stages) greater than 50 lots in size OR infrastructure designed in accordance with the IDM and passing into
Council ownership whose estimated cost exceeds $2,000,000 in 2017 dollars.
Where the Design Engineer can demonstrate that proposed variations from the Manual are consistent with the SIG, the
Councils listed in Selection Table 3.5 as having adopted the SIG, will normally accept that the objectives of the relevant
IDM clauses have been met, although the proposal may not comply with all their technical provisions.
• Site establishment
• Setout for construction
• Traffic Management
• Environmental management works
• Stripping topsoil and stockpiling
• Excavations for road, footpaths, kerb and channel, vehicle crossings and drainage work, including stormwater
treatment
• Earthworks including lotfilling and nature strips
• Laying of pipes, construction of pits, headwalls, outlets and other associated works including house connections
• Installation of GPT’s, litter traps etc
• Preparation and treatment of subgrade
• Supply and installation of pavement materials, including compaction testing
• Construction of footpaths and shared paths
• Construction of kerb and channel
• Construction of vehicle crossings, where they are required to be installed.
• Construction of street lighting
• Installation of street signs
• Installation of traffic calming devices and measures, traffic islands, school crossings, pedestrian crossings,
traffic lights, splitter islands
• Asphalting and sealing works
• Street trees and landscaping works
• Linemarking
• Street furniture
If more than one construction inspection or Acceptance of Works inspection is required (refer Clause 7.5) because the
Council Engineer has been called before the works are ready for inspection an extra fee of $50.00 will apply for the first
additional inspection, $100.00 for the second additional inspection, and $150 for the third additional inspection, unless
varied by a previous written agreement.
The Planning and Environment Act 1987 allows for development contributions to be provided through:
• A Development Contributions Plan
• An Infrastructure Contributions Plan
VERSION 5.30 Page 32 of 275
• A Section 173 agreement
• Planning permit conditions.
Development contributions may be required for road works, drainage, public open space, traffic management works,
community infrastructure or other works that are required as a result of the development.
To request a contribution from the relevant authority to the proposed drainage infrastructure, Developers must submit a
request in writing, and the associated plans, specifications, cost estimates and other relevant documents, prior to a
specified date each year. The request should detail the proposed contribution of all benefiting parties and the date or
trigger for the contribution requested. The allocation of funding through the budget process of the authority in question
cannot be guaranteed.
• To provide Developers with clear guidelines regarding the engineering requirements of Council.
• To ensure that new and upgraded Infrastructure is of consistent standard across the municipalities.
• To ensure that the works are designed such that they will fulfil the purpose for which they are intended.
• To ensure that minimum design standards are achieved and works meet Councils’ legislative obligations.
• To ensure that community amenity will be improved through development.
• To ensure that environmental, public and employee risk during and after development is considered.
• To ensure that maintenance requirements are considered at the planning and design stages.
• To ensure all relevant statutory authorities/stakeholders have been consulted and their requirements considered.
• To ensure continuity in township / local character, where desired by Council.
5.2 General
Comprehensive design criteria included in the Manual convey engineering requirements for the internal or external delivery
of design and construction of roads and drainage Infrastructure, while considering local conditions and the requirements
of the Council.
For Developer’s Representatives, the Manual provides the basis for expedient acceptance of works built by Developers
for incorporation into the Infrastructure systems controlled by the Council. The engineering process for Developments,
including subdivisions, is outlined as a flowchart included in Appendix B: Engineering Acceptance Process for
Developments). Council does not guarantee the accuracy or completeness of any document, regardless of any review
undertaken by Council and its responsible officers.
Unless otherwise agreed by Council, engineering plans and documentation should be submitted at three stages during
the design process:
The Functional Layout Plan process is aimed at improving outcomes and reducing timelines for approvals. More work
upfront will often help to ensure that time is saved in the later stages. While the Functional Layout Plans should be
consistent with any relevant Precinct Structure Plan or Outline Development Plan, the process will also ensure that both
designers and Council have confidence in proceeding to the development of detailed engineering and landscape designs
and plans.
The preparation of Functional Layout Plans is considered to be part of a best practice approach to the documentation of
subdivision developments, and is recommended even where there is no specific requirement on a planning permit.
Functional Layout Plan(s) should show all engineering elements which may influence either the dimensions of the plan of
subdivision, the functionality of civil infrastructure, the achievement of an acceptable landscaped area or the preservation
of prescribed features on the site.
For Developers, these checklists form an integral part of each submission of documentation, and provide the basis for
fast-tracking acceptances. Councils, to check authenticity, will randomly undertake audits of submitted checklists.
Consultants providing reliable checklists will be ranked accordingly and attract less auditing. Others may experience
delays in the review process due to increased rates of auditing.
Where Developer submissions are accompanied by completed checklists, Council’s Engineering Department need not
spend time checking quality or minor documentation details, and will therefore be able to review documentation in a
significantly shorter time.
Where Developer submissions are not accompanied by completed checklists, or where auditing has shown that previous
checklists have not been reliably completed, Council’s Engineering Department will have no option but to review the
submission in greater detail prior to approval. This may include a check of design details and quality of documentation
against the checklists and requests for further information.
Unless otherwise agreed by the Council, the Construction Supervision of all subdivision road and drainage works should
be undertaken by a Qualified Engineer who will hereafter be referred to as the Construction Engineer.
While it is generally preferred that the Design Engineer and the Construction Engineer be the same person, the
Developer may decide not to utilize this arrangement. All parties will be employed at the expense of the Developer.
For the purpose of this Manual, in all matters relating to the design and design review of the development roads, drainage
and landscaping works, the Design Engineer will be deemed to be the Developer’s Representative.
For the purpose of this Manual, in all matters relating to the construction and handover of the development roads, drainage
and landscaping works, the Superintendent will be deemed to be the Developer’s Representative.
The Design Engineer should plan to conduct a separate pre-design site inspection with a representative from Council’s
Engineering Department to discuss technical issues and requirements for the site and surrounds.
Unless otherwise agreed by Council, service alignments in Developments should comply with the requirements of the
"Code of Practice - Management of Infrastructure in Road Reserves” and other relevant regulations or codes established
pursuant to the Road Management Act.
In general, Council will expect the clearances between and covers for services located within easements to be the same
as those specified in the "Code of Practice - Management of Infrastructure in Road Reserves”
Engineering plan acceptance for the construction of roads and drainage will not be granted until a master services plan
has been provided showing the alignments and structures of all services and the location of all street trees. The Developer
or their representative will be responsible for providing sufficient information on the master services plan to identify potential
clashes of services, and to determine the clearance between these services where they cross. Footpath alignments and
kerb crossings should be shown on the master services plan, as should proposed landscaping features such as trees and
irrigation systems.
The Design Engineer is responsible for reviewing any planning permit conditions, determining whether any engineering
acceptance for design variation requires an amendment to the Planning Permit conditions, and arranging for an application
to be lodged with Council’s Planning Department for planning permit amendment if required.
Note
Variations accepted for some subdivisions or Developments may not be accepted for other current or future proposals.
In considering whether to approve any functional layout submissions, Council will take into account the requirements of
this Manual, relevant general engineering principles, the planning permit conditions, and all other information collated from
the site. Council will expect the Design Engineer to provide sufficient data on the proposed roads, drainage and parking
for the development to enable review and approval of the functional layout.
Road Design:
Drainage Design:
The submission should be accompanied by a brief report outlining key engineering issues and their proposed treatment,
and by a completed checklist as found in Appendix C: Council Review Checklists . Connectivity to existing
Infrastructure should be demonstrated, as should relevant social and community linkages.
Any traffic management strategy required by Council should be submitted with the request for approval of functional layout
(refer to Clause 9). The road safety audit team should be nominated to Council’s Engineering Department at this time
for their consideration (refer Clause 10).
Once the functional layout has been approved, the Design Engineer can undertake detailed design with confidence that
their proposed strategies are acceptable to Council.
In considering whether to approve detailed design documentation, Council will take into account the requirements of this
Manual, relevant general engineering principles, the planning permit conditions and all other information collated from the
site, the requirements of any relevant Precinct Structure Plan, the accepted Functional Layout Plans, service authority
requirements and other relevant factors.
Unless otherwise agreed by Council, one (1) hardcopy set and one (1) electronic set of draft plans and specifications
should be submitted to Council for comment, prior to lodging final design plans and specifications for review. The hard
copy set of plans is to be unbound and the copies of the specifications are to be bound. Completed checklists as found in
Appendix C: Council Review Checklists should accompany this submission.
Documentation should be prepared in accordance with Appendix D: Checklists and Forms for Developer’s
Representatives and include a master services plan. This plan should, so far as reasonably practicable, show the overall
layout of all existing and proposed services within the limit of works. The plan should identify potential clashes of services
and demonstrate that appropriate clearances will be achieved. Individual cables for electrical, telecommunication and
similar services are not required to be delineated, but may be shown as a single line representing the alignment of trenches.
The location of fire hydrants, fire plugs, streetlights, sub-stations, pump stations, and similar items should be shown on the
master services plan, together with major landscaping features.
Council will expect the Design Engineer to provide hydraulic calculations showing both surface and underground flows
into and out of the drainage system during major and minor storm events (refer Clause 16), and pavement design
computations, including relevant Californian Bearing Ratio (CBR) results from laboratory analysis of soil samples.
For infrastructure that will be vested in Council or is located adjacent to or abutting Council infrastructure, Council
property or reserve or Public Open Space, a Certificate of Compliance for Design and a Certificate of Compliance for
Construction is required for the following infrastructure items constructed as a part of a subdivision development:
Quality Assurance sections of the specification should, as a minimum, list witness points and hold points as nominated in
Appendix E: List of Council Inspections. The Council may choose to be represented at specific hold points that relate
to roads and drainage construction and documentation should reflect this.
Any Road Safety Audit required by Council should be submitted with the request for detailed design approval.
After review by the Council’s Engineering Department, one set of plans and specifications will be returned to the Design
Engineer, with mark-ups or comments regarding any required amendments.
The Design Engineer should, unless otherwise specified by Council, provide three (3) hardcopies and one (1) electronic
copy of the final design plans and specifications to the Council’s Engineering Department with a covering letter certifying
that the documentation complies fully with the guidelines of this Manual, except for any agreed variations. An additional
set of hardcopy plans should be provided if landscaping is to be incorporated into the development. All hard copy sets of
plans are to be unbound and all copies of the specification are to be bound.
Prior to issuing the Statement of Compliance for any subdivision, Council will expect the Design Engineer to submit an
estimate of the full cost of all road and drainage construction works, in order to establish the prescribed checking fee.
Council cannot guarantee thorough checking of all calculations and design details. The Design Engineer submitting the
documents is entirely responsible for ensuring that designs and specifications comply with the Manual requirements,
relevant Australian standards and relevant local, state and federal government legislation.
Final design approval does not relieve the Developer of responsibility for rectifying errors and omissions that become
evident during construction. Where the engineering plans and/or calculations have been subject to significant revision
following approval of the design, amended drawings should be resubmitted to Council for review. Council will expect all
revisions to be documented. This can be achieved through (where appropriate) the use of revision clouds and labelling
within the title block, provided clarity can be maintained on the drawings. Where clarity would be compromised, Council
will consider accepting separate documentation of revisions.
Approval of design drawings is current for two (2) years only from the date of that approval. If the engineering works have
not substantially commenced within the two-year period, the Council’s Engineering Department may require that revised
engineering drawings and construction specification be submitted for review.
Should the Plan of Subdivision be altered after the Final Design approval, the Design Engineer will be responsible for
resubmitting the Certified Plan (as amended) together with amended engineering drawings to Council for review.
Once final design approval has been granted, one (1) copy of stamped and signed plans and specifications will be returned
to the Design Engineer. Final design approval should be received before construction commences. Tendering of works
prior to the receipt of final design approval will be undertaken solely at the Developer’s risk.
The issue of a planning permit and approval of Final Design does not constitute consent to undertake works within existing
road reserves under the management and responsibility of Council or VicRoads.
In addition to this, all Councils operate electronic data management systems for all correspondence to and from the
organisation, including plans. Letters, forms, certificates and minor reports (generally up to 20 pages) that are received
are transferred to electronic format by its records department. However, unless otherwise agreed by Council, major reports
and all plans larger than A3 should normally be submitted in both electronic and hardcopy format.
Council’s Engineering Department should be advised of the installation dates of any authorised Major Traffic Control
Item to enable advice to be forwarded to VicRoads within 30 calendar days of enacting VicRoads delegation.
6.3 Plans
Unless otherwise agreed by Council, plans should be prepared as outlined in the following sections. Council will expect
electronic submissions of plans to be such that normal reproduction from the electronic files will deliver a hardcopy that is
an exact duplicate of an equivalent hardcopy submission.
6.3.2 Scales
For general consultation prior to planning permit issue, plans may be submitted as A1 or A3 sheets.
Development Plans should generally be submitted on A3 sheets as a minimum. Councils may require Development Plans
to be submitted on A1 sheets at scale of 1:1000.
When requesting approval of functional layout, plans should be submitted on A3 sheets with the following scales:
6.3.3 Datum
Unless otherwise agreed by Council, levels should be related to Australian Height Datum (AHD). Plans should nominate
a minimum of two (2) permanent survey marks (PSM’s) and their respective numbers/identification, and any temporary
benchmarks (TBM’s) relevant to the works. Where it is not possible to nominate two survey marks, Council may agree to
accept the use of only one survey mark.
In order to comply with the requirements of regulation 11 (3) of the Surveying (Cadastral Surveys) Regulations 2005,
subdivision plans must nominate all the permanent survey marks created, and their respective numbers/identification.
Road chainages should commence at clearly designated and identifiable locations, nominated on the plans.
Unless, otherwise agreed by Council, coordinates should be related to Geocentric Datum Australia GDA94 or the MGA94
derived from it.
Councils will provide plan numbers for any plans prepared for them if this is required. Plan numbers are not required for
subdivision and Developments.
6.4 Specifications
Project specifications should ensure that all works are undertaken to meet Council requirements, and that there will be
no outstanding liabilities when the projects are handed over at completion.
Council will expect specifications for contracted works to include a quality section nominating minimum hold points and
witness points, including as a minimum, those inspections nominated in Appendix E: List of Council Inspections.
Unless otherwise agreed by Council, the specifications for assets should ensure that the design life as listed below can
be achieved with industry standard maintenance:
The Design Engineer is responsible for ensuring that the standard drawing used is correct for the application and should
consult with Council’s Engineering Department where necessary.
• the works are constructed so that they fulfil the purpose for which they were intended;
• long-term maintenance requirements are considered;
• there is no detrimental effect on other existing assets in the locality;
• the works are safe, both during and after construction; and
• environmental impacts are minimised, both during and after construction.
Council will expect the Construction Engineer to notify Council’s Engineering Department at least five working days
before construction is scheduled to commence by submitting the following documents:
The Intention to Commence Construction form may be found in Appendix D Design Engineer’s Intention to Commence
#D4
Council will expect the “Record of Pre-start Meeting” to be signed all relevant parties, prior to the commencement of
works, for all Developments involving the construction of Infrastructure to be vested in Council.
The Council Engineer or an officer nominated by the Council Engineer will inspect the works at critical milestones and
may do so at witness points to ensure that the works are constructed in accordance with Council requirements and the
approved plan. Council will expect the Construction Engineer to contact the Council’s Engineering Department to
arrange for joint inspections at each hold point relating to road and drainage construction to advise of witness points as
detailed in Appendix E: List of Council Inspections, and to be present at all joint inspections.
Council will expect the Construction Engineer to give at least 48 hours’ notice when requesting the Council Engineer
or an officer nominated by the Council Engineer to attend a construction inspection at a hold point or witness point, unless
otherwise provided within this Manual.
While as much guidance and assistance as possible will be provided on site to assist the Construction Engineer, Council
cannot give a Contractor a direct instruction regarding the works.
The Construction Engineer is responsible for arranging for a joint inspection of the works to be made, together with the
Council Engineer or an officer nominated by the Council Engineer, and the Contractor. The Developer should be
invited to attend. The purpose of the inspection will be to identify any outstanding items or minor defects for recording, and
to determine whether the works have been completed to the Council’s satisfaction so that they may be accepted into
Council’s asset systems. Council will expect the Construction Engineer to notify them at least one week prior to any
Acceptance of Works inspection, providing detailed operation and maintenance manuals for Infrastructure such as
pump stations, retardation basins and wetlands so that any questions can be resolved in the course of the inspection.
Training of Council staff responsible for operations and maintenance may be required for specific Infrastructure. Such
training will be undertaken, at the cost of the Developer, during or prior to the Acceptance of Works inspection.
The Construction Engineer should ensure that all works have been completed in accordance with the approved plans,
prior to calling for the joint inspection (refer to Appendix C: Council Review Checklists ). The whole site should be
presented in a tidy manner, including all required reinstatement of existing surfaces, erection of all signs and street lighting.
Pump stations may be commissioned during the inspection. Streets should be swept prior to the final inspection.
Subsequent to the Acceptance of Works inspection the Developer’s Representative is responsible for forwarding to the
Council:
• Certification that the works have been completed in accordance with the documents previously reviewed and
approved by Council (Checklist found in Appendix C: Council Review Checklists ).
• ‘As Constructed’ drawings in hardcopy format, in electronic format compatible with Council’s Asset Management
system, and in AutoCAD format.
• Operation and Maintenance (O&M) Manuals for all relevant Infrastructure.
Council’s Engineering Department will forward a copy of the Letter of Acceptance to the Planning Department.
Satisfactory site inspection and issue of a Letter of Acceptance is not to be taken as engineering consent for a Statement
of Compliance to be issued for the development. It is only one step in the Statement of Compliance process, as there may
be other engineering conditions on the planning permit to be addressed.
For works constructed by Council’s internal works departments, the “As Constructed” Plans should be prepared in
accordance with the requirements of the Assets Department and signed off by the Construction Engineer.
Selection Table 7.6(a) shows those Councils which require “As Constructed” plans to be provided in ASpec Format. This
format covers roads (R Spec), drainage (D Spec), buildings (B Spec), open space (O Spec)
The Councils listed in Selection Table 7.6(b) require “As Constructed plans” to be provided in AutoCAD electronic format
to GDA 94 spatial coordinates for translation into the Council’s GIS.
Where required the signed Defects Liability Agreement should be lodged with, or prior to, the request for Statement of
Compliance (refer to Clause 8.3).
When satisfied that all engineering conditions on the planning permit have been complied with, Council’s Engineering
Department will advise Council’s Planning Department that it has no objection to the issue of Statement of Compliance.
Council’s Planning Department will, where appropriate, seek confirmation from VicRoads and other referral authorities
that there are no objections to the issue of a Statement of Compliance.
Prior to consenting to the Statement of Compliance, Council’s Engineering Department will require that the following
actions be completed:
• All engineering and landscape works have reached Practical Completion, or Council has accepted a bond for the
uncompleted works.
• Construction supervision fees in accordance with Clause 5 of the Subdivision (Permit and Certification Fees)
Regulations 2000 (currently to the value of 2.5% of the total estimated cost of constructing the works which are
subject to supervision) have been paid.
People who represent a company responsible for any excavation work also have a duty of care to locate underground
services or assets that are in the vicinity of the dig site, and then find and expose them before excavating near or around
them.
The preferred method of obtaining information about the location of underground assets is the Dial Before You Dig service.
Not all services are covered by the Dial Before You Dig service. In particular, the underground drainage services owned
by some Councils and assets belonging to some service authorities may not be covered. In such instances, the
Council and service authorities concerned should be contacted for information as to the location of their underground
assets.
• It is often the only method used by people intending to carry out excavation works when searching for information
about the location of underground pipes and cables at a proposed dig site.
• It is referred to in publications from WorkSafe Victoria and Energy Safe Victoria as best practice.
• The service aims to provide all excavators with the best possible access to plans and information direct from asset
owners of underground services using a national enquiry service.
• Its overall purpose is to educate and promote the importance of safe digging practices to the excavation community
and to develop its membership base to include all asset owners of underground services.
• A request for information can be made by logging on at the web site (www.1100.com.au) or by phoning 1100.
Customer details and the proposed area of the dig site will be sent to all asset owners registered with Dial before
The Dial Before You Dig Service Guidelines for Victoria outline the responsibilities of all underground asset owners to
register assets and provide information when requested, and also the responsibilities of people intending to undertake
excavation work to obtain information about underground assets in the area and to follow safe work practices. These
guidelines can be obtained from:
(http://www.1100.com.au/Aboutus/ServiceGuidelinesforVictoria.aspx)
The Councils listed in Selection Table 7.9.1 will expect the Developer to arrange for CCTV verification of all underground
drainage assets to be handed over to them, and to supply the results of that verification to Council at the time specified
in that Selection Table and in the format specified in Appendix H.
Selection Table 7.9.1 Councils Requiring CCTV Verification of Underground Drainage Assets
Council will expect the cost of CCTV verification to be borne by the Developer.
Council will expect CCTV inspectors to have obtained at least a Statement of Attainment in NWP331A Perform conduit
condition evaluation based on WSA05, together with recognised qualifications in:
• occupational health and safety; and
• traffic control; and
• confined space entry.
Council will expect the camera and scanner to meet the requirements of WSA05, and defects found during the verification
to be scored in accordance with Appendix D of WSA05: Storing of Defects and the Preliminary Grading of Apparent
Condition of Stormwater Drains. Confirmation that the specified pipe material, size and class has been used, and that all
components have been correctly aligned and connected, is an essential part of the acceptance of works based on CCTV
inspections.
Problems that have been identified in the past include pipes cracked due to excessive compaction loadings during the
laying process, damaged pipe ends due to poor handling, poorly jointed segments with inordinate gaps and/or misplaced
rubber rings and damage at the lifting holes or unplugged lifting holes. Inspections of new or recently installed work should
look for any evidence of such defects and ensure that, even when not attracting a formal defect score, they are noted and
brought to the attention of Council’s Engineering Department.
Council will normally accept transfer only of sections with a structural grading of 1 and a service grading of 1, and defective
sections will require replacement or repair by techniques acceptable to Councils Engineering Department. Acceptable
repair techniques may include patching, lining, sleeving or bonding using a range of proprietary systems.
Acceptance Criteria
A table of typical structural defects in rigid and flexible pipes appears in Appendix H.
8.2 General
A Defects Liability Period will apply to all Council Infrastructure constructed by Developers, and will cover any fault,
deficiency or inadequacy of the works from defective design, workmanship or materials.
During the Defects Liability Period the Council will carry out operational maintenance in accordance with its normal
practice, unless specified otherwise. The Developer will be held responsible for all maintenance costs arising from design
error, defective workmanship and/or defective materials.
Unless specified otherwise on the planning permit, the Defects Liability Period for all assets, other than landscaping assets,
to be vested in Council will be 12 months. Landscaping and WSUD assets will have a Defect Liability Period of 24 months.
If more than 8 weeks have elapsed between the Acceptance of Works inspection and the issue of Statement of
Compliance, Council may request that a formal handover meeting be held prior to commencement of the Defects Liability
Period to review and amend any outstanding minor defects and deal with site-specific issues.
Prior to the issue of a Statement of Compliance, Council may require the Developer to enter into an agreement with them
regarding their respective responsibilities for the maintenance and correction of defects arising from faulty workmanship
or materials during this period.
Council will expect the guarantee to be for a minimum of 5% of the total cost of roads, drainage and hard landscaping,
with the calculated amount being based on the priced Bill of Quantities, and to be lodged with the Council for the term of
the Defects Liability Period. If differing periods are nominated for different Infrastructure, the Developer may choose to
lodge individual bank guarantees, or a single bank guarantee for the whole amount in question.
The guarantee for soft landscaping should be a percentage of the replacement cost, as agreed by the parties.
The guarantee will be released at the termination of the Defects Liability Period, subject to the satisfactory completion of
defect rectification works required by Council’s Engineering Department.
In the event that damage to infrastructure occurs during the defects period, and the Contractor can prove, to the
satisfaction of Council, that this is not the result of defective workmanship, Council will be responsible for the carrying
out the repairs at its cost and for recovering the cost from those who caused the damage.
Where consent is given to lodge a bond for outstanding works, Council will normally expect separate security bonds to be
lodged for civil and landscaping works.
Council will expect the bond to be for $5,000 excluding GST, or 1.5 times the estimated cost of completing the works,
whichever is the greater, and to take the form of cash or a bank guarantee with no expiry date.
If bonded works are not completed within 12 months, unless otherwise agreed in writing, the Council may arrange for the
works to be carried out and meet all costs, including those of supervising and administering the works, from the bond.
However, in the case of bonds for uncompleted landscape works, Council will consider whether:
• it would otherwise be unreasonable to withhold consent to statement of compliance;
• opportunities for growth and development during appropriate planting seasons would be improved;
• deferment of the landscape works would assist in the staging of future development, and/or reduce wear and tear or
damage to the landscape works caused by subsequent works, such as housing construction.
Where Council agrees to accept a bond for uncompleted landscape works, the bond should be lodged following the
approval of landscape plans and detailed documentation and before statement of compliance and will be returned to the
developer following the completion of all required landscape works to the satisfaction of Council.
During the Defects Liability Period the Developer no longer has possession of site, and will be required to obtain a permit
from the relevant authority giving Consent to Work within a Road Reserve before undertaking any remedial work in the
road reserve.
9.2 General
As explained in Clause 3 of this Manual, where new roads are to be provided, and/or existing roads are to be upgraded,
in the course of a Development, Council may require that a Traffic Management Strategy be prepared to identify and
address the impact of the development on the existing road network, and to establish the key features of the internal road
network. The Traffic Management Strategy will normally recommend:
• appropriate mitigating works to address impacts on the existing road network; and/or
• the appropriate internal road layout, road widths, functions and connectivity for all road users.
Council will expect the Developer to engage a Qualified Engineer to prepare a Traffic Management Strategy and may
request additional information concerning the experience of the proposed appointee prior to approving the relevant
document.
While some commercial and industrial Developments may not create new roads or intersections, they may generate
sufficient changes in traffic volumes and movements to cause Council to require the preparation of a TMS, as defined
above.
Where a TMS is required to be prepared as a condition of the Planning Permit, the submitted plans will not be approved
until the recommendations have been accepted in principle by the Council’s Engineering Department.
The provisions of this section apply equally to Developments carried out by Council.
Where both VicRoads and the Council require a TMS, one report may be prepared meeting the requirements of both
organisations.
Developments that contain more than 200 lots in a Development Plan may be required to establish bicycle routes through
the development PRINCIPLE. Development proposals should complement and enhance the principles of any Council Bike
Strategy Plans.
Council will expect provision to be made so that no emergency service vehicles, waste and recycling collection vehicles
or street-sweepers are required to reverse within the development PRINCIPLE. Staging of works does not negate this
requirement and temporary turning areas may need to be established between development stages, with carriageway
easements as necessary.
Issues to be addressed in the TMS include, but need not be limited to, the following:
• estimated traffic volumes;
• proposed road closures;
• impact of staged development;
• pedestrian and cyclist movements;
• entry to and egress from the development;
• road layout, function and connectivity;
• bus routes, bus stops, and bus bays;
• access for emergency and service vehicles;
• off-street and on-street parking;
• major traffic control items; and
Parking within a Development should normally be shown on a separate plan submitted in conjunction with a request by
the Developer for approval of functional layout. Where Developments create new roads (e.g. subdivisions) Council will
expect a parking plan to be submitted clearly demonstrating that at least one practical space has been provided per two
allotments, with these provisions being achieved outside of any court bowls.
For larger industrial, commercial and retail Developments, Council will expect the traffic management strategy to consider
traffic and pedestrian conflict points, location of loading zones and movement of forklifts and other vehicles for loading and
unloading, ingress and egress from the site, provision of disabled parking, and parking requirements overall.
Council will expect TMS to include clear recommendations. The Developer will be responsible for identifying any
recommendations that are not proposed to be implemented and for providing cogent reasons for the omission. Where
Council accepts those reasons, they may choose to consider the recommendations in the context of their own Capital
Works Program. Council will also expect a TMS to address Planning Scheme objectives and standards as outlined in
Section 56.03 of the Planning Scheme.
The Design Engineer will be responsible for ensuring that, where major Traffic Control Items are proposed to be used,
those items are submitted to and approved by Council or VicRoads in a timely manner so that they do not impact on the
works program.
10.2 General
Road safety should be considered at all stages of road design, upgrade or construction. Conducting road safety audits at
the design stage, before construction commences, will normally help to achieve the most cost-effective outcomes.
The provisions of this section also apply to Development carried out by Council.
10.3 Requirements
Council will expect Road Safety Audits to be conducted in accordance with the Austroads Guide to Road Safety Part 6:
Road Safety Audit and any VicRoads supplement to those guidelines for all development designs that require a Traffic
Management Strategy (refer to Clause 9). The guidelines specify that audits should be carried out at the detailed design
stage and after construction has been completed.
The Design Engineer will be responsible for selecting an audit team including two or more experienced or qualified people,
at least one of whom should be a Senior Road Safety Auditor accredited by VicRoads. The person responsible for
designing the roads in question should not be a member of the team. The Design Engineer will be responsible for
determining that the Senior Road Safety Auditor has suitable experience for the type for works proposed, or that such
experience is available elsewhere within the audit team. Council will expect the Design Engineer to advise them of the
audit team membership when requesting approval of functional layout.
The Design Engineer will be responsible for proposing actions to be taken in response to the recommendations of the
audit report, but consultation with Council is encouraged if the recommendations are complicated or require community
involvement. Council will expect to receive a copy of the road safety audit report, with documented responses to the
recommendations, when the detailed design documentation is submitted for approval. The report of the audit conducted
after construction has been completed should be submitted to and accepted by Council prior to the issue of a Statement
of Compliance, where relevant, or to the commencement of use.
11.2 General
As explained in Clause 3 of this Manual, Council will normally expect a comprehensive SMS to and assess:
• stormwater impacts on the surrounding properties, floodways, flood plains, flood storage and Council
infrastructure; and
• appropriate measures for the collection, conveyance and treatment of stormwater originating from and passing
through the development.
Unless otherwise agreed, Council will expect the subsequent stormwater management framework and drainage
infrastructure design to be consistent with the recommendations of any approved SMS.
The provisions of this section apply equally to Developments carried out by Council
12.2 General
This section sets out the standard design criteria for road works. The provisions are not intended to prohibit any
alternative arrangements or approaches. Innovative or non-standard designs may be considered, but not necessarily
accepted. Council will expect the Design Engineer to submit sufficient data and calculations based on accepted
engineering principles to allow Council’s Engineering Department to assess the merits of any proposed innovative or
non-standard design.
Aspects not specifically referred to in this Manual should be generally in accordance with the following documents:
• The road cross sections included in any applicable Precinct Structure Plan
• Austroads: Guide to Road Design, incorporating AGRD01 to AGRD07 and all sub-sections.
• The Standard Drawings associated with this Manual.
Council will expect all plans to be prepared in accordance with Appendix D: Checklists and Forms for Developer’s
Representatives.
Council will expect all the required physical works to be completed as part of the Development, in accordance with
Council standards. Where the Developer is unable to provide the physical roads and accesses, Council may consider
accepting a contribution that is equivalent to the total actual cost of preparing plans and specifications and constructing
the required Infrastructure.
The road and drainage requirements for developments in Low Density Residential Zones will vary according to the
characteristic lot size. Developments in which most lots already have, or could soon be expected to gain, access to a piped
sewerage network, and minimum lot areas could be reduced to 2000m2, are considered to be urban in character, and
Council will expect the infrastructure provisions of Clause 12.3 to be satisfied. For the purposes of Clause 12.3 and Clause
12.9, these developments are designated by the abbreviation LDRZ-U.
Developments in which minimum lot areas will be at least 4000m 2, either because subdivision will be limited by planning
mechanisms, or because access to a piped sewerage network is unlikely to become available in the foreseeable future,
are considered to be rural in character, and Council will expect the infrastructure provisions of Clause 12.4 to be satisfied.
For the purposes of Clause 12.4 and Clause 12.9, these developments are designated by the abbreviation LDRZ-R.
In response to the Road Management Act, Councils may have established an alternative road hierarchy to determine
routine maintenance requirements, as well as establishing the overall management of its road network. The road
classification referred to within this Manual relate specifically to the design and construction of new or upgraded roads.
Access Lanes as defined in The Planning Scheme are not considered desirable by the Councils listed in Selection
Table 12.3.1 and should not be provided within Developments unless specific agreement is obtained from Council’s
Engineering Department PRINCIPLE.
Roads of width and function similar to Access Lanes may be approved as private roads or common property. However,
Council may require specific treatment such as fencing, paving and drainage. It is recommended that this issue be
addressed as early as possible in the planning process.
Ultimate traffic volumes for road classification and road design should be based upon accepted multipliers of existing traffic
movements (measured), through traffic, and an estimate of traffic generated by proposed and future development. The
estimated traffic volumes for undeveloped areas should normally be based upon the following factors:
• Commercial/Industrial To be determined on a case by case basis utilising the RTA NSW Guide to Traffic
Generating Developments 2002
Where other traffic generation assumptions are to be adopted in preparing a Traffic Impact Study, Council will expect the
Design Engineer to submit details of the proposed assumptions to Council’s Engineering Department for acceptance
prior to commencing work on the study.
Where Council holds traffic count data on relevant roads, this information will normally be made available to the Design
Engineer on request. In some instances, the Design Engineer may be asked to undertake additional traffic count data
collection on affected roads to ascertain predevelopment traffic volumes and types. This will generally only occur when
traffic count data is more than three years old, or when significant development has taken place since traffic count data
was last collected. Where traffic volumes and type vary seasonally, Council will expect the Design Engineer to use the
available data conservatively and to identify any assumptions when lodging a request for approval of functional layout.
12.3.2 Road / Street Characteristics and Road Reserve Widths for Developers
The classification, function and general composition of roads and streets in urban and LDRZ(U) developments are detailed
in Table 2. Council will expect all these roads and streets to be constructed with a sealed pavement and provided with
kerb and channel unless an alternative treatment is integral to a WSUD treatment solution, and Council has given prior
agreement in writing for the use of that particular solution.
VERSION 5.30 Page 62 of 275
Road or street outcomes should be consistent with any Precinct Structure Plan applying to the land. Where a Precinct
Structure Plan does not apply to the land, new subdivisions and developments should:
• Reflect or reference streetscape treatments in existing township areas that make a proactive contribution to the
township character.
• Provide a diversity of streetscape outcomes. Approximately 30% of local streets (including connector streets) within
a subdivision should apply an alternative treatment to the remainder of this type of street within the
subdivision. Changes to street tree species between or within streets do not constitute a variation. Examples of
acceptable variations may include but are not limited to:
o varied street tree placement; and/or
o varied footpath of carriageway placement; and/or
o introduction of elements to achieve a boulevard effect; and/or
o varied carriageway or parking bay pavement; and/or
o differing tree outstand treatments.
• Maintain the road cross-sections outlined in Table 2 so that:
o the carriageway dimensions are sufficient to ensure:
▪ safe and efficient operation of emergency vehicles on all streets; and
▪ safe and efficient operation of buses on connector streets; and
o relevant minimum road reserve widths for each type of street are maintained; and
o specified performance characteristics for pedestrian and cycle use are maintained.
• Achieve regular street tree planting and interlinking street tree canopy cover (when trees reach maturity) wherever
possible.
Council will expect all road reserve widths to be sufficient to accommodate the Carriageway, the required services with
all necessary clearances, pedestrian and bicycle access, parking, landscaping, drainage and bus routes. Should the
development design incorporate certain WSUD devices, increased road reserve widths may be required.
The minimum road reserve widths in residential and low density residential Developments are detailed in Table 2
PRINCIPLE
Lesser width industrial road reserves may be permitted for short industrial cul-de-sacs, provided that turning at
the court bowl will not be compromised.
Footpath, bus, bicycle and pedestrian provisions are detailed elsewhere in the Manual. Council will not accept the use of
minimum road reserve widths where that would compromise the standard of provision for these road users.
Road reserve boundaries may be curved around court bowls, but where they are to be fenced as chords, these should not
be less than 10 metres in length. Where a number of such chords occur adjacent to each other, they should, as far as
possible, be practically equal in length.
Council will expect the road or street outcomes to be consistent with any applicable Precinct Structure Plan.
Note 1
Higher traffic volumes and other intended use/s of carriageway may require greater Carriageway widths.
Note 2
Council will expect the Design Engineer to demonstrate that verge widths are sufficient to accommodate all services
required to be located there.
Note 3
Note 4
Note 5
The minimum width of the road reserve cannot be calculated by adding the minimum distances of the components within
the road reserve.
Note 6
Council will expect the Design Engineer to ensure that the road reserve width adopted complies with the requirements
of the following documents and requirements:
• Department of Transport - Public Transport Guidelines.
• Any applicable pedestrian and bicycle strategies.
• CFA requirements (the minimum Carriageway width to be 7.3m unless parking is restricted to one side).
• Where service vehicles use access lanes the minimum carriageway width will be 6m.
Where a Council has a bicycle strategy/policy/plan that requires on-road bicycle lanes then the Council may agree to
reduce the number of shared paths required from two to one, to reflect the provision of those lanes. In such cases, the
minimum pavement width for each relevant carriageway will be increased by 1.0m.
Note 8
No separate provision for cycle traffic is required in Access Places and Access Streets. In LDRZ(U) developments, Council
will expect a footpath or a shared path to be provided on at least one side of each category of street to which this note
applies save in exceptional circumstances.
Note 9
Where Council has agreed that a Residential Collector Road can be exempted from kerb-and-channel installation in order
to accommodate specific WSUD devices, the minimum sealed carriageway width will be as defined in Selection Table
12.4.2(a).
Note 10
The above standards will apply unless otherwise agreed in writing or otherwise specified in the planning permit conditions.
Note 11
The road reserve width for frontage streets may be reduced where it can be demonstrated that services can be
accommodated within the frontage road reserve or the abutting road or other reserve
Other Notes
Cross sections of the various street types shown in Table 2 appear in Standard Drawings numbered SD600-620.
The width of the Carriageway is defined as the distance between the inverts of kerbs for roads with kerb and channel.
The width of the roadside is defined as the area between the invert of kerb or edge of formation where there is no kerb
and the near road reserve boundary.
Table 2 does NOT apply to roads within the Gannawarra Shire Council or City of Ballarat boundaries. Classifications and
construction of new roads in these municipalities are to be in accordance with Council’s Roads Management Plan and
Road Asset Management Plan.
Where pedestrian and/or bicycle access reserves are incorporated into Developments the minimum reserve width is 10m.
The width may need to be increased for reserves deeper than one average allotment (see Clause 24).
Council will expect a vehicle crossing layback and full concrete crossing to title boundary to be provided to all pedestrian
and bicycle reserves, and removable bollards to be provided within the reserve, offset by 1m from each adjacent road
reserve, in sufficient numbers and spacing to prevent vehicular access. Where mountable kerb and channel is used, the
layback may be omitted, but Council will expect a sealed crossing to be constructed from the back of kerb to the title
boundary.
Reserves that are required specifically for provision of services other than those for which Council is responsible must be
vested with the relevant authority.
Council will expect all roads for which they are responsible to provide sufficient space for emergency service vehicles,
waste collection vehicles and street-cleaning vehicles to carry out their functions while travelling in a forward-only
direction throughout the Development. Unless otherwise agreed by Council, cul-de-sacs should be of bowl geometry,
and ‘T’ or ‘Y’ cul-de-sac heads are not permittedPRINCIPLE.
Staging of works does not negate this requirement and temporary turning areas may need to be established between
development stages including Carriageway easements as required. Where temporary turning areas are to be provided
on private land, and not in the road reserve, a Section 173 agreement may need to be provided upon the subject land to
provide turning area until such time as the road is extended and/or a permanent turning area is established.
Parking, bicycle and bus requirements may impact upon the minimum carriageway widths, and Council will expect to see
evidence prior to the approval of functional layout that the proposed carriageway widths are adequate to accommodate
these functions.
• General road design – Austroads Guide to Road Design Part 3: Geometric Design
• Intersections – Austroads Guide to Road Design Part 4A: Signalised and Unsignalised Intersections
• Roundabouts – Austroads Guide to Road Design Part 4B: Roundabouts
Council will expect the Design Engineer to ensure that landscaping plans, and any plans for estate entrance structures,
are prepared with due consideration for sightline requirements, and that plans submitted for approval show all existing and
proposed features in sufficient detail to demonstrate that appropriate sight distances have been achieved.
Road design grading should be extended a minimum of 100 metres beyond the end of the street where such street is to
be extended in the future. Where new roads meet existing roads, Council will expect the Design Engineer to check the
grading for a distance of 50 metres and to demonstrate that roads match well and that no abrupt change in grade occurs.
In extremely flat locations, a grade of 0.25% (1 in 400) may be considered for a limited length.
The kerb and channel grades on curves should be calculated along the outer kerb for minimum grade and along the inner
kerb when grades approach maximum limits.
At intersections, each kerb should be graded individually around the return and designed to match the kerb grade of the
adjoining street and to follow as closely as possible the vertical curve produced on the pavement by designing to match
the through street.
The desirable minimum grade for kerb returns is 0.75% and the absolute minimum is 0.25%.
In intersection design, the 600mm clearance for above ground structures is intended to be applied to the total swept path
of the design vehicle, and not just to the wheel path. Vehicle accesses and driveways are NOT to be used for turning
movementsPRINCIPLE. All roadways, rights-of-way and vehicle crossings should be designed to accommodate a standard
vehicle (car).
Council will expect the Design Engineer to supply the turning movement plans nominated in Table 5 when seeking
approval of functional layout from Council’s Engineering Department.
VERSION 5.30 Page 69 of 275
Table 5 Turning Movement Plans
When new kerb and channel or footpath is to be constructed adjacent to existing roadways and/or excessive cross-falls
may occur on either the road pavement or nature strip, Council will expect the Design Engineer to check all vehicle
crossings to allotments using standard car templates to ensure that car access can be provided.
Batter slopes should reflect the predominant use of the locality and, within the Clear Zone, should preferably be less than
1:6 and should not exceed 1:4. In residential areas, driveway slopes should not exceed 1:10.
Whenever it is impractical to provide batters flatter than the maximum slopes specified, Council will expect the Design
Engineer to provide special infrastructure such as retaining walls within the property and, in areas prone to erosion, to
give careful consideration to erosion control measures.
So far as reasonably practicable, road designs should avoid filling on the low side street alignment.
Council will expect the Design Engineer to demonstrate that the kerb and channel design secures adequate and safe
access to each allotment for vehicles, bicycles and pedestrians, and meets drainage needs. Unless otherwise required to
maintain township character, kerb and channel variants should be constructed in accordance with Council’s Standard
Drawings as found in Appendix F: Standard Drawings.
Unless otherwise agreed in writing, the Councils listed in Selection Table 12.3.10, require subsoil drainage to be
provided below all kerb and channel laid, unless the subgrade is rock or sand, or no drainage network is available to
which subsoil drainage could be connected.
Where non-standard kerb profiles are to be matched, the Design Engineer should consult with Council’s Engineering
Department to determine the most appropriate kerb to be used.
Where it is considered impractical to have the Developer construct an isolated section of kerb and channel, Council may
accept a contribution-in-lieu, based on a cost estimate prepared by the Council’s Engineering Department.
Kerb crossings should be constructed at appropriate locations and, unless otherwise agreed by Council, should comply
with Council’s Standard Drawings as found in Appendix F: Standard Drawings.
Kerb crossings near intersections should be located far enough from the intersection to allow each ramp to be fully
constructed to height of back of kerb, as per the standard drawings.
Control joints should be constructed as per Council’s Standard Drawings, refer Appendix F: Standard Drawings.
12.4.1 General
The design and construction of roads and allotment accesses should meet or exceed the requirements of the Austroads
Guide to Road Design, this Manual and any relevant Acts, Regulations and Australian Standards.
Council will expect all new and upgraded roads in Rural Living and relevant Low-Density Residential Developments to
be to full road construction standards. Any contribution by Council toward the cost of such road construction will be in
accordance with the policies of the Council concerned.
Traffic generated as a result of any relevant Development should be encouraged to use the route identified for access in
the submitted documents. Council may require that all off-site intersections be constructed or upgraded and that additional
signage be provided.
Before any works are undertaken in an existing road reserve, a permit must be obtained from Council granting Consent to
Work within a Road Reserve.
Council will expect the minimum road reserve width in Rural Living and relevant Low-Density Residential Developments
to be 20 metres. However, additional reserve width is encouraged to facilitate landscaping and pedestrian/bicycle facilities.
Splays at intersections should normally be in accordance with Clause 12.5.5 of this Manual.
Road Type Indicative Maximum Minimum Reserve Minimum Seal Minimum Kerbing (see also
Traffic Volume Width Width Shoulder Width Clause 12.4.9)
(vehicles/day)
Rural Living 1000 20.0m 6.2m 1.5m nil
Access Road
Rural Living 6000 25.0m 6.2m 1.5m nil
Collector Road 7.0m for Councils
listed below in
Selection Table
12.4.2(a).
Rural Living or n/a 32.0m 9.5m 1 1.5m 1 n/a 1
Low Density 10.5m 2 0.0 2 SM2 2
Residential
Court Bowls
Low Density 1000. 20.0m 6.2m 1.5m n/a
Residential
Access Road
6.2m and 7m Councils (see Selection Table 12.4.2(a) below)
Low Density
Residential 6000 20.0m See Selection 1.5m n/a
Collector Road Table 12.4.2(b)
below
Cross sections for the above road types can be viewed in Standard Drawings numbered SD600 to 620.
Note 1
These seal widths apply within the boundaries of all Councils, other than those specified in Note 2, where waste collection
vehicles are allowed to travel on the unsealed shoulders of the court bowl, on the condition that the shoulders are
constructed with full depth pavement.
Note 2
These seal widths and kerbs where court bowls include kerbing apply within the boundaries of Councils listed below:
Table 6 does NOT apply to roads within the Ararat Rural City Council, Gannawarra Shire Council and Latrobe City Council
boundaries. Classifications and construction of new roads are to be in accordance with Council’s Roads Management
Plan and Road Asset Management Plan.
Council will expect road widths to be in accordance with Clause 12.4.7, and road geometry in Rural Living and relevant
Low-Density Residential Developments to provide sufficient space for emergency service vehicles and waste collection
vehicles to carry out their functions while travelling in a forwards-only direction throughout the development. Significant
Developments may require provision for school buses, and Council will expect all relevant roads to be so designed that
these vehicles do not need to reverse.
Staging of works does not negate the requirement for forward-only travel, and temporary turning areas may need to be
established between development stages, including Carriageway easements as required. This may therefore require that
temporary table drains be constructed around these turning areas.
Road design grading should be extended for a minimum of 100 metres beyond the end of any street which is to be extended
in the future. Where new roads meet existing roads, Council will expect the Design Engineer to check the grading for a
distance of 100 metres, and ensure that roads match well and that no abrupt change in grade occurs.
Landscaping plans should be prepared with consideration to sight distance requirements, as should any proposal for estate
entrance structures. Council will expect plans submitted for approval to show all existing and proposed features in
sufficient detail to demonstrate that the appropriate sight distances are achieved.
Council will expect the Design Engineer not to terminate the cross-section design at the property boundaries but to
extend the design sufficiently to determine cut and fill requirements, and show these on plans.
The normal cross-fall on sealed pavements should be 3%. Where design speeds require super-elevation of horizontal
curves, cross-fall design should be based on the Austroads Guide to Road Design Part 3: Geometric Design and any
VicRoads supplement to those guidelines.
Where the Design Engineer proposes to use cross-falls of greater than 6% at intersections or horizontal curves, specific
prior agreement should be sought from Council’s Engineering Department.
Batter slopes should be appropriate for the predominant use of the locality and be designed with consideration to Clear
Zones as defined in the Austroads Guide to Road Safety Part 6: Roadside Design, Safety Barriers and any VicRoads
supplement to those guidelines. In areas within the Clear Zone batter slopes should preferably be no more than 1:6, and
the absolute maximum should be 1:4. Residential driveway slopes should not exceed 1:10.
Council will expect that, where batters cannot reasonably be restricted to the maximum specified slopes, the Design
Engineer will provide special treatments such as retaining walls within the property and, in areas prone to erosion, give
particular consideration to appropriate control measures.
Council will expect the Design Engineer to ensure that any intersections with State rural or urban roads or National
Highways are designed and constructed in accordance with VicRoads requirements.
The road network within a Development should be designed so that at least 90% of dwellings are within 400m safe walking
distance from an existing or proposed bus or tram route and from existing or proposed Public Open Space facilities.
Council will expect the Design Engineer to submit pedestrian path mapping to support the proposed layout.
Tee-junctions should be adopted in preference to four-way intersections. Where four-way intersections, or other cross
intersections, are to be constructed, the road centrelines should intersect at an angle between 70 and 110 degrees, and
Council will expect the Design Engineer to specify appropriate traffic control treatment.
Council will expect the Design Engineer to design any roundabouts proposed to be used at intersections in accordance
with the Austroads Guide to Road Design Part 4B: Roundabouts and any VicRoads supplement to those guidelines. All
roundabouts are Major Traffic Control Items requiring VicRoads authorisation. On municipal roads, VicRoads has
delegated authority for such approval to Councils under various conditions, including timely reporting back to VicRoads.
Intersection spacing on, and access to, declared arterial roads requires VicRoads authorisation. Access to these roads
will be in accordance with VicRoads requirements, having regard to the Austroads Guide to Traffic Management Part 5A,
Austroads Guide to Road Design Part 4A and the Victorian Planning Provisions. Developers are encouraged to discuss
access to arterial roads with VicRoads prior to making a planning application for any relevant Development.
12.5.5 Splays
Splays of suitable dimensions should be provided at all corners of all intersections.
At intersections involving at least one collector road the minimum splay on the intersecting roads is 5m x 5m. At intersecting
roads of lesser classification, the minimum splay is 3m x 3m. Larger splays may be required to secure traffic safety and/or
to accommodate the provision of services.
Council will expect the Design Engineer to demonstrate that all splays can accommodate the turning movement
requirements as detailed in Clause 12.3.8.
Some traffic calming devices, such as road humps, are Major Traffic Control Items requiring special authorisation. The
Design Engineer will be responsible for securing any necessary approvals and should refer to Part 2.2 of the VicRoads
Traffic Engineering Manual Volume 3.
Council will expect the Design Engineer to seek specific prior agreement for the installation or construction of traffic
calming devices, and to address the following issues in the relevant submission:
• Streetscape
o Reduce the linearity of the street by segmentation.
o Avoid continuous long straight lines (e.g. kerb lines).
o Enhance existing landscape character.
o Maximise continuity between existing and new landscape areas.
• Location of Devices/Changes
o Devices other than at intersections should be located to be consistent with streetscape requirements.
o Existing street lighting, drainage pits, driveways, and services may decide the exact location of devices.
o Slowing devices are optimally located at spacings of 100-150m PRINCIPLE.
• Design Vehicles
o Emergency vehicles must be able to reach all residences and properties.
o Where local streets link arterial roads and minor local streets, consideration should be given to designing
those streets for an Austroads Design Single Unit Truck/Bus.
o Where bus routes are involved, buses should be able to pass without mounting kerbs and with minimum
discomfort to passengers.
• In newly developing areas where street systems are being developed in line with LATM principles, provision should
be made for building construction traffic.
• Control of Vehicle Speeds
o Maximum vehicle speeds can only be reduced by deviation of the travelled path. Pavement narrowing has
only minor effects on average speeds, and usually little or no effect on maximum speeds.
o Speed reduction can be achieved using devices that shift vehicle paths laterally (slow points, roundabouts,
corners) or vertically (humps, platform intersections, platforms pedestrian/school/bicycle crossings).
o Speed reduction can be helped by creating a visual environment conducive to lower speeds. This can be
achieved by segmenting streets into relatively short lengths (less than 300m) using appropriate devices,
streetscapes, or street alignment to create short sight lines.
• Visibility Requirements (sight distance)
o Adequate sight distances, reflecting the likely operating speeds, should be provided to allow evasive action
by pedestrians, cyclists and drivers in a potential conflict situation.
o Sight distances to be considered include those of and for pedestrians and cyclists, as well as for others.
To accommodate the heavy vehicle traffic generated by construction during the development of subdivisions, the Design
Traffic computed for flexible pavements, DESA, should be increased by not less than the values outlined below.
Access Lane 5%
Access Place 4%
Access Street 3%
VicRoads Standard Specification 820 – Crushed Concrete for Pavement Sub Base and Light Duty Base provides details
of materials that can be substituted for conventional Class 2,3 & 4 Crushed Rock. Materials complying with Specification
820 may also be used as bedding under footpaths, slabs and kerbs and similar applications.
Notwithstanding any of the above requirements, the pavement thickness for residential streets should not be less than that
specified in Selection Table 12.7.6 for roads bounded by kerb and channel (or edge strips), 200mm for unkerbed roads
Minimum Pavement Depth = Minimum Pavement Depth = Minimum Pavement Depth = 400mm
250mm 300mm
Ararat Rural City Council Ballarat City Council Glenelg Shire Council
Campaspe Shire Bass Coast Shire Council Horsham Rural City Council
Gannawarra Shire Council Baw Baw Shire Council
Greater Bendigo City Council Benalla Rural City Council
Greater Geelong City Council Central Goldfields Shire Council
Greater Shepparton City Council Colac Otway Shire Council
Indigo Shire Council Corangamite Shire Council
Mansfield Shire Council East Gippsland Shire Council
Moira Shire Council Golden Plains Shire Council
Murrindindi Shire Council Hepburn Shire Council
Strathbogie Shire Council Latrobe City Council
Towong Shire Council Macedon Ranges Shire Council
Mitchell Shire Council
Moorabool Shire Council
Mount Alexander Shire Council
Moyne Shire Council
Pyrenees Shire Council
Rural City of Wangaratta
South Gippsland Shire Council
Southern Grampians Shire Council
Surf Coast Shire Council
Swan Hill Rural City Council
Warrnambool City Council
Wellington Shire Council
Wodonga City Council
Yarriambiack Shire Council
Council will expect the Design Engineer to submit copies of all geotechnical results for consideration by Council’s
Engineering Department.
Unless otherwise agreed by Council, compaction testing should be undertaken within 48 hours of a successful proof roll.
12.7.11 Sub-Grade
Proof rolling of the subgrade, in accordance with Clause 12.7.14 Proof Rolling, must be undertaken prior to the placement
of subbase material
Compaction testing of the subgrade will be required when imported or site-won material is used to raise the existing surface
to finished subgrade level and/or when approved subgrade treatments (including the addition of granular material) extend
more than 200 mm below the finished subgrade level. When such testing is required, the subgrade material must be
compacted to 98% of the standard dry density [STDDD] or in accordance with the Construction Specification and/or AS
3798.
12.7.12 Sub-Base
The typical flexible pavement sub-base consisting of fine crushed rock should be compacted as follows:
Court bowls 3 No
Intersections 2 No
Unless otherwise agreed by the Council, tests should be taken on alternate sides of the road and be evenly spaced.
12.7.14 Proof-Rolling
The subgrade should not deflect more than 2 mm vertically within 300 mm of the test roller in isolated locations during the
proof rolling of the subgrade. If deflection of the subgrade is found in more than 20% of the project area, Council will
expect the total area to be reworked.
Council will expect that proof-rolling of the subgrade, sub-base and base will be undertaken in accordance with the
requirements of AS 3798 and Section 173 of the VicRoads specifications.
There should be no visible deformation or cracking of the pavement during a sub-base or base proof-roll.
The Contractor will be responsible for rectifying areas that fail a proof-roll test. In accordance with Clause 7.4, adequate
notice should be given to allow the Council Engineer or a person nominated by the Council Engineer to attend proof-
rolling inspections. If a proof-roll test fails, a further Council inspection will be required, and appropriate notice should be
given.
The preferred road surface for all urban residential roads is a minimum of 30mm Type N Asphaltic Concrete. The surface
of the final wearing course should be between 5-10 mm above the concrete edging and detailed on the construction plans
for each edging type. To eliminate any trip hazard, Council will expect the wearing course to be flush with the lip of the
kerb and channel at all footpath kerb crossings.
Unless otherwise agreed by Council, all new and upgraded roads, including widened roads, located in or adjacent to
commercial or industrial Developments, and any residential collector streets where heavy vehicles comprise 5% or more
of the overall traffic, should be sealed with Type H Asphaltic Concrete of suitable thickness for the expected traffic loading,
with a minimum thickness of 40mm.
Unless otherwise agreed by Council, all new and upgraded intersections or roundabouts should be sealed with a Type H
Asphaltic Concrete of suitable thickness for the expected traffic loading, with a minimum thickness of 50mm. The Design
Engineer should seek advice from Council’s Engineering Department on specific sub-grade treatments and/or
pavement profiles that have given satisfactory service under local conditions.
For all new and upgraded roads, including widened roads, located in or adjacent to Rural, Rural Living and Low Density
Residential Developments, the minimum required wearing surface should be a two-coat seal. The first coat should use a
10mm aggregate with the second coat using 7mm aggregate. Where significant turning movements by heavy vehicles are
expected, the first coat should use a 14mm aggregate, with the second coat using 7mm aggregate.
Current VicRoads Specifications allow between 10% and 40% of recycled asphalt to be included in new mixes depending
on the particular mix type (Refer VicRoads Standard Specification 407). A combination of warm-mix asphalt and recycled
asphalt, providing even greater environmental benefits, appears to have no adverse impact on pavement performance on
typical lower-volume Council roads.
Emulsion binders can be used as an alternative to hot bitumen, particularly under cool and/or damp conditions. Austroads
Guide to Pavement Technology Part 4F: Bituminous Binders states that:
Emulsions can be used in sprayed seals for many of the applications of hot bitumen. The advantages include less heating,
reduced use of cutter oils in cool conditions and improved adhesion to damp surfaces in some circumstances. The
disadvantages include a higher cost due to the cost of emulsification and a slower rate of strength gain that increases the time
before seals can be trafficked, particularly in cooler conditions.
VicRoads Technical Note TN 107 – Use of Recycled Materials for Road Construction provides further information on the
availability and use of alternative pavement materials.
A two-coat bitumen seal may be considered as an alternative in some residential Developments, such as those located
in heritage areas, subject to prior agreement by Council’s Engineering Department. New and upgraded roads
constructed in areas with heritage characteristics may require specific colours of gravel to be used. Liaison with Council’s
Engineering Department and Council’s Planning Department will be required in these instances.
Council will expect the Design Engineer to specify all relevant design information, including mix design, aggregate size
and any colour or other additives, prior to construction. Where disputes arise concerning the finished surface texture or
integrity, core samples and compaction testing, undertaken at the cost of the Developer, may be required.
Many major traffic control Items will require VicRoads authorisation. The Design Engineer will be responsible for obtaining
any necessary authorisations, and should refer to Table 2.1 of the VicRoads Traffic Engineering Manual Volume 1.
*Note Ballarat City Council will enforce if a developer nominates vehicle crossings as part of their development.
Unless otherwise agreed by Council, where Developments include construction of barrier kerb and channel or SM2 kerb
and channel, a vehicle crossing and layback section in the kerb and channel constructed in accordance with the Standard
Drawings should be provided to each allotment frontage at the time of development.
Where Council has permitted swale drains to be used in LDRZ(U) or LDRZ(R) developments as part of an integrated
WSUD treatment system, the minimum pipe diameter will be 300mm, and the pipes should be laid so that the pipe invert
matches the table drain invert.
12.9.1.1 Entry/Exit
Driveways and direct vehicle access to collector streets Level 2 should be designed to allow forward entry and exit from
properties.
Note where a crossing is approved by Council to be constructed over an existing drainage pit the pit must be modified to
comply with SD 496 Modified Existing Pit to Grated Pit in Vehicle Crossing / Layback.
Crossings should be located at least 2.5m from the trunk of the street tree.
Crossings should be located so as not to reduce traffic safety by ensuring that vehicular movements associated with new
or modified crossings do not conflict with street traffic flow and the pedestrian, cyclist and motorist visibility. This can be
achieved by
a. a minimum clearance from the property boundary of 6m from any intersection to reduce confusion at intersections
and reduce the number of conflict points as shown in the figure below:
c. Crossings not located in line with a traffic control item such as a speed hump, other speed reducing feature or to any
school crossing unless those items have been specifically designed for these.
d. Crossings should generally align with internal driveways and garages as this will make for safer entry and exit of
vehicles.
Council will expect greater clearances to be applied when crossings provide access to and from Collector streets and
may require the Design Engineer to demonstrate that vehicles can enter and leave the roadway while travelling in a
forward direction at all times.
Crossings should generally be spaced along the street to provide a space for a street tree to be planted (minimum 5m)
and for the servicing of properties including properties on the opposite side of the street.
Crossings should be located in a position where the grades on the crossings will not be excessive and prevent or hinder
ingress and egress of vehicles from the property.
In accordance with the requirements of Clause 12.3.9, where grades through vehicle crossings exceed 1:10, Council will
expect the Design Engineer to demonstrate using standard car templates that safe and convenient car access can be
provided to the relevant allotments.
Council will expect all rural vehicle access crossings to include a culvert unless they are located at an obvious high point.
The minimum width of culvert is 4.8m, and all culverts should be equipped with an end-wall at each end of the pipe. Council
will expect trafficable end-walls to be used when the culvert is located within the Clear Zone (refer to Standard Drawings).
The minimum pipe size varies according to the slope of the terrain. In flat terrain the minimum pipe size is 375mm in
rural and rural living zones, and pipes should be laid with the pipe invert 150mm below the invert of the table drain. In
steeper terrain the risk of silting and blockage is reduced, and the minimum pipe size is 300mm.
Where Council has permitted swale drains to be used in LDRZ as part of an integrated WSUD treatment system, the
minimum pipe size will be 300mm, and the pipes should be laid so that the pipe invert matches the table drain invert.
Reinforced concrete swale crossings can be used where the depth of the table drain is less than 350mm and the product
of the depth and the peak flow velocity is less than 0.35, provided that Council’s Engineering Department is satisfied
that the crossing can be safely and conveniently negotiated by standard cars.
At existing entrances with either a 300mm or 375mm culvert, new end-walls may be added to the existing culvert as
long as the existing pipes are in good condition, are laid at the correct level, and are demonstrated to have sufficient
hydraulic capacity.
Council will expect culverts to be designed with the following hydraulic capacity:
• 20% AEP capacity before the property culvert overtops.
• 2% AEP capacity before the overtopping depth reaches 300mm.
• No water may encroach on the edge of shoulder on sealed roads, or the edge of gravel on gravel roads.
Council will expect rural vehicle crossings to be upgraded to meet current standards whenever rural land is subdivided,
unless the location of the access is at an obvious high point. Where a planning permit relates to boundary realignment
only, there will generally be no engineering requirement for upgrade to accesses, unless the proposed realignment would
see a significant change in the use of such access.
Dust Suppression Works Councils – Council Funds Dust Councils – Where Dust Suppression
Required Suppression Works Works are Determined on a Case by
Case Basis
Campaspe Shire Greater Shepparton City Council Ararat Rural City Council
Horsham Rural City Council Ballarat City Council
Macedon Ranges Shire Council Bass Coast Shire Council
Moira Shire Council Baw Baw Shire Council
Moyne Shire Council Benalla Rural City Council
Central Goldfields Shire Council
Colac Otway Shire Council
Corangamite Shire Council
Glenelg Shire Council
Golden Plains Shire Council
Greater Bendigo City Council
Greater Geelong City Council
Hepburn Shire Council
Indigo Shire Council
Latrobe City Council
Mitchell Shire Council
Moorabool Shire Council
Murrindindi Shire Council
Rural City of Wangaratta
Southern Grampians Shire Council
Strathbogie Shire Council
Surf Coast Shire Council
Swan Hill Rural City Council
Towong Shire Council
Warrnambool City Council
Wellington Shire Council
• to develop layouts that allow for access in all directions, link to public transport, reduce dependence on cars and
provide walkways and cycle-ways that are continuous and linked to each other.
13.2 General
Council will expect the Developer to provide continuous footpaths for all property frontages and sideages in urban
residential and commercial Developments PRINCIPLE. In accordance with Table 2 , Developers may also be required to
establish connective links to existing footpaths where demand is directly related to the development. Connective links are
generally required from commercial Developments to off-site car-parking related to the development.
The Austroads publication Cycling Aspects of Austroads Guides (2014) provides comprehensive information on planning,
design and traffic management of cycling facilities.
13.3 Requirements
The following requirements apply to footpaths and pedestrian accesses:
• Footpaths are to be constructed at the time of development in accordance with Appendix E: List of Council
Inspections and Inspection Checklists.
• Footpath alignments are to be offset by no more than 300mm from property boundaries in existing areas and by no
more than 50mm from property boundaries in new Developments.
• The minimum footpath width should be 1.5m in residential areas and 2.0m in commercial areas.
• Footpaths of 75mm thickness are acceptable only in well-established areas where the risk of site construction damage
is negligible. On greenfield sites, or where there is significant scope for further development, the depth of the footpath
should be 125mm throughout.
• The desirable maximum cross-fall on footpaths is 1:50 and the absolute maximum cross-fall is 1:40, including kerb
crossings. Kerb crossings are to be provided in accordance with Australian Standard AS/NZS1428.4, 2009 Design for
Access and Mobility – Means to Assist the Orientation of People with Vision Impairment – Tactile Ground Surface
Indicators at locations identified in consultation with Council’s Engineering Department.
• Council will expect footpaths to be constructed of concrete or asphalt, and to comply with Australian Standard
AS/NZS1428.4, 2009 Design for Access and Mobility – Means to Assist the Orientation of People with Vision
Impairment – Tactile Ground Surface Indicators for surface finish. Tactile Ground Surface Indicators should be
provided in accordance with AS/NZS 1428.4, with the VicRoads Traffic Engineering Manual Volume 3 – Part 2.19
Accessibility DDA Guidelines and with Appendix B: Engineering Acceptance Process for Developments.
Footpaths should slope away from the property boundary, and be elevated above the adjacent nature strip. In
general, reverse fall on nature strips is undesirable and will only be accepted where no practical alternative is
available.
The minimum width of the paths should be 2.8 metres. Batter slopes from the path should not be greater than 1 in 6 to
ensure ease of maintenance when mowing.
Consideration of the path location is vital with respect to drainage and potential property access and ensure a minimum
life of ten (10) years. Where possible, the path should have a uniform grade in steeper terrain where there is a potential
for scouring of the gravel surface.
Where a path must cross a natural surface drainage line, the path surface should either be raised above the surrounding
ground level to allow a culvert to be installed or follow the natural contour of the land.
Culverts should be equipped with low-profile headwalls and, when the pipe diameter exceeds 225mm, with guard rails on
each side of the path. The path width should be maintained across the culverts, and the overall formation width increased
accordingly.
If the preferred option is to follow the natural contour of the land, and allow stormwater to flow over the path, the section
liable to inundation should be sealed with;
• reinforced concrete constructed to the same specification as a residential footpath; or
• an asphalt layer at least 30 mm thick, with protective concrete edge strips.
The typical cross-fall for gravel paths should be as follows:
• Crown along centre of path, 1:25 fall from the centre.
• One way cross-fall, minimum of 1:50.
Typical physical properties of the gravel should meet the following criteria:
• All passing sieve size 13.2 mm
• Liquid Limit (max) 30%
• Plasticity Index max 15
0.425 10
0.075 5
In appropriate cases, the path may incorporate a wearing course comprising 50mm of stabilised granitic sand or crushed
limestone.
Permitted in Open Space Areas Permitted in Low Density Permitted for Shared Paths
Residential Developments
East Gippsland Shire Council East Gippsland Shire Council East Gippsland Shire Council
14.2 General
The number of parking spaces to be provided for any development should be in accordance with the Council’s Planning
Scheme or with the accepted Traffic Impact Assessment Report. Council will expect all required physical works to be
constructed as part of the Development, in accordance with accepted plans and specifications and to the satisfaction of
Council’s Engineering Department. The design should ensure that parked vehicles do not obstruct the passage of
vehicles, do not create traffic hazards or undue pedestrian hazards and do not detract from the streetscape amenity.
If the Developer is unable to provide the required number of on-site car-parking spaces for residents, staff and visitors,
and Council has not identified and addressed an existing or future need in the vicinity of the development, then the
Development may not be permitted to proceed unless the Design Engineer can satisfy Council that alternative car-
parking can be provided which meets the requirements set out in Clause 14.3. In particular, where Council has a Parking
Strategy that identifies existing or proposed parking within 100m of the Development, Council may require the Developer
to contribute to the actual costs of providing additional off-site vehicle spaces, and to enter into a Section 173 Agreement
with Council to that effect.
14.3 Requirements
The following parking requirements apply to all Developments:
• The parking required for normal levels of activity associated with any land use should be accommodated on-site and
should be located and should have dimensions that permit safe and convenient access and use.
• Unless Council has agreed to an alternative treatment, all parking, both on and off site, should be finished with an
all-weather seal and line marked.
• The layout and access arrangements for all parking areas should comply with the Austroads Guide to Traffic
Management: Part 11 Parking or Australian Standard AS2890.1 – 2004 Off Street Parking, AS2890.2 – 2002 Off
Street Commercial Vehicle Parking, AS2890.3 Bicycle Parking Facilities, Australian Standard AS2890.5 -1993.On
Street Parking and AS2890.6 Off Street Parking for People with Disabilities.
• The number of on-site parking and off-site parking spaces to be provided for non-residential land uses should comply
with the standards specified on the planning permit, where applicable, or with Council’s relevant Parking Strategies.
• Lighting should be provided to the satisfaction of Council’s Engineering Department.
• Loading/unloading requirements should consider forklift/pedestrian conflicts and other movements on the site.
In addition to the above, the following parking requirements apply to all residential Developments:
• Sufficient parking should be available to minimise the possibility of driveway access being obstructed by cars parked
on the opposite side of the street.
• Where a particular dwelling may generate a high demand for parking, the Developer may provide adequate additional
parking within the road reserve for visitors, service vehicles and any excess resident parking. Such parking should be
convenient to dwellings.
In addition to the general requirements, the following parking requirements apply to all on-site parking:
• Council will expect the Design Engineer, when designing the pavement, to make specific allowance for traffic load
concentrations at areas within the car park such as entrances and exits.
• Unless otherwise agreed by the Council, all loading and unloading zones should be constructed of concrete pavement
or concrete segmental pavers to resist damage from diesel and fuel spills. Paving should be mottled to mask spills.
Where parking is to be provided through a contribution to Council in accordance with an identified Parking Strategy, the
following requirements will apply:
• Customer parking spaces should be located within 100m of the development site.
• Dedicated permanent staff parking spaces can be provided within 500m of the site at the Developer’s cost.
• There is a direct pedestrian linkage with the Development, or one will be provided by the Developer.
• Disabled parking spaces are provided in accordance with the requirements of the Disability and Discrimination Act
and relevant Australian Standards.
• Lighting is provided to the satisfaction of Council’s Engineering Department.
• The car park design includes retention of significant existing vegetation, proposed landscaping, the selection of
colours and materials for any structures on the site.
• The status of each element within the proposed car park, including common property, Council reserves, indented
road reserves, and parking spaces, has been confirmed in writing by Council’s Engineering Department.
• Agreement has been reached regarding public indemnity for the carpark.
• Access and availability to Public Transport systems have been considered.
• The proposal accommodates existing or future location of non-residential uses such as schools, commercial and
industrial premises and local shops located, or likely to be developed, in the area.
• The effect of on-street parking works is to slow vehicle speeds and enhance the pedestrian environment.
15.2 General
Approval of engineering plans by Council’s Engineering Department relates only to the capacity of earthworks to
accommodate road and drainage systems to the satisfaction of Council, and does not negate the need for planning
consent for such earthworks. The Design Engineer will be responsible for ensuring that a planning permit is obtained
where required for any earthworks. Where works are to be staged, the permit should, wherever possible, be obtained for
the entire site, rather than for each individual stage in turn.
Earthworks may adversely affect the ability of lots to be serviced by gravity sewerage and may require alterations to
existing maintenance structures and fittings to match finished surface levels. Council will expect the Design Engineer to
consult with the relevant service authority before submitting engineering plans for approval.
Where roads, footpaths or shared paths are constructed over filled areas, Council will expect the pavement materials,
structure and geometry to be designed by a Qualified Engineer, with the drawings, calculations, and geotechnical data
being submitted to Council’s Engineering Department for approval.
Where driveway gradients exceed 1:10, vehicle clearances should be checked in accordance with the Austroads Guide to
Road Design: Part 3: Geometric Design (Section 8.2.5). Council will expect the Design Engineer to restrict batter slopes
to 1:4 unless special treatments, such as retaining walls, and appropriate erosion control measures, are applied.
15.3 Requirements
The following earthworks and lot filling requirements apply to all Developments:
• All work should be undertaken in accordance with AS 3798-2007 Guidelines on Earthworks for Commercial and
Residential Developments.
• Particular care should be taken to ensure that earthworks in an area liable to flooding have no adverse impact on the
floodplain characteristics. Existing depressions cannot be filled, either temporarily or permanently, unless the consent
of the Relevant Authority is given in writing and any relevant permits have been obtained.
• Where works are undertaken in a floodway, all spoil should be removed to an area above the 1% AEP flood level.
• Council will expect all new urban subdivision allotments to be graded, cut or filled, so that a minimum grade of 1:200
is achieved along the low side of the allotment toward the drainage outlet.
• The finished floor surface level of buildings must be at least 300mm above the 1% AEP flood level.
• The finished surface of lotfilling must be at or above the 1% AEP flood level.
• The extent and depth of all proposed lotfilling should be denoted on the construction plans. Where depths of fill on
allotments exceed 300 mm, those areas are to be clearly differentiated from areas where the depths of fill are less
than 300 mm.
• Council will expect full records to be kept of all areas filled and the information to be recorded on the ‘as constructed’
plans.
• Where the depth of fill exceeds 300mm, Council will expect the fill to be compacted in accordance with the
requirements of Table 204.131 Compaction Requirements Scale C of VicRoads Specification and trimmed and
shaped to match existing site levels, except in areas nominated for soft landscaping. Council will expect the
geotechnical test results to be submitted to Council’s Engineering Department for approval.
• The requirements for backfilling drainage trenches are specified in the Standard Drawing.
• Where earthworks abut structures, Council will expect the Design Engineer to demonstrate the continued safety and
integrity of those structures to the satisfaction of Council’s Engineering Department.
• The desirable maximum depth of fill allowable against fencing (where a plinth has been provided at the base of the
fencing) is 200mm.
• Council will expect retaining walls to be provided when the depth of fill exceeds 200mm or the maximum batter slopes
are exceeded. The Design Engineer should check with the relevant authority to ensure that the construction of such
walls will not impact on existing underground services (which may be in unregistered easements).
• No water may be directed to flow into adjoining properties.
16.2 General
Council will expect the Design Engineer to design the drainage system in accordance with the relevant provisions of
Australian Rainfall and Runoff - A Guide to Flood Estimation 2019, Water Sensitive Urban Design Engineering Procedures
published by Melbourne Water, Urban Stormwater Best Practice Environmental Management Guidelines 2006, published
by the CSIRO and, where relevant, Australian Standard AS3500.3 Stormwater Drainage.
These standards and guidelines require that the complete drainage catchment be taken into account, not just the area
included in the subdivision or Development. Council will expect the Design Engineer to base the calculated peak flow
on the full potential development of the project and the upstream areas for normal flow situations, and to consider the
overland flooding caused by pipe blockages, general flooding and high water levels. Staged upgrading of the system can
only be undertaken with the prior agreement of Council.
Prior to commencing detailed design, the Design Engineer should determine the possible ultimate zoning of all external
catchment areas contributing to the drainage system within the Development. This may require consultation with the
Council’s Engineering Department and Council’s Planning Department.
The minor system typically comprises a pipeline network with sufficient capacity to collect and convey stormwater flows
from nominated design storm events (see Clause 16.7). These pipelines prevent stormwater damage to properties and
limit the frequency and quantity of surface water to a level acceptable to the community. The pipelines do not always follow
the natural drainage paths and are usually aligned along property boundaries and the roadway kerbs and channels.
The major drainage system caters for the runoff from storms of higher intensity than those for which the minor drainage
system has been designed. The major drainage system is designed to handle flows resulting from storms with a 1% AEP.
These flows should follow a designated overland flow path, which will normally be a road reserve if the catchment area is
small, and/or a drainage reserve when it is impractical for unsafe for a road reserve to carry the excess flows.
Council will expect the finished floor level of buildings to be at least 300mm above the 1% AEP flood level.
Partial areas should be considered when determining peak flow sites, particularly when a catchment contains sub-areas,
such as reserves, that may have relatively large time of concentration in conjunction with a small coefficient of runoff. In
some instances, a partial area design discharge may result in runoff that is less (or the same) than a discharge calculated
at some upstream point. Careful checking of the partial area flows may be required to determine the largest flow, which
Council will expect to be used for the design of the stormwater system downstream of the connection point.
In assessing the major drainage system, the Design Engineer should consider using a Unit Hydrograph or Non-Linear
Run-Off Routing model. The Design Engineer will be responsible for determining the most appropriate methodology for
each application. Various drainage tools, programs and construction methods are available to the Design Engineer to
achieve the objectives of the drainage system. Regardless of the technique or method used, Council will expect detailed
documentation to be submitted for review and approval.
Two separate recognised runoff estimation methods, in addition to the Rational Method, should be used for catchment
areas greater than 50 hectares.
1 1EY 1
2 50% 1.44
VERSION 5.30 Page 103 of 275
ARR/BOM 1987 ARR/BOM 2016
5 20% 4.48
10 10% 9.49
20 5% 20
50 2% 50
100 1% 100
Intensity/Frequency/Duration curves (IFD) are available from the Bureau of Meteorology Website:
http://www.bom.gov.au/water/designRainfalls/revised-ifd/
Online resources allow curves to be established for any Australian location based on its latitude and longitude.
The initial time of concentration from building to property boundary can normally be assumed to be six (6) minutes in urban
residential areas. Special consideration may be necessary for other areas and/or circumstances.
Council will expect the Design Engineer to identify all overland flow pathways to be activated in 1% AEP events, and to
demonstrate that these pathways (normally including road reserves in urban areas) have sufficient capacity to convey all
excess runoff once the available capacity of the minor drainage system has been fully mobilised. Care should be taken
to ensure that any adjacent properties will not suffer adverse consequences from the mobilisation of those paths. These
requirements may not be applicable when pipes discharge to retarding basins, as provided for in Clause 18.5.
Table 10 specifies the minimum runoff coefficients to be used in the design of drainage systems:
LDRZ – lot areas >2000 m2 to 4000 m2 0.45 See notes 1, 2 and 3 0.35
Residential areas – lot areas >1000 m2 to 2000 m2 0.50 See notes 1, 2 and 3 0.40
Residential areas – lot areas >600 m2 to 1,000 m2 0.70 See notes 1, 2 and 3 0.55
Note 1
The runoff coefficients shown in Table 10 for residential lots greater than 600m2 in area do not include an allowance for
the road reserves within these subdivisions.
Note 2
Where there is a likelihood of further subdivision occurring of allotments in new subdivisions an allowance of 10% should
be added to the coefficients to avoid the need for on-site detention to be provided for these further subdivisions.
VERSION 5.30 Page 105 of 275
Note 3
The Councils listed in Selection Table 16.7 have differing coefficients of runoff for 20% AEP and 1% AEP. All other
Councils use the coefficients listed in the first column of Table 10.
When an external area contributes stormwater to the system, the drain should be located at a depth sufficient to serve the
total upstream area, and due consideration should be given to any possible upstream backwater effects.
The HGL in pipes running partially full may be assumed to follow the pipe obvert. However, the actual velocities within the
pipe under such circumstances should be checked.
Pipe designs should reflect appropriate pipe parameters for either the Colebrook – White formula or Manning’s formula as
shown in Table 11.
Where Council has agreed that other pipe materials may be used, the manufacturer’s recommendations should be
adopted, having due regard to the potential for pipe roughness to increase over the service life of the system.
Minimum Grade of Stormwater Pipe to be 1 in 500 Minimum Grade of Stormwater Pipe to be 1 in 300
Subject to a Minimum Velocity of 0.7m/sec Subject to a Minimum Velocity of 1.0m/sec
Benalla Rural City Council Ararat Rural City Council
Campaspe Shire Council Ballarat City Council
Gannawarra Shire Council Bass Coast Shire Council
Greater Shepparton City Council Baw Baw Shire Council
Horsham Rural City Council Central Goldfields Shire Council
Mansfield Shire Council Colac Otway Shire Council
Moira Shire Council Corangamite Shire Council
Wellington Shire Council East Gippsland Shire Council.
Yarriambiack Shire Council Glenelg Shire Council
Golden Plains Shire Council
Greater Bendigo City Council
Greater Geelong City Council
Hepburn Shire Council
Indigo Shire Council
Latrobe City Council
Macedon Ranges Shire Council
Mitchell Shire Council
Moorabool Shire Council
Moyne Shire Council
Murrindindi Shire Council (minimum grade 1 in 200)
Pyrenees Shire Council
Rural City of Wangaratta
South Gippsland Shire Council
Southern Grampians Shire Council
Strathbogie Shire Council
Surf Coast Shire Council
Swan Hill Rural City Council
Towong Shire Council
Minimum cover to and clearances between utility services can be obtained from VicRoads Code of Practice for the
Management of Infrastructure Within Road Reserves.
Where sizes of future utility services are not known contact the Council to determine what minimum cover should be
provided for.
The Design Engineer should discuss any proposed exceptions to the minimum cover requirements with Council’s
Engineering Department prior to submitting documents for approval of the functional layout.
Values of K for various pit configurations are given in Austroads Road Design Guidelines - Part 5 General and Hydrology
Considerations and any VicRoads Supplement to those guidelines.
Double side entry pits should be used where approach grades to intersections are in excess of 6% and at all low points in
roads, unless the Design Engineer can satisfy Council’s Engineering Department that a single side entry pit will provide
sufficient inlet capacity for the pipes to operate at their required capacity.
The Design Engineer should discuss the design criteria for main drains with Council’s Engineering Department at the
earliest possible stage in the design process.
16.10 Pipes
16.10.1 Pipe Type
16.10.1.1 Reinforced Concrete Pipes
Reinforced concrete pipes with spigot-and-socket profile and rubber ring joints, manufactured to meet the requirements of
AS/NZS 4058-2007 Precast concrete pipe (pressure and non-pressure), and designed and installed in accordance with
Clause 16.10.3, are accepted by all Councils. Flush-jointed reinforced concrete pipes with external bands, manufactured,
designed and installed to the above standards, may be used for culverts and other specific applications, subject to the
prior agreement from Council’s Engineering Department.
Ribbed polypropylene or high-density polyethylene stormwater pipes, designed and installed in compliance with Clause
16.10.3, may be used as an alternative to reinforced concrete pipes where a Council has indicated its acceptance of such
use in Selection Table 16.10.1 Ribbed Polypropylene or High Density Polyethylene Stormwater Pipes.
Selection Table 16.10.1 Ribbed Polypropylene or High Density Polyethylene Stormwater Pipes
Accepted for use Accepted for use except under road pavements
Prior agreement in writing from Council’s Engineering Department is required for all other pipe profiles and/or materials.
These include ribbed polypropylene or high density polyethylene stormwater pipes for those Councils not listed in Selection
Table 16.10.1 Ribbed Polypropylene or High Density Polyethylene Stormwater Pipes.
Council recognises that sustainable material alternatives, including recycled plastics and concretes containing recycled
aggregates or fibre reinforced concretes, can demonstrate similar hydraulic performance to that of conventional materials,
but will require that the Design Engineer provides additional evidence on the structural integrity and durability of proposed
pipe profiles and materials. The information provided should include:
• details of any Australian or overseas Standards covering the design and installation of the pipeline;
• the manufacturer’s recommendations for type, class, loading, cover, and installation procedures;
• details of where, by whom, and for what purposes similar pipes have previously been accepted;
• details of testing and inspection proposed to be undertaken; and
• other details as required by the Council
Pipes that are or will become Council assets, and are not required to convey runoff from a road or street, should have a
minimum diameter of 225mm. Pipes that are or will become Council assets, and do convey runoff from a road or street,
should have a minimum diameter of 375mm, to reduce the risk of blockage.
The Design Engineer may apply in writing to Council’s Engineering Department for agreement to vary the above
minimum sizes. Such applications should be accompanied by computations to show that the required minimum flow
velocities have been achieved, and the pipe capacities are adequate for the intended purpose. The application should
explain how blockages are to be avoided when the pipes in question are required to convey runoff from a road or street.
Pipeline designs should consider both dead and live loads. In addition to the live loads imposed by normal traffic
movements, Council will expect the Design Engineer to have regard to the transient live loads associated with
construction equipment, heavy service vehicles and emergency vehicles.
When pipelines are located within road reserves or public spaces, or may otherwise be subjected to significant live loads,
Council may require the Design Engineer to provide specific calculations, based on the live loads specified in AS 5100.2
Bridge design, to confirm the adequacy of the proposed type and class of pipe, rather than relying on generic
recommendations by manufacturers.
Where any departures from these provisions are proposed, Council will expect the Design Engineer to seek agreement
for those departures at the earliest possible stage in the design process, and to provide detailed justification for their
proposals.
Note: The Design Engineer should ensure that any commercially available software package relied upon in performing
such calculations uses the live load distribution ratios specified in Clause 6.2 of AS 5100.2.
16.10.3.2 Reinforced Concrete Pipes
Reinforced concrete pipes, as specified in Clause 16.10.1, should be designed and installed in accordance with AS/NZS
3725-2007 Design for installation of buried concrete pipes. The Design Engineer should have regard to the
recommendations in AS/NZS 3725-2007 Supplement 1 (Commentary), particularly in situations where a buried pipeline
may be required to carry significant live loads.
Note: Table B2 of AS 3725-2007 does not reflect the live load distribution ratios specified in Clause 6.2 of AS 5100.2,
and should not be relied upon when submitting specific calculations for pipelines to be located within road
reserves or public spaces.
16.10.3.3 Ribbed Polypropylene or High Density Polyethylene Stormwater Pipes
Ribbed Polypropylene or High Density Polyethylene Stormwater Pipes, as specified in Clause 16.10.1, should:
• be designed to comply with AS/NZS 2566.1-1998 Buried flexible pipes – structural design;
• be installed as required by AS/NZS 2566.2-2002 Buried flexible pipes – installation;
• comply fully with any additional technical recommendations provided by the manufacturer;
• when installed behind mountable or semi-mountable kerb, have a cover of at least 750mm;
• when installed in easements subject to occasional traffic, have a cover of at least 600mm; and
• when installed within a Bushfire Management Overlay, have a cover of at least 450mm.
When particular pipe materials and/or systems are not specifically covered in AS/NZS 2566.1-1998, Council may require
the Design Engineer to provide evidence that the testing and quality control regimes applied, and the design parameters
recommended, by the manufacturer are equivalent to, or more stringent, than those specified in the standard.
16.11 Structures
16.11.1 Drainage Structures
Council will expect drainage structures to comply with the applicable standard drawings. Where modifications are required
or special structures are to be constructed or installed, the Design Engineer should submit full details with the detailed
design documentation. Normal good practice should be observed in determining the pit layouts, and shallow intersection
angles between drainage lines at pits will not be permitted.
Murrindindi Shire Council requires floors of pits shown in the Standard Drawings to be shaped to suit the pipe radius and
change of pipe lower inverts, unless otherwise agreed by the Council.
Junction pits at the back of kerb within intersections should be avoided wherever possible.
Council may request catch basins, also known as sumped drainage pits, in locations where a drainage system is tributary
to a receiving water which is vulnerable to siltation, such as a constructed wetland. For efficiency of future maintenance,
these structures have the effect of settling out solids during low-flow storm events and storing the solids for subsequent
collection by vacuum truck, and can assist to minimise the frequency of dredging sediments from the receiving water body
Council may accept the use of prefabricated pits, but may require the Design Engineer or Construction Engineer to
provide full technical details of the proposed pits, including material, specification, dimensions, and product data sheet,
and to give careful consideration to any advantages or disadvantages of using such pits in the proposed location. Council
may also require that a certificate be provided by a Qualified Engineer to confirm the structural integrity of the pits in the
specific application, having regard to the nature of the pipes to be used and the dead and live loads to be sustained.
Approved trafficable load-bearing covers should be provided on all side entry pits in exposed kerb areas, particularly at
intersections, and on all pits located within industrial Developments. The drainage network should be designed to locate
pits away from exposed kerb areas wherever possible
For design purposes, the default period for the cleaning of litter collection pits should be assumed to be 6 months.
These larger systems will usually fall into one of two distinct categories:
• Low-head, high-volume pumps are normally used behind a levee bank when a watercourse is at or above minor
flood level and backflow into the urban drainage system must be prevented. When the required discharge rates
exceed the capacity of portable pumps, permanent pump stations should be constructed. In either case, the pump
platforms should be above the 1% AEP flood level, with the pumps drawing water by suction from a sump. The
maximum practicable sump depth will then be between 5m and 6m.
• Higher-head, lower-volume pumps are normally used to transfer water from a retardation basin or wetland to the
receiving watercourse. They are generally submersible pumps in permanent installations, designed to operate
whenever a local rainfall event occurs. Good practice then requires that there be two separate pumps, one being
on duty at any given time while the other remains on standby. The pumps should rotate automatically from duty
to standby status after each rainfall event.
Pump station components which have not been designed to operate safely when fully immersed should be installed above
the relevant 1% AEP flood level, and ready access should be available for maintenance crews during such events. So far
as practicable, the control cabinets and warning lights should be clearly visible from a public road.
All pump stations should be:
• screened in order to reduce the likelihood of blockage by sediment and debris; and
• configured so that failure of a single pump will not result in failure of the overall system; and
• provided with enough upstream retardation capacity to accommodate projected outages; and
• capable of being quickly and effectively isolated from the adjacent drainage networks; and
• designed so that all major operating components can readily be removed and replaced; and
In principle, for each station, the pump motor and impeller should be selected to ensure that peak energy efficiency
coincides with the duty point (where the capacity and head intersect on the performance graphs provided by the
manufacturer). In practice, given the high level of uncertainty associated with stormwater computations, this may not
always be the key design factor, and some measure of compromise may have to be accepted. In particular, so far as
possible under Council purchasing policies and procedures, every effort should be made to limit the range of pump types
and capacities deployed across a municipality, thus reducing the need to hold extensive spare part inventories and to train
maintenance crews to handle varying pump issues and responses.
Further information can be found in the most recent version of the Guide for Development Engineers published by the
Local Government Infrastructure Design Association and freely available from www.designmanual.com.au.
The desirable minimum grade for sub-surface drainage for pavements is 1: 250 with an absolute minimum of 1:300.
Typically, circular 100mm rigid wall or flexible UPVC Class 400 slotted pipe, including geotextile sock where required, is
installed under each concrete pavement edging to a minimum depth of subgrade level.
Council will expect the Design Engineer to submit details of all sub-surface drainage to be used in the Development,
including groundwater discharge systems from sewerage trenches, to Council’s Engineering Department for
approval.
In in-fill urban residential and commercial Developments where connection to underground drains is impractical, two (2)
kerb adaptors per 20m of frontage should be provided at the time of development. Unless otherwise agreed by Council,
kerb adaptors should be located clear of all driveway crossings and at least 1m from kerb crossings.
Generally galvanised steel or UPVC adaptors are acceptable unless there is a specific Council requirement as detailed
in Selection Table 16.16.
Council will expect the Design Engineer to provide easement drains to all allotments that fall to the rear, and to ensure
that such drains are deep enough to serve the entire allotment. A property inlet, as per Council’s Standard Drawings,
should normally be constructed at the low corner of each allotment. The minimum fall towards the underground drainage
outlet along the low side of allotments should be 1:200.
Major drainage in railway reserves should be limited to cross track drainage rather than longitudinal drainage. Council will
expect the Design Engineer to obtain written consent from the relevant authority for all Infrastructure proposed to be
located in railway reserves before seeking detailed design approval from Council’s Engineering Department. The
The normal minimum requirements of the major drainage system are as follows:
• Council will expect the design of major drainage systems to be based on the critical 1% AEP storm with some
consideration being given to the impact of a rarer storm event. Best practice requires that the critical storm be
determined by routing storms of varying duration until the peak flows are identified. Council will expect two recognised
flow estimation methods (runoff routing computer models) in addition to the Rational Method to be used for
comparative purposes when urban catchments or sub-catchments are greater than 50 Ha in area.
• Hydraulic Grade Line analysis should be used for the design of floodways, low-flow pipes and retarding basins.
Council will expect the Design Engineer to demonstrate that the dimensions of major floodways are sufficient both
to meet hydraulic requirements and to facilitate maintenance (including mowing), and that street drainage in urban
areas will not be directed into easement drains.
• The depth of overland flows in urban areas should be controlled by freeboard to properties or by the upper limits of
surface flow depth/velocity consistent with public safety, as detailed in Austroads Road Design Guidelines Part 5A
Drainage – Road Surfaces, Networks, Basins and Subsurface and any VicRoads supplement to those guidelines.
16.18 Floodways
Major floodways generally comprise engineered open waterways, and often involve roadways, trapezoidal channels and
sometimes sheet flow through open spaces. Major floodways are generally located within road reserves, drainage reserves
or Public Open Space. Council will not accept major floodways through easements on private land in urban situations,
and will expect the computed peak discharge to be contained entirely within reserves.
Where a Development will have a significant impact on overland flows or flood-storage, Council will expect the Design
Engineer to design and construct appropriate compensatory works.
Where active floodways are present Council will not accept development without hydraulic modelling and analysis. The
Design Engineer may also be requested to submit a risk assessment report including details of the measures proposed
to be taken to ensure that the potential for loss of life, risk to health and damage to property is minimised, and flood
conveyance or storage accommodated.
Council will expect hydraulic modelling to be undertaken by a suitably qualified person or organisation, to identify works
that will ensure that adjacent landholders are not detrimentally affected, and to identify the extent, velocities and depth of
overland flood flows through the development and downstream.
Council will generally view alteration to existing wetlands as a last resort, to be considered only after all other options
have been reviewed and found wanting. The function of a floodplain is to convey and store flood water and preserve the
inherent values of wetlands.
The minimum requirements that apply to design and treatment of floodways, and open unlined drains, are as follows:
• The depth of floodways should be kept to a minimum (generally less than 1.2m).
• The desirable maximum batter slope is 1:8; the absolute maximum slope is 1:5.
• The desirable minimum cross-fall for inverts is 1:40, and the minimum bed width 2.5m.
• The maximum permissible longitudinal grades for major floodways will be governed by the need to minimise flow
velocities in order to avoid scour and secure public safety.
Wherever possible drainage reserves should be sited to abut Public Open Space, but will only contribute to the provision
of Public Open Space in accordance with requirements of Clause 18.2. Council will expect the Design Engineer to
consider increasing the reserve width for conservation and landscaping purposes.
Where drainage Infrastructure within the drainage reserve does not comply with the standards for public access, the
reserve should be fenced to prohibit public access. Council will expect the Design Engineer to submit a landscaping plan
and fencing details for approval, with all fencing and landscaping being completed at the full cost of the Developer.
• collect and control all stormwater generated in or transferred through the Development or subdivision and ensure
that it is discharged from the site without detriment to any upstream or downstream property;
• ensure that any Developments or subdivisions that would otherwise increase the rate and quantity of stormwater
runoff retard outflows to rural runoff rates where applicable;
• provide an effective outlet to an acceptable outfall;
• ensure that culverts and waterways are designed so the safe passage of vehicles is maintained at all times;
• restrict stormwater flows to natural drainage lines and avoid crossing drainage catchment boundaries;
• comply with the objectives and requirements of any relevant Floodplain Authority;
• ensure that there are no detrimental effects on:
o the environment generally;
o surface and subsurface water quality;
o groundwater infiltration characteristics;
o adjoining landowners and other landowners in the vicinity of the drainage outlet; and
o water-courses either upstream or downstream of the Development or subdivision.
17.2 General
Council will expect the Design Engineer to consider the complete drainage catchment, not just the area included in any
individual Development or subdivision and to comply with the provisions of the Austroads Road Design Guidelines Part 5
Drainage – General and Hydrology Considerations and any VicRoads Supplement to those guidelines.
The Design Engineer should therefore take into account upstream developments, overland flow paths, natural drainage
lines, the possible removal of unnatural drainage obstructions, the depth of flooding that may occur on roads and private
property and other factors which may impact on or be affected by the design of any rural drainage system.
The Design Engineer will be responsible for ensuring that their design complies with the requirements of s16 of the Water
Act 1989 and s199 of the Local Government Act 1989. In particular, under S16 of the Water Act 1989, Council is
considered a landowner/manager of local roads. The construction and maintenance of such roads must not cause water
to flow from the road reserve in an unreasonable manner or prevent the natural flow of water across or along a local road
reserve from occurring in a reasonable manner. In addition, under S199 of the Local Government Act 1989, Council must
give notice of its intention to divert or concentrate the drainage flowing onto a road or discharge it or permit it to flow onto,
into or through any land. Any persons may make a submission to Council under section 223 of the Act. In practice this
means that Council must give notice of its intention before any new culverts are placed under a road.
17.3 Requirements
Council will expect the Design Engineer to base stormwater runoff estimation for rural catchments (undeveloped areas)
on the hydrological methods and data contained within the latest issue of Austroads Road Design Guidelines Part 5
Drainage – General and Hydrology Considerations and any VicRoads Supplement to those guidelines, unless otherwise
provided within this Manual.
VERSION 5.30 Page 119 of 275
These guidelines specify that two recognised flow estimation methods (runoff routing computer models) should be used
for comparative purposes when dealing with rural farming catchments or sub-catchments greater than 50ha in area.
Minimum Slope of Earth Drain 1 in 2000 Minimum Slope of Earth Drain 1 in 500
Benalla Rural City Council Ararat Rural City Council
Campaspe Shire Council Ballarat City Council
Gannawarra Shire Council Bass Coast Shire Council
Greater Shepparton City Council Baw Baw Shire Council
Horsham Rural City Council Central Goldfields Shire Council
Swan Hill Rural City Council Colac Otway Shire Council
Yarriambiack Shire Council East Gippsland Shire Council
Glenelg Shire Council
Golden Plains Shire Council
Greater Bendigo City Council
Greater Geelong City Council
Hepburn Shire Council
Indigo Shire Council
Latrobe City Council
Macedon Ranges Shire Council
Mansfield Shire Council
Mitchell Shire Council
Moira Shire Council
Moorabool Shire Council
Mount Alexander Shire Council
Moyne Shire Council
Murrindindi Shire Council
Pyrenees Shire Council
Rural City of Wangaratta
South Gippsland Shire Council
Strathbogie Shire Council
Surf Coast Shire Council
VERSION 5.30 Page 120 of 275
Minimum Slope of Earth Drain 1 in 2000 Minimum Slope of Earth Drain 1 in 500
Towong Shire Council
Warrnambool City Council
Wellington Shire Council
Wodonga City Council
• Unless otherwise agreed by Council, the minimum bed width of the drain should be 1m.
• The desirable maximum batter slope of earth drains within the Clear Zone is 1:6, with the absolute maximum slope
being 1:4. Where the drain is located outside the Clear Zone the maximum batter slope is 1:1.5.
• Council will expect driveable end-walls complying with VicRoads Standard Drawing SD1991 to be provided for all
culverts that are parallel to the traffic flow and located within the Clear Zone.
• Where possible, cross-culverts should be extended to terminate outside of the Clear Zone. Council will expect end-
walls complying with the relevant VicRoads standard drawings to be provided for cross-culverts terminating within
the Clear Zone.
• The discharge of any roadside table drain into a Drainage Authority drain requires consent from that Authority and
the structure should be constructed in accordance with their requirements.
• Section 199 of Local Government Act 1989 requires Council to give notice to all affected landowners for any drainage
works that will divert or concentrate drainage waters.
Unless otherwise agreed by Council, property connections in low density residential Developments should discharge
through the side of the end-wall and not directly into the table drain. Council will expect the Design Engineers to design
culverts to accommodate peak runoff associated with the following rainfall events:
Council will expect the Design Engineer to ensure that flows exceeding the capacity of a culvert are so conveyed as to
avoid flooding by, for example, incorporating a floodway with the culvert installation.
The Design Engineer should consider incorporating wetlands, gross pollutant traps and/or sediment interception ponds
within the major drainage system.
Major drainage within railway reserves should be limited to cross track drainage rather than longitudinal drainage and
Council will expect the Design Engineer to obtain consent from the relevant authority for all such Infrastructure before
seeking detailed design approval from Council’s Engineering Department. The Developer will be responsible for
Where no practicable options are available, Council will consider proposals for major floodways through easements in
private land in rural living Developments.
The minimum requirements of the major drainage system in rural areas are as follows:
• The design of major drainage systems should be based on the critical 1% AEP storm with some consideration given
to the impact of less probable storm events. The critical storm should be determined by routing storms of varying
duration until the peak flows are identified.
• Hydraulic Grade Line analysis should be used for the design of floodways, low-flow pipes and retarding basins. The
dimensions of major floodways should be sufficient to meet hydraulic requirements and to facilitate maintenance
(including mowing).
• The depth of overland flows should be controlled so as to maintain public safety and avoid damage to properties,
based on the criteria in Austroads Road Design Guidelines Part 5 – General and Hydrology Considerations and any
VicRoads Supplement to those guidelines.
• Road drainage in Low Density Residential and Rural Living areas may be directed into easement drains.
• The normal minimum width of easements for open drains in rural areas is 5m.
• To limit, as much as possible, the number of retardation basins servicing an area in order to reduce Council’s future
maintenance expenditure.
• To ensure that standalone retardation basins drain completely within a reasonable time following each rainfall event
and, wherever practicable, are constructed so that the area can be used for passive or active recreation or other uses
such as car parks as determined by Council.
• To incorporate stormwater treatment and litter traps into the retardation basin design where practical and required by
Council.
• To protect existing stormwater drainage assets, owned by Council or by other drainage authorities, from overloading
as a result of works carried out by Council or Developers that are or will become the property of Council.
• To standardise the type and operation of pumping systems and outfalls associated with retardation basins.
• To improve the quality of stormwater runoff being discharged from a particular development using WSUD principles.
o be aesthetically pleasing,
18.2 The Use of Drainage Basins for Public Open Space Purposes
Developers and Design Engineers need to satisfy the requirements of clause 56.05-2 of the relevant planning scheme
and in particular Standard C13. The provision of Public Open Space should be:
• Suitably dimensioned and designed to for the intended use, buffer areas around sporting fields and passive open
space.
• Located with access to, or making provision for, a recycled or sustainable water supply.
The design events for various kinds of POS proposed for use as a retardation basin should be:
• Regional Parks and Sports Fields 2% AEP
• Local Parks 5% AEP
• Linear Parks 10% AEP
18.3 General
Council will expect the detailed design and documentation of drainage basins and/or similar detention facilities to be
carried out by a Qualified Engineer, and to demonstrate that any required storm water retardation or detention systems
can be integrated into the drainage system.
The facility should normally be located and designed in accordance with a relevant Development Plan, Council Strategy,
or Stormwater Management Strategy. Where the necessary policy framework is not in place, Council will expect the
Design Engineer to seek specific agreement for the siting of any proposed retardation basins prior to proceeding with the
design of the minor and major drainage system. Catchment boundaries may be increased only if written consent is obtained
from the relevant drainage authority.
Council will expect any design to be consistent with this Manual, and to meet all the requirements of the local Catchment
Management Authority (CMA) and Irrigation and Drainage Authority. For example, retarding basins with outfall to relevant
authority drains are required to be designed for the 1% AEP storm event of 24-hour duration, with a no-outfall condition,
and with a maximum discharge rate to the drainage system as specified by the authority (typically 1.2 lit/sec/ha).
Land that has been identified for storm water retardation basins to be maintained by Council, whether existing or proposed,
must be shown on a Plan of Subdivision as a Municipal Reserve for drainage purposes and be vested in the Council. In
circumstances where retarding basins are not to be maintained by Council and are located within land that is common
property, Council is unlikely to be a member of the Owners Corporation corporate. In such instances, Council will expect
a Section 173 Agreement to be placed on each benefiting allotment to ensure that Council drainage networks are not
compromised by any act, or omission by the Owners Corporation.
When a retardation basin is required for any development, the basin and any overland flow paths should normally be
constructed as part of the first stage of the works. Where the Design Engineer considers that the retardation basin is not
required to service that stage, Council will expect them to submit plans, computations, and approvals from the relevant
authorities demonstrating that satisfactory temporary provisions can be made for storage and outfall.
Council will expect that where a retardation basin poses potential risk to lives, buildings or infrastructure downstream its
design will comply with the Australian National Committee on Large Dams (ANCOLD) guidelines.
Retardation basins may need to be protected from unrelated overland flows entering the basin and therefore, apart from
the above limitations, should not be located in an area designated on the floodplain maps maintained by the Department
of Environment, Land and Planning as an active floodway. Council will expect appropriate works to be carried out to
minimise erosion and maintenance resulting from overland flows. The location of basins should have regard to:
Where the Design Engineer can demonstrate that a 1% AEP storm event will be irrelevant due to cross-catchment storm
flows and overland flows swamping the catchment and/or the basin, Council may consider a design based on a more
probable storm event and with reduced storage capacity.
Council will expect the minimum freeboard within the basin following a 1% AEP event, under no outfall conditions, to be
300 mm for earth structures and 200 mm for hard structures, and peak basin water level to be lower than the lowest kerb
invert level in the catchment area. Council will also expect the Design Engineer to ensure that:
• the peak water level in the retarding basin resulting from the minor drainage storm event detailed in Table 12 remain
below the invert of the lowest inlet pipe discharging to the basin; and
• the overland flow path for a major storm has been designed with no minor system contribution to flow capacity; and
• for storage calculations, the volume of storage in pits and pipes in the minor system has been ignored.
Council will expect any inlet pipe to the basin to be fitted with a headwall designed to allow debris to escape and to impede
the entry of children or animals, and all headwalls to be fitted with an acceptable post and rail barrier to prevent falls and
to identify their location.
The minimum depth of overland flow must be designed so that it is no higher than 300mm below the lowest floor level of
any dwelling impacted by the overflow.
In such circumstances, Council will expect the Design Engineer to ensure that retardation basins have an impervious
lining, or other acceptable treatment, to prevent the ingress of groundwater, and that any structures which penetrate the
groundwater zone, such as footings and drainage lines, are appropriately treated to prevent possible damage caused by
extended contact with groundwater.
Groundwater may be able to be extracted and used, subject to the requirements of the relevant authority.
If the use of the land changes from that of agricultural production, any former grants for subsoil/groundwater pumps may
be required to be refunded. Any development that does not retain an irrigation right will be required to finalise any
outstanding debts or annual maintenance charges for ground water pumps. Council will not accept any future charges in
this regard unless prior written agreement has been obtained
The depth of all retardation basins with public access will be determined having regard to the safety of persons who may
fall into or enter the basin during times of operation. To allow for this possibility, inside batters should have a maximum
slope of 1:8, which will determine the maximum practicable depth of many basins.
• soil type.
• erosion.
• maintenance.
• safety and minimisation of risk.
To ensure that maintenance of any portion of the basin and its associated works can be safely carried out, a 5m wide
reserve should be provided around the perimeter of any retardation basin, unless the Council has given prior written
consent for alternative arrangements.
Additionally, if the retardation basin poses a high risk when assessed using the Australian National Committee on Large
Dams (ANCOLD) guidelines then Council will expect that the structure will be designed, and the construction to be
supervised and approved, by a qualified engineer with specific expertise in the field.
The Design Engineer will be responsible for deciding on the action required in response to the risk assessment report
and its recommendations, but should consult with Council if the recommendations are complicated, require community
involvement, or may involve significant ongoing maintenance issues.
Council will expect the Design Engineer to include a copy of the risk assessment report, with recommendations and
associated works, when submitting the detailed design documentation for review and approval.
Where the risk assessment determines that the retardation basin complex should be securely fenced, Council will expect
a 1.8m high chain-mesh fence to be installed around the entire perimeter, with access for maintenance purposes being by
lockable gates.
18.4.11 Landscaping
Council will expect the Design Engineer to submit a detailed landscape plan for all retardation basins for acceptance.
18.4.12 Maintenance
Council will expect a heavy duty grate or cover to be provided for each pit located in the wheel path of vehicles. In other
circumstances, light duty grates and covers may be sufficient. Access covers and grates should be designed to facilitate
the use of a lifting system acceptable to Council.
Council will expect any large pipe inlets into the basin to be grated in a satisfactory manner to prevent entry. The grates
should be designed so that they can easily be maintained and will not cause blockages during storm events. Pits, pipes
and screens that require regular cleaning and maintenance should be readily accessible, with the geometry of openings
allowing for cleaning and removal of debris and silt accumulations.
• To ensure that the capacity of existing drainage Infrastructure is not exceeded as a result of Developments that
increase the volumes and peak rates of stormwater runoff beyond the capacities for which the Infrastructure was
originally designed;
• To ensure that the cumulative impact of future Developments will not exceed the capacity of the existing drainage
system;
• To reduce total stormwater volumes and peak flows from urban and rural Developments into receiving waters;
• To minimise the development costs of drainage Infrastructure by reducing peak outflows
• To ensure that on-site detention systems can be effectively maintained by landowners and provide a cost effective
method of meeting the other objectives of this section.
19.2 General
19.2.1 Types of Developments requiring on-site detention
The following types of development typically require on-site detention:
• Multi-unit development in newer residential areas where no specific provision for such development was made in the
design of the drainage system for these areas.
• Multi-unit development in older residential areas where the drainage system was designed to handle a peak discharge
significantly lower than that predicted by applying the runoff coefficients defined in Clause 16 to a 20% AEP event.
• Industrial development in areas where the drainage system was designed to handle a peak discharge significantly
lower than that that predicted by applying the runoff coefficients defined in Clause 16 to a 10% AEP event
• Major commercial development in areas where the drainage system was designed to handle a peak discharge
significantly lower than that predicted by applying the runoff coefficients defined in Clause 16 to a 5% AEP event.
• Low-density residential development within or adjacent to urban or rural township areas.
• On-site detention will not usually be required in rural locations when lot sizes exceed 2ha, unless specific measures
are required to protect streams or constructed waterways from erosion associated with increased peak flow rates.
19.2.2 Methodology
This Manual provides a simplified method for Design Engineers, builders and owners to estimate the requirements for
on-site detention to limit discharges into the existing drainage system to the actual capacity of that system. Note that
specific calculations carried out by a Qualified Civil Engineer will be required when the peak discharge rates nominated
by Council differ significantly from those assumed in the simplified method.
The primary objective of this section is to ensure that existing minor drainage networks continue to meet current needs
and expectations as more intensive development takes place. Situations will also arise in which the impact of a proposed
development on major drainage networks should be considered. Unless flooding problems are already evident, the basic
principle should be to limit the peak outflow from any site in a 1% AEP rainfall event to pre-development levels. The volume
of on-site storage required to achieve that outcome may be greater than that required to ensure that the capacity of the
minor drainage network is not exceeded. Council will expect the relevant designs and calculations to be prepared by a
Qualified Civil Engineer and submitted for review and approved by Council’s Engineering Department.
VERSION 5.30 Page 129 of 275
19.3 Requirements
19.3.1 General Requirements
Where on-site detention is required in order to discharge into the existing drainage system, Council will expect the Design
Engineer to provide computations that demonstrate how the permissible rate of discharge and the volume of on-site
detention required have been determined and show that the existing drainage system will not be adversely impacted by
the Development.
Where the development site in question discharges to an established minor drainage network, Council will expect the
permissible site discharge [PSD] to be based on the actual network design capacity rather than the peak discharge prior
to development.
The basic principle behind on-site detention is that, unless there are particular reasons to believe the contrary to be the
case, and Council has declared a specific PSD for the development, the original drainage network design should be
assumed by the Designer to have been carried out properly by the standards of the time. Where, as is often the case in
established urban areas, the site and the upstream catchment are relatively small in extent and uniform in character, the
rational method should be used to calculate a site PSD based on the rainfall intensity at the design recurrence interval and
the concentration time (Tc) for the upstream catchment. The reason for using the catchment, rather than site, concentration
time is that the former time would have governed the original site discharge on which the network design was based.
Most methods for determining the storage volume needed to achieve a calculated or specified PSD assume that the
relevant rainfall event can be represented by a symmetrical triangular (trapezoidal when the event duration exceeds double
the concentration time) site discharge hydrograph. The modified rational method allows for the discharge fall time to exceed
the initial rise time, and delivers a somewhat more conservative assessment of required storage.
Under the Boyd Method, when a storage device is drained under gravity via a control mechanism, the outflow is assumed
to increase in a linear manner from zero at the start of the event until the discharge entering the device, after reaching and
passing the peak value, decreases to the PSD. The required storage is then taken to be equal to the difference between
the overall volumes flowing into and out of the device during that period. Similar considerations apply to pump drawdown,
save that the outflow remains constant over the time interval between the inflow initially reaching the PSD and then, after
reaching and passing the peak, decreasing again to the PSD.
With certain adjustments, methods based on these assumptions are appropriate for developments up to ~5ha in area, and
upstream catchments to ~50ha in area. Beyond these limits, volumetric runoff-routing methods should be used. Within the
above limits, however, the main errors in the procedure arise from the assumption that the storage drawdown rates under
gravity increase linearly with time. The actual relationships between head and discharge, and between head and device
capacity, are markedly nonlinear. When a linear response has been assumed, a better estimate of the required storage
volume is achieved by reducing the nominal PSD by 25% for storage in tanks or basins whose plan shape is basically
constant with increasing depth, or 40% for storage in pipes or horizontal cylindrical tanks. A better approach, however, is
to use the Swinburne Method, which makes soundly-based adjustments to compensate for both the above nonlinearities.
When the development location so requires, or when the existing drainage infrastructure is known to be unable to accept
the peak discharge flows estimated by the rational or modified rational method, Council’s Engineering Department may
specify the permissible site discharge and/or may require that the Design Engineer carry out specific calculations to
establish the appropriate storage volume for any Development.
• The original design event should be assumed to have been based on a 1EY (1-year) event.
• Annual exceedance probability for the current design event see Section 16.6 of this Manual
• Coefficients of runoff see Section 16.7 of this Manual
For the reasons set out in Clause 16.5 of this Manual, the AEP terminology recommended by Australian Rainfall and
Runoff has been adopted to describe events with an average return period greater than or equal to one year, and reference
should be had to Table 8 as required to confirm the equivalence between these measures.
The provisions of this sub-clause only apply to residential, industrial or commercial developments where the total site area
does not exceed ~1ha, and where the permissible site discharge has not been specified by Council.
Table 13 provides guidance on the allowable discharge rates and storage volumes for the most common types of small
Developments within the ambit of this sub-clause taking place within municipalities across regional Victoria.
Table 13 Storage Volumes and Discharge Rates for Small Detention Systems
STORAGE REQUIRED
ALLOWABLE (litres/ m2)
ORIGINAL AND
DISCHARGE
TYPE OF DEVELOPMENT REQUIRED DESIGN VERTICAL HORIZONT
RATE
PARAMETERS (Tank/ AL (Pipe)
(litres/sec/ha)
Basin)
The storage requirements in any given case should be calculated having regard to the proportion of the stormwater runoff
from the developed site to be directed to each category of storage device. For example, for a multi-unit development on a
750m2 site in an older area, if 60% of the total runoff can be directed to conventional rainwater tanks and 40% has to be
directed to underground pipes, the table would require that the following storage volumes be provided:
The allowable discharge rates set out above have been calculated based on a concentration time of 20 minutes for the
upstream catchment served by the relevant minor drainage network, and reflecting the rainfall intensity assumed when the
latter network was originally designed. The Swinburne Method has been applied to determine the required on-site storage
volume.
Council’s Engineering Department may waive the requirement for on-site detention where it can be shown that there
are no adverse impacts resulting from the increased rate and volume of stormwater from the development and that the
level of service adopted by the Council will not be compromised.
Where stormwater discharge is to be controlled by an orifice or tube located on the downstream face of a pit, Council will
expect the Design Engineer to consider and address the consequences of device blockage in a design storm. Options
might include providing a safe overland route conveying surplus flows from the location where the detention system will
surcharge to an acceptable destination, installing sufficient storage to retain the flows on-site, or using dual-chamber pits
with the controlled flow passing through an internal weir wall.
Any overflows should be directed away from buildings, adjoining properties and associated Infrastructure, and Council
will expect the Design Engineer to demonstrate that the maximum water surface level will remain at least 300mm below
the lowest floor level of any residence within the overflow zone.
Council will expect the Design Engineer to ensure that all pipes conveying water within a detention system are at least
90mm in diameter, unless they form part of a proprietary system acceptable to Council, or contribute directly to the
restriction required to achieve the design PSD.
When specific calculations are carried out, Council will expect the Design Engineer to estimate the concentration times
for the relevant catchment and from the top of the catchment to the development site using recognised methods, and to
submit the following additional information for review and approval:
• Plans showing the invert levels of all pipes at or above 100mm in diameter.
• Plans showing the designed finished surface level of all driveways, car parking areas, landscaping areas and lawns.
• Plans showing the floor levels of all buildings, existing or proposed.
• Plans showing the locations of storage devices, pipes and pits, pervious and impervious areas, buildings, driveways
and other relevant infrastructure.
• Evidence that, when the detention system relies on surface storage, all floor levels in habitable buildings will be at least
300 mm above the peak water level in the storage area at design capacity.
• Evidence that, where depressed driveways are used to provide storage, they are bounded by kerbs not less than 100
mm in width, cast integrally with the main slab unless otherwise agreed by Council.
• Cross-sections of each storage device or devices.
• Existing surface levels on at least a 10 metre grid in the subject property and adjoining properties.
• One copy of the drainage computations.
• One copy of the structural computations for any underground storage tanks.
Typical outflow control arrangements are for gravity drawdown to take place through a pipe (with no provision to vary the
flow capacity), an orifice plate, or a proprietary multi-cell unit. When a site is located below street level, and no network
drainage is available along the rear boundary, pumping may become the only viable option.
Council and the Developer may therefore enter a Section 173 Agreement binding future landowners to maintain their on-
site detention systems in satisfactory working condition, and to provide reasonable access to enable authorised Council
officers to inspect the systems. The Agreement may also require landowners to pay an annual inspection fee as set by
Council from time to time.
20.2 General
Council will expect all Developers to make provision for the improvement of water quality leaving the Development site
by works located close to the nominated point of discharge for the Development. The Developer is responsible for the
maintenance of all completed water sensitive urban design (WSUD) works for a period of two (2) years unless otherwise
agreed in writing or specified in the planning permit. The maintenance period shall commence on the date of Council’s
Acceptance of Works for the WSUD works. A record of the inspection and maintenance works undertaken are to be
provided to Council on a regular basis to the satisfaction of Council..
All urban Developments should meet the requirements of the Urban Stormwater Best Practice Environmental
Management Guidelines 1999, the Water Sensitive Urban Design Engineering Procedures 2005 and the Water Sensitive
Urban Design Guidelines South Eastern Councils 2011 prepared by Melbourne Water.
The storm-water treatment methods which may be considered, subject to Council agreement, include:
• Bioretention swales.
• Bioretention basins.
• Vegetated swales.
• Underground sand filters.
• Sedimentation basins.
• Constructed wetlands.
• Pond system with edge vegetation.
• Water tanks.
• Gross pollutant traps.
• Litter traps.
Council will expect the Design Engineer to develop appropriate strategies for addressing these goals, and may require
that land be set aside and works constructed within a Development or subdivision for the specific purpose of treating
stormwater to ensure appropriate water quality at the point of discharge into the receiving waters.
VERSION 5.30 Page 134 of 275
The Design Engineer may be required by Council to demonstrate to Council that the proposed method of treatment is
the most cost-effective and sustainable for Council having regard to the whole of life costs of the treatment elements.
Melbourne Water publication “Water Sensitive Urban Design Life Cycle Costing Data” can assist the Design Engineer to
determine the maintenance and renewal costs of the various elements of stormwater treatment.
20.3 Requirements
20.3.1 General Requirements
The following are general requirements for the provision of stormwater treatment:
• Developments should comply with principles and recommendations of Water Sensitive Urban Design Guidelines
2009, Urban Stormwater – Best Practice Environmental Management Guidelines and Council’s Stormwater
Management Plans to achieve the following water quality standards:
o 80% retention of the typical urban annual load for Total Suspended Solids (TSS).
o 45% retention of the typical urban annual load for Total Phosphorus (TP).
o 45% retention of the typical urban annual load for Total Nitrogen (TN).
o 70% retention of the typical urban annual load for gross pollutants (litter).
• Discharges for a 50%AEP should be maintained at pre-development levels for stormwater treatments.
• Council will expect the Design Engineer to select the most suitable treatment types for the Development, and to
submit designs for review and approval by Council’s Engineering Department demonstrating that Council
standards for maintenance, ongoing costs, and stormwater quality can be achieved.
• Where Council has constructed whole-of-catchment treatment facilities, Developers of industrial estates within such
catchments will be required to contribute to treatment costs within those facilities, and may also need to install pre-
treatment facilities in those estates in accordance with the requirements of Council’s Stormwater Management Plan.
Where whole-of-catchment treatment is not available, Council will expect Developers to provide separate treatment
facilities within the Development.
• Council will expect the Design Engineer to consider the staging and construction of Developments. Treatment
facilities should normally be commissioned only when sufficient runoff is available to keep plants alive, and Council
may bond the value of the plantings in preference to have planting proceed at an inappropriate time.
• Council will expect the Design Engineer to ensure that cleaning and maintenance of structures and equipment
associated with stormwater treatment can be achieved without manual handling, and that routine maintenance does
not require access to confined spaces.
• Council will expect the Design Engineer to undertake a full risk assessment for all treatment sites, taking into
account fencing, grates across drains, wetlands, retarding basins, pumping stations, and other structures, and to
submit the assessment and recommendations for review and approval by Council’s Engineering Department.
• Council will expect the Developer’s Representative to submit comprehensive operational documentation and
manuals for treatment sites prior to the commencement of Defects Liability Period.
• Where constructed wetlands are being provided to serve a staged development the Developer will be expected to
maintain the wetlands at his cost until the defects liability period is completed for the last stage of the development.
• Selecting a design flow rate will require the Design Engineer to balance the cost and space requirements of the
device (a higher design flow will usually require a larger facility with additional costs) and the volume of water that
could bypass the unit and avoid treatment. The minimum design flow should be that associated with a 4EY event.
Council will expect the Design Engineer to provide all-weather access to all treatment sites, permitting crane access
to GPT units, which should be assumed to require cleaning every six months. In new Developments or public areas,
Council will expect maintenance vehicles to be able to travel in a forward direction at all times.
• Council will expect the Design Engineer to ensure that the quality of the water being discharged will meet the
requirements of the relevant drainage authority, and to submit supporting evidence to Council’s Engineering
Department for review and approval.
• Water ponding at entry points to the swale should not occur for longer than 1 hour after the cessation of rainfall, as
prescribed in Clause 56.07-4 of the VPP.
• The design details should otherwise be in accordance with the guidelines set out in Chapter 6 (Clause 6.3) of the
Water Sensitive Urban Design Engineering Procedures: Stormwater Manual (Melbourne Water, 2005).
• Selection Table 20.3.4 provides details of the location and other criteria under which Councils will be prepared to
consider accepting bioretention basins and rain gardens as part of the stormwater treatment systems within the
municipalities concerned.
Permitted in Private Property Permitted in Nature Permitted Except in Unsuitable Not Permitted
and Drainage Reserves Strips Locations for Access, Under Any
Permanent Subsurface Flow Circumstances
Conditions, Etc.
Ararat Rural City Council Murrindindi Shire Ballarat City Council Horsham Rural
Council City Council
Baw Baw Shire Council Bass Coast Shire Council Latrobe City
Council
Mount Alexander Shire Council Mount Alexander Shire Greater Geelong City Council
Council
• Swales are most efficient when longitudinal grades are between 1% and 4%. Flatter grades tend to cause swales to
become waterlogged and/or have stagnant pooling, while steeper grades may lead to high velocities, with potential
risks of erosion and damage to vegetation. Check banks (small porous walls) may be constructed to distribute flows
evenly across the swale.
• Batter slopes are typically 1:9. Grassed swales requiring mowing should have batter slopes less than 1:4.
• The design details should otherwise be in accordance with the guidelines set out in Chapter 8 (Clause 8.3) of the
Water Sensitive Urban Design Engineering Procedures: Stormwater Manual (Melbourne Water, 2005).
• Subject to road reserve width and service locations, Councils other than those identified in Selection Table 20.3.5
will consider approving vegetated swales, grassed swales and buffer strips for use in open space reserves within
normal or low-density residential zones and/or in central median strips on roads.
• Selection Table 20.3.5 also provides details of the circumstances under which Councils will be prepared to consider
accepting vegetated swales, grassed swales and buffer strips located within nature strips as part of the stormwater
treatment systems within the municipalities concerned.
21.2 General
Since drainage systems have been designed to different design standards and Developments have taken place that have
increased the volume and rate of stormwater runoff beyond the levels for which the existing drainage networks were
designed, the impact of new Developments on the existing drainage systems should be assessed prior to allowing them
to discharge directly into these networks.
Council will be concerned to ensure that more frequent flooding does not occur and that existing drainage problems are
not increased as a result of new Developments.
Council may need to determine the impact of new Developments on existing drainage systems prior to determining the
legal point of discharge. The impact will need to be assessed from both volumetric and rate of flow perspectives.
Where a Development is likely to cause increased flooding frequency or extent, Council will determine what works are
necessary for a particular location within a drainage network to become the nominated point of discharge.
21.3 Requirements
Council will expect the Design Engineer to obtain drainage rights and/or easements from all downstream owners who
may be affected by the discharge of stormwater wherever the point of discharge is not to either a Council-owned drain or
a natural watercourse.
Applications for nomination of point of discharge for dwellings should include the following information:
• Plan showing the proposed development including the pervious and impervious areas.
• Existing and proposed surface levels at an interval not exceeding 10m.
Applications for nomination of point of discharge for other Developments should include the following information:
• Plan showing the proposed development including the pervious and impervious areas.
• Existing and proposed surface levels at an interval not exceeding 10m.
• Description of the proposed development.
• Locality plan showing the development location and catchment boundaries.
• Location and size of existing drains and easements and reserves within and adjacent to the development.
Where Council determines that a Development is likely to adversely impact the existing drainage system, Council will
expect the Design Engineer to provide further plans and computations to identify the works necessary to minimise the
impact of the Development on the existing drainage network, and to submit these plans to Council’s Engineering
Department for review and approval. The works may include on-site detention designed in accordance with the provisions
of Clause 19 of this Manual.
22.2 General
Council will expect the Construction Engineer and Contractors engaged by the Developer to ensure that all practical
steps are taken during the construction of works to minimise any detrimental impact on the environment.
Council will expect all earthworks to be undertaken in accordance with the provisions of Australian Standard AS3798-
2007 Guidelines on Earthworks for Commercial and Residential Developments.
Subdivision access points should to be kept to a minimum to minimize the number of areas required for stabilization and
vehicle cleaning, and sections of road targeted for cleaning in the event that mud is accidentally conveyed from the site.
Soil movement at subdivision access and exit points should be controlled by using a rumble grid or by requiring vehicles
to travel the length of a stabilised access track. All machinery should be prevented from accessing non-essential parts of
the site.
In accordance with EPA Publication 960, batter slopes should be no steeper than 2:1, be finished as soon as possible with
at least 75mm of weed-free topsoil, either topped with weed mat or mulch or hydro-seeded, to establish vegetation such
as suitable grass species and ensure that erosion is minimised.
All boundaries between the Development and public land should be protected and maintained with adequate sediment
control measures as soon as is practicable upon completion of works.
22.5 Pollution
Council will expect the Design Engineer to prepare Environmental Management Plans addressing all possible sources
of pollution and methods of control, and to submit these plans to Council’s Engineering Department for review and
approval.
22.6 Noise
Council will expect the Construction Engineer to ensure that noise emitted from the site remains at all times within the
specified limits set by the EPA for the relevant activity.
The applicable EPA policies and guidelines are available from the EPA website.
Should Council receive a complaint from the public relating to noise generated from the site, Council will expect the
Construction Engineer immediately to arrange for independent noise testing to be undertaken, and to submit the results
of that testing to Council’s Engineering Department for consideration.
Depending on the nature of the development and the location of the site, Council may require the Construction Engineer
to silence or replace particular items of equipment, install noise attenuation buffers or barriers, and/or create a buffer zone,
before construction works resume.
• Council Infrastructure is not adversely impacted by the implementation of the whole farm plan; and
• property accesses are provided at appropriate locations and constructed to appropriate standards; and
• appropriate stormwater management measures are in place to avoid adverse impacts on other properties.
Council’s Planning Departments are obliged to ensure that any certification of Whole Farm Plans is appropriate, and
will therefore refer applications to other relevant authorities, whose requirements are included in the application form.
23.2 Requirements
The requirements for Whole Farm Plans are that:
24.2 General
Council expects the Developer to prepare landscape plans and submit them to the relevant Council Department for review
and approval for the following types of Developments:
• Land vested in Council, including road reserves, Public Open Space, and drainage reserves.
• Multi-unit Developments, Commercial Developments, Industrial Developments and other types of development as
per the requirements of any planning permit issued for that development.
• Development Plans for an area. (Concept plans only).
Landscaping plans should reference applicable Structure Plans, Open Space Strategies and Play Space Strategies.
Council expects that landscaping works will not commence until full landscaping plans, documenting and addressing
design, construction and maintenance issues, have been submitted to and approved by Council Department.
The definitions for local, large and district parks are found in section 56.05-2 of The Planning Scheme.
Council will expect Public Open Space as per the requirements of the Planning Scheme and in accordance with any
relevant Public Open Space / Playground Strategy and to be consulted to determine their specific requirements in relation
to this section. Landscaping Plans should normally be submitted with Engineering Plans for the relevant stage.
Playgrounds should be provided in Public Open Space as per the requirements of individual Council strategic plans.
VERSION 5.30 Page 148 of 275
24.2.1 Councils Landscaping Design Manuals
The following Councils have specific Landscape Design Manuals that take precedence over these guidelines.
The submitted landscape plan is to address the matters listed in Table 14 Residential Developments Design Requirements
• http://www.police.vic.gov.au/
Use of ‘best practice’ in water sensitive urban Council will expect the Design
Irrigation design (WSUD) Engineer to consider storm
water retention for irrigation
http://wsud.melbournewater.com.au/ purposes, and to submit the
• http://www.wsud.org/ design plans for irrigation
systems to Council for review
and approval.
Trees (park and street) Tree selection should consider The location of street trees
should be in accordance with the
• Scale Code of Practice – Management
• Longevity of Infrastructure in Road
• Neighbourhood character Reserves.
• Soil type and available volume
• Existing or proposed nearby To avoid future conflicts and to
infrastructure allow servicing, consideration
VERSION 5.30 Page 150 of 275
Element Design Requirements Comments
• Maintenance requirements should be given to planting
• Biodiversity distances from other
• Climate change impact infrastructure.
Heritage The preservation and integration of heritage Design and development that
elements respects the individual site, the
local context and the regional
characteristics are encouraged
Remnant Vegetation The retention of existing high quality vegetation A management plan for any
remnant vegetation should be
The use of indigenous plants in close proximity developed as part of any
to a Nature or Bush land Reserve development
Public art Any proposal for the installation of public art Council will expect a clear prior
must comply with relevant Council policies agreement to be in place on the
ownership of and maintenance
responsibilities for this art.
Heritage The preservation and integration of heritage Design and development that
elements respects the individual site, the
local context and the regional
characteristics are encouraged.
The submitted landscape plan is to address the requirements for the relevant type of Development as described in Clause
24.3.1 or 24.3.2.
• In most cases, where land will be subdivided into more than 16 lots, the development will be required to meet the
objectives and standards set out in Clause 56 of the Planning Scheme, and the provision of open space may be
required to exceed 5% of the total developed area.
• Council will expect any requirements specified in the schedule to Clause 52.01 to be satisfied. If no such
requirements are specified, the requirements of the Subdivision Act 1988 will apply.
Council will require Developers to satisfy the requirements of clause 56.05-2 of the relevant planning scheme and in
particular Standard C13. The provision of Public Open Space should thus, at a minimum, include:
• Active open space of at least 8 hectares in area within 1 kilometre of 95% of all dwellings that is:
o suitably dimensioned and designed to provide for the intended use, together with buffer areas around sporting
fields and passive open space; and
o able to incorporate two football/cricket ovals; and
o appropriate for the intended use in terms of quality and orientation; and
o located on flat land (which can be cost-effectively graded); and
o has access to, or can make provision for, a recycled or sustainable water supply; and
o adjoins schools and other community facilities where practical; and
o designed to achieve sharing of space between sports.
• Linear parks and trails along waterways, vegetation corridors and road reserves should be located within 1 kilometre
of 95% of all dwellings
• Local parks should be located within 400 metres safe walking distance of at least 95% of all dwellings. Where not
designed to include active open space, local parks should be generally 1 hectare in area and be suitably dimensioned
and designed to provide for their intended use and to allow easy adaption in response to changing community
preferences.
For the purposes of this section, Council will expect the Developer, as part of an application for a planning permit or a
development plan, to prepare and submit a Public Open Space plan to Council for review and approval, together with a
report showing how the provisions of clause 56 of the relevant planning scheme and the specific requirements of this
Manual are to be satisfied.
• The location of existing Public Open Space within 2 kilometres of the proposed development and the area of such
Public Open Space.
• How the proposed Public Open Space and any existing Public Open Space are linked.
• How the distance requirements of clause 56 for large and local parks are satisfied for properties to be developed.
• Details of landscaping.
Council will expect the report to show how the objectives and specific requirements for Public Open Space are satisfied,
and to include the specific landscaping specifications and details that are to be applied to the Public Open Space. This will
enable Council to estimate the future maintenance costs of the Public Open Space.
Where a contribution or amount of land is specified in the schedule to clause 52.01 of the relevant planning scheme, which
applies to residential, industrial or commercial Developments, Council will expect Developers to comply with these
requirements. When considerable areas of Public Open Space are being provided and developed as required by clause
56, Council may determine, in its sole discretion, that any Public Open Space requirement under clause 52.01 is satisfied.
If no contribution or amount of land is specified in the schedule to clause 52.01 of the relevant planning scheme, a Public
Open Space contribution may still be required under Section 18 of the Subdivision Act 1988. The Subdivision Act specifies
criteria for assessing whether Public Open Space may be required. A requirement under the Subdivision Act will generally
be relevant in circumstances where Public Open Space is not being provided as part of the subdivision pursuant to clause
56 of the relevant planning scheme.
Prior to construction, Council will expect the Developer to prepare and submit landscaping plans for review and approval.
These plans should provide the following information:
Prior to the Acceptance of Works, Council will expect the Developer to provide the following information:
• Management plans as required covering, for example, control of weeds and vermin for the site during the
Maintenance Period, and nominating the responsible contact person.
• Final irrigation design, including a detailed listing of all components and details of suppliers.
• Detailed listing of hard landscaping materials and equipment such as shelters, bin surrounds, seating, and
barbeques. including details of suppliers.
• Operations manuals and installation certificates for plumbing works, electrical installations, and similar works.
Elements in the approved landscape plan are to be maintained to an agreed standard by the Developer for a minimum
period of 24 months, including 2 summers, from Acceptance of Works, or other agreed period. Prior to the Acceptance
of Works, Council will expect the Developer to provide an asset list identifying manufacturers, models or style numbers.
Hard landscaping elements in the approved landscape plan are to be maintained to an agreed standard by the Developer
for a minimum period of 12 months.
The Defect Liability Period commences from the date of Acceptance of Works and extend for a minimum period of 24
months, including 2 summers, or other agreed period. Acceptance of Works for landscaping may not coincide with the
acceptance of civil works, and inspections will not be undertaken during the period from 30th November to 1st March in the
following year.
It requires protection zones be used to safeguard trees during the construction phase of Development. The figure below
shows indicative protection zones.
The following table is an indicative guide only, but can be used in assisting in the early design phase of the development.
Trunk Diameter - mm Tree Protection Zone (TPZ) Structural Root Zone (SRZ)
(Approx.)
(measured 1.4m above ground)
200 2.4m 1.7m
400 4.8m 2.2m
600 7.2m 2.7m
800 9.6m 3.0m
1000 12m 3.4m
The Structural Root Zone (SRZ) is a ‘No Go Zone’ and works that encroach into the SRZ will not be allowed. Sometimes,
Council does allow works to encroach into the Tree Protection Zone (TPZ), although this is dependent upon site specific
factors.
Where trees are proposed to be retained, Council will expect that the works proposed will not affect the long-term health
of the tree. In situations where Council does agree to the removal of a tree, offset replanting and the care of the newly
VERSION 5.30 Page 156 of 275
planted trees for two years. The number of replacement trees is based on the size, age, and type of tree being removed.
All works will normally be undertaken by Council or its approved contractors on the applicant’s behalf.
Vegetation of this nature deemed by the Council to be protected is to be fenced during construction. Fencing should be as
detailed in AS 4970-2009 Protection of trees on development sites
Generally, a 1200mm clear area should be maintained from the edge of seal or invert of kerb or edge of gravel. The
treatment for this area can be grass, groundcovers, or pavement, with selection being subject to Council agreement.
Where traffic volumes on the abutting road exceed 200vpd or the speed is greater than 50kph, Council will expect a
detailed risk assessment to be carried out to determine the appropriate clear zone and the risks to and the safety
requirements of employees maintaining these areas.
References for undertaking risk assessments include the Road Management Act 2004 Code of Practice Worksite Safety
– Traffic Management and AS1742.3 Manual of Uniform Traffic Control Devices Part 3: Traffic Control for Works on Roads.
1. Developers will supply, plant and maintain street trees, with the tree size and species being specified by Council,
and maintain the trees for 2 years, or until the Developer can demonstrate that the plantings have become
established.
2. Council may elect to supply, plant and maintain trees and accept defects responsibility for them, charging the
Developer a fee per tree.
Councils that require Councils that charge Councils that will negotiate
Developers to supply and Developers for the supply and with Developers for either
maintain Street Trees and maintenance of Street Trees. option
lodge maintenance bonds
Bass Coast Shire Council Horsham Rural City Council Latrobe City Council
Baw Baw Shire Council Wellington Shire Council South Gippsland Shire Council
Colac Otway Shire Council Warrnambool City Council
East Gippsland Shire Council
Greater Bendigo City Council
Greater Geelong City Council
Hepburn Shire Council
Mitchell Shire Council
Moira Shire Council
Surf Coast Shire Council
Where the Developer is required to undertake street tree planting, Council may agree to such planting being carried out
after the Acceptance of Civil Works and issue of the Statement of Compliance. Trees should not be planted during the
period from 30th November to 1st March in the following year.
Street trees should be provided on both sides of all roads and streets (excluding laneways) at regular intervals appropriate
to tree size at maturity in accordance with the guidance provided in Table 16 Street Tree Spacing unless otherwise agreed
by the Responsible Authority.
Council will expect species selection to ensure that, at maturity, the clear zone requirements, vertical and horizontal, will
comply with their adopted Road Management Plan.
No landscaping other than lawn is permitted on nature strips without Council consent. Council will expect the Developer,
when applying for such consent, to demonstrate that the product or material will:
• not result in increased public risk (e.g. stones on footpaths increase tripping hazard); and
• leave the nature strip in a state able to be used safely by pedestrians; and
• not be able to be easily removed or used for nuisance purposes; and
• contribute to a consistent neighbourhood landscaping approach; and
• be appropriate for the environment and be sustainable and easily maintained.
24.4.10 Soft Landscaping (refer to the Table 14 in clause 24.3.1 for further detail)
If edges to paths are required, Council will expect the Developer to seek prior approval for the design and materials of
the proposed edging system.
Additional Vic Roads Guidelines that may be used as reference documents are:
• Roadside Handbook – An Environmental Guide for Road Construction and Maintenance 2006
• Environmental Management
• Cultural Heritage
• Biodiversity
• All associated Infrastructure vested in the Council meets their requirements and standards as set out in this Manual.
• In accepting associated Infrastructure, Council will have regard to any future maintenance and operating costs, the
likely availability of replacement parts and conformity with any Council policy or strategy for example, in relation to
greenhouse emissions.
• The urban character and amenity of a locality, neighbourhood or development should not be adversely impacted by
the proposed associated in Infrastructure.
• The location of the proposed associated Infrastructure should not conflict with other existing or proposed services
and/or with Council Infrastructure.
• Council will consider the requirements of all servicing authorities before accepting any particular infrastructure item.
• The requirements of any relevant Codes of Practice, Australian Standard, regulation or act of parliament will be
considered by Council before accepting the type and location of any associated Infrastructure.
25.2 General
The design, documentation and installation of all related Infrastructure required to service the development should be in
accordance with the relevant Authority’s criteria, specifications and instructions.
25.3 Telecommunications
The design, documentation and installation of all related Infrastructure required to service the development should be in
accordance with the relevant Authority’s criteria, specifications and instructions.
Council will expect the Design Engineer to liaise with the authority responsible for telecommunications, and coordinate
design and construction of the required Infrastructure, in association with other works required for the Development.
25.4 Gas
The design, documentation and installation of all related Infrastructure required to service the development should be in
accordance with the relevant Authority criteria, specifications and instructions.
Council will expect the Design Engineer to liaise with the Authority responsible for gas Infrastructure, and coordinate
design and construction of the required Infrastructure, in association with other works required for the Development.
Council will expect the Design Engineer to liaise with the authority responsible for water and sewerage Infrastructure,
and coordinate the design and construction of the required Infrastructure, in association with other works required for the
Development.
VERSION 5.30 Page 160 of 275
Council will expect the Design Engineer to ensure that the location and spacing of fire hydrants and fire plugs should be
in accordance with the Country Fire Authority’s publication “Requirements for water supplies and access for subdivisions
in Residential 1 and 2 and Township Zones” (October 9, 2006) or as amended; and the marking of fire hydrants and fire
plugs should be in accordance with Fire Service Guidelines on “Identification of Street Hydrants for Firefighting Purposes”.
25.6 Electrical
The design, documentation and installation of all electrical Infrastructure required to service the development should be
in accordance with the Authority responsible for electrical, specifications and instructions.
Council will expect a power supply plan to be provided documenting the supply standard for each lot within Commercial
and Industrial Developments.
The power supply within any newly constructed road is to be provided in underground conduits. No overhead power is to
be constructed in a new road without the written consent of the Council.
Detailed requirements for public lighting are presented in Clause 26 of this Manual.
Emergency Markers can be located, but not be restricted to the following locations:
• Locations offering higher risk activities to the visitor, such as mountain bike riding, rock climbing, or abseiling;
• Walking trails and shared paths – Emergency Markers should be located at major trail heads, significant features, or
intersections. Emergency Markers on linear trails should be placed approximately every 500m;
• Water bodies, swimming holes, and beach, river or lake access & egress points;
• Piers and Jetties should have a marker at the beginning and end of the infrastructure. Emergency Markers may be
placed at intervals of 250 - 500m if the length of the asset warrants;
• Recreational playgrounds with no verifiable address points or visible naming convention e.g., a person could not see
the signage, describe with certainty the unique feature or the open space was that of a linear path, or large recreation
facility with multiple recreations uses, such as more than one oval, barbeque area, playgrounds.
Category V lighting is applicable on roads where the visual requirements of motorists are dominant, such as sub-arterial
roads. Category P lighting is applicable on roads (and other public outdoor areas) where the visual requirements of
pedestrians are dominant. These include local roads and outdoor shopping precincts.
Council will expect all public lighting to incorporate the use of energy efficient luminaires. Energy-efficient fluorescent-
tube devices, such as T5 units, have been widely used for this purpose, but many Councils now consider that LED units
represent a more cost-effective and environmentally responsible option.
Lighting installations for declared State Arterial Roads and associated intersections are subject to review and approved by
VicRoads as the responsible coordinating road authority. Copies of drawings should be submitted to Council for
assessment, with advice being forwarded to VicRoads prior to approval.
Allowance for pole locations should be made in all road reserves and offsets should be shown in ‘Service Location Tables’
on FLP’s and Road Construction Plans.
A minimum 800mm offset should be provided from back of kerb to pole for all roads with P category lighting, including
laneways and shared zones where kerbing is provided.
‘Easy Fit’ pole bases/foundations are required where maintenance access is restricted (e.g. in laneways, ‘paper roads’
and shared driveways).
With the exception of lighting in speed zones of 50 km/hr or less, frangible poles should be adopted for roads with V
category lighting in accordance with AS 1158 – Lighting for Roads and Public Places. The specific pole type (impact
absorbing or slip base) should be determined according to VicRoads standards and be nominated on the drawings.
Public lighting is required for all principal footpaths and bike paths within parks and reserves of any development. All
cabling for this purpose should be from a metered point of supply at the reserve boundary and Council will accept
In rural areas, low density and rural living Developments should, as a minimum, provide one light at intersections and one
at the end of the court bowl PRINCIPLE. This provision may be reduced for short cul-de-sacs where the Design Engineer
can demonstrate that lesser lighting provision will be sufficient.
The amount and type of lighting, including recommended light technical parameters, in any external public area, is driven
by three main considerations:
• The type and quantity of pedestrian and vehicular traffic in the area (to facilitate safe movement).
• The security risk of the area (to discourage illegal acts).
• The need to enhance the amenity of the area (to increase aesthetic appeal).
Council may determine the boundaries of a street lighting precinct within its urban area so as to have a consistent lighting
standard within that precinct.
The manufacture, type and model of the Decorative (non-standard) lighting should be determined after consultation with
the Developers/landowners within the boundaries of the precinct at the time the precinct boundaries are being determined.
Decorative (non-standard) lighting will only be accepted in identified precincts. Council will not accept the use of decorative
(non-standard) lighting in industrial estates.
Decorative or non-standard lighting, lamps and luminaires should comply with the Public Lighting Service Provider’s
technical requirements and be acceptable to Council.
Council will consider giving consent for the use of decorative (non-standard) lighting when subdivisions have a minimum
of 50 allotments and when the Developer has obtained written agreement from the relevant Public Lighting Service
Provider for:
• The street lighting design.
• The type of the decorative lighting Infrastructure and fittings.
• The applicability of the standard street lighting tariff.
The Public Lighting Services Provider will energise public lighting within the estate only after receiving written notification
from the Council that the proposed design has been accepted.
Unless otherwise specified, all new standard street lighting will be supplied from an underground supply. Overhead supply
will only be installed under exceptional circumstances and on a case by case basis, and will require specific approval by
the Public Lighting Service Provider.
• Supply all initial stock of poles, lamps, photo electric cells and other fittings.
• Arrange for and meet the cost of all installation to the satisfaction of the Council and the Public Lighting Service
Provider.
• Accept responsibility for all maintenance and replacement costs of poles and lanterns until the expiry of the defects
liability period where decorative lighting is erected.
Council will expect Developers to supply replacement damaged or non-operational poles or fittings within 48 hours from
notice given by Council to allow the Public Lighting Service Provider to arrange the required maintenance and replacement
works. After the defects liability period has concluded, the Developer may either continue to accept responsibility for
providing replacement poles and light fittings as required, or make a cash contribution to Council to cover the future
replacement and maintenance of the assets. The unit value of any such cash contribution will be based on the purchase
price of the poles and lanterns, including ballast, where applicable, applying at the date on which the Statement of
Compliance is issued. The total contribution will be based on the value of the number of lights and lanterns in Table 17:
11-20 10% of the total number of 20% of the total number of lights
lights provided in the provided in the subdivision.
subdivision.
21-50 7.5% of the total number of 15% of the total number of lights
lights provided in the provided in the subdivision.
subdivision.
11 plus 10% of the total number of 20% of the total number of street lights
street lights provided in the provided in the subdivision.
subdivision.
For any lighting type not previously accepted by Council, the Design Engineer should provide full information on the
proposed pole and lantern together with details of the current supply and delivery cost of a single unit and likely availability
into the future. Council will not normally accept items from a limited production line.
https://vpa-web.s3.amazonaws.com/wp-content/uploads/2016/07/GAA-Model-Permit-Conditions-Manual-FINAL-
November-2011.pdf
VERSION 5.30 Page 166 of 275 Appendix A: Model Conditions for Planning Permits
Appendix B: Engineering Acceptance Process for Developments
APPENDIX B: ENGINEERING ACCEPTANCE PROCESS FOR DEVELOPMENTS
VERSION 5.30 Page 167 of 275 Appendix B: Engineering Acceptance Process for Developments
Appendix C: Council Review Checklists
APPENDIX C: COUNCIL REVIEW CHECKLISTS
General
Is a lot layout provided with lots numbered and dimensioned, and reserves
clearly identified.
Is the Public Open Space provided in correct area? (should have been
identified at planning stage but re-check)
Street names are nominated. (Check with Planning Dept. and Asset Mgt
Dept. whether names okay and advise Design Engineer if not acceptable)
Estimated traffic volumes are shown on plans (check consistency with road
hierarchy?)
Plans show the total catchment area, nominated sub-catchment areas and
co-efficient of runoff for each sub-catchment, including allowance for
connection of adjoining properties outside development.
Associated Documents
Relevant PSM’s shown clearly on plans and protected from works (all layout
plans)
Natural Surface Levels are shown at all lot corners and major changes of
grade within the lots (all layout plans).
Check minimum grade across lot of 1 in 200 is achieved.
Check each lot has A discharge point nominated.
Does the design reflect recommendations within the Road Safety Audit that
were accepted by the Council?
Should garbage pads be provided for areas where service vehicles cannot
achieve reasonable access?
Are indented parking bays to be provided, and are they adequately designed
and documented?
Is the location and type of street lighting clearly documented and compatible
with engineering requirements?
Have public risk issues been identified and Risk Report provided? Does
design reflect recommendations? Does Council need to take further
actions? Some issues to consider include:
• Manholes in footpaths.
• Accessible headwalls.
• Electrical substations.
• Gantries.
• Assumptions reasonable?
QF
• Location.
• Design.
• Litter traps.
• Erosion protection.
Have the minimum clearances from the face of the pole been achieved:
800mm to back of kerb
1000mm from pram crossings and vehicle crossings
2500mm from a tree (preferably 4000mm)
300mm to any other asset
At least 5000mm from a side/front joint boundary if driveway position not
fixed
Have spacing tables been provided for the poles and lamps proposed to be
used?
Have frangible poles been used where the traffic speed limit is greater than
50km/hr?
Are there any conflicts with street sign blades? If so, consider having these
affixed to street light poles so as sign blades can be viewed from all
directions.
Have the streetlights been shown on the Road Cross-Section plans and
checked for other service conflicts including sufficient allowance for street
trees and pram crossing points?
Local roads should be designed in accordance category P and designed
using either category P4 and P5 lighting and should cover:
o Pathways for pedestrians or cyclists (i.e. footpaths)
o Public activity areas primarily for pedestrian use
o Connecting elements (i.e. steps, stairways, ramps, footbridges,
pedestrian ways, subways including associated ramps and
stairways)
o Outdoor car parks (i.e. parking spaces, aisles and circulation
roadways, including designated spaces for people with
disabilities or for prams).
Note 1: For an illustration of the road and area types involving all the public
lighting categories (both P and V), refer Figure 1.1 of AS/NZS 1158.3.1
General
Have all outstanding matters such as cost sharing, etc been finalised to the
satisfaction of Council?
__________________________________
Is final design approval granted for the proposed development?
General
Is the drainage overland flow path for 100 year ARI flows free of
obstructions?
__________________________________
Is there any objection to the issue of Statement of Compliance?
Commentary.
Check to see what background information is available and review the critical elements. Does Council have a plan
for this area? Check -
• Contours
• Flood Prone layer
• Environment Layer
• Planning zones and overlays
• Aerial Photos
• Abutting land use
• Access to the site
• Existing infrastructure, Water also Gas, Electricity and Telecom if possible / practical.
• Existing watercourses
Write a brief summary of the site putting the proposed development in context.
Roads
Hierarchy
Does the proposed hierarchy fit with the abutting road system?
Is appropriate provision made for access, through the proposal, to provide appropriate, legal access to abutting
land (cannot land lock abutting land)
Intersections
General
• Check linkages to major destinations – reserves, shopping centres, sporting areas etc
Car parking
• What major service conduits are there and where do they go –are they through public open space?
• Check where utilities cross each other and roads or drains – will levels be an issue?
Sewerage
Power
Gas
• Check existing bridges – are they adequate for the proposed traffic (Expected traffic loadings, widths -
including bike lane and footpaths)
• Check existing Intersections – are they adequate for proposed traffic
Water Management
• Does it need any of the Site Stormwater Management Plan (SSMP) reports – see checklist C5 Most will require
at least the Drainage Feasibility Report, may need Water Quality and Flooding reports.
Upstream Catchments
Infrastructure
•Are there any sensitive areas downstream – what effect has the changed flood regime on them?
Check flow rates and times of inundation.
• Are they protected in any way?
Within the development
Flood regime/modelling
• Check with the relevant CMA re their plans/requirements for the waterway
• What access is there to be to the waterway for recreation – what needs to be provided for those types of
recreation?
• What in–stream works are required – erosion control, safety, drainage outlets etc
• Can the waterway be developed further for recreation?
Ensure that a current stage is viable in the long term – whether or not future stages are developed
• Where it is necessary to use land in a future stage to make a current stage practical, ensure that Council has
rights over that land required - e.g.
o Turnarounds in future stages may need temporary easements
o Drainage discharges into future stages may need easements
• What happens if the developer “pulls-out”? Can what’s left operate in the short to medium term
VERSION 5.30 Page 184 of 275 Appendix C: Council Review Checklists
Adjacent development
Write a report to the Planning Unit summarising the findings of the assessment under each of the above headings
and concluding the report with the statement that the Engineering Design Services OBJECTS / HAS NO
OBJECTION to the proposed Planning Scheme Amendment.
NUMBER OF PLANS IN
SET
Write a summary statement on the adequacy of the information provided and identify any additional
information requirements.
Does the proposed hierarchy fit with the abutting road system?
Is appropriate provision made for access, through the proposal, to provide appropriate, legal
access to abutting land (cannot land lock abutting land)
Are the proposed cross sections of the various types of roads consistent with the IDM?
Are the assumptions for traffic generation and estimated flows reasonable?
Has VicRoads been consulted in relation to any arterial roads and of so have their concerns
been addressed?
Has emergency services vehicles and service vehicles needs been adequately addressed?
Has the adequacy of the existing road network and associated infrastructure been considered
for the proposed increase in traffic?
Existing bridges – are they adequate for the proposed traffic (Expected traffic loadings, widths -
including bike lane and footpaths)?
Existing Intersections – are they adequate for proposed traffic?
Existing Roads – are they adequate in width, surface type and capacity?
List any upgrade works required below:
If the existing road network and associated infrastructure need to be upgraded has the issue of
who pays for the works been adequately and fairly addressed?
Provision for utilities – can the proposed road cross sections accommodate all the services
required to service the development?
Has the provision of street trees been adequately considered in relation to the proposed service
locations?
Check footway, cycleways and shared paths linkages to major destinations – reserves, shopping
centres, sporting areas etc.
Check that proposed footpaths, cycleways and shared paths are consistent with relevant Council
strategies and plans.
Check the impact of staging on the existing roads, pedestrian and cycling networks.
In times of flooding do other catchments overtop and flow into the upstream catchment?
Will the existing downstream infrastructure cope with the new flows?
Are the landscaping and streetscaping proposals for the development reasonable?
Does the proposal show the location and spacing of street trees and how does this impact on
the provision of utility services?
Identify works within stages that impact on other stages and check whether this has been
addressed.
Summary of Assessment
CHECKED BY
Has evidence been provided that Council has supplied the Legal Point of
Discharge?
Has evidence been provided that Council advised where the connection point to
Council drainage system is located (note this is different to the Legal Point of
Discharge)?
Has evidence been provided that the person carrying out the drainage design is
qualified to do so in accordance with the provisions of the IDM?
Has evidence been provided that Council advised what AEP the drainage
network servicing the development has been designed for?
Do the plans show surface levels to AHD and finished floor levels and proposed
driveways?
Do the plans show the Council drainage network servicing the property?
Have computations been included with the plans submitted for approval?
If so, is it reasonable?
Is it reasonable?
In the case of rainwater tanks is the outlet size reasonable or could it be made
larger by reducing the height of the tank and increase its width?
Does the drainage design include devices to reduce blockages in orifice?
Have bike safe grated pit lids been specified for all pits in trafficable areas?
Have pits for surface water collection been provided in the backyard and other
low areas of proposed new development site?
Do the plans include a note stating that all pits and pipes must be in accordance
with the IDM and any relevant Australian Standards?
Have internal overland flow paths for a 1% AEP storm event shown on plan?
Has Music model or Melbourne Water Storm report calculations been provided
when stormwater treatment is required for the development?
VERSION 5.30 Page 195 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
DESIGN ENGINEER’S CHECKLIST #D1 –REQUEST FOR FUNCTIONAL LAYOUT APPROVAL
DEVELOPER’S NUMBER OF
REPRESENTATIVE PLANS IN SET
CHECKLIST #D1
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
General
Is the design is in accordance with the planning permit conditions and the
endorsed plan?
Do other planning permits affect this development? (if yes, list permit numbers)
Has consultation taken place with all relevant authorities? If yes, list the
authorities below.(attach separate list if necessary).
Has consultation has taken place with all relevant landowners and affected
persons? List those consulted below (attach separate list if necessary).
VERSION 5.30 Page 196 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D1
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Do the plans clearly show allotment layout, with allotments numbered and
dimensioned, reserves clearly identified and proposed easements shown?
Are estimated traffic volumes shown on plans (for each stage of any staged
developments).
VERSION 5.30 Page 197 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D1
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Have public transport, including DOT, requirements been reflected in the road
widths?
Has local area traffic management been considered and reflected in proposed
designs?
Has the total catchment area has been identified and shown?
VERSION 5.30 Page 198 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D1
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Has the overland flow path/s been nominated and approximate depth of flow
shown?
Associated Documents
Has a Traffic Management Report been prepared and does it accompany this
submission?
Has any deviations between the proposed design and the recommendations
within the Traffic Management Report been noted on the plan?
Has the need for Developer contributions or headworks charges been identified
and a preliminary cost-sharing proposal to Council for early consideration been
supplied?
The plans provided with this submission for approval of functional layout have been prepared in accordance with the
relevant sections of the Council’s Manual. All of the above checklist items have been initialled as correct and complete, or
marked N/A (not applicable) as appropriate.
Signed Dated
VERSION 5.30 Page 199 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
DESIGN ENGINEER’S CHECKLIST #D2 – REQUEST FOR DETAILED DESIGN APPROVAL
DEVELOPER’S NUMBER OF
REPRESENTATIVE PLANS IN SET
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Is the detailed design in accordance with the planning permit conditions and the
endorsed plan, and has the physical design features been incorporated on
construction plans.
Has the Plan of Subdivision has been certified at the time of this submission?
Are the easement locations and widths in accordance with certified plan?
Has protection of water bodies and waterways been considered and requirements
are documented?
Have the necessary consents been obtained from other service authorities? List
consents received below:
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Is the north arrow shown on all layout plans and detailed plans (should be shown up
or to left).
Are all dams, wells, depressions and watercourses and fill requirements identified?
Are existing trees shown? Does the design attempt to retain trees?
Is existing native vegetation shown and suitably specified? Does design attempt to
retain significant native vegetation?
Are all required service conduit locations are indicated on the plans?
Are shared paths minimum width of 2.5 m, and is their location clearly shown?
VERSION 5.30 Page 201 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Have all turning movements been checked and intersections designed accordingly?
Are the locations and type of all new signage complying with the Australian Standards
shown on plans?.
Are the locations and type of all linemarking complying with Australian Standards
shown on plans?
Are traffic calming devices designed and documented in accordance with AustRoads
“Guide to Road Design” and any VicRoads supplement to those guidelines, with the
Manual, and with the accepted functional layout plan?
Does the limit of works of roads include temporary turning area if required?
Has the necessary ‘No Road’ signage or hazard markers been provided?
VERSION 5.30 Page 202 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Have levels been checked by Design Engineer, do they comply with Manual, and
match into existing surfaces?
Are design surface profile and levels shown at left and right back of kerb (including
high and low points)?
Have grades been checked by Design Engineer, and do they comply with Manual,
and match into existing grades.
Min. grade
= % Max. grade
= % Match existing?
Have levels and grades given on long sections been checked by the Design
Engineer?
Is the minimum length of vertical curve for >1% grade change, 15 m (except on kerb
returns).
Does the external road grading for future stages extend a minimum of 100 metres
beyond the limit of works?
Does the vertical curves and longitudinal grades provide satisfactory sight distances
for standard roads, particularly at intersections?
Has the coordination of vertical and horizontal curves provided a desirable design
outcome?
VERSION 5.30 Page 203 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Road Cross-Sections
Has the Design Engineer checked that cross-sections agree with longitudinal
sections?
• Back of kerb?
• Lip of kerb?
• Crown?
• Property lines?
• Front of footpath?
Are all pavement, nature strip, footpath and batter crossfalls in accordance with the
Manual?
Are profile and geometry of design surface grades shown as % or 1 in X and comply
with Manual requirements?
Are details of road pavement construction, including materials, compaction and type
of seal shown?
Are details of footpath construction, including materials, compaction and seal shown,
or is the relevant standard drawing noted?
VERSION 5.30 Page 204 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Do tangent point levels and chainages align with longitudinal and cross sections?
Are set-out details shown including angle, radii and tangent points?
Has the Design Engineer checked that drainage design in accordance with AR&R?
Are finished surface levels shown where the natural surface is altered?
VERSION 5.30 Page 205 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Do plans show layout of proposed drainage systems with offset from property
boundaries?
For all non-concrete pipes is there a note on the plan stating that all bedding, laying,
jointing and backfilling is to be in accordance with manufacturer’s specifications?
Is the kerb and channel and footpath depressed where the overland flow path leaves
the road pavement?
Are pits at appropriate locations (e.g. away from kerb returns, vehicle crossings, kerb
crossings etc.)?
VERSION 5.30 Page 206 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Are existing fences, buildings, trees and obstructions shown in path of overland
flows?
Are all proposed fences, buildings, trees and obstructions shown in path of overland
flows?
Are existing or proposed open earth drains, dams, watercourses, boreholes, sink
holes, wells and springs within the area shown?
Is the extent of required erosion protection at headwalls and other structures shown?
Do all properties have identified drainage discharge points (to underground drainage
systems for industrial and commercial developments, and residential wherever
possible)?
Have longitudinal sections been prepared for all legs of drainage, open drains, and
nominated overland flow paths?
Is the pipe diameter, class and grade shown for all legs of drainage?
Have pipe classes been determined with consideration to construction loads and final
cover?
VERSION 5.30 Page 207 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Are finished top of pit levels and finished surface level adjacent to pits shown?
Has the minimum 150mm freeboard to kerb invert been achieved for minor storms?
Have all the energy losses in drainage system been accounted for?
Has all crosses with other services been plotted and clearances nominated (street
names should be referred to identify crossings)?
Is FCR backfill specified under road pavements, footpaths, crossovers and building
lines?
Has the location and type of special backfill requirements been noted (e.g. to prevent
piping of backfill material)?
Open Drains
Is the drain accessible from both sides and all-weather tracks provided?
VERSION 5.30 Page 208 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Were scour velocities and siltation both checked in determining longitudinal grades?
Has the low-flow pipe been provided in accordance with the Manual?
Detail Plans
Non-standard drainage structures are fully detailed for construction - headwalls - drop
structures - erosion protection at outlet structures - erosion protection for batters
where needed.
Non-standard pits are fully documented including reinforcement and pit lid details.
Structural details of all retaining walls are shown, as well as details of natural surface
levels and design surface levels, foundation requirements, drainage requirements,
and type of finish.
Details of any estate entrance structures, including structural details, location details
and method of finish.
Traffic calming devices are fully detailed to ensure construction is in accordance with
design requirements (e.g. splitter islands, chicanes, speed humps, roundabout
construction).
VERSION 5.30 Page 209 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Are material and compaction requirements, complying with the relevant Australian
Standard, fully documented in the plans and specifications?
Is the extent of lot filling, top and toe of batters and retaining walls all noted?
Do wetland plantings have alternative source of water for establishing plants and for
periodic dry spells?
Are ALL major aboveground features shown such as street lights, power supply
pillars, fencing, street trees, and landscaping etc?
Landscaping Plans
Is detailed irrigation layout plans provided showing valves, controllers, pipe material
and sizes, alignments, nozzle details, and backflow devices?
VERSION 5.30 Page 210 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CHECKLIST #D2
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
Associated Documents
If required, was a Road Safety Audit Report prepared and accompanies this
submission?
Is there a note provided for any deviations between the proposed design and the
recommendations within the Road Safety Audit report?
Are hydrological calculations provided for whole of catchment and partial areas if
relevant, and 100yr ARI design flows calculated at critical points? (Method
nominated and assumptions clearly stated ARI’s in accordance with Manual.)
Are hydraulic calculations provided for above and underground drainage, for major
and minor storm events. (Method nominated and assumptions clearly stated.
Roughness coefficients nominated)?
Has there been a copy of geotechnical reports provided with the submission?
Are operation and maintenance (O&M) manuals provided with this submission?
The plans, specifications and associated documents provided with this submission for detailed design approval have been
prepared in accordance with the relevant sections of Council’s Manual. All of the above checklist items have been initialled
as correct and complete, or marked N/A (not applicable) as appropriate.
VERSION 5.30 Page 211 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
Signed _____________________________________ Dated
VERSION 5.30 Page 212 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
DESIGN ENGINEER’S CHECKLIST #D3 – REQUEST FOR FINAL DESIGN APPROVAL
DEVELOPER’S NUMBER OF
REPRESENTATIVE PLANS IN SET
CHECKLIST #D3
ITEM Y / N / NA OR DESIGNER’S
COMMENT INITIALS
General
Has detailed design approval been received from Council – if so note date?
Is the final design is in accordance with the planning permit conditions and the
endorsed plan, and physical design features incorporated on construction
plans?
Has the plan of subdivision been certified at the time of this submission?
Have the appropriate consents been obtained from service authorities? List
any consents received below:
25.3
25.4
25.5
Plans
Other
DEVELOPER’S CONSTRUCTION
REPRESENTATIVE ENGINEER
CONTRACTOR CONTRACTOR’S
NOMINATED
REPRESENTATIVE
ON SITE
• Construction Program.
VERSION 5.30 Page 214 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
CONSTRUCTION ENGINEER’S CHECKLIST #D5 – REQUEST FOR ACCEPTANCE OF WORKS INSPECTION
CHECKLIST #D5
Is linemarking complete?
Are all drainage works complete, clean and ready for inspection?
Have fire hydrants and fire plugs been installed and marked in accordance
with fire authority’s requirements?
Are erosion protection works complete?
Is landscaping complete?
Have installation dates for any major traffic control items been provided to
Council?
All construction works should be complete prior to calling for an Acceptance of Works inspection. Any outstanding works
should be noted below:
VERSION 5.30 Page 215 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
An Acceptance of Works inspection is requested of Council. Proposed date and time:
VERSION 5.30 Page 216 of 275 Appendix D: Checklists and Forms for Developer’s Representatives
Appendix E: List of Council Inspections and Inspection Checklists
APPENDIX E: LIST OF COUNCIL INSPECTIONS AND INSPECTION CHECKLISTS
LANDSCAPING
Pre-start meeting
CIVIL WORKS
Pre-start meeting
Drainage inspection
Subgrade inspection
Subbase inspection
WSUD inspections
QUALITY
Non-conformance report
VERSION 5.30 Page 217 of 275 Appendix E: List of Council Inspections and Inspection Checklists
The following represents the minimum number of Council inspections and are considered hold points:
• Prior to pouring footpath (excluding Greater Bendigo City Council, Wellington Shire Council, Central Goldfields Shire
Council, Baw Baw Shire Council, Moira Shire Council and Pyrenees Shire Council see witness points below).
• At proof-rolling of sub-grade.
• Prior to pouring footpath (For Greater Bendigo City Council, Wellington Shire Council, Central Goldfields Shire
Council, Moira Shire Council and Pyrenees Shire Council only).
VERSION 5.30 Page 218 of 275 Appendix E: List of Council Inspections and Inspection Checklists
PRE-START MEETING CHECKLIST - LANDSCAPING
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
VERSION 5.30 Page 219 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ADDITIONAL COMMENTS
VERSION 5.30 Page 220 of 275 Appendix E: List of Council Inspections and Inspection Checklists
PRIOR TO PLANTING – LANDSCAPING
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
Weeds removed.
Topsoiling in place.
ADDITIONAL COMMENTS
VERSION 5.30 Page 221 of 275 Appendix E: List of Council Inspections and Inspection Checklists
PRELIMINARY ACCEPTANCE INSPECTION-LANDSCAPING
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
VERSION 5.30 Page 222 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ADDITIONAL COMMENTS
VERSION 5.30 Page 223 of 275 Appendix E: List of Council Inspections and Inspection Checklists
FINAL ACCEPTANCE INSPECTION – LANDSCAPING
DATE OF INSPECTION
LOCATION/STAGE/SECTION
CHECK COMPLETED
Mulching in place.
ADDITIONAL COMMENTS
VERSION 5.30 Page 224 of 275 Appendix E: List of Council Inspections and Inspection Checklists
PRE-START MEETING CHECKLIST – CIVIL WORKS
DATE OF MEETING
LOCATION
Principal (Developer)
Superintendent / Consultant
Construction Engineer
Council Representative
Principal Contractor
Principal (Developer)
Superintendent / Consultant
Construction Engineer
Council Representative
Principal Contractor
Principal Contractor 1
Contractor 2
Contractor 3
GENERAL MATTERS
VERSION 5.30 Page 225 of 275 Appendix E: List of Council Inspections and Inspection Checklists
Date construction works should commence
by (refer to contract and planning
requirements)
Landscaping Works
Others as listed
Landscaping Works
Others as listed
1. Hold points (delete any that are not required) as specified in Clause 7.4 of the IDM and listed in Appendix E of
the IDM
a. Pre-start for Civil Works
i. Prior to pouring concrete on large reinforced concrete structures and footings.
ii. Prior to placement of GPT’s, litter traps, precast pumpstations.
iii. At proof rolling of subgrade
iv. Prior to the placement of each pavement course
v. Prior to placement of kerb and channel
vi. Prior to pouring of footpaths and driveways
vii. Prior to the placement of the primer coat
viii. Prior to the placement of first asphalt course or sealing.
ix. Prior to covers being placed on pits
x. Prior to placement of each fill layer
xi. Prior to construction of table drains
xii. Prior to construction of retaining walls
b. Pre-start for Landscaping Works
i. Prior to planting out wetlands.
ii. Prior to removal of native vegetation and other existing vegetation.
iii. Prior to planting (landscaping).
VERSION 5.30 Page 226 of 275 Appendix E: List of Council Inspections and Inspection Checklists
2. Witness Points (delete any that are not required) as required by Clause 7.4 of the IDM and as listed in Appendix
E of the IDM
a. Prior to the backfilling of stormwater drains
b. Prior to backfilling subsoil drains
c. Prior to pouring of footpaths and driveways (when not a hold point)
d. Prior to connection of house and property connections to stormwater drains
3. Other Inspections (delete any that are not required)
a. Acceptance of Works
b. Release From Defects Liability
c. Others as listed below:
____________________________________________________________________________________________
____________________________________________________________________________________________
____________________________________________________________________________________________
____________________________________________________________________________________________
____________________________________________________________________________________________
____________________________________________________________________________________________
Works Program
VERSION 5.30 Page 227 of 275 Appendix E: List of Council Inspections and Inspection Checklists
Nominated Working Hours
Quality Plan
Coordination Plan
Have the requirements of any planning permit conditions which include the words “prior to works
commencing” been satisfied?
All Parties
1. Provide economical, fit for purpose infrastructure to meet Council requirements as generally specified in the IDM.
Principal (Developer)
The minimum value of the guarantee is 5% of the total cost of roads, drainage and hard landscaping based on
the priced Bill of Quantities. The guarantee is lodged with the Council for the term of the Defects Liability Period.
VERSION 5.30 Page 228 of 275 Appendix E: List of Council Inspections and Inspection Checklists
If differing periods are nominated for different Infrastructure, the Developer may choose to lodge individual bank
guarantees, or a single bank guarantee for the whole amount to be held.
5. ensuring that at all times there is a Superintendent, who acts in accordance with the requirements of
AS2124/AS4000 where there is a contract signed for the delivery of the works.
6. ensuring that all necessary and other permissions to undertake the Work are obtained, prior to the start of
works.
7. ensuring that a video or photographic survey of the constructed assets to be vested in Council prior to the time
of the Acceptance of Works so that any damage that occurs during the Defects Liability Period can be assessed
to determine whether the damage is a result of faulty workmanship or the result of actions outside the control of
the Contractor.
8. ensuring that any testing required to enable Council’s Engineering Department to ascertain whether assets that
are to be vested in Council meet the IDM standards is undertaken and the results reported to Council, in an
efficient and timely manner.
9. ensuring neighbouring properties are checked for pre-existing damage prior to works commencing.
Consultant
1. Ensure that the Principal is aware of the requirements of the General Conditions of Contract, usually AS2124 or
AS4000.
2. Providing the Principal and the Superintendent with a copy of the Final Design Acceptance and evidence that
the Plan of Subdivision has been certified.
3. Ensuring that all necessary consents and other permissions required under the Contract are obtained by the
contractor, i.e. road opening, traffic management and SEMP.
4. Ensuring that any request to apply material change to the approved design that occurs during construction, is
accepted by the Council Engineer, within 48 hours, or otherwise agreed, prior to providing written instruction to
the Superintendent.
5. Provide Council with “As Constructed” plans prepared by a registered surveyor or qualified engineer and
endorsed by the Clerk of Works (Construction Engineer). Council will expect the “As Constructed” Plans to be
prepared in accordance with Appendix I: Information to be Shown of Plans of the IDM.
Construction Engineer
1 Supervision of the works on a regular basis to ensure that the Principal’s requirements as specified in the plans
approved by are satisfied.
2 Liaising with the Contractor to ensure that all of Council’s preconstruction requirements have been met.
3 Liaising with the Contractor to ensure that the works to be inspected are ready to be inspected and generally
provide a minimum of 48 hours’ notice to the Council Engineer and Superintendent to arrange a joint inspection
at each hold point, Acceptance of Works inspection, Release from Defects Liability inspection and other
inspections as listed in this record.
4 Generally providing a minimum of 48 hours’ notice advising of witness points
5 Ensuring that any request to change to the design that occurs during construction, is forwarded forthwith to the
Superintendent for review and accepted within 1 working day, or otherwise agreed. If the Superintendent
identifies that a material change is required, refer to the Consultant role.
6 If there is no superintendent appointed by the developer- undertake the roles of the superintendent in relation to
works being constructed
Superintendent
VERSION 5.30 Page 229 of 275 Appendix E: List of Council Inspections and Inspection Checklists
1. The Superintendent is a person named in a contract by the two parties to that contract (the Developer and the
Contractor) and is required to undertake certain functions under that contract by those two parties. The
Superintendent is not a party to the contract.
a.
to assess quality of materials and workmanship in accordance with the contract documents;
b.
to assess progress claims and issue of progress certificates;
c.
to assess claims for extra payment for variations to the contract;
d.
to assess claims for extra payment (such as claims under the latent conditions provisions) under the
contract; and
e. to assess claims for extension of time.
2. Council will expect the Superintendent to effect these requirements by the periodic inspection and attendance
on site and attending, where appropriate, meetings with contractors, suppliers and other parties as required to
progress and finalise the works. The Superintendent is not required to provide continuous nor detailed
supervision, nor to act as a clerk or inspector.
3. Council will expect the Developer to ensure that the Superintendent acts fairly at all times.
Contractor/s
1. Undertaking the Work in accordance with the provisions of the Contract (where applicable) and with the plans
and specifications approved by Council.
2. Complying with any written instruction issued by the Superintendent or Construction Engineer where there is no
contract in place.
3. Not making any changes to the approved design without the written instruction from the Superintendent or
Construction Engineer where there is contract in place.
4. As required by Council, produce a video or photographic survey of the assets to be vested in Council prior to
the time of the Acceptance of Works so that any damage that occurs during the Defects Liability Period can be
assessed to determine whether the damage is a result of faulty workmanship or the result of actions outside the
control of the Contractor.
5. As required by Council undertaking any testing required by the Council (as already defined in the IDM), as listed
this record, to enable Council to ascertain whether the assets that are to be vested in Council meet the
standards of Council. The time when the testing is required to undertaken is also listed in this record.
Council
1 Nominating the Council Engineer who will be responsible for inspections and for issuing acceptances or written
notices of non-conformance with the approved plans to the Superintendent.
2 Liaising with the Developer’s representative required changes outside the scope of work covered by the
approved plans.
3 Confirming that Council’s preconstruction requirements have been met, which satisfy Council’s requirements,
within 1 working week of receipt of all relevant information, unless otherwise agreed.
4 Undertaking joint inspections with the Superintendent and or Construction Engineer and Contractor as listed in
this record providing 48 hours’ notice in writing requesting the inspection has been received.
5 Advising the Developer’s Representative in writing, including details of the non–conformance, within 24 hours of
when Council’s Engineer becomes aware of any non-conformance with the requirements of the Council in
relation to the Works.
VERSION 5.30 Page 230 of 275 Appendix E: List of Council Inspections and Inspection Checklists
6 Ensuring that Council’s Engineer responds to queries and request for information from the Developer’s
Representative within 48 hours, unless otherwise agreed.
7 Ensuring that Council’s Engineer advises the Developer’s Representative of the results of any inspection within
one working day, unless otherwise agreed, of the following:
• acceptance, with or without conditions; OR
• non-acceptance and steps to be taken to secure the council's requirements; AND
• process for securing a further inspection where there is non-acceptance.
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
SIGNATURE OF ALL PARTIES AT THE MEETING THAT THIS IS A TRUE AND ACCURATE RECORD OF THE ITEMS
DISCUSSED AT THE MEETING (PRINT NAME AND SIGN AND DATE IN THE SPACE PROVIDED)
Developer
Developer’s Representative
Superintendent / Consultant
Construction Engineer
Council Representative
Contractor
Date _______________________________
VERSION 5.30 Page 231 of 275 Appendix E: List of Council Inspections and Inspection Checklists
DRAINAGE INSPECTION – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
Pipes
Is bedding of sufficient depth & compacted?
VERSION 5.30 Page 232 of 275 Appendix E: List of Council Inspections and Inspection Checklists
CATEGORY CHECKLIST ITEMS YES NO NOT COMMENTS
REQUIRED
ADDITIONAL COMMENTS
VERSION 5.30 Page 233 of 275 Appendix E: List of Council Inspections and Inspection Checklists
SUBGRADE INSPECTION – CIVIL WORKS
SUBDIVISION
FILE NUMBER
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
ADDITIONAL COMMENTS
VERSION 5.30 Page 234 of 275 Appendix E: List of Council Inspections and Inspection Checklists
SUB BASE INSPECTION – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
ADDITIONAL COMMENTS
VERSION 5.30 Page 235 of 275 Appendix E: List of Council Inspections and Inspection Checklists
KERB & CHANNEL PRE-POUR INSPECTION - CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
VERSION 5.30 Page 236 of 275 Appendix E: List of Council Inspections and Inspection Checklists
List any special design requirements that need to be
considered.
ADDITIONAL COMMENTS
VERSION 5.30 Page 237 of 275 Appendix E: List of Council Inspections and Inspection Checklists
FOOTPATH PRE-POUR INSPECTION – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
ADDITIONAL COMMENTS
VERSION 5.30 Page 238 of 275 Appendix E: List of Council Inspections and Inspection Checklists
KERB AND CHANNEL OR FOOTPATH POUR – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
Dowelling included.
ADDITIONAL COMMENTS
VERSION 5.30 Page 239 of 275 Appendix E: List of Council Inspections and Inspection Checklists
BASE INSPECTION (PRIOR TO PRIMING) – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
ADDITIONAL COMMENTS
VERSION 5.30 Page 240 of 275 Appendix E: List of Council Inspections and Inspection Checklists
PRIOR TO WEARING COURSE BEING PLACED – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
ADDITIONAL COMMENTS
VERSION 5.30 Page 241 of 275 Appendix E: List of Council Inspections and Inspection Checklists
WSUD – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
PRELIMINARY WORKS
Erosion and sediment control plan adopted.
SWALES
EARTHWORKS - SWALES
VERSION 5.30 Page 242 of 275 Appendix E: List of Council Inspections and Inspection Checklists
CHECKLIST ITEMS CHECK COMPLETED COMMENTS
YES NO NOT
REQUIRED
Appropriate topsoil.
Minimum depth of 150mm for turf 200mm for
groundcovers/small shrubs
VEGETATION - SWALES
COMMENTS
Vegetation is as designed.
VERSION 5.30 Page 243 of 275 Appendix E: List of Council Inspections and Inspection Checklists
CHECKLIST ITEMS CHECK COMPLETED COMMENTS
YES NO NOT
REQUIRED
VERSION 5.30 Page 244 of 275 Appendix E: List of Council Inspections and Inspection Checklists
CHECKLIST ITEMS CHECK COMPLETED COMMENTS
YES NO NOT
REQUIRED
COMMENTS
Vegetation as designed.
VERSION 5.30 Page 245 of 275 Appendix E: List of Council Inspections and Inspection Checklists
POND / LAKE
Spillway is level.
COMMENTS
VERSION 5.30 Page 246 of 275 Appendix E: List of Council Inspections and Inspection Checklists
Inspection 1 – Hard assets (i.e. pits/pipes) constructed. Date checked ……….
Inspection 2 – Planting about to be undertaken. Date checked ……….
Inspection 3 – Entering defects liability period. Date checked ……….
Inspection 4 – End defects liability period. Date checked ……….
Vegetation is as designed.
VERSION 5.30 Page 247 of 275 Appendix E: List of Council Inspections and Inspection Checklists
BIORETENTION RAINGARDEN
Liner provided.
Perforated pipe installed as designed.
Drainage layer media as designed.
COMMENTS
VERSION 5.30 Page 248 of 275 Appendix E: List of Council Inspections and Inspection Checklists
Inspection 1 – Hard assets (i.e. pits/pipes) constructed. Date checked ……….
Inspection 2 – Planting about to be undertaken. Date checked ……….
Inspection 3 – Entering defects liability period. Date checked ……….
Inspection 4 – End defects liability period. Date checked ……….
Vegetation as designed.
VERSION 5.30 Page 249 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ADDITIONAL COMMENTS
VERSION 5.30 Page 250 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ACCEPTANCE OF WORKS (PRELIMINARY) INSPECTION – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
VERSION 5.30 Page 251 of 275 Appendix E: List of Council Inspections and Inspection Checklists
CHECKLIST ITEMS CHECKS COMPLETED COMMENTS
YES NO NOT
REQUIRED
VERSION 5.30 Page 252 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ADDITIONAL COMMENTS
VERSION 5.30 Page 253 of 275 Appendix E: List of Council Inspections and Inspection Checklists
FINAL ACCEPTANCE INSPECTION (END OF DEFECTS PERIOD) – CIVIL WORKS
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
Final Acceptance
VERSION 5.30 Page 254 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ADDITIONAL COMMENTS
VERSION 5.30 Page 255 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ASSET HANDOVER – WSUD
DATE OF INSPECTION
LOCATION/STAGE/SECTION
YES NO NOT
REQUIRED
TREATMENT
MAINTENANCE
ASSET INFORMATION
VERSION 5.30 Page 256 of 275 Appendix E: List of Council Inspections and Inspection Checklists
ADDITIONAL COMMENTS
VERSION 5.30 Page 257 of 275 Appendix E: List of Council Inspections and Inspection Checklists
NON CONFORMANCE REPORT
DATE
CONTRACTOR
NAME OF CONTRACT
LOCATION
SIGNATURE OF CONTRACTOR
COUNCIL REPRESENTATIVE
ADDITIONAL COMMENTS
VERSION 5.30 Page 258 of 275 Appendix E: List of Council Inspections and Inspection Checklists
Appendix F: Standard Drawings
APPENDIX F: STANDARD DRAWINGS
Councils may prepare and lodge S173 agreements for on-site detention at the cost of the Developer. Where Councils
choose not to prepare such agreements it will the applicant’s responsibility to do so.
The following is an extract of the typical wording of the ‘Covenants of the Owner’.
1. The on-site detention for stormwater for each specified lot will be designed by a Qualified Engineer and be
approved by the Council prior to construction. A copy of the approved plans will be held by Council for future
reference.
2. Each on-site detention stormwater system will be constructed either prior to, or concurrently with, the construction
of any dwelling on the specified lots. Each on-site detention stormwater system on the specified lots will be
completed prior to connection to Council’s drainage system. The Owner will notify the Council when on-site
detention works commence on the specified lots and request an inspection by Council on completion of works.
3. They will maintain, and not modify without prior written agreement of Council, each on-site detention system and
will allow each on-site stormwater detention system to be inspected by a duly appointed officer of the Council at
mutually agreed times.
4. The Owner will pay for all the costs associated with the construction and maintenance of each on-site detention
system.
5. The Council will register this Agreement at the Lands Title Office at the cost of the Owner on the title or titles for
the land.
Cracking (all forms) Surface cracking is common in concrete and is not usually a concern since it is usually
of limited extent and not related to structural failure. However, surface cracking that is
exhaustive may indicate a problem with concrete quality and should be reported for the
Council to review.
Council will expect other types of cracking to be reported for Council review. These types
of cracking are indicative of poor handling and/or unsatisfactory installation and/or
overloading, and will normally be found unacceptable.
Displaced Joint Not acceptable if joint displacement exceeds maximum specified by the acceptable code
or standard for the pipe
Displaced joint Not acceptable if joint displacement exceeds maximum specified by the acceptable code
or standard for the pipe.
Surface damage other Report and refer to Council for acceptance determination
• Scales.
• Chainages on traverse lines at all tangent points and cross-sections (at intervals of not more than 20 metres, along
the centre line of roads).
• Kerb radii (to back of kerb) and kerb type and offsets.
• Footpaths, bicycle paths, and/or shared paths, and all pedestrian kerb crossings to concord with the Disability
Discrimination Act. Levels should be sufficiently documented to demonstrate compliance with requirements of
Australian Standard AS1428 ‘Design for Access and Mobility’.
• Service conduit positions, including water, stormwater, telephone and electricity conduits where required (locations to
be marked on footpaths or kerbs during construction).
• Locations of all existing driveways, drains, pits, services (existing and proposed) and poles.
• Locations and description of roadside furniture and regulatory warning and guide signs where required.
• Linemarking.
• Locations of culvert crossings and hard-standing areas for vehicle access into allotments.
ROAD LONGITUDINAL PLANS
• Centreline chainage.
• Street name.
• Centreline and top of kerb levels required at lease every 20 metres on straight grades and a maximum distance of 10
metres on vertical curves, at all tangent points, changes of grade, low points and at each end of vertical curves.
• Plot of each proposed top of kerb, back of path and existing surface level on title boundaries.
• Grading on rural roads to include a grading of table drains on the same section.
• Location of intersecting streets and court bowls, including temporary court bowls for streets that are constructed in
stages.
• Road grading a minimum distance of 100 metres beyond the limit of works.
• Kerb levels shown on returns at quarter points in addition to tangent points. This may be tabulated as an alternative.
• Kerb returns grading showing the grading into the adjoining street. Note this is not required if detailed contours are
provided.
• Level and location of all existing services to be in conflict with proposed works.
• Datum RL.
• Levels of existing surface for the full width of the road reserve.
• Street name.
• Design levels for kerb, footpaths and road pavement for urban works.
• Location and level of existing services (level where there is to be a conflict with proposed works).
• Datum RL.
• Drainage location.
• Street Names.
• Road chainages.
• Levels at all tangent points, along crown of road and crown/high point in court bowl.
• Scale Bar.
• Other Services.
Drainage Layout Plans
Drainage layout Plans should as a minimum show the following:
• All proposed allotments (numbered), reserves and easements within the development
• All drains to be constructed, including stormwater treatment structures and outfall drains.
• Existing surface levels at the corners of all allotments and all significant changes of grade within the allotment, or
alternatively contour information of sufficient detail to show same.
• Drainage pipe diameters and offsets from property boundaries to pipe centreline.
• All existing fences, buildings, trees, and other obstructions on the street alignment or land through which drains or
flow paths are intended to pass.
• Existing or proposed open earth drains, dams, watercourses, bore holes, sink holes, wells and springs within the area.
• Existing dams and water course, boreholes, sink holes, wells and springs within the area.
Drainage Longitudinal Sections
A drainage longitudinal section for each leg of drainage should be plotted regardless of the length of the leg. Drainage
longitudinal sections should as a minimum show the following:
• Centreline chainage.
• Existing and finished surface levels at 20m spacing maximum, and at all grade changes.
• Datum level.
• Pit description.
• All existing services on the section where the designed pipe crosses.
o Pit type.
o Pipe sizes.
• The location of the pipe (i.e. Street name, reserve, lot number) on the longitudinal section.
• Limit of works to be constructed including all connections to existing and proposed work.
• All existing or proposed fences, buildings, trees, public open space features in the vicinity of the works.
• Invert levels of all inlet and outfall structures including pipes and open drains.
• Top water levels during both the minor storm event and 1% AEP storm event.
• The hydraulic grade line in the inlet pipe/drain for both the minor storm event and the 1% AEP storm event.
• Invert levels and cover levels of associated pits and litter traps.
• Planting schedules for wetlands including quantity and species of all plantings.
Detail Drawings
Detail drawings should as a minimum show the following:
• Structural pits, switching mechanisms, operating levels and pump details for pump stations.
• Planting schedules and any specific planting requirements such as size of hole, root barriers, fertiliser etc.
• Irrigation details including metering, backflow prevention devices, pipe diameter and materials, valve details.
• Street furniture and signage details including type, location and fixing requirements.
• Lighting details.
• Open water bodies to cross reference to other retardation basin or drainage plans.
• Street trees.
• Drainage, treated/potable water, fire hydrants, fire plugs, raw water, sewer, communications, gas, electrical, private
works.
• Trench alignments of all services within the limit of works (single line representation for shared trench).
Council will expect “As Constructed” drawings to be provided in PDF format as a minimum.
VERSION 5.30 Page 274 of 275 Appendix J: Notes on Council’s Engineering Principles
PRINCIPLE Clause 1.5 This principle provides additional requirements to that of The Planning Scheme, and
relates to developments that do not necessarily include collector streets, but may still
warrant establishing bicycle links through the development. Council will review and
determine at planning permit stage the need for these facilities.
PRINCIPLE Clause 9.4 This principle provides additional requirements to that of The Planning Scheme, and
relates to developments that do not necessarily include collector streets, but may still
warrant establishing bicycle links through the development. Council will review and
determine the need for these facilities at the planning permit stage.
PRINCIPLE Clause 9.4 The Planning Scheme allows three-point turning of service vehicles in developments.
Council have adopted an engineering principle that no waste vehicle, emergency
service vehicle or street-sweeper should need to reverse in developments. This is in
response to recommendations made by the Coroner in relation to fatalities resulting
from these types of vehicle movements. In addition to the Coroner’s recommendation
Council believes that cul-de-sacs are beneficial to the amenity of the residents
concerned because of footpath connectivity and safer environments for children.
PRINCIPLE Clause 12.3.1 The Planning Scheme standards discuss Access Lanes. These are considered to be
socially undesirable as they provide out-of-sight places where undesirable behaviour
often takes place. Where they are accepted, specific conditions may be imposed by
Council such as open fencing to adjacent properties, planting restrictions etc to create
more open and visible environment.
PRINCIPLE Clause 12.3.2 These differ from The Planning Scheme standards, and are based upon reserve widths
needed to accommodate desirable Carriageway widths and verge widths as outlined
within the manual. Negative feedback has been received by Council regarding
previous developments with lesser widths of road reserve, and those proposed herein
are more in line with community expectations in areas outside of metropolitan areas.
PRINCIPLE Clause 12.3.4 * The Planning Scheme allows three-point turning of service vehicles in developments.
Council have adopted an engineering principle that no waste vehicle, emergency
service vehicle or street-sweeper should need to reverse in developments. This is in
response to recommendations made by the Coroner in relation to fatalities resulting
from these types of vehicle movements. In addition to the Coroner’s recommendation
Council believes that cul-de-sacs are beneficial to the amenity of the residents living
in the cul-de-sac because of footpath connectivity and safer environments for children.
PRINCIPLE Clause 12.3.8 The Planning Scheme allows the use of any part of the pavement for turning
movements in some street types. Council has adopted an engineering principle that
vehicles should always use the correct side of the pavement for turning due to safety
concerns. ARRB have issued draft user guide to Austroads turning templates
consistent with Council’s principle of using the correct lanes when turning.
VERSION 5.30 Page 275 of 275 Appendix J: Notes on Council’s Engineering Principles
PRINCIPLE Clause 12.3.8 The Planning Scheme allows use of driveways for three-point turning of vehicles in
developments. Council have adopted an engineering principle about not using
driveways or vehicle accesses for turning around due to safety concerns.
PRINCIPLE Clause 12.6 This differs from The Planning Scheme standards. This principle is based upon
experience outside of the metropolitan area. This is also more in line with Austroads
principles and consistent with advice to Council from experienced traffic engineers.
PRINCIPLE Clause 13.2 The Planning Scheme requires footpaths for both sides of streets for Access Streets,
or higher order streets, but not Access Places. Council requires footpaths are required
for all frontages, including fully around court to in accordance with the principles of the
Disability Discrimination Act 1992. This principle has also been determined through
consultation with access impaired representatives of the community.
PRINCIPLE Clause 13.3 The Planning Scheme allows footpaths to abut kerbs. Council principle is that they
should be separated to avoid conflict between pedestrians and doors of parked cars
and to provide a buffer between children and moving vehicles.
PRINCIPLE Clause 26.3 Council has received numerous requests to address street lighting in these
developments. This principle has been adopted to cover the gap in the various
standards and to meet community expectations.
VERSION 5.30 Page 276 of 275 Appendix J: Notes on Council’s Engineering Principles