This document is a contract between PT PLN and PT Perintis Sarana Elektrik for the replacement of earthwires on transmission lines in the Cilegon region. It outlines the materials needed, including 50,000 meters of AS 95 earthwire and 35,000 meters of AS 70 earthwire, as well as accessories like clamps, dampers, and joints. A schedule is provided showing the work is to be completed within 12 months from June 2022.

Uploaded by

rei
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views1 page

KURVA S NOV 008 PJ

This document is a contract between PT PLN and PT Perintis Sarana Elektrik for the replacement of earthwires on transmission lines in the Cilegon region. It outlines the materials needed, including 50,000 meters of AS 95 earthwire and 35,000 meters of AS 70 earthwire, as well as accessories like clamps, dampers, and joints. A schedule is provided showing the work is to be completed within 12 months from June 2022.

Uploaded by

rei
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PT.

PLN (PERSERO)
UNIT PELAKSANA TRANSMISI
KURVA - S
CILEGON
PENGGANTIAN GSW TERSEBAR PADA SALURAN TRANSMISI WILAYAH UPT CILEGON
PT PERINTIS SARANA ELEKTRIK
KONTRAK NOMOR & TANGGAL : 0008.Pj/DAN.01.03/C34030000/2022, Tanggal 7 Juni 2022
No. URAIAN PEKERJAAN Vol SAT. Bobot WAKTU PELAKSANAAN
I PENGADAAN MATERIAL EARTHWIRE & ACESSORIES BULAN
A MATERIAL & ASSESORIES EARTHWIRE (AS 95) FOR SUTET 500 kV 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
1 Kawat GSW AS 95 50.000,00 mtr 29,48% 9,83% 9,83% 9,83%
RENCANA AKTUAL
2 Single Tension Clamp for AS 95 include sackle 45,00 set 0,49% 100,00% 0,16% 0,16% 0,16% 100,00%
99,40%
Suspension Clamp for AS 95 include armour rods, U-Bolt & Jumper lugs assembly 98,80%
3 91,00 set 0,77% 0,26% 0,26% 0,26% 98,19%
(1000 mm) 97,59%
4 Vibrator Damper for AS 95 227,00 set 1,34% 0,45% 0,45% 0,45% 96,99%

5 CCO Clamp for AS 95 44,00 set 0,06% 0,02% 0,02% 0,02%


6 Skun jumper grounding to body tower for AS 95 44,00 set 0,05% 0,02% 0,02% 0,02%
7 Mid Span Joint for AS 95 25,00 set 0,24% 0,08% 0,08% 0,08% 93,74%

B MATERIAL & ASSESORIES EARTHWIRE (AS 70) FOR SUTT 150 kV


1 Kawat GSW AS 70 35.000,00 mtr 15,79% 5,26% 5,26% 5,26% 90,49%
90,00%
2 Single Tension Clamp for AS 70 include sackle 102,00 set 1,21% 0,40% 0,40% 0,40%
Suspension Clamp for AS 70 include armour rods, U-Bolt & Jumper lugs assembly
3 64,00 set 0,52% 0,17% 0,17% 0,17%
(1000 mm) 87,25%
4 Vibrator Damper for AS 70 230,00 set 1,36% 0,45% 0,45% 0,45%
5 CCO Clamp for AS 70 96,00 set 0,11% 0,04% 0,04% 0,04%
6 Skun jumper grounding to body tower for AS 70 96,00 set 0,09% 0,03% 0,03% 0,03%
84,20%
7 Mid Span Joint for AS 70 18,00 set 0,13% 0,04% 0,04% 0,04%
82,61%

C MATERIAL & ASSESORIES EARTHWIRE (AS 55) FOR SUTT 150 kV


81,03%
1 Kawat GSW AS 55 20.000,00 mtr 7,22% 2,41% 2,41% 2,41%
80,00%
2 Single Tension Clamp for AS 55 include sackle 116,00 set 1,31% 0,44% 0,44% 0,44%
Suspension Clamp for AS 55 include armour rods, U-Bolt & Jumper lugs assembly
3 46,00 set 0,37% 0,12% 0,12% 0,12%
(1000 mm) 77,49%

4 Vibrator Damper for AS 55 208,00 set 1,23% 0,41% 0,41% 0,41%


5 CCO Clamp for AS 55 116,00 set 0,11% 0,04% 0,04% 0,04%
74,58%
6 Skun jumper grounding to body tower for AS 55 112,00 set 0,08% 0,03% 0,03% 0,03%
7 Mid Span Joint for AS 55 9,00 set 0,07% 0,02% 0,02% 0,02%

71,67%
II PENGGANTIAN GSW AS 95 SUTET 500 kV CILEGON BARU - CIBINONG
114 TOWER LATICE (23 TOWER TENSION, 91 TOWER SUSPENSION) 70,00%
1 Survey dan Dokumentasi 1,00 ls 0,42% 0,42% 69,02%
2 Mobilisasi dan demobilisasi (alat, tenaga dan material) 1,00 ls 1,90% 1,90%
67,81%
68,41%

3 Cordination with local government 1,00 ls 0,18% 0,18% 67,21%


66,61%
4 Steiger bambu crossing jalan 1,00 ls 1,58% 1,58%
5 Dismantling earthwire conductor eksisting 49,06 kms 2,28% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12% 0,12%
6 Dismantling earthwire single tension clamp eksisting with vibrator dumper 45,00 set 0,18% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01%
7 Dismantling earthwire suspension clamp eksisting with vibrator dumper 91,00 set 0,32% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02%
8 Instaled earthwire single tension clamp for AS 95 include shackle 45,00 set 0,84% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04%
9 Instaled earthwire suspension clamp for AS 95 include armour rod 91,00 set 1,51% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08% 0,08%
10 Stringing earthwire conductor AS 95 49,06 kms 3,46% 60,00% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18% 0,18%
11 Sagging earthwire conductor AS 95 114,00 set 0,45% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02% 0,02%
12 Instaled earthwire vibrator damper for AS 95 227,00 set 1,35% 0,07%58,16% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07% 0,07%
13 Pekerjaan pemasangan assesories (CCO, skun, midspan,jumper, etc) 113,00 set 0,67% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04% 0,04%
14 Transportasi GSW dan assesories eksisting bongkaran dari site ke Menes 1,00 ls 0,15% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01%
15 Finishing & Perapihan Eks Pekerjaan include pembongkaran montage roll 1,00 ls 0,21% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01% 0,01%

III PENGGANTIAN GSW AS 70 SUTT 150 kV CILEGON BARU - SERANG


52,38%
80 TOWER LATICE (25 TOWER TENSION, 55 TOWER SUSPENSION)
1 Survey dan Dokumentasi 1,00 ls 0,25% 0,25%
2 Mobilisasi dan demobilisasi (alat, tenaga dan material) 1,00 ls 1,33% 50,00% 1,33%
3 Cordination with local government 1,00 ls 0,13% 0,13%
4 Steiger bambu crossing jalan 1,00 ls 0,59% 0,59%
5 Dismantling earthwire conductor eksisting 26,49 kms 1,23% 0,41% 0,41% 0,41%
6 Dismantling earthwire single tension clamp eksisting with vibrator dumper 54,00 set 0,22% 0,07% 0,07% 0,07%
7 Dismantling earthwire suspension clamp eksisting with vibrator dumper 54,00 set 0,19% 0,06% 0,06% 0,06%
8 Instaled earthwire single tension clamp for AS 70 include shackle 54,00 set 1,01% 0,34% 0,34% 0,34%
43,14%
9 Instaled earthwire suspension clamp for AS 70 include armour rod 54,00 set 0,19% 42,27%
0,06% 0,06% 0,06%
10 Stringing earthwire conductor AS 70 26,49 kms 1,87% 0,62% 0,62% 0,62%
11 Sagging earthwire conductor AS 70 80,00 set 0,32% 0,11% 0,11% 0,11%
40,00%
12 Instaled earthwire vibrator damper for AS 70 162,00 set 0,97% 0,32% 0,32% 0,32%
13 Pekerjaan pemasangan assesories (CCO, skun, midspan,jumper, etc) 118,00 set 0,70% 0,23% 0,23% 0,23%
14 Transportasi GSW dan assesories eksisting bongkaran dari site ke Menes 1,00 ls 0,08% 0,03% 0,03% 0,03%
15 Finishing & Perapihan Eks Pekerjaan include pembongkaran montage roll 1,00 ls 0,15% 0,05% 0,05% 0,05%

IV PENGGANTIAN GSW AS 70 SUTT 150 kV CIKANDE - PUCAM


15 TOWER LATICE + 1 GANTRY (10 TOWER TENSION, 5 TOWER SUSPENSION)
1 Survey dan Dokumentasi 1,00 ls 0,06% 0,06%
2 Mobilisasi dan demobilisasi (alat, tenaga dan material) 1,00 ls 0,27% 0,27%
3 Cordination with local government 1,00 ls 0,09% 0,09%
30,00% 29,98%
4 Steiger bambu crossing jalan 1,00 ls 0,26% 0,26%
5 Dismantling earthwire conductor eksisting 6,19 kms 0,29% 0,10% 0,10% 0,10%
6 Dismantling earthwire single tension clamp eksisting with vibrator dumper 48,00 set 0,20% 0,07% 0,07% 0,07%
7 Dismantling earthwire suspension clamp eksisting with vibrator dumper 10,00 set 0,04% 0,01% 0,01% 0,01%
8 Instaled earthwire single tension clamp for AS 70 include shackle 48,00 set 0,90% 0,30% 0,30% 0,30%
9 Instaled earthwire suspension clamp for AS 70 include armour rod 10,00 set 0,04% 0,01% 0,01% 0,01%
10 Stringing earthwire conductor AS 70 6,19 kms 0,44% 0,15% 0,15% 0,15%
11 Sagging earthwire conductor AS 70 15,00 set 0,06% 0,02% 0,02% 0,02%
21,59%
12 Instaled earthwire vibrator damper for AS 70 68,00 set 0,41% 0,14% 0,14% 0,14%
13 Pekerjaan pemasangan assesories (CCO, skun, midspan,jumper, etc) 92,00 set 0,55% 20,00%
0,18% 0,18% 0,18%
14 Transportasi GSW dan assesories eksisting bongkaran dari site ke Menes 1,00 ls 0,02% 0,01% 0,01% 0,01%
15 Finishing & Perapihan Eks Pekerjaan include pembongkaran montage roll 1,00 ls 0,03% 0,01% 0,01% 0,01%

V PENGGANTIAN GSW AS 55 SUTT 150 kV CILEGON BARU-POLYPRIMA-ASAHIMAS


48 TOWER STEELPOLE + 2 GANTRY (25 TOWER TENSION, 23 TOWER SUSPENSION)
1 Survey dan Dokumentasi 1,00 ls 0,18% 0,18%
2 Mobilisasi dan demobilisasi (alat, tenaga dan material) 1,00 ls 0,83% 0,83%
3 Cordination with local government 1,00 ls 0,10% 0,10%
4 Steiger bambu crossing jalan 1,00 ls 0,53% 0,53%
5 Dismantling earthwire conductor eksisting 16,97 kms 0,79% 10,00% 0,26% 0,26% 0,26%
6 Dismantling earthwire single tension clamp eksisting with vibrator dumper 116,00 set 0,48% 0,16% 0,16% 0,16%
7 Dismantling earthwire suspension clamp eksisting with vibrator dumper 46,00 set 0,16% 0,05% 0,05% 0,05%
8 Instaled earthwire single tension clamp for AS 55 include shackle 116,00 set 2,17% 0,72% 0,72% 0,72%
9 Instaled earthwire suspension clamp for AS 55 include armour rod 46,00 set 0,16% 0,05% 0,05% 0,05%
10 Stringing earthwire conductor AS 55 16,97 kms 1,20% 0,40% 0,40% 0,40%
11 Sagging earthwire conductor AS 55 48,00 set 0,19% 0,06% 0,06% 0,06%
12 Instaled earthwire vibrator damper for AS 55 208,00 set 1,24% 0,41% 0,41% 0,41%
13 Pekerjaan pemasangan assesories (CCO, skun, midspan,jumper, etc) 237,00 set 1,41% 0,47% 0,47% 0,47%
14 Transportasi GSW dan assesories eksisting bongkaran dari site ke Menes 1,00 ls 0,05% 0,91% 0,02% 0,02% 0,02%
15 Finishing & Perapihan Eks Pekerjaan include pembongkaran montage roll 1,00 ls 0,09% 0,00% 0,00% 0,03% 0,03% 0,03%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

0,00% 0,91% 20,68% 20,68% 24,34% 0,60% 0,60% 0,60% 0,60% 2,65% 2,91% 2,91% 3,53% 1,59% 1,59% 3,05% 3,25% 3,25% 3,25% 0,60% 0,60% 0,60% 0,60% 0,60%
BULAN B0 B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12 B13 B14 B15 B16 B17 B18 B19 B20 B21 B22 B23 B24
RENCANA 0% 0,00% 0,91% 21,59% 42,27% 66,61% 67,21% 67,81% 68,41% 69,02% 71,67% 74,58% 77,49% 81,03% 82,61% 84,20% 87,25% 90,49% 93,74% 96,99% 97,59% 98,19% 98,80% 99,40% 100,00%
AKTUAL 0% 0,00% 0,91% 29,98% 43,14% 52,38% 58,16% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%