Understanding Solar PV Permitting Inspecting
Understanding Solar PV Permitting Inspecting
and Inspecting
Understanding the solar permitting and inspecting process
for local governments and authorities having jurisdiction (AHJ)
17
Section Contents 7. Sample Installation Errors . . . . . . . . . . . . . . . . . . . . . . 50
1. Intended Use . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 8. Solar PV System Labeling Guidelines . . . . . . . . . . . . 54
1.1 What the Tool Is . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 8.1 Scope and Purpose . . . . . . . . . . . . . . . . . . . . . . . . . 54
1.2 What the Tool is Not . . . . . . . . . . . . . . . . . . . . . . . . 19 8.2 Overview of Label Locations
1.3 Distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 and Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . 54
1.3.1 Disclaimer . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19 8.3 Label Construction, Placement,
2. Solar PV System Design Issues . . . . . . . . . . . . . . . . . 20 Color, and Marking . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
8.3.1 Materials and Construction. . . . . . . . . . . . . 55
2.1 Array Siting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20
2.2 Irradiance and Temperature . . . . . . . . . . . . . . . . . 20 8.3.2 Placement. . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
2.3 System Sizing and Equipment Selection . . . . . . 20 8.3.3 Colors. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
2.4 Grounding . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 8.3.4 Marking. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
2.5 Labeling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 8.4 Label Descriptions and NEC References . . . . . . . . 55
2.6 Zoning Considerations . . . . . . . . . . . . . . . . . . . . . . 21 8.4.1 Arc-Flash Hazard Warning. . . . . . . . . . . . . . 55
2.7 Wind and Snow Loads . . . . . . . . . . . . . . . . . . . . . . 21 8.4.2 Conductor Identification and Grouping. . . 56
3. Design Review of Construction Documents . . . . . . . 22 8.4.3 Identification of PV Disconnects. . . . . . . . . 58
3.1 Site Plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 8.4.4 Terminals Energized on Line and
3.2 Electrical Diagram . . . . . . . . . . . . . . . . . . . . . . . . . . 23 Load Sides of Disconnect in
3.3 Structural Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . 24 Open Position . . . . . . . . . . . . . . . . . . . . . . . . 59
4. Field Inspection Checklist . . . . . . . . . . . . . . . . . . . . . . 25 8.4.5 DC PV Source and Output Circuits
4.1 Array . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 Inside a Building. . . . . . . . . . . . . . . . . . . . . . 59
4.2 DC Optimizer . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 8.4.6. DC Photovoltaic Power Source. . . . . . . . . . 60
4.3 Structural (Roof-Mounted Only) . . . . . . . . . . . . . . 26 8.4.7 Identification of PV System
4.4 Junction Box . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26 Interconnection. . . . . . . . . . . . . . . . . . . . . . . . 61
4.5 Inverter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 8.4.8 Identification of Power Sources. . . . . . . . . . 61
4.6 Microinverter . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 8.4.9 Point of Connection Identification . . . . . . . 62
4.7 AC Combiner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
8.4.10 NEC 408 Switchboards,
4.8 Load-Side Connection . . . . . . . . . . . . . . . . . . . . . . 28
Switchgear, and Panelboards. . . . . . . . . . . 62
4.9 Supply Side Connection . . . . . . . . . . . . . . . . . . . . . 29
4.10 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 8.5 Common Labeling Mistakes to Avoid . . . . . . . . . . 63
18
Overview
To allow officials to better understand the permitting and inspecting process, and
ensure them an efficient, transparent, and safe beginning to their solar development
project, this section reviews the solar photovoltaic (PV) permitting and inspection
process for local government officials and authorities having jurisdiction (AHJs).
Tools and materials are provided to assist local officials and AHJs on evaluations of solar systems less than 25kW. Solar PV
design issues, design reviews of construction documents, and field inspection checklists are among the topics discussed.
Within this chapter, we provide the following supplemental material for government officials and AHJs:
• NY State Unified Solar Permit Application
• Sample construction photos of correctly installed equipment
• Sample installation errors
• Labeling guidelines
• Sample wiring diagrams
• Sample site map for roof mounted solar PV systems
1. Intended Use
NYSERDA developed this tool in collaboration with the New York Department of State, solar contractors, and other
stakeholders. It supports NYSERDA’s efforts to implement a unified permitting process for residential solar PV systems.
Standardizing the permitting and inspecting process across New York State will reduce costs for municipalities and solar
customers, create local jobs, and advance New York’s clean energy goals.
1.3 Distribution
AHJs and other entities are welcome to use and distribute this tool. AHJs may wish to update the Unified Solar Permit
Application itself and Submittal Instructions to reflect any unique requirements that apply to their municipality (such as a
schedule of fees). The inspection and design review checklists can also be changed to reflect additional requirements.
AHJs should keep in mind that changing the Unified Solar Permit’s contents may diminish consistency and increase the cost
of solar energy for their constituents. Changes may not be obvious to contractors working across many local governments, so
AHJs should highlight any changes made to the standard documents.
1.3.1 Disclaimer
This document and the New York Unified Solar Permit are provided to support and standardize the solar permitting process.
These documents should not be used as a substitute for proper solar PV system design calculations. Users of these
documents assume all responsibility for solar PV system design, installation, and permitting, as required by New York State
law. NYSERDA and its contractors cannot be held liable for any errors or omissions in these documents.
19
2. Solar PV System Design Issues
This section provides an overview of issues involved in solar PV system design. It is critical that designers optimize safety and
performance because systems have expected lifespans of 20-30 years.
20
2.4 Grounding
One of the more challenging aspects of solar PV system design and installation is thoroughly grounding and bonding the
system in accordance with the NEC.
The grounding electrode conductor (GEC) is the reference ground that establishes the voltage relationships between the
ungrounded conductors and earth ground. The GEC must be run with irreversible splices from any separately derived power
supply (i.e., inverters that contain transformers) to the grounding electrode. All solar PV systems with a transformer-based
inverter will require a GEC from the inverter to the grounding electrode. Table 250.66 in the NEC governs the sizing of the
GEC. The GEC must be a minimum of number six American Wire Gauge Building Wire (#6 AWG) when exposed and must be
bare or covered with green insulation. When exposed and insulated, the wire must be UV-protected.
The grounded conductor (or “neutral” conductor) is intentionally grounded and carries current under normal conditions. It
is always insulated and may be white or gray in color. Current flows out on the ungrounded conductors and returns on the
grounded conductor, completing the circuit.
The equipment grounding conductor (EGC) does not carry current under normal conditions. It provides a path back to the
grounded conductor (neutral) when a fault occurs. The EGC may include all bonded metal components, such as the racking,
boxes, enclosures, building steel, and metal roofing materials. (Bonding is the physical connecting of metal components so
that they are at equal potential. They may or may not be grounded. Bonding jumpers may be extensions of the GEC, EGC, or
grounded conductor.) Table 250.122 in the NEC governs EGC sizing. The EGC is required on both grounded and ungrounded
(transformer-less) systems. The EGC must be a minimum of #6 AWG when exposed and must be bare or insulated green.
When exposed and insulated, the wire must be UV-protected.
The GEC, EGC, and grounded conductor must be bonded together at the main service disconnect(s) and at the overcurrent
protection/disconnects when performing a supply-side connection.
2.5 Labeling
The NEC provides many unique labeling requirements for solar PV systems, located in Sections 690, 705, 706 and
elsewhere. To assist contractors and inspections, NYSERDA has developed an extensive Labeling Guide, located as
Section 8 of this document.
21
Figure R301.2(5)A from the 2020 Residential Code of New York Figure R301.2(6) from the 2020 Residential Code of New York
State: Ultimate Design Wind Speeds State: Ground Snow Loads
3. Design Review of
Construction Documents
As part of their permit application, applicants must submit a site plan, an electrical wiring diagram, a structural analysis, and
specification sheets for the modules, inverter, and racking system. This section includes a checklist of items for code officials
to check as part of their design review.
The construction documents must be stamped by a New York State licensed professional engineer (PE) or registered
architect (RA). The local code official will determine the depth of review necessary. The following three-part checklist may be
expanded should the code official require examination at greater depth, such as checking wire sizing and other calculations.
22
3.2 Electrical Diagram
Yes/No Electrical Wiring Diagram
Electrical wiring diagram prepared and stamped by a New York State-licensed Professional
Engineer or Registered Architect, who incorporated the following into system design.
• Solar electric module array information – number of modules in series, number of strings.
• Quantity, make, and model of UL-listed solar PV modules.
• All conductor types, ratings, and conduit type (if applicable). Solar electric source circuit conductors
are solar PV wire (NEC 690.31(B)).
• Max voltage of 600 VDC (NEC 690.7(C)) (1,000 VDC wire may be used on 600 VDC systems).
• Rating (voltage and current) for all disconnects.
• Voltage drop is minimized (NEC 210.19(A)Informational Note No. 4).
• Provision for Rapid Shutdown per NEC 690.12. Using microinverters or string inverters
with DC Power optimizers is one way of meeting this requirement.
• DC disconnect is present (may be integral to inverter) (NEC 690.13).
• Quantity, make, and model of UL-listed inverter provided.
• AC disconnect appropriately sized for inverter output (NEC 690.8(A)(3), 690.8(B)(1)).
• Conductor type, rating, and conduit type (if applicable) provided for all conductors.
• If supply-side connection, meets all requirements of NEC 705.12(A), including:
- Service-rated AC disconnect specified, at least 60 amps, with appropriate overcurrent protection device.
If breaker used, must meet or exceed utility fault current kAIC rating.
- Conductors between disconnect and point of interconnection are sized at least 60 amps (#6 or larger).
- Supply side connection made between main service panel’s main disconnect and utility meter.
• If load side connection, meets all requirements of NEC 705.12(B), including:
- Inverter output connection is made at a dedicated circuit breaker or fusible disconnect.
- The sum of 125% of the inverter(s) output current plus the main circuit breaker rating must be less than or
equal to 120% of the bus or cable rating (NEC 705.12(B)(3)(b)).
- Backfed breaker located at opposite end of busbar from main breaker (NEC 705.12(B)(2)(1)).
• Equipment grounding conductor (EGC) present at all components likely to become energized, and sized
according to NEC 250.122.
• If not using an isolated/ungrounded/transformer-less inverter, grounding electrode conductor (GEC) present
and continuous from inverter to service disconnect, sized according to NEC 250.66.
23
3.3 Structural Analysis
Yes/No Structural Analysis
Structural analysis prepared and stamped by a New York State licensed professional
engineer or registered architect, who incorporated the following into their review.
• Weight of the existing roofing (composition shingle, metal, masonry, etc.).
• Number of layers of roof covering.
• Method of waterproofing penetrations (flashing is required by the 2020 NYS Uniform Code).
• Type of racking system (engineered product) and height of solar PV modules from surface of roof.
• Location-specific wind load and snow load.
• Type, dimensions, and spacing of roof structural framing.
• Calculations must be provided if any of the following apply:
- Roofing is not lightweight, or roof has multiple layers of covering.
- Racking system is not engineered for mounting of solar PV modules.
- Modules will be mounted more than 18 inches above roof surface.
- Modifications must be made to framing to strengthen roof structure.
- Solar electric system and racking will add more than 5 pounds per square foot to dead load,
or more than 45 pounds per attachment point, calculated as follows:
• Total weight of solar PV modules, racking, and mounting hardware __________pounds.
• Total number of attachment points to roof __________.
• Weight per attachment point (A ÷ B) __________pounds.
• Total area of solar PV array __________square feet.
• Distributed weight of solar PV array on roof (A ÷ D) __________pounds/square foot.
24
4. Field Inspection Checklist
The Field Inspection Checklist in this chapter can be used directly by the AHJ or provided to a third-party inspection
agency, where applicable. The checklist is intended to highlight key system characteristics and common installation errors.
Completing the checklist should take approximately 20 minutes per field inspection. Not all sections may apply to a given
installation.
A “rough inspection” (which occurs when all boxes and wires are installed to the point when walls or trenches are ready to be
closed) is not necessary on most small residential installations with existing construction.
When a field inspection is necessary, inspectors should consider bringing the following items:
• Ladder with non-conductive sides.
• Binoculars for surveying inaccessible roof-mounted equipment.
• Screwdriver for opening enclosures.
• A copy of the contractor’s submitted design.
Code enforcement officers should consider asking solar PV contractors for a set of construction photos. Contractors typically
document their installation progress with photos, which are sometimes required by their internal quality assurance team or
financing partners. NYSERDA also requires construction photos from participating contractors. Code enforcement officers can
use such photos to review hard-to-access parts of the installation (such as roof-mounted racking).
4.1 Array
1. C
ircuit conductors are properly supported and are not touching the roof surface N Y N/A
[NEC 338.30, 350.30, 376.30]
2. Circuit conductors are same conductor type/size as on plan set N Y N/A
3. Module count matches plan set. If no, investigate stringing configuration N Y N/A
4. Module manufacturer/model matches plan set N Y N/A
5. Modules are effectively grounded using lugs, WEEBs, or a racking integrated grounding method N Y N/A
[NEC 690.43]
6. Modules and racking are properly secured [NEC 110.3(B), 250.5, 250.8, 250.12, 690.43] N Y N/A
7. DC optimizers or microinverters are properly grounded N Y N/A
[NEC 110.3(B), 250.4(A)(5), 250.64(E), 250.97]
8. Wire ties are UV-rated (generally black) N Y N/A
9. All electrical connections are secured to ensure no arcing N Y N/A
10. Racking system is properly grounded (EGC bonding the rails [NEC 690.43]) N Y N/A
11. Conductors are properly identified (ungrounded, grounded, grounding) N Y N/A
[NEC 200.7, 200.6, 250.119]
12. Outdoor components are UL-listed for the environment [NEC 110.3(B)] N Y N/A
13. Roof vents are not covered by the modules [2020 NYS Uniform Code] N Y N/A
14. DC conduit is labeled “WARNING: PHOTOVOLTAIC POWER SOURCE” every 10 feet, N Y N/A
and is reflective, and meets color and size requirements [NEC 690.31(G)(3) and (4)]
15. Conductors over 30V are guarded, installed in raceways, or otherwise inaccessible N Y N/A
[NEC 690.31(G)(3)(4)]
16. Equipment Grounding Conductor (EGC) is protected if smaller than #6 AWG N Y N/A
[NEC 690.46, 250.120(C)]
17. Source circuit conductors are not in contact with the roof [NEC 338.10, 334.30] N Y N/A
25
4.2 DC Optimizer
1. D
C Optimizer chassis is properly grounded per manufacturer’s instructions N Y N/A
[NEC 110.3(B), 250.4(A)(5), 250.64(E), 250.97]
2. Rapid Shutdown label is present and meets the requirements of NEC 690.56(C)(1)(a) N Y N/A
Note 1: Many violations from the “Array” section also apply to the “DC Optimizer” section.
Note 2: DC optimizer can have an integrated ground, or not. Bring the specifications sheet to the inspection
for quick reference.
26
4.5 Inverter
1. The number of strings match the plan set N Y N/A
2. The conductors have sufficient ampacity for each string N Y N/A
3. DC conductors in metal when on or inside a building [NEC 690.31(G)] N Y N/A
4. Conduit penetrations are properly sealed between conditioned and unconditioned space N Y N/A
[NEC 300.7(A)]
5. Conduit is properly supported e.g., [LFMC NEC 350.30, EMT NEC 358.30, PVC NEC 352.30] N Y N/A
6. Conduit is not being used as conductor support [NEC 725.143] N Y N/A
7. The enclosure is properly grounded [NEC 690.43, 250.8, 250.12] N Y N/A
8. Grounding equipment is properly installed [NEC 690.43, 250.8, 250.12] N Y N/A
9. Point of interconnection enclosure is labeled as a PV disconnect [NEC 110.21(B) and/or 690.13(B)] N Y N/A
10. DC characteristics label is present [NEC 690.53] N Y N/A
11. The ungrounded DC conductors are properly identified (shall not be white, gray, or white striped) N Y N/A
[NEC 200.6(A)(B)]
12. Max string voltage below inverter max [NEC 110.3(B), 690.7] N Y N/A
13. Inverter string fuses are rated for use in application [NEC 110.3(B), 690.9] N Y N/A
14. DC and AC disconnecting means are located within sight of or in each inverter [NEC 690.15] N Y N/A
15. AFCI protection is present and enabled [NEC 690.11] N Y N/A
16. System is equipped with Rapid Shutdown [NEC 690.12] N Y N/A
17. Rapid Shutdown label is present and meets the requirements of NEC 690.56(C)(1)(a) N Y N/A
18. System is marked with a permanent label with the following wording: N Y N/A
“PHOTOVOLTAIC SYSTEM EQUIPPED WITH RAPID SHUTDOWN” [NEC 690.56(C)]
4.6 Microinverter
1. Microinverter chassis is properly grounded per manufacturer’s instructions N Y N/A
[NEC 690.43(A), 250.4, 110.3(B)]
2. EGC is protected if smaller than #6 AWG [NEC 690.46, 250.120(C)] N Y N/A
3. Rapid Shutdown label is present and meets the requirements of NEC 690.56(C)(1)(a) N Y N/A
Note 1: Many items from the “Array” section also apply to the “Microinverter” section.
Note 2: Microinverters can have an integrated ground, or not. This information is found on the specification sheet.
Note 3: As long as the microinverters are listed, they are inherently equipped with rapid shutdown, which is required by
NEC 690.12. This does not negate the label requirement in NEC 690.56(C)(1)(a).
27
4.7 AC Combiner
1. The number of branch circuits match the plan set. N Y N/A
2. The conductors have sufficient ampacity for each branch circuit. N Y N/A
3. T
he Overcurrent Protective Device (OCPD) for the conductors have a rating sufficient to protect N Y N/A
them [NEC 240.4]
4. C
onduit penetrations are properly sealed between conditioned and unconditioned space N Y N/A
[NEC 300.7(A)]
5. Conduit is properly supported e.g., [LFMC NEC 350.30, EMT NEC 358.30, PVC NEC 352.30] N Y N/A
6. Conduit is not being used as conductor support [NEC 300.11(B), 725.143] N Y N/A
7. The enclosure is properly grounded [NEC 690.43, 250.8, 250.12] N Y N/A
8. Grounding equipment is properly installed [NEC 690.43, 250.8, 250.12] N Y N/A
9. Enclosure is labeled as a disconnect [NEC 690.13] N Y N/A
10. AC characteristics label is present (voltage and amperage), [NEC 690.54] N Y N/A
11. The main breaker is fastened in place [NEC 408.36(D)] N Y N/A
12. Grounded conductors are isolated from enclosure [NEC 250.24(A)(5)] N Y N/A
28
4.9 Supply Side Connection
1. Disconnect is service-rated and has a current rating of at least 60 Amp [NEC 230.79(D)] N Y N/A
2. Circuit conductors have sufficient ampacity [NEC 690.8, 310.15] N Y N/A
3. New service entrance tap conductors are less than 10 feet [NEC 705.31] N Y N/A
4. The AC OCPD is properly sized for the expected output current of the PV system [NEC 690.9] N Y N/A
5. The disconnect utility conductors are on LINE terminals [NEC 110.3(B), 240.40(if fusible)] N Y N/A
6. There is no OCPD in the grounded conductor [NEC 230.90(B)] N Y N/A
7. The AIC rating on the OCPD meets, or exceeds the rating of other main OCPD on the premises N Y N/A
[NEC 110.9, 110.10]
8. T
he neutral (white or grey grounded conductor) is bonded to the PV disconnect enclosure/GEC N Y N/A
[NEC 250.24(C)]
9. The GEC is present and sufficiently sized [NEC 690.47, 250.66] N Y N/A
10. The GEC is continuous (or irreversibly spliced) [NEC 250.64(C), 690.47(C)] N Y N/A
11. F
errous conduit and the enclosure are appropriately bonded to the GEC N Y N/A
[NEC 250.64(E), 250.4(A)(5)]
12. AC characteristics label is present and suitable for the environment (voltage and amperage) N Y N/A
[NEC 690.54, 110.21(B)]
13. Power source directory is present, denoting all locations of power sources and disconnects on N Y N/A
premises, at each service equipment location [NEC 110.21, 705.10]
14. AC disconnect label is present and suitable for the environment [NEC 690.13(B), 110.21] N Y N/A
15. Dissimilar metals are separated and will not cause a galvanic reaction N Y N/A
[NEC 110.14, RMC NEC 344.14, EMT NEC 358.14]
4.10 General
1. Work is done in a neat and workmanlike manner [NEC 110.12] N Y N/A
2. Working clearances are observed per NEC 110.26 N Y N/A
3. Equipment is visibility damaged N Y N/A
29
5. Resources
5.1 Sample Wiring Diagram 1: Microinverters with Supply Side Connection
Equipment Schedule
TAG DESCRIPTION: (Provide manufacturer and model number if applicable)
1 Solar PV Module or AC Module: (45) Trina TSM250PA05: (3) strings of (15)
2 Microinverter (if not ACM): (45) Enphase M250
3 Junction Box(es): (3) Soladeck NEMA 3R, on roof
4 Solar Load Center, Yes / No: YES, 60 amps with (3) 20 amp breakers.
5 Performance Meter Yes / No: YES, online monitoring through Enphase Envoy unit
6 *Utility External Disconnect Switch Yes / No: Yes
7 Supply Side Disconnect with OCPD: Disconnect rating 60 amps. OCPD Rating 60 amps
8 Main Electrical Service Panel: Cutler-Hammer 200-amp bus, 200-amp main breaker
1 2 3 4 5 6 7 8
DC DC
PV PV
AC AC
DC DC M
PV PV G N
AC AC
G
C
PV
DC
PV
DC B
AC AC
30
5.2 Sample Wiring Diagram 2: String Inverter with Supply Side Connection
Equipment Schedule
TAG DESCRIPTION: (Provide manufacturer and model # if applicable)
1 Solar PV Module: (24) SolarWorld SW280 Mono, (2) strings of (12)
2 Grounding Electrode for Array
3 Junction Box(es): Soladeck NEMA 3R, on roof
4 Inverter Model: (1) Fronius Primo 6.0-1, Transformerless
5 Performance Meter Yes / No
6 *Utility External Disconnect, or AC disconnect grouped with inverter if not grouped with main service panel
7 Backfed AC breaker in Main Service Panel rating: 35 amps
8 Main Service Panel Main Breaker rating:200 amps; Bus Bar rating: 200 amps
1 2 3 4 5 6 7 8
PV PV
INVERTER M
PV PV
G
C
A B
31
5.3 Sample Site Map
Site Plan for
John Smith,
80' to 123 East Main St,
Property Line
Albany NY 12208
Driveway to East Main St. Tax Map Parcel
#77-66-5555
C
A
60' to
Property Line
A
32
6. Sample Photos
NYSERDA requires contractors participating in the NY-Sun program to provide construction photos. The photos in this
chapter are illustrative examples only. Not all photos will apply to a given installation. Code enforcement officers may require
construction photos from solar PV contractors to supplement or replace an in-person inspection. These example photos also
help give a sense of solar PV system components and installation methods, and how they look when installed correctly.
33
6.1.2 General Array Photographs
Pull Back Image of Array
Guidance: Wide angle shot or multiple images with clear reference point of each array so module count can be verified.
Inspection Items: Module and array count and must match what was reported
Example Photos:
34
6.1.3 Array Racking Photographs
Module Racking System Documentation
Guidance: Multiple angles of racking being used. Must provide pictures of complete array and sub-arrays. Pictures should be
taken just before panels are installed to show all grounding and wire management.
Inspection Items: Racking system mechanical connections must be installed to manufacturer specifications
Example Photos:
35
Racking End Clip Documentation
Guidance: Photos should demonstrate the end clips are properly installed.
Inspection Items: Modules must be properly secured to the end of the racking system with end clips and sufficient clearance
Example Photos:
36
6.1.4 Module Installation Photos
Module Grounding
Guidance: Demonstrate the bond between the module and rails by means of approved rail components or appropriate
grounding hardware at each array. Provide documentation if necessary.
Inspection Items:
• Module grounding hardware must be present
• Module grounding hardware must be properly installed to effectively ground module frames; including solid contact
between grounding device and metal of the module frames, at designated grounding points
Example Photos:
37
6.1.5 Conductor Conduit Photos
Conductor Support and Management
Guidance: Take pictures showing all conduit is properly supported. Include photos to illustrate thermal expansion fittings and
frost sleeves are used when required. Include close-ups of fittings and connectors.
Inspection Items: Thermal expansion fitting must be present on raceways to compensate for expansion and contraction
• PV circuit conduit or raceway must be properly supported and secured
• Conduit below grade must be installed with provisions for movement (e.g., frost sleeve)
• Conduit fittings and connectors must be designed and listed for use
Example Photos:
38
Conduit Penetrations into Conditioned Space
Guidance: Include photos of conduit pass through into building to illustrate it is sealed.
Inspection Items: Conduit must have an approved internal sealant between conditioned and unconditioned spaces
Example Photos:
39
External Photo (cover on)
Guidance: Pictures should show proper labels close enough to verify language, wires are secured no more than 12” from
junction box and should show proper use of strain relief. Include images for all junction/combiner boxes onsite.
Inspection Items:
• Junction Box must be properly guarded against accidental contact and/or physical damage and have proper
working clearances
• Junction Box must be properly identified and listed
• Junction Box must be suitable for wet locations
• Junction Box must be properly secured in place
Example Photos:
40
6.1.7 Inverter Photos
External Photo (with lid on)
Guidance: Photos showing proper labels installed, and proper working and manufacturer clearances are provided.
Inspection Items:
• Inverter detailed system information label must be present
• The completed installation appears to be neat and of good workmanship
• Inverter must be mounted in accordance with manufacturer instructions and its listing
• Inverter mounting location provides clearance required by the manufacturer
• Inverter Ground Fault warning label must be present
Example Photos:
41
6.1.8 Balance of System
Balance of System Wall Photos
Guidance: A pulled back shot showing all BOS equipment. Take multiple shots if necessary.
Inspection Items:
• AC disconnect switch must be labeled with AC output information
• AC disconnect switch must be properly labeled as a photovoltaic system disconnect
• The completed installation appears to be neat and of good workmanship
• PV Service Disconnect must be installed in accordance with its listing and manufacturer instructions
• Installed with appropriate working clearances and guarding from accidental contact
• AC Disconnect must be in a readily accessible location
• Service Disconnects must be properly grouped
• Permanent plaque or directory must be properly installed
Example Photos:
42
GEC Path Photos
Guidance: Sequence of photos showing the path of the GEC from the inverter(s) to the structure’s GEC. Must show use of
bond bushings and irreversible splices when used.
Inspection Items:
• Grounding electrode conductor must be present and sufficiently sized
• Grounding electrode conductor must be properly bonded to the main premise grounding electrode system
• Grounded conductor(s) must be bonded to the enclosure of the PV service disconnect through a listed grounding
terminal or bus
Example Photos:
43
6.1.9 A/C Combiner
Internal Photos (cover off)
Guidance: Include photos to show correct wiring and grounding at all terminals. Include close ups of any breakers
with rating visible.
Inspection Items:
• Ferrous conduit and enclosures must be either electrically continuous or bonded to the grounding
electrode conductor
• Enclosure must be properly grounded using a listed grounding method
• AC Combiner overcurrent protection must be sufficient
• Grounded conductor(s) must be insulated from metal enclosure surfaces and the ground terminal inside combiner box
• Grounded conductor must be properly identified
• Ungrounded conductor must be properly identified
• Equipment grounding conductor must be properly identified
• Conduit or raceway must have adequate support
• AC Combiner circuit conductors must be properly sized for expected current load
• PV backfeed breaker must be sufficiently sized to prevent nuisance tripping
• Electrochemically dissimilar metals must not be in direct physical contact, which may lead to a galvanic reaction
Example Photos:
External Photo
Guidance: Include photos to show all labeling and enclosure ratings, with photos provided to allow wording
and value verification.
Inspection Items:
• Integrated AC combiner/disconnect switch must be labeled with AC output information
• AC Combiner must be labeled to indicate presence of multiple sources
• The completed installation appears to be neat and of good workmanship
• AC Combiner must be suitable for wet locations
• AC Combiner must be properly secured in place
• AC Combiner must be installed with the appropriate clearances
Example Photos:
44
6.1.10 A/C Disconnect Photos
Interior Photo
Guidance: Show correct wiring and grounding. Make sure OCPD rating is clear and readable.
Inspection Items:
• AC Disconnect must be properly rated for expected current load
• Electrochemically dissimilar metals must not be in direct physical contact
• Disconnect terminals must be properly wired
• Ferrous conduit and enclosures must be either electrically continuous or appropriately bonded to GEC
• AC Disconnect Switch must be breaking the ungrounded conductor and keep the grounded conductor properly grounded
and unenergized
• Ungrounded conductor must be properly identified
• Outdoor conductor insulation type must be rated for 90C and wet conditions
• Grounded conductor(s) must be insulated from metal enclosure surface and ground terminal inside Disconnect enclosure
• Equipment grounding conductor must be properly identified
• Enclosure must be properly grounded by a listed means
• AC Disconnect must be grounded
• Equipment grounding conductor must be properly sized
• Equipment grounding conductor must be larger than #6AWG or else it must be protected from physical damage
• Grounding electrode conductor must be sufficiently sized
• Grounding electrode conductor must be continuous
• AC Disconnect must be present when required to isolate equipment for service
Example Photos:
45
Exterior Photo
Guidance: Photos should allow for factory installed listings, and field installed label wording and values to be assessed.
Inspection Items:
• AC Disconnect switch must be properly labeled as a photovoltaic system Disconnect
• AC Disconnect switch must be labeled with AC output information
• The completed installation appears to be neat and of good workmanship
• AC Disconnect must be installed with the appropriate clearances
• AC Disconnect enclosure must be suitable for wet locations
Example Photos:
46
6.1.11 Main Panel Tie-In Pictures
Interior of Main Service Panel
Guidance: Take both close up and pulled back shots to correct wiring, grounding, and overcurrent protection (solar and
main). Include clear shots of all splices for load and line side taps. Include a back-up photo showing circuit run to illustrate
interconnection point/method.
Inspection Items:
• Main panel overcurrent protection must be sufficient
• PV system AC output conductors must be appropriately sized for expected current load
• Grounded conductor must be identified properly
• PV back feed breaker rating size must be properly sized to protect circuit conductors
• PV backfeed breaker must be sufficiently sized to prevent nuisance tripping
• Sum of back feed breaker(s) and main breaker must be less than or equal to 120% of busbar rating
• Inverter output connection must be properly located in main panel
• PV system AC output conductors must be appropriately sized for expected current load
• Enclosure must be properly grounded using a listed grounding method
• Equipment grounding conductor must be properly identified
• Grounding electrode conductor must be sufficiently sized
• Grounding electrode conductor must be properly bonded to the main premise’s grounding electrode system
• GEC must be continuous/irreversibly spliced
• The completed installation appears to be neat and of good workmanship
• Grounded conductor(s) terminal lug must be properly installed in accordance with its listing
Example Photos:
47
Busbar label
Guidance: Include a clear photo(s) of the busbar rating of the main service panel or other enclosure where PV is connected.
Inspection Items: Sum of backfeed breaker(s) and main breaker must be less than or equal to 120% of busbar rating
Example Photos:
48
6.1.12 If Applicable Photos
Pole Mounted Systems Photo
Inspection Items:
• All array conductors must be properly connected
• Thermal expansion fittings must be installed on raceways
• Conduit below grade must be installed with provisions for movement
• PV source and output circuits operating in readily accessible locations must be installed in a raceway
• Racking system and support structure must be properly grounded per manufacturer instructions
• The completed installation appears to be neat and of good workmanship
• Ground/pole mount support structure, anchor system, and or footings must be installed and used according to
manufacturer instructions
• Outdoor wire ties/clips must be UV and outdoor rated
49
7. Sample Installation Errors
The following photos are examples of common yet serious installation errors. Each item presents a safety concern, a system
performance issue, or both. For each of these installations, a certificate of completion had been issued by the AHJ.
Photo 1: Main service panel overloaded per NEC 705.12(B)(3)(b).
(100 amp main circuit breaker + 40 amps of PV) ÷ 100 amp bus rating >120%.
Photo 2: Backfed PV breaker not installed at opposite end of buss bar from main breaker: NEC 705.12(B)(3)(b)
50
Photo 5 - Conductors over 30V not guarded, installed in raceway, or otherwise inaccessible: NEC 690.31(A)
Photo 6: Roof penetrations and anchors not flashed, or improper flashing and sealing: 2020 NYS Uniform Code including
applicable 2020 Building Code of NYS and NEC 110.3(B)
Photo 7: Where not protected from physical damage, equipment grounding conductor must be #6 or larger: NEC 690.46,
250.120(C). Conductors laying on asphalt shingles will become damaged and will not last a PV system’s expected 30-year lifespan.
Photo 8: Source circuit conductors in contact with roof: NEC 338.10, 334.30
51
Photo 9: Equipment is not rated for location. In this case, a non-GFCI outlet for PV monitoring equipment
is located in a wet location: NEC 110.3(B), 210.8(A)(3)
52
Photo 12: Conductors entering conditioned space must be sealed: NEC 300.7
Photo 13: Two Hole conduit strap, with only one point of attachment, and no strain relief on conductors: NEC 110.3(B)
Photo 14: Failure to torque the lugs to the manufacturers specification: NEC 110.14(D)
53
8. Solar PV System Labeling Guidelines
Technical Bulletin: NYSERDA Solar Photovoltaic System Labeling Guidelines
54
8.3 Label Construction, Placement, Color, and Marking
8.3.1 Materials and Construction
Labeling used outdoors must be of durable construction and intended to withstand conditions including high temperatures,
UV exposure, and moisture as required by NEC 110.21(B)(3). Heavy duty UV resistant vinyl, metal, or plastic may all be
suitable materials, depending on the specific product ratings. Installers should also consider the label attachment method
(e.g., adhesive) when considering longevity and are encouraged to review ANSI Z535.4-2011 for guidance on selecting the
appropriate labeling and adhesive materials.
8.3.2 Placement
It is a violation of an enclosure’s UL listing (and NEC 110.3(B)) to cover any existing manufacturer applied labels with installation
specific labels, so this should be avoided. Additionally, it is highly recommended that the installer attaches a label or magnet
with the company name and contact information at the inverter or interconnection point for easy reference.
8.3.3 Colors
Label colors are chosen per OSHA 29 CFR 1910.145 direction that the requirements of ANSI Z535.4-2011 be used.
NFPA 70 (NEC) is driven by NFPA 1 (Fire Code) which provides specific colors and characteristics for certain labels as required
by the NEC, so these requirements over rule the referenced ANSI standards in these cases, as noted in this Technical Bulletin
and the text of the NEC.
8.3.4 Marking
Marking on labels for system specific values, such as short circuit current, shall not be hand-written and must be legible, as
required by NEC 110.21(B)(2). Marking may be achieved by means of engraving or use of a long-lasting ink or paint as part of
the printing process.
Figure 1
Note: does not apply to residential PV systems
55
Directory / Identification of Power Sources
A directory identifying the solar system and other power sources on site should be placed at service equipment and state the
location of system disconnecting means. The NEC stipulates this requirement in the following articles:
Figure 2
Figure 3
56
NEC 690.31(B) Identification and Grouping
PV system conductors shall be identified and grouped as required by 690.31(B). The means of identification shall be permitted
by separate color coding, marking tape, tagging, or other approved means.
1. PV Source Circuits. PV source circuits shall be identified at all points of termination, connection, and splices.
2. Grouping. Where the conductors of more than one PV system occupy the same junction box or raceway with a
removable cover(s), the AC and DC conductors of each system shall be grouped separately by wire ties or similar means
at least once, and then shall be grouped at intervals not to exceed 1.8 m (6 feet).
Exception: The requirement for grouping shall not apply if the circuit enters from a cable or raceway unique
to the circuit that makes the grouping obvious.
57
NEC 200.7 Use of Insulation of a White or Gray Color or with Three Continuous White or Gray Stripes
The following shall be used only for the grounded circuit conductor, unless otherwise permitted in 200.7(B) and (C):
1. A conductor with continuous white or gray covering
2. A conductor with three continuous white or gray stripes on other than green insulation
3. A marking of white or gray color at the termination
Note: PV systems utilizing transformerless (ungrounded) inverters do not ground either polarity of the PV array conductors.
Therefore, conductors in these circuits cannot have insulation colored white or gray.
Figure 4
Figures 5
58
8.4.4 Terminals Energized on Line and Load Sides of Disconnect in Open Position
NEC 690.13(B) Switch or Circuit Breaker
Each PV system disconnecting means shall plainly indicate whether in the open (off) or closed (on) position and be
permanently marked “PV SYSTEM DISCONNECT” or equivalent. Additional markings shall be permitted based upon the
specific system configuration. For PV system disconnecting means where the line and load terminals may be the open
position, the device shall be marked with the following words or equivalent:
WARNING
ELECTRIC SHOCK HAZARD.
DO NOT TOUCH TERMINALS.
TERMINALS ON BOTH THE LINE AND LOAD SIDES
MAY BE ENERGIZED IN THE OPEN POSITION.
Figure 6
Note: This requirement does not apply to AC disconnects for any inverter Listed to UL 1741
Figure 7
59
NEC 690.31 (G) (4) Marking and Labeling Methods and Locations
The labels or markings shall be visible after installation. The labels shall be reflective, and all letters shall be capitalized and
shall be minimum height of 9.5mm (3/8in) in white on a red background. PV system dc circuit labels shall appear on every
section of the wiring system that is separated by enclosures, walls, partitions, ceilings, or floors. Spacing between labels
or makings, or between a label and a marking, shall not be more than 3 m (10 feet). Labels required by this section shall be
suitable for the environment where they are installed.
Note: Although the ANSI standard directs that these types of labels have different coloring, the NEC has been driven by
fire codes and thus specifies characteristics explicitly for these applications.
Figure 8
Figure 9
60
8.4.7 Identification of PV System Interconnection
NEC 690.54 Interactive System Point of Interconnection
All interactive system(s) points of interconnection with other sources shall be marked at an accessible location at the
disconnecting means as a power source and with the rated AC output current and the nominal operating AC voltage.
Note: Examples of points of interconnection are AC combining panels, AC disconnects, backfed breakers at point
of utility interconnection, etc. This requirement does not apply only to the point of common coupling for the PV system
and the utility grid.
Figure 10
Figure 11
The plaque or directory shall be reflective, with all letters capitalized and having a minimum height of 9.5 mm (3/8 inch),
in white on red background.
Note: Although the NEC does not explicitly define a location for this labeling, it is suggested that one be located at the main
service disconnect for the utility, and one at the inverter location, or the location of the ‘rapid shutdown’ initiator if different.
61
8.4.9 Point of Connection Identification
NEC 705.12(A) or (B)
The output of an interconnected electric power source shall be connected as specified in NEC 705.12(A) or (B).
Figure 12
Figure 13
62
8.5 Common Labeling Mistakes to Avoid
Do not cover manufacturer’s labeling with other labels (NEC 690.13(B), 110.21(B)).
Figure 14
Figure 15
Make sure labels are permanent and suitable for use in the environment to which it will be exposed. In this example,
these light duty adhesive labels will not withstand 20+ years of wind, sun and rain, and are in violation of NEC 110.21.
Figure 16
63
Label Not of Permanent Construction, nor conforming with NEC 690.31(G)(4).
Figure 17
64
9. Example Labels
The following pages provide example NEC-compliant labels based on NEC required/recommended text as well as their
related code articles.
While the use of these labels on NY-Sun-funded solar PV projects is encouraged; final selection, preparation, and placement
of labels in compliance with the NEC and other relevant codes is the responsibility of the installer.
1) All labeling used outdoors must be engraved metal, UV stabilized engraved plastic or of a material sufficiently durable
to withstand the environment involved. Values hand written or in written in marker are not acceptable per NEC.
2) L
abels used indoors may be made of durable vinyl or paper
3) Do not cover any existing manufacturer applied labels with installation specific labels
4) Label colors chosen per NEC directs that ANSI Z535-2011 be used
5) R
equirements comply with the NEC
6) Additionally, it is highly recommended that the installer attach a label with the company name and
contact information at the inverter
7) All warning signs or labels shall comply with NEC 110.21(B)
Label #1 Label #4
NEC 690.13(B) NEC 690.13(B)
Label #2
NEC 110.27(C)
Label #5
NEC 690.13(B)
Label #3
NEC 705.10 & 690.56(B) Label #6
NEC 690.53
65
Label #7 Label #13
NEC 690.3(I)
NEC 690.31(G)(3)(4)
Label #8
NEC 705.12(D)(3) & 690.59
Label #14
NEC 710.15(C) & 692.9(C)
Label #9
NEC 690.13(B)
Label #10
NEC 690.13(B)
Label #15
NEC 690.15(C) & 690.33(E)(2)
Label #16
NEC 690.13(F), 705.12(B)(3-4), & 690.59
Label #11
NEC 690.52
Label #17
NEC 705.12(B)(3-4) & 690.59
Label #12
NEC 690.54
66
Label #18
NEC 705.12(B)(2)(c)
Label #19
NEC 690.13(B)
67
10. Top Deficiencies in
Solar Electric Systems
In order to provide a summary of common PV system installation issues and help the New York solar industry prioritize
education and process improvement, the NY-Sun program has compiled the results of 287 recent PV system inspections.
The summaries below are generated from PV installations within a three-month time period based on the 2014 National
Electrical Code (NEC). The chart shows that the most frequent violation is Labeling. The table provides an overview of the
9 most common deficiencies found with the top five categories being, Labeling, Grounding, Conductors, Conduit, and
Structural. For each category, the list shows the most prevalent violations.
68
10.2.1 Labeling Deficiencies: 78% of Systems Inspected
Below, we have summarized the top 5 deficiencies found related to labeling.
69
10.2.2 Grounding Deficiencies: 53% of Systems Inspected
Below, we have summarized the top 5 deficiencies found related to Grounding.
2 Supply Side The top of the grounding electrode is not flush with, or
Connection below, ground level in violation of NEC Article 250.53(G).
70
10.2.3 Conduit Deficiencies: 52% of Systems Inspected
Below, we have summarized the top 5 deficiencies found related to Conduits.
71
10.2.4 Conductor Deficiencies: 40% of Systems Inspected
Below, we have summarized the top 5 deficiencies found related to Conductors.
72
10.2.5 Structural Deficiencies: 28% of Systems Inspected
Below, we have summarized the top 5 deficiencies found related to Structural issues.
73
Table 7. Deficiency as a Percent of All Deficiencies Found
Frequency System Defect Deficiency Description
Component Category
44% All Labeling This deficiency includes all labeling violations found within all the
Regions.
2.3% Supply Side Grounding Grounded (neutral) conductor is not properly bonded to PV service
Connection disconnect enclosure using a listed grounding bus or terminal, or
the grounded conductors are not properly bonded to the Grounding
Electrode Conductor (GEC), in violation of NEC Article 250.24(C).
2.2% Supply Side Grounding The top of the grounding electrode is not flush with, or below, ground
Connection level in violation of NEC Article 250.53(G).
1.8% AC Disconnect Grounding Enclosure is not properly grounded using a listed grounding method,
in violation of NEC Articles 690.43, 250.8, and 250.12. Enclosure must
be grounded with equipment listed for the purpose and that is solidly
connected to the enclosure body.
1.6% Supply Side Conduit Conduit is missing an approved internal sealant at penetrations
Connection between conditioned and unconditioned spaces to prevent
condensation, in violation of NEC Article 300.7(A).
1.5% Supply Side Conductors Service Entrance conductor splice is not installed in accordance with its
Connection listing, in violation of NEC Article 110.3(B) and 110.14.
1.4% Supply Side Grounding The GEC is not continuous or irreversibly spliced, in violation of NEC
Connection Articles 250.64(C) and 690.47(C). Allowable means of splicing the GEC
include compression crimp and exothermic welding processes.
1.1% Array Structural Racking system mechanical connections not made correctly and/or
racking not installed per manufacturer instructions, in violation of NEC
Article 110.3(B).
1.1% AC Combiner Grounding Enclosure is not properly grounded using a listed grounding method,
in violation of NEC Articles 690.43, 250.8, and 250.12. Enclosure must
be grounded with equipment listed for the purpose and that is solidly
connected to the enclosure body.
1.0% Array Electrical Electrochemically dissimilar metals are in direct physical contact, which
may lead to a galvanic reaction, in violation of NEC Article 110.14 (for
conductors/splice components) and/or RMC-NEC 344.14, EMT-NEC
358.12(6) (for conduit and surrounding materials).
1.0% Inverter Conduit Conduit is improperly used to support conductors, in violation of NEC
Article 300.11(B).
0.9% AC Disconnect Conduit Conduit is missing an approved internal sealant at penetrations
between conditioned and unconditioned spaces to prevent
condensation in violation of NEC Article 300.7(A).
0.9% Supply Side Conduit Circuit conduit or raceway lacks adequate support, in violation of NEC
Connection (LFMC-350.30, EMT-358.30, Metal Trough-376.30).
0.9% Supply Side Grounding Enclosure is not properly grounded using a listed grounding method,
Connection in violation of NEC Articles 690.43, 250.8, and 250.12. Enclosure must
be grounded with equipment listed for the purpose and that is solidly
connected to the enclosure body.
0.9% Array Conduit Conduit is missing an approved internal sealant at penetrations
between conditioned and unconditioned spaces to prevent
condensation, in violation of NEC Article 300.7(A).
74
11. Unified Residential Solar PV Permit
Application The workable version of this document can be found at nyserda.ny.gov/
SolarGuidebook, under the Solar Permitting and Inspecting tab.
PERMIT APPLICATION
For solar PV systems not meeting these eligibility criteria, the applicant is not eligible for the Unified Solar Permit and
must submit conventional permit applications. Permit applications may be downloaded here: [BUILDING
DEPARTMENT WEBSITE] or obtained in person at [BUILDING DEPARTMENT ADDRESS] during business hours
[INDICATE BUSINESS HOURS].
SUBMITTAL INSTRUCTIONS
For projects meeting the eligibility criteria, this application and the following attachments will constitute the
Unified Solar Permitting package.
• This application form, with all fields completed and bearing relevant signatures.
• Permitting fee of $[ENTER FEE HERE], payable by [ENTER VALID PAYMENT METHODS, If checks are
allowed INCLUDING WHO CHECKS SHOULD BE MADE PAYABLE TO]
• Required Construction Documents for the solar PV system type being installed, including required attachments.
Completed permit applications can be submitted electronically to [EMAIL ADDRESS] or in person at [BUILDING
DEPARTMENT ADDRESS] during business hours [INDICATE BUSINESS HOURS].
Page 1 of 5
75
Page 1 of 5
PROPERTY OWNER
Property Address
EXISTING USE
Single Family 2-4 Family Commercial Other
Please sign below to affirm that all answers are correct and that you have met all the conditions and requirements to submit
a unified solar permit.
Page 2 of 5
76
SUBMITTAL REQUIREMENTS SOLAR PV 25KW OR LESS (ATTACHMENTS)
SUBMITTAL REQUIREMENTS
In order to submit a complete permit application for a new solar PV system, the applicant must include:
a) Completed Standard Permit Application form which includes confirmed eligibility for the Unified Solar
Permitting process. This permit application form can be downloaded at [WEBSITE ADDRESS].
b) Construction Documents, with listed attachments [SAMPLES ARE AVAILABLE IN Understanding Solar PV
Permitting and Inspecting in New York State AT WEBSITE ADDRESS]. Construction Documents must be by
stamped and signed by a New York State Registered Architect or New York State Licensed Professional
Engineer.
[MUNICIPALITY NAME], through adopting the Unified Solar Permitting process, requires contractors to provide
construction documents, such as the examples included in the Understanding Solar PV Permitting and Inspecting in
New York State document. Should the applicant wish to submit Construction Documents in another format, ensure
that the submittal includes the following information:
• Manufacturer/model number/quantity of solar PV modules and inverter(s).
• String configuration for solar PV array, clearly indicating the number of modules in series and strings in
parallel (if applicable).
• Combiner boxes: Manufacturer, model number, NEMA rating.
• From array to the point of interconnection with existing (or new) electrical distribution equipment: identification
of all raceways (conduit, boxes, fittings, etc.), conductors and cable assemblies, including size and type of
raceways, conductors, and cable assemblies.
• Sizing and location of the EGC (equipment grounding conductor).
• Sizing and location of GEC (grounding electrode conductor, if applicable).
• Disconnecting means of both AC and DC including indication of voltage, ampere, and NEMA rating.
• Interconnection type/location (supply side or load side connection)
• For supply side connections only, indication that breaker or disconnect meets or exceeds
available utility fault current rating kAIC (amps interrupting capacity in thousands).
• Ratings of service entrance conductors (size insulation type AL or CU), proposed service disconnect, and
overcurrent protection device for new supply side connected solar PV system (reference NEC 230.82,
230.70).
• Rapid shutdown device location/method and relevant labeling.
Page 3 of 5
77
c) (For Roof Mounted Systems) A roof plan showing roof layout, solar PV panels and the following fire safety
items: approximate location of roof access point, location of code-compliant access pathways, code
exemptions,
solar PV system fire classification, and the locations of all required labels and markings.
d) Provide construction drawings with the following information:
• The type of roof covering and the number of roof coverings installed.
• Type of roof framing, size of members, and spacing.
• Weight of panels, support locations, and method of attachment.
• Framing plan and details for any work necessary to strengthen the existing roof structure.
• Site-specific structural calculations.
e) Where an approved racking system is used, provide documentation showing manufacturer of the racking system,
maximum allowable weight the system can support, attachment method to roof or ground, and product evaluation
information or structural design for the rack.
PLAN REVIEW
Permit applications can be submitted to [DEPARTMENT NAME] in person at [ADDRESS] and [IF APPLICABLE]
electronically through: [WEBSITE/EMAIL/FAX].
FEES
[PROVIDE CLEAR FEE SCHEDULE]
INSPECTIONS
Once all permits to construct the solar PV installation have been issued and the system has been installed, it must
be inspected before final approval is granted for the solar PV system. On-site inspections can be scheduled by
contacting [DEPARTMENT] by telephone at [PHONE NUMBER] or electronically at [WEBSITE OR EMAIL ADDRESS].
Inspection requests received within business hours are typically scheduled for the next business day. If next business
day is not available, inspection should happen within a five-day window. [IF MUNICIPALITY ACCEPTS THIRD PARTY
INSPECTIONS, INDICATE THIS AND PROVIDE A LIST OF APPROVED INSPECTORS].
In order to receive final approval, the following inspections are required:
Delete Rough/Final inspection descriptions if not applicable in your jurisdiction
[ROUGH INSPECTION, IF REQUIRED] During a rough inspection, the applicant must demonstrate that the work in
progress complies with relevant codes and standards. The purpose of the rough inspection is to allow the inspector to
view aspects of the system that may be concealed once the system is complete, such as:
• Wiring concealed by new construction.
• Portions of the system that are contained in trenches or foundations that will be buried upon completion
of the system.
It is the responsibility of the applicant to notify [ENTER CONTACT INFORMATION] before the components are buried
or concealed and to provide safe access (including necessary climbing and fall arrest equipment) to the inspector.
The inspector will attempt, if possible, to accommodate requests for rough inspections in a timely manner.
[FINAL INSPECTION] The applicant must contact [INSERT CONTACT INFORMATION] when ready for a final inspection.
During this inspection, the inspector will review the complete installation to ensure compliance with codes and
standards, as well as confirming that the installation matches the records included with the permit application. The
applicant must have ready, at the time of inspection, the following materials and make them available to the inspector:
• Copies of as-built drawings and equipment specifications, if different than the materials provided
with the application.
• Photographs of key hard to access equipment, including;
– Example of array attachment point and flashing/sealing methods used.
– Opened rooftop enclosures, combiners, and junction boxes.
– Bonding point with premises grounding electrode system.
– Supply side connection tap method/device.
– Module and microinverter/DC optimizer nameplates.
– Microinverter/DC optimizer attachment.
Page 4 of 5
78
and specification sheets.
• Array conductors and components are installed in a neat and workman-like manner.
• Solar PV array is properly grounded.
• Electrical boxes and connections are suitable for environment.
• Array is fastened and sealed according to attachment detail.
• Conductor’s ratings and sizes match plans.
• AppropriateNAME]
[MUNICIPALITY signs has
are adopted
property aconstructed,
standardized installed andchecklist,
inspection displayed, including
which can bethefound
following:
in the Understanding
Solar PV– Permitting and Inspecting
Sign identifying PV power in New
sourceYork State attributes
system document,atfound here: [WEBSITE ADDRESS].
DC disconnect.
– Signchecklist
The inspection identifying AC point
provides an of connection.
overview of common points of inspection that the applicant should be prepared
– Rapid shutdown device
to show compliance. If not available, commonmeets applicable
checks requirements of NEC 690.12.
include the following:
• • Equipment ratings are consistent with application
Number of solar PV modules and model number match plans and and installed signs on the installation,
specification including
sheets number match plans
the
andfollowing:
specification sheets.
– Inverter
• Array has aand
conductors rating as high asare
components max voltageinon
installed PV power
a neat source sign. manner.
and workman-like
– DC-side overcurrent circuit
• Solar PV array is properly grounded. protection devices (OCPDs) are DC rated at least as high as max voltage
on sign.
• Electrical boxes and connections are suitable for environment.
– Inverter
• Array is rated
is fastened andfor the site
sealed AC voltage
according supplied and
to attachment shown on the AC point of connection sign.
detail.
– OCPD connected
• Conductor’s ratings andtosizes
the AC output
match of the inverter is rated at least 125% of maximum current on sign
plans.
and is no
• Appropriate larger
signs arethan the maximum
property OCPD
constructed, on theand
installed inverter listingincluding
displayed, label. the following:
–– Sum of the main OCPD and the inverter OCPD is rated
Sign identifying PV power source system attributes at DC disconnect.for not more than 120% of the buss bar rating.
– Sign identifying AC point of connection.
UNIFIED SOLAR
– RapidPERMITTING
shutdown RESOURCES
device meets applicable requirements of NEC 690.12.
• Equipment ratings are consistent with application and installed signs on the installation, including
the following:
The jurisdiction has adopted the following documents from the New York Unified Solar Permit process:
– Inverter has a rating as high as max voltage on PV power source sign.
Delete any documents not adopted by the jurisdiction.
– DC-side overcurrent circuit protection devices (OCPDs) are DC rated at least as high as max voltage
• Standard on Application
sign. [WEB ADDRESS]
• Understanding Solar PVforPermitting
– Inverter is rated the site AC andvoltage supplied
Inspecting in NewandYork
shown on the
State AC pointwhich
document, of connection
includes sign.
sample
– OCPDdocuments,
construction connected to the AC output
inspection of thedesign
checklist, inverter is rated
review at leastand
checklist, 125% of maximum
labelling guidecurrent on sign
[WEB ADDRESS]
and is no larger than the maximum OCPD on the inverter listing label.
DEPARTMENTAL
– Sum CONTACT INFORMATION
of the main OCPD and the inverter OCPD is rated for not more than 120% of the buss bar rating.
For additional information regarding this permit process, please consult our departmental website at [WEBSITE]
orUNIFIED
contactSOLAR PERMITTING
[DIVISION NAME] RESOURCES
at [PHONE NUMBER].
The jurisdiction has adopted the following documents from the New York Unified Solar Permit process:
Delete any documents not adopted by the jurisdiction.
• Standard Application [WEB ADDRESS]
• Understanding Solar PV Permitting and Inspecting in New York State document, which includes sample
construction documents, inspection checklist, design review checklist, and labelling guide [WEB ADDRESS]
SUN-GEN-uspi-form-1-v3 Page 5 of 5
9/16
Questions?
If you have any questions regarding the solar permitting and inspecting process, please email questions to
[email protected]
SUN-GEN-uspi-form-1-v3 or request free technical assistance at nyserda.ny.gov/siting.
Page 5 of 5
The NYSERDA
9/16
team looks forward to partnering with communities across the state to help them meet their
solar energy goals.
79