Construction Measurement ME Works Module 1
Construction Measurement ME Works Module 1
8
BENEFITS OF ADOPTING SMM
Benefits:
Prompts the design team and clients to finalize the design prior
to bill preparation
Avoids the need for contractors to Measure the works
themselves.
Provides commonality in tenders
The coding system enable ease of computer application
Can be used as basis for interim valuation
The rates contained therein can be used as basis for valuing
variation
Assist in risk management
(Hore, et al., 1997; Molloy, 2007, Potts 2008; Davis and Bacarini 2009)
PROBLEMS WITH THE LUMP SUM METHOD
KNOWLEDGE SKILLS
Output
BILL OF QUANTITIES
14
ESTIMATING PROCESSES
PROJECT MANAGEMENT
APPROXIMATE DETAILED
ESTIMATE ESTIMATE
Unit method: Cost/ bed space or work station, price forecast here are based on
skeletal information are available, degree of accuracy here is very low. +/- 30%
Low
Space: Cost per m2 or gross floor area, when more information are available
than is at unit method stage . The degree of accuracy is also low. +/- 25 –
30%
Element: Prepared when more detail information are available, the degrees of
accuracy is +/- 20 – 25%.
ETC q1r1
n
i 1
21
WORK BREAKDOWN
STRUCTURE
The WBS clarifies and provides the necessary details for a number
of project management activities such as
1 SUBSTRUCTURE 2 SUPERSTRUCTURE
1 Piling 1 Building Frames
2 Work Below Lowest Floor Finishes 1 Column
1 Pad Foundation 1 Reinforced concrete
1 Excavation 2 Formwork
2 Lean concrete 3 Reinforcement
3 Reinforced concrete grade 20
4 Formwork 2 Floor beams
5 Reinforcement 1 Reinforced concrete
2 Formwork
2 Column Stumps 3 Reinforcement
1 Reinforced Concrete grade 20
3 Roof Beams
2 Formwork
1 Reinforced concrete
3 Reinforcement
2 Formwork
3 Reinforcement
3 Ground Beams
1 Excavation 4 Upper Floors
2 Lean concrete 1 Reinforced concrete
3 Reinforced Concrete grade 20 2 Formwork
4 Formwork 3 Reinforcement
5 Reinforcement
2 External Walls
4 Ground floor 1 Brickwall
1 Reinforced concrete grade 20 2 Damp proof course (DPC)
2 BRC
3 Damp proof membrane (DPM) 3 Roof
4 Hardcore 1 Roof structures
2 Roof covering
WORK BREAKDOWN STRUCTURE FOR BUILDING ELEMENTS
3 FINISHES
2 SUPERSTRUCTURES (Cont'd.)
1 External wall finishes
1 Internal Wall
2 Internal wall finishes
1 Brickwalls
3 External floor finishes
2 Partition
4 Internal floor finishes
1 Timber wall frame
5 Ceiling finishes
2 Plywood/timber boarding 6 Painting
L.S.
11/25/2021
29
PRIME COST SUMS : AIR COND. WORKS
COMPONENTS
Pipe works
Insulation
Sundries
Builder’s work
3D ME Works
CURRENT PRACTICE & SMM
COND WATER
PUMP
Items of work are not classified under the
appropriate headings as required by
sections Q.2 and R.2 of SMM2.
DIFFUSER
M&E services drawings are often not
completed at the time of preparing BoQ
for tender purposes.
M&E Works Cost Estimating and Cost Control Tools
Project
Initiation Historical
Cost
Database
Budget
Scope Current
1. _______
Change Estimate
Variation of 2. _______
Authorization 3. _______
Works
Historical
Final Cost
Account Database
VIDEO PRESENTATION
ORGANIC LEARNING
IN CONSTRUCTION
THANK YOU
CONSTRUCTION MEASUREMENT (M&E WORKS)
ONLINE LEARNING
openlearning.com/courses/SBEQ3213x