Chapter 3
Chapter 3
2
CONTENTS
3. Contract Management
Contract Administration, Specification and Quantity Survey 3.2. 1.Contract Change Management
(Ceng3162)
3.2.2.Claim Management
Chapter - 3
Contract Administration and Claim 3.2.3.Dispute Resolution Method
1
8/21/2022
2
8/21/2022
9 10
Determining and understanding the construction components Record, Monitor and Evaluate the Progress of Mobilizations,
of the project. Works and Completions.
Reviewing the Contract Drawings and Technical Specifications. Report project status daily and / or periodically and completions.
Extract the Construction Methods and Sequences. Certify qualities of materials, shop drawings (set of drawigs),
samples, workmanships and works.
Prepare Construction Methods and Over all Sequences Sheets.
Measure Works, Record Site Potentials and Certify Payments and
Completions.
Review submitted (Integrated) schedules and breakdowns for
operations such as Organizational Breakdowns, Resources Administer contract changes.
Breakdowns &Time Schedules.
Mediate Disputes.
3
8/21/2022
13 Variation/Changes 14
Refer Civil code (Art 3031-3034).
Modification of scope of work as anticipated in the contract
Similar character to the existing scope of work Variation/change is addition, alteration, and omission.
Contractor legally obligated to perform Directed by the Owner and authorized in the contract
documents.
Changes/Extras
Independent of construction contract Additional/Extra is additional work directed by the Owner but
not within the original scope of work.
Different character -not anticipated by contractor
May disrupt a Contractor’s plan for the work.
Contractor not legally obligated to perform but can perform if it
chooses. Requires close attention to prevent disputes.
15 16
There are three types of variations Examples of constructive variations
Formal/Directed Variations:
Defective plans and specifications
Directed by an owner using authorization written in the contract Engineer’s interpretation
documents.
Improper inspection and rejection
Constructive Variations:
Change in the method of performance
Is directing a modification to the contract caused by an actor
failure to act.
Change in the construction sequence
Must be claimed in writing by the contract or within the time
specified in the contract documents in order to be considered
4
8/21/2022
19 20
Causes of change/variation B. Contractor related change
A. Owner related change
Unavailability of equipment
Change of plans or scope by the owner.
Differing site condition
Change of schedule
Defective workmanship
Owners financial problem
Unfamiliarity with local condition
Replacement of materials
Contractors lack of required data
Change in specification by the owner
5
8/21/2022
21 22
C. Design consultant related change D. Other change
6
8/21/2022
25 26
Types of Excusable Delay
Generally , Time delays can be classified into the following categories
7
8/21/2022
The amount of and application of liquidated damages are Increased (material escalation) material direct costs that
normally set forth in the contract. (1/1000 of project cost per occur during the delay.
each days of delay) (0.1 %).
Lost productivity caused by the delay and;
When there is no liquidated damage provision in the contract
Other damages directly related to and attributable to the delay.
the owner will be able to collect its actual damages.
Classification of claims
If the Claim does not resolved by the parties it goes to Dispute.
Generation and avoidance of claims
Claim management does address the way in which claims should be
administered. Proper presentation and assessment of claims
8
8/21/2022
Contractual claim is
Additional expense for both parties
Event and remedy specified in Contract
‘Cat and Mouse’ relationship between contracting parties
Breach of contract for which the remedy is specified in the
Contract (Art 1771 of civil code)
The most important tort claim is arise due to: Art.3032 of Ethiopian Civil Code is related to this type of claim
which states that if there is unexpected alteration of work, the client
Negligence raises claim to reduce the price, when the price due to the
alteration is reduced from the original one. And also the contractor
quotes to increase the prices when the price for alteration increases
The responsibility of the 3rd party (Art.2134 of Civil Code ) his expense.Where they do not agree arbitrators are allocated.
9
8/21/2022
37 38 Types of Claim
III. Ex-Gratia Claim: Ex-gratia claims are the claims that there is
no ground existing in the contract or the law, but the contractor I. Time Related Claims: Claims associated with delay or in time
believes that he has the rights on the moral grounds, completion of projects where either of the following Entitlements or
Penalties are subjected to:
E.g. additional costs incurred as a result of rapidly increased prices.
Time Extension only
IV. Counter Claim (set off):Art 1831
Liquidated Damages only
E.g. if contractor claim on payment delay the client also counter
claim on payment adjustment for omission of work. Time Extension and Cost Compensation
40
As much as possible claim has to be mitigated / prevented because
2. Cost Related Claims: Claims associated with monetary the successful completion of projects has been thought to depend
compensation where either of the following entitlements or mainly on cooperation between the contractor, consultant, & owner.
penalties are entertained:
Claim administration has a key role to prevent occurrence of claim;
Additions requiring rate adjustments The most important principle in the administration of claims is
the complete knowledge of the text of the contract between
Price Changes phrases and clauses. In other words, just read the contract
carefully and compare it with existing realities, can recognize the
Provisional sum adjustments claims are intended.
10
8/21/2022
Claim
41
Administration Process 42
• Claim Identification The documentation usually required for claim analysis and
documentation is derived from the following sources
Drawing register ~ details of amendments and revisions Basically, three types of dispute resolution systems are well
made to plans! recognized.These included:
11
8/21/2022
45
I. Preventive Dispute Resolution System 46 ii. Amicable Dispute Resolution System
including Negotiation, Mediation and Conciliation to administer
The best way of handling claims is prevention before it rises. the claim in a less formal, simple procedure, more flexible, less
adversarial and strictly confidential mode so as to avoid the time
and cost implication of claim processing.
Claim prevention can be accomplished most effectively during the
design phase of construction project. Contracting parties discusses their differences around the table
and mostly the Engineer act as a mediator.
Before inviting qualified contractor to submit bids for the
construction work the design is sufficiently complete. The Engineer during this time will guide the parties to focus their
point of discussion on their differences and summarizes their
The careful preparation of well-considered contract document points of agreements.
offers the next greatest opportunity for claims prevention.
The speedy and cheapest dispute resolution technique
47 Negotiation 48 Conciliation
Negotiations may be conducted on an open basis(that is to say It involves the appointment of an independent third party, mutually
that the records of the negotiations may be used by the parties in agreed by the parties, to hear both parties' points of view.
any proceedings), or they may be without prejudice.
The conciliator will usually be a recognized expert on the matters
If there is agreement on any section of the claim, the contractor in dispute and he will look at the evidence and listen to the
should endeavor to persuade the employer to make the agreement arguments put forward by each side (see Art 3318 -3324 for more.)
open and certify any sums which should to flow from it.
He will not meet any party in private and all discussions take place
with both parties present.
12
8/21/2022
49 50
Mediation
The conciliator's aim will be to bring the two sides together to
discuss all aspects of the matters in dispute and lead them to an This process is similar to conciliation. However, the mediator
amicable settlement. normally meets the parties separately.
Adjudication is a process in which the parties to a dispute submit An impartial third party, known as an Arbitrator, is chosen by the
their cases to a third party (an individual or a panel) for a decision. parties to listen to their case and make a decision.
The adjudicator may be named in the contract or he may be The meeting takes place outside court, but is much like a hearing,
agreed by the parties. in that both sides present testimony and evidence.
13
8/21/2022
53 54
c. Litigation
Arbitration can be binding or non binding
Litigation is facilitated by the government within federal, state,
The method is very similar to litigation but offers more speedy and municipal courts. The proceedings are very formal and are
resolution. governed by rules, such as rules of evidence and procedure, which
are established by the legislature.
Another advantage of arbitration over litigation is that the
arbitrator’s panel is composed of individuals with experience in CI. Outcomes are decided by an impartial Judge and/or Jury, based on
the factual questions of the case and the application law.
Standard forms of contract have express provisions for arbitration
in the articles or in the conditions of contract. (See Art 3325 to The decision of the court is binding, not advisory; however, both
3346 of Ethiopian civil code) parties have the right to appeal the judgment to a higher court.
14
8/21/2022
59
Thank You
15