0% found this document useful (0 votes)
36 views1 page

CPM Coc 22 003

The document is a certificate of completion for maintenance performed on equipment. It certifies that hydrotesting was completed on a subplate mounted ball valve for an accumulator bladder drain valve according to drawings, procedures, specifications, and standards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views1 page

CPM Coc 22 003

The document is a certificate of completion for maintenance performed on equipment. It certifies that hydrotesting was completed on a subplate mounted ball valve for an accumulator bladder drain valve according to drawings, procedures, specifications, and standards.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

REPORT NO.

: CPM-COC-22-003

CERTIFICATE OF COMPLETION

Maintenance of the equipment mentioned below has been inspected, tested


and found to be conforming with the requirement in accordance with drawing,
procedure, specification and standard, and certify to be completely accepted.

PROJECT : EMS - ITMS


DESCRIPTION : Hydrotest of Subplate mounted ball valve for Z-2803 HPU
Accumulator Bladder Drain Valve

SHELL IMPORT FACILITIES TABANGAO CPM CONSTRUTION & GENERAL SERVICES, INC.

ACCEPTED BY :

MARK DARREL ARANAS 03-Sep-22


QA/QC INSPECTOR DATE

ALEX CALANGI 03-Sep-22


CPM SUPERINTENDENT DATE